DEVELOPMENT CONSTRUCTION PERMIT
Permit Number: 01-23 Issuance Date:
Project Name: Harmony Village P.U.D. Lot 9
Project A.K.A.: Harmony Village Office Park
Project Location: West of Timberline Road, South of Harmony Road on
Wilmington Drive
Permittee: Richard K. Johnson —Peace River Company & Larry B. Wilson
City and developer contacts: See attached Exhibit A for names and phone
numbers of all contact persons for this project.
Fees: Permit Application Fee (paid at the time of application) $300.00 paid
Construction Inspection Fee (paid prior to issuance of this permit) $ 2918.00
Total $2918.00
Development Bond or other approved security:
Amount of security deposited with the City to guarantee the completion of all public
improvements to be constructed as shown on the approved plans for the
development. $55,776.40
Form of security deposited with the City
Wells Fargo Letter of credit # NZS401186
PERFORMANCE REQUIREMENTS OF THIS PERMIT:
1. The Permittee shall be responsible to require their Project Engineer to incorporate into
all design drawings and specifications the certification of all materials testing by an
Engineer. The Permittee shall have an Engineer prepare revised design drawings and
secure City approval for all revisions to the Utility Plans and related documents. The
Permittee shall have an Engineer represent, as required by the City in the Development
1 'rn i h t nll ,r rrnm. • I'(l B<t 7K(� • Fnrt Collin. C0 80522-0580 • (970) 221-6605 • F.AX (97W 221-6378
��',v �\ Acgov.com
Agreement, that the improvements are constructed in conformance with the approved
Utility Plans and the standards and specifications of the City. The Permittee shall provide
as -constructed plans prepared by an Engineer prior to the City's acceptance of the
constructed public improvements. (All references above to the terms "Project Engineer
and Engineer shall mean a Professional Engineer licensed in Colorado.)
2. All contractors. who perform work on this project must be bonded and licensed in
conformance with City requirements.
3. Construction time restrictions: Work hours 7:00 a.m. to 6:30 p.m.
4. The applicant understands that additional permits maybe required for this development
project and the applicant shall secure those permits directly from the issuing departments.
5. This permit, along with a complete set of all approved plans and documents for this
project (utility plans, site plan, landscape plan, development agreement, soils report,
pavement design, traffic study, drainage report, plat easements and any other official
documents), shall be kept on the development site available for use by City staff doing
inspections.
6. Permit Expiration (in accordance with Section 29-12 of the Transitional Land Use
Regulations or Section 2.6.3(K) of the Land Use Code, whichever is applicable):
a. If construction has not begun within sixty (60) days from the date of issuance of
this permit, this permit shall expire and the applicant will forfeit the permit fee paid
for this permit, whereupon the applicant must repay a new permit fee.
b. In addition, this permit shall expire one year from the date of issuance. The
applicant may apply for an extension by reapplication at least two weeks prior to the
expiration date. Such application shall contain information sufficient to justify the
granting of the extension. An extension may be granted for up to six months.
7. Building permits and certificates of occupancy will only be issued when all conditions
contained in the Development Agreement and Sections 3.3.2(C) and (D) of the Land Use
Code or Sections 29-678 and 29-679 of the Transitional Land Use Regulations, whichever
is applicable, are met. If the Development Agreement does not specify times for
completion of public improvements, or if there is no Development Agreement, then the
improvement requirements specified in Section 24-95 of the City Code shall apply, which
provides that construction of all improvements shall be required prior to the time of
issuance of the first building permit.
8. Acceptance by the City of the public improvements shall be after (1) final inspection
has been conducted by the City; (2) punch list items from the final inspection are
completed and accepted by the City; and (3) required certifications from the licensed
professional engineer that improvements are completed to City standards, specifications
and approved Utility Plans, and the as -constructed plans have been received and accepted
by the City.
9. The warranty on street improvements is for five (5) years from the date of acceptance
by the City of the completed improvements, in accordance with Sections 3 3 -13 and 22
9-14
of the Transitional Land Use Regulations and/or Sections 2.2.3(C)(3)(g), 1 ( )( ), and
3.3.2(C) of the Land Use Code, as applicable.
10. The City Erosion Control Inspector must be notified at least twenty-four (24) hours
prior to any planned construction on this project. All required perimeter silt fencing and
other erosion/sediment control best management practices (BMPs) that can be installed
prior to construction must be in place and inspected by the City Erosion Control Inspector
before any land disturbing activity begins.
11. No work (including grading) shall be started in State Highway right-of-way until a
permit is issued by the Colorado Department of Transportation to allow such work to begin.
12. Other conditions: None
Permittee acknowledgment signature:
By signing this permit I acknowledges that I am acting
with
the having legal knowledge,
consent
int, and
authority of the owners of the property (including all owners
rest
in the real property, as defined in Section 1-2 of the City Code; and including common areas
legally connected to or associated with the property which is the subject of this application)
without whose consent and authority the requested action could not lawfully be accomplished.
Pursuant to said authority, I hereby permit City officials to enter upon the property for purposes
of inspection and, if necessary, to enter upon such property to perform work required of the
applicant if the applicant were to fail to perform the required work. I also acknowledge that I
have read this permit document with all its requirements and conditions, and I agree to all
of the terms and conditions so stated in this permit.
Applicant/Project Managers Signature: 2 1Z L°C`
Date: _
Approval for issuance:
v
City Engineer pr va1:
Date: S_ 3 2^
(Permit. I suance Date)