HomeMy WebLinkAboutRIVERSIDE SEVENTH - Filed CS-COMMENT SHEETS - 2008-04-17u
PROJECT
COMMENT SHEET
Citv of Fort Collins
DATE: June 14, 1999 DEPT: ENGINEERING
PROJECT: #11-99 A-Z Party Rental, Type I - LUC
PLANNER: Gen. Troy Jones
ENGINEER: Marc Virata
All comments must be received by: <Date>
❑ No Problems
❑ Problems or Concerns (see below or attached)
General Comments:
A soils report was not received for this development.
A traffic impact analysis was not received for this development. The traffic impact analysis
should address the frequency of truck traffic to and from this site.
This development is required to dedicate an additional 7.5' of right-of-way (for a total half
street width of 57.5') and provide for a 15' utility easement along Riverside Avenue per our
arterial street standard.
Site Plan:
• Please indicate on the plan how an SU-30 vehicle can maneuver on -site to back into the truck
dock (this should not show SU-30 vehicles backing into the driveway from Riverside
Avenue.)
• What is the function of the (assumed) three parking spaces on the northwest corner of the
site? The stall depth appears to be insufficient. A joint access easement appears to be
needed, provided by the property to the north.
Utility Plans:
• Replace all occurrences of "Director of Engineering" with "City Engineer".
• Add "Traffic Engineer" to the signature block approval.
• The patterned colored concrete across the driveway is not allowed. If this affect is desired it
should be relocated outside of public right-of-way. Provide a detail on how the ramps shown
will be incorporated into the new driveway approach detail.
/ (see plans for any additional comments)
�
Date: / /Z� /yL Signature.
PLEASE SEND COPIES [�F'PLAT
OF MARKED REVISIONS: a SITE ❑ NO COMMENTS — SUBMIT MYLARS
10 UTILITY
lY LANDSCAPE
``✓
*40
City of Fort Collins
Current Planning
PROJECT
COMMENT SHEET
DATE: October 19,1999 DEPT: ENGINEERING
PROJECT: #11-99 A-Z Party Rental, Type I - LUC
PLANNER: Gen. Troy Jones
ENGINEER: Marc Virata
All comments must be received by: November 10, 1999
❑ No Problems
E"roblems or Concerns (see below or attached)
General Comments:
• The street dedication and easement dedication No. 2, close properly. Easement No. 1 does
not appear to close, a sketch would be beneficial in determing this as well as its use.
Sketches should be provided for the easement and the right-of-way dedications and originals
given to the City prior to processing. The documents provided are ok, however, please revise
the documents as follows:
For the easement dedication:
• It is understood by the undersigned that, by acceptance of this dedication, the City of
Fort Collins will not accept the duty of maintenance of such easement.
• Change the word "easement" in the third line of the Attorney's Certificate to "deed".
For the right-of-way dedication:
• It is understood by the undersigned that, by acceptance of this dedication, the City of
Fort Collins will not accept the duty of maintenance of such right-of-way until
permanent improvements have been made and accepted by the City.
Utility Plans:
• What type of material is used for the 4" diameter pipe called out?
(see plans for any additional comments)
Date:
PLEASE SE14D COPIES ❑ PLAT
OF MARKED REVISIONS: ,a SITE
I& UTILITY
q LANDSCAPE
❑ NO COMMENTS — SUBMIT MYLARS
REVISION e� 00T2I199
y,g
COMMENT SHEET
DATE: October 19, 1999 TO: Transportation Ping.
PROJECT: #11-99 A-Z Party Rental — Type 1 (LUC)
All comments must be received by Troy Jones no later than the
staff review meeting:
Wednesday, November 10, 1999
No Comment
❑ Problems or Concerns (see below or attached)
Date:
CM HERE IF YOU WISH TO RECEN COPIES OF REVISIONS
-Plat _ site _ Ihawap Repot _ 0&
— UWY — Redline M _UndsW
REVISION
COMMENT SHEET
DATE: December 23,1999
DEPT: ENGINEERING
PROJECT: #11-99 A to Z Party Rental (Type 1— LUC)
PLANNER: Troy Jones
ENGINEER: Marc Virata
All comments must be received by: January 12, 2000
❑ No Problems
0 Problems or Concems (see below or attached)
Comments:
The easement and right-of-way dedication documents need to be provided to begin recordation process.
Please again note the language changes outlined below:
For the easement dedication:
• It is understood by the undersigned that, by acceptance of this dedication, the City of Fort Collins will not accept the duty
of maintenance of such easement.
• Change the word "easement" in the third line of the Attorney's Certificate to "deed".
For the right-of-way dedication:
• It is understood by the undersigned that, by acceptance of this dedication, the City of Fort Collins will not accept the duty
of maintenance of such right-of-way until permanent improvements have been made and accepted by the City.
Date: January 20, 2000 Signature:
PLEASE SEND COPIES OF MARKED REVISION
0 Plat 0 Site 0 Utility 0 Landscape ❑ Drainage Report 0 NO COMMENTS -SUBMIT MYLARS