Citv of Fort Collins
M E M O R A N D U M
DATE: June 5, 1991
TO: Matt Baker, SID Coordinator
Susan Hayes, Civil Engineer II
Mike Herzig, Development Engineering Manager
Mark Taylor, Civil Engineer II
FROM: W. Paul Eckman, Deputy City Attorney
JON
Enn;nle('frin Dept.
RE: Reimbursement Request/Harmony Village Joint Venture
You will recall that on April 18, 1991, I forwarded a letter to
Michael C. Emo responding to his earlier letter to Steve Burkett.
My response attempted to incorporate all of your various comments
regarding his demand letter.
On June 3, 1991, I received a letter from Mr. Emo dated May 28,
1991, responding to my letter to him. A copy is attached. I would
ask that you take a look at his new letter, see if there are any
valid points that he raises as far as your various departments are
concerned and respond back to me. He has indicated that he will
provide us with the documentation that we requested and,
accordingly, before we respond to him, we will wait to receive that
documentation.
Please let me know your thoughts.
WPE:whm
Attachment
;oi I j1',,Tt(-AccnLw • f' 0 B0v ;80 • Fort Collins. CO 80522-0;80 • ('103) 221-6820
DATE: November 10, 1993
TO: Paul Eckman, Deputy City Attorney
FROM: Matt Baker, Engineering �'./
RE: Street Oversizing Reimbursement for Harmony Village
I have recently received two requests for street
oversizing reimbursement from Equity Builders
representing Mr. M.C. Emo. As you are aware, Harmony
Village Joint Venture included Mr. Emo and Bob Peterson
as partners. Mr. Emo has received a monetary judgement
against his former partner, Mr. Peterson, which he claims
is on file in the City Attorney's office.
I had originally budgeted this reimbursement in 1984 when
the project was under construction. However, the project
was never completed and no request for reimbursement was
filed. I kept the budgeted payment "on the books" for a
few years, until the revisions to the Street Oversizing
Ordinance in 1988. I do not contest the fact that the
City has an oversizing obligation in this development,
however, I would like to be sure the payment is made to
the correct party in this matter.
There are Two reimbursements for street oversizing funds
requested. The first request is for Regency Drive at
Belair PUD. There was Approximately 530 feet of
Collector street constructed from Harmony Road north to
Hilburn Drive. Although I made some minor adjustments to
the calculations, the request for $35,910 in Oversizing
Funds has been substantiated with adequate documentation.
The second request for reimbursement is for improvements
to Shields Street at Pineview PUD. There was 1327 feet
of Shields Street constructed with Pineview PUD. Again, I
made some minor adjustments to the calculations. Harmony
Village Joint Venture was unable to find records
indicating prices or actual payments for this work.
Support for this payment is from bid prices for other
work performed around this time. Although I am
comfortable with the estimate, there is no way to prove
costs of construction on this reimbursement. The
requested reimbursement is for $114,978.
In our previous discussions on this matter, you asked
that send you a memo outlining my concerns with this
reimbursement.
My first concern is the amount of time that has passed
since the construction. The revisions to the Street
Oversizing ordinance in 1988 added a clause that any
reimbursements for previous work that were not claimed by
August 1988, were forfeit. I understand that this
partnership has been in court for several years. Maybe
this circumstance is reason enough for us to consider a
reimbursement request nine years after construction of
the improvements.
My second concern is that any reimbursement be given to
the correct party. Since the default of the Harmony
Village Joint Venture, several other interests in the
property have emerged, including Home Federal Savings
(now Key Bank) and Craig Platt. In fact most of the
property once owned by Harmony Village Joint Venture has
been sold off. I also understand there is an agreement
between these parties regarding any reimbursement and how
it is to be distributed. In this area, I need your
guidance as to the correct party to reimburse. If you
could verify Mr. Emo's claim to this reimbursement, I
will initiate the payments.
PO BOX 18
CALIMESA, CA 92320
(909) 421-8443
September 30, 1993
Matt J. Baker
City of Fort Collins
Engineering Department
281 N. College Avenue
P.O. Box 580
Fort Collins, CO 80522-0580
(303) 221-6605
*HAND DELIVERED
Re: Oversizing Regency Dr. & Seneca St. at Belair P.U.D.
Dear Matt,
Thank you for your help the other day concerning these street
oversizing reimbursements. We appreciate your willingness to
work with us and waive the time limits on applying for these
reimbursements in view of the foreclosure and other difficulties
involved.
Enclosed please find a summary and breakdown of the oversizing
work I performed at Belair and the corresponding evidence.
If you have an questions, please give me a call @ 800 477-9814.
ZB Schubert -
GENERAL CONTRACTORS 0 BUILDING YOU EQUITY SINCE'77 —L'_ No aaonn
PO BOX 18
CALIMESA, CA 92320
(800) 477-9814
October 18, 1993
Matt J. Baker
City of Fort Collins
Engineering Department
281 N. College Avenue
P.O. Box 580
Fort Collins, CO 80522-0580
(303) 221-6605
*HAND DELIVERED
Re: Oversizing Reimbursement for Shields Street at Pineview.
Dear Matt,
Enclosed please find my summary, breakdown, and supporting
evidence for the oversizing of Shields Street performed by
Bob Peterson at Pineview P.U.D.
I've put together the best supporting evidence available,
including a Pineview contractors payment voucher, several
invoices, bids and contracts for this type of work from that time
period, and a current bid from Western Mobile, the successor to
Stirling Paving which actually did the work for Bob Peterson.
As I believe you know, our claim to these funds is through our
Judgment against Mr. Peterson, (our former Managing General
Partner), on file with the City Attorney, which as of October 1,
was in excess of $520,000. Please make all reimbursements for
Pineview payable only to:
Harmony Village Joint Venture
c/o M.C. Emo, C.P.A.
556 N. Diamond Bar Blvd., Ste. 307
Diamond Bar, CA 91765
If you have any e ions, please give me a call @ 800 477-9814.
ZB Schubert`