HomeMy WebLinkAboutOAKRIDGE BLOCK ONE PUD - Filed GC-GENERAL CORRESPONDENCE - 2005-05-03Commu `v Planning and Environmental -vices
Fngineering Department
City of Fort Collins
September 3, 1993
The Neenan Company
Jim Mattern
2290 East Prospect Road
Fort Collins, CO 80525
Re: Oakridge Block 1
Dear Mr. Mattern:
The intent of this letter is to inform you that the public improvement on the City right-
of-way to include asphalt paving only has been inspected and initially accepted by the
City of Fort Collins pending the normal contractors warranty period with the exception
of the punch list items listed below.
Please be informed that this letter of acceptance does not relieve the developer or the
contractors of their responsibilities for the repair of any damage that may occur as a
result of the building construction.
Punch List Items
1. Repair top lift on Haxton Drive at the crosspan at Oakridge Drive.
2. Adjust manhole #A-3. (To high on south edge).
If you have any questions, please call me at 222-1135.
Sincerely,
Todd Juergens
Engineering Inspector
2ti1 \orth College Avenue • ('.C). Boy -,W • Fort Collin,, CO
I
July 15, 1993
Kerri Ashbeck
Civil Engineer One
City of Fort Collins
P. O. Box 580
Fort Collins, CO 80522
Dear Kerrie:
Thank you for your help regarding the issue of the existing cottonwood trees at the
intersection of the new Haxton Drive (to be completed the summer of 1993) and South
Lemay Avenue.
As per our discussion on Monday, July 12, 1993, at the jobsite, we (The Neenan
Company) are proceeding with the removal of the two cottonwoods located in the right
of way of Haxton Drive. We will not be removing the first cottonwood directly north of
the right of way (approximately 10 feet) of Haxton Drive.
The radius for the flowline from Haxton Drive to Lemay Avenue, on both sides of
Haxton, will be 21) feet as per our discussion.
Enclosed please find an example of the detached walk detail we will be using at Haxton
Drive and Lemay Avenue to avoid any damage to the cottonwood tree north of Haxton
Drive.
If you would like to review this matter further, please call. Thank you.
Sincerely,
H. Robert Hosanna
Project Architect
HRH/saa
Enclosure
cc: John Barberio - TNC
Tom Van Horn - TNC
Stuart McMillan - Everitt Companies
Tim Buchannan, City Forester
Commu- v Planning and Environmental -vices
Engineering Department
City of Fort Collins
July 7, 1993
Mr. Andy Krill
Schmidt Earth Builders Inc.
621 Sherry Drive
Fort Collins, CO 80524
RE: Reconstruction of Storm Sewer Inlet at Oakridge Block Tla
1 ,r ir;_
Dear Andy:
This letter, as per your request in our conversation on June 30, 1993, is to inform you
in writing as to the repairs required to the existing 4' curb inlet on Lemay Avenue.
Due to the amount of structural damage that occurred to the east wall of the box
structure while removing the existing 30" x 19" HERCP and installing the new 15" ADS
you will be required to structurally rebuild that wall. This includes dowelling into the
remaining walls and floor in a manner sufficient to replace the reinforcing steel to the
same integrity as that existing in the structure. The walls shall be formed prior to re -
pouring. You will also be required to rework the invert in the existing floor so it will
drain to the 15" ADS outlet.
If you have any questions or comments, please call me at 221-6605 or 222-1135.
Sincerely,
Todd Juergens
Engineering Construction Inspector
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-060,