HomeMy WebLinkAboutBELLAVISTA PDP - Filed CS-COMMENT SHEETS - 2004-12-29PROJECT
COMMENT SHEET
City of Fort Co (fins
MM�M=
Current Planninu
DATE: N,wember 28, 2001 TO: Traffic Operation
01
PROJECT: #45-01A Bella Vista PDP - Type I (LUC)
All comments must be received by Steve Olt no later than the staff
review meeting:
December 26, 2001
l� Note- Please identify your redlines for future reference
W-jam:=Te;lfr-1a.Dr-N�l'�-T� 1'�G ✓4--`^'
7-IS.
�
RECEIVED
rURRENT PLANNING
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site _Drainage Report _Other
_Utility —Redline Utility _Landscape
City of Fort Collins
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals). (It
appears that a straight-line grade from the crown of Horsetooth Road to the flowline is not
being provided as shown on the grading plan, cross -sections will help confirm or deny this.)
36
Show centerline and flowline profiles on Horsetooth Road.
37
Provide the bearing and distance for the flowline on the plan view portion of the plan and
profile sheet for Horsetooth Road.
38
15' of utility easement is required along Horsetooth per LCUASS. An approved variance
request is required to deviate from this. A variance request should be submitted to
Engineering and will require approval from all the utilities in order to reduce the utility
easement down to 9'. In addition, 9' of utility easement should be provided along Stanford
Road. Again, a variance request should be submitted to Engineering and will require
approval from all the utilities in order to eliminate this easement.
39
Show 150' past the limits of construction (vertically and horizontally) to show how proposed
improvements tie into existing. (Plan and profile street views, as well as street striping.) (per
LCUASS Page E4-6)
40
Can the striping for the bikelane continue further east to tie into the existing bikelane?
41
Per LCUASS in Section 16.6.4, the maximum length of a crosswalk without a pedestrian
refuge area is 56'. This distance is being exceeded on Stanford Drive and Horsetooth
Road. Transportation Services has agreed that pedestrian refuge on Stanford will not be
required. As previously mentioned, a ped refuge should be looked at across Horsetooth in
between the right turn lane and the through lanes.
60
Because of the aforementioned need for the right -turn lane, eliminating the offset through the intersection, and the constraint of the existing storm drainage
improvements, it is understood that the hike lane design for westbound Horsetooth may have to he compromised. A reduced hike lane width of 6' fincluding
gutter) with a continuous concrete pour should be looked at as one potential compromise. It may also he necessary for the bike lane to stop short of the
intersection to accommodate the right turn lane. An additional option would be to look at widening the sidewalk and create a combined hikelped area
behind the curb if the bikelane cannot be accomplished.
62
Add the following note as reference wherever patching is shown on the plans: Limits of street repair are approximate. Final limits to he determined in the
field by the City Engineering Inspector. All repairs to be in accordance with City Street repair standards.
Page 3
urban design, inc.
(original comment). General note 1(C)(ii) - B&B's would not be allowed. Such a use is a
use that is conducted in a private house, not in a condo building.
Applicant Response:
a) The term Live/Work has been dropped.
b) The mea:wrement of "contextual height" at this PDP is in feet — and considers
"perceived height" - per the Code Interpretation by the Planning Director. While
the five story buildings in the revised submittal are limited to 65' (the height of the
six story Aarriott) the perceived height is somewhat less due to the extensive
use of pitched roofs on the proposed buildings. A six story building on this site
could be perceived to be of less height than the Marriott, even if the actual
maximum height in feet were greater than 65'.
c) Food sere ice is now limited by the LUC definition of Convenience Retail, and
accessory food preparation areas as commonly found in Convenience Retail
uses.
d) Condominium units including B&Bs may include more than 3 bedrooms.
The following comments were expressed at Staff Review on February 20, 2002:
Engineering:
1. The East Horsetooth Road design is still of concern. A westbound right -turn lane is
needed. It is warranted based on City street standards.
2. The striping as shown on East Horsetooth Road is unsafe.
3. The center left -turn lane is unneeded.
4. There are issues with the cross sections on East Horsetooth Road. They are not to
City standards.
5. Dedicate 57.5' of street right-of-way all the way to the east property line.
6. Flowlines need to be on the outside of the proposed bulb -outs on Stanford Road.
7. The 3 variance requests from Northern Engineering are still being reviewed.
8. There should be an emergency access easement on the surface parking only and
this should Ibe noted on the subdivision plat.
Stormwater:
Storm water from this site will have to go into Tract D of Cove Island, to the south.
A storm drainage easement may be needed from them.
The proposed 12" storm sewer from the parking area needs to be a 15" pipe.
The storm sewer in East Horsetooth Road needs to be out from under the curb &
gutter.
4. There are lots of tree and storm sewer conflicts.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
Co����a o 0
urban design, inc.
Transportation Planning:
1. The off -site sidewalk along the east side of Stanford Road, going to the north, is
needed. This proposal fails the Pedestrian Level of Service portion of the TIS
without it.
2. The proposed mid -block pedestrian crossing on Stanford Road, on the curve, is not
in a good location for safety reasons.
Water/Wastewater:
1. Water/Wastewater is still reviewing the plans. A meeting with the applicant &
developer is needed.
Applicant response:
The above comments were resolved at our meeting of June 10rh, and/or with the
revised PDP and utility plans.
Planning:
1. The proposed small food service uses, Item iii) under Accessory Uses in the
General Notes, are of concern. If there are several very small users (up to 1,500
square feet in size), as staff and the developer have previously discussed, then
these food services could be considered to be accessory uses. However, if a single
restaurant were to occupy the bulk of the defined food service space (up to 3,600
square feet as shown on the Site Plan) then there would be a problem associated
with the list of permitted uses in the MMN District. Restaurants are not a permitted
use in this district.
2. The proposed live/work office uses, Item ii) under Accessory Uses in the General
Notes, is a good idea; however, offices (per say) are listed as a Type II, Planning &
Zoning Board review use in the MMN District. What assurance is there that the
office users will not be separate from residents?
3. While reviewing the Shadow Analysis Plan and Streetscape & Building Elevations
Plans against the criteria set forth in Section 3.5.1(G) Building Height Review of the
LUC, several comments have arisen:
a. Regarding Views, are there still desirable views of the foothills from the
residential areas north and south of East Horsetooth Road that will be
affected by this development? Are there views of Warren Lake from
properties north of East Horsetooth Road that will be affected? Section
3.5.1(G)(1)(b)2 of the LUC requires that a visual analysis of views be
submitted for review.
b. There would appear to be several areas of concern regarding Light and
Shadow on adjacent properties, mostly at the 9:00 a.m. and 3:00 p.m. times
as shown on the Shadow Analysis Plan. Most significant is the potential
affects on buildings and parking lots to the west, across Stanford Road.
c. Regarding Neighborhood Scale, the City still has some "contextual' concerns
regarding this issue. Understanding the "Contextual Height' definition in
Section 3.8.17(A)(3) of the LUC, there is still some discussion needed about
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
o
urban design, inc.
where this site is situated relative to the taller buildings (such as the Marriott
Hotel) in the area. How tall. in feet, is the hotel and is one building in excess
of 3 stories in height in a larger surrounding area sufficient to justify 4
buildings that exceed the maximum allowable height in the proposed zoning
district for this site?
d. Typically, elevations for all 4 sides of buildings should be submitted. What do
the building ends look like?
Applicant response:
1) Food Service uses are now limited to the LUC definition of Convenience Retail, and
limited food preparation areas -as an accessory use -as commonly found in many
existing convenience retail stores.
2) The term Live/work has been eliminated, and limited to Home Occupations with the
/eve/ of flexibility allowed by condominium ownership. The enforcement of home
occupation u:sers not being separate from residents will be no different here than at
other locations in Fort Collins.
3) Additional bu�Vding elevations, view information, and shadow analysis information are
included in Vaught"Frye's revised plans.
Additional information is also attached for Staff consideration, including.
Alternative building elevations indicating the Applicants' preferred approach to a
mix of 4 and 6 story buildings (averaging 65' in height) as opposed to the
proposed plan - that has resulted from the Planning Director's interpretation that
contextual height is measured in feet - including all buildings at 5 stories (65'
maximum) in height.
Three-dimensional views comparing the actual and "perceived" heights of the
Marriott and proposed Bella Vista buildings.
Additional neighborhood context/architectural compatibility information will be
forthcoming.
Sincerely,
Eldon Ward
Cityscape Urban Design, Inc.
cc: Chuck McNeal
Javier Martinez Campos
Frank Vaught
Daryl Sigler
Matt Deliclh
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
Project Comments Sheet
6it of tl)m ort (tritin Selected Departments
Department: Engineering
Date: August 16, 2002
Project: BIELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
August 21, 2002
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
102 /
The site plan shows some sort of access ramp across one of the proposed bump outs"
along Stanford Drive. This is not reflected on the utility drawings.
�0
ove General Note #4 on the site plan.
Topic: Grading
45
Offsite grad ng and stru ion is showp cc ring alon�hern b da of the site.
A letter of i tent from the pr perty ow er not plbjecting-tb the( ffsde work is req fired to be
Sul � to any publi hepririg for theCroject:
Topic: Plat
46
The Developmentyeed5 to dedicate an access ease nt along tanford Drive to ensure e side alk proposed is
in an access e�ment. Additional right-of-wa s not necessar .
(2/20) It ppears that add tional access e� ein
long S anfor Drive (and H setooth Road)ecessary to
ensure hat all ofthe nroo sed sidewatk'is in easement.
66
A minimum of 57.5' of half street right-of-way is required to be dedicated along the entire
length of the property with a consistent utility easement width, in conformance with
LCUASS. It is understood that 9' instead of the 15' of necessary utility easement is
Signature Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ Site Drainage Report Other_
Utility _ Redline Utility- Landscape
Page 1
being proposed behind the right-of-way; when all the design and utility issues are
resolved along Horsetooth, the variance request for reduction in utility easement width
will be routed to the utilities for approval.
75
There may be a benefit in designating on the plat that the emergency access easement is
for the "surface level" only. There may be issues from a title company on how the
emergency access easement is represented as going through a building envelope.
Topic: Sidewalk
99
The grading plan appears to show that inlets with straw bales will be in close proximity
or perhaps even overlapping with the street sidewalks. These straw bales need to be
outside of the sidewalk section. Perhaps a different erosion control measure can be
used if the straw bales are encroaching into the sidewalk for a period of time.
Topic: Street Design
32
Directional ramps are required on new construction in accordance with LCUASS. (Standard Drawing 164D:
Provide the detail on the plan set.
(2/20) The response from the applicant stated that this could not be accommodated due to existing constraints.
The design engineer should provide documentation on why this cannot be accomplished. Note that because of
the right turn discussion, any previous limitations due to existing constraints may no longer be applicable.
34
A right -turn lane for westbound Horsetooth onto northbound Stanford still should be designed and constructed.
'['here is a community wide benefit in the construction of the right turn lane, thus this is eligible for Street
Oversizing reimbursement. The design of the right -turn lane should look at providing pedestrian refuge
between the right -turn and through lane, especially since the width of Horsetooth would require a ped refuge
under LCUASS.
(2/20) The issue of the right turn lane was discussed at the City's 2/14 Transportation Coordination Meeting. It
was viewed that the submitted justification for not designing the right turn lane was not compelling and that a
I ight turn lane could be designed into the project. Please note that any written documentation regarding the
designing of the right -turn lane should be provided by the design engineer (a licensed professional engineer.)
35
Provide cross-sectionson Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals). (It appears that a straight-
line grade from the crown of Horsetooth Road to the flowline is not being provided as shown on the grading
plan, cross -sections will help confirm or deny this.)
(2/20) The cross section sheets need to have the centerline elevations labeled, the curb and gutter
section should be distinguishable from the asphalt section, and the right-of-way should also be
shown.
36
Show centerline and flowline profiles on Horsetooth Road.
Page 2
(2/20) Can the grid lines or scale be modified in order to allow for every XX+00 stationing to be on a grid line?
Only every 3rd XX+00 stationing is on a grid line.
37
Provide the bearing and distance for the flowline on the plan view portion of the plan and profile sheet for
Horsetooth Road.
(2/20) This information isn't shown east of the driveway and only bearing (no distance) is being shown west of
the driveway.
60
Because of the aforementioned need for the right -turn lane, eliminating the offset through the intersection, and the
constraint of the existing storm drainage improvements, it is understood that the bike lane design for westbound Horsetooth
may have to be compromised. A reduced bike lane width of 6' (including gutter) with a continuous concrete pour should
be looked at as one poteraial compromise. It may also be necessary for the bike lane to stop short of the intersection to
accommodate the right -turn lane. An additional option would be to look at widening the sidewalk and create a combined
bike/ped area behind the curb if the bikelane cannot be accomplished.
(2/20) With the right turn lane still being an outstanding issue, the proposed design of the westbound bike lane will not be
commented on by Engineering at this time. It is still considered ideal that the bike lane is continuous to the intersection.
62
Add the following note as, reference wherever patching is shown on the plans: Limits of street repair are approximate. Final
limits to be determined in the field by the City Engineering Inspector. All repairs to be in accordance with City Street
repair standards.
(2/20) Ensure that this note is referenced to the work along Stanford as well.
67
The "bulb -outs" proposed on Stanford Drive may be allowed only if the gutter is
redesigned to go around and along the bulb outs, not through them. There are
maintenance concerns with the current proposal due to dirt and debris collecting
between the bulb outs and the flowline.
68
[12] The vertical curve shown is too short in length for the street classification of
Horsetooth. A K value of 110 is required, 60 is shown.
69
[13] A vertical curve is needed for the Horsetooth proposed flowline as it approaches the
existing storm lines. A grade break is shown with a 0.6% grade going to a 1.69% grade.
70
[13] Fix the vertical elevation labeling on this sheet for the profile view.
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the variance to
Page 3
reduce the utility easement along Horsetooth were all viewed favorably upon by the City
Engineer. Final approval of these variance requests will occur with completion of the
designs for Horsetooth and Stanford that are acceptable to the City and the utilities.
72
[13] The 2.55% shown on this sheet appears to actually calculate to 4.2% with the
elevations and stationing shown.
77
The Traffic Engineer has noted that the center turn lane should be continuous from the
intersection to the Cove Island development and continuing east. The Traffic Engineer
notes that a 3/4 movement to allow left turns into the site could be designed (with painted
medians) in conjunction with the porkchop island to facilitate right turns out of this driveway.
78
The cross section sheets show the additional road width to be 4% or even greater.
Because a saw cut is being shown to the centerline for most of Horsetooth, a continuous
straight line grade needs to be maintained along the entire north half of the roadway
where the sawcut is shown. For the additional width between stations 10+00 and
11+00, (where the roadway is not being sawcut to centerline), this new portion of
roadway is limited to 3%.
79
A grade break is shown on Sheet [12] that exceeds .40%. A vertical curve would be
required based on this design.
98
Provide spot elevations at the Horsetooth and Stanford intersection in accordance with
LCUASS Standard Detail 7-32B.
100
The submitted "Street Cross Sections" from the site planner is not appropriate to be
submitted as a document along with the site and landscape development plan
documents. Street cross sections are to be shown on the utility plan set and will be
established based upon an approved design for the roadway(s).
101
Angle points along the flowine appear to be shown along Horsetooth, please revise and
use curves as shown in LCUASS 7.4.1.
104
It appears that redirects are too abrupt on the street striping plan. See traffic comments
regarding this.
Topic: Utility plans
76
The drawings regarding the storm system across Horsetooth originally approved by the City
showed an inlet being tied to the easternmost pipe, the submitted plans show that the inlet is
tied to the westernmost pipe.
Page 4
Project Comments Sheet
Selected Departments
Department: Transportation Planning
Date: August 21, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
August 21, 2002
Note - Please identify your redlines for future reference
Issue Contact: Mark Jackson
Topic: General
106
1 understand this is not my call. That being said, I have serious reservations about the mid -block crossing shown on
Stanford Rd. This is in my opinion a terrible end -around way of technically meeting Pedestrian LOS, rather than doing
A correctly.
107
Will a ramp cut be made on the west end of Stanford Rd. at the new mid -block crossing? It is unclear from the site &
utility plan. Please provide ramp cut.
108
Can we provide appropriate signage warning motorists of the mid -block pedestrian crossing?
Signature
a/Z 1 /UZ
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat NC, Site Drainage Report Other
o Utility _ Redline Utility Landscape
Page 1
Pit
e. Project Comments Sheet
Selected Departments
Citv of Port Collins
Department: Water Wastewater
Date: August 21, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meetiing:
August 21, 2002
Mote - Please identify your redlines for future reference
Issue Contact: ,Jeff Hill
Topic: General
109
Provide steel casing around proposed water main at multiple storm sewer crossing. Include
detail on detail sheet.
110
No permanent structures are allowed in sanitary sewer easement (I.e. retaining walls,
headwalls, etc.).
112
Are 1.5' water services adequate for these size of buildings? Provide flow demand
calculations for our review. Provide separate water and sewer services for residential and
commercial uses.
113
Provide grease traps for all food preparation facilities.
114
Provide concrete encasement of all sewers which cross above or within 18-inches vertically
of water lines. Clearly define this on plans. Show all water, storm and sanitary sewer
crossings in all profile views.
115
Maintain 4 feet of separation between outside wall of meter pit and all permanent structures.
116
It is unacceptable to have multiple underground storm sewers cross at a sanitary sewer
crossing.
Topic: Landscaping
48
Repeat Comment: Coordinate landscape design with the civil design and provide the
required land scape,futility separation distances. Correctly show all existing and proposed
Signature Date
CHECK ]HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ Site Drainage Report Other_
Utilitv _ Redline Utility Landscape
Page I
water/sewer mains and services on the landscape plans. With the tight constraints on this
site we would be willing to relax our separation requirements, however we will not allow
landscaping to be placed directly on top of our facilitates. Please consider the placement of
shrubs and trees to minimize the impact to our facilities.
Topic: Utility plans,
54
Repeat Comment: Maintain 18-inches of vertical separation between all water, sanitary
sewer and storm sewer crossings.
92
Repeat Comment: Place all curb stops and meter pits adjacent to the main when at all
possible. Curb stops must be located within a utility easement. Water and sewer services
must be perpendicular to the main when possible.
94
Repeat Comment: Clearly define all water main joint deflection (Le. Vertical, Horizontal,
Beginning, ending, etc.). Is entire length of proposed 8-inch water main to be lowered?
See site, landscape and utility plans for other comments.
Page 2
STAFF PROJECT REVIEW
CIIF ul FortCollins
STANFORD DEVELOPMENT, LLC Date: 1/8/2002
c/o Cityscape Urban Design - Eldon Ward
3555 Stanford Road, Suite 105
Fort Collins, CO. 80525
Staff has reviewed your submittal for BELLA VISTA PDP, TYPE I (LUC), and we
offer the following comments:
Department: Current Planning
Issue Contact: Steve Olt
Topic: Street Design
63
Len Hilderbrand of Excel Energy (PSCO) offered the following comments:
1. PSCO has a 2" MW existing gas main along the west boundary of the project
and a 4" FB gas main existing along the south edge of the property. Both gas
mains lay in the street right-of-way. No trees may be planted within 4' of gas
lines.
2. The plans show a 12" storm sewer proposed in areas of PSCO's gas lines.
Any relocation of existing gas lines would be at the developer's expense.
3. Gas meters would be clustered together @ the ends of buildings, with 2 gas
service lines per building.
64
Eric Bracke of Traffic Operations offered the following comments:
1. The proposed raised median is insufficient. A median should be constructed
to "match" the west leg.
2. The westbound right -turn should be included @ East Horsetooth Road and
Stanford Road. This developer is not generating the need, however, the right -
turn lane should be included in the design.
3. The westbound left -turn lane @ East Horsetooth Road and Landings Drive
should be 12' wide, not 11'. The thru lanes @ 11' wide are OK.
Please contact Eric, at 224-6062, if you have questions about his comments.
Page 1
Project Comments Sheet
Selected Departments
Department: Stormwater Utility
Date: August 27, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
August 21, 2002
.Note - Please identify your redlines for future reference
Issue Contact: Basil Harridan
Topic: Construction Easements
80
The proposed 24" RCP across Horsetooth Rd. will necessitate the construction of a headwall and part of the culvert on
Tract D of The Landings 1st Filing. Prior to construction on this Tract owned by that HOA the contractor should make
sure that the HOA is notified and that the area will be properly restored. Even though this area is in an existing
drainage easement, the: landings 1st Filing HOA which maintains this area should ensure that the area is put back to an
acceptable level, equal or better than before construction.
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the warren Lake Ditch company must sign off on
these plans.
Topic: Easements
129
The drainage pan proposed on the north end of the site extends into neighboring property. Please provide a drainage
easement for that pan.
Topic: Erosion Control
117
Second Review
February 4, 2002
The plan still indicates straw bales on concrete and/or asphalt. This doesn't work, they float. Please correct.
Your report/calculations call for mulching in certain areas of the project. Please spell out with a note on the plan what
areas are to be seeded/mulched.
Third Review
August 22, 2002
Same com as last
ZL b
Signatu / Date
HECK: HERE IF YOU WISH TO RECEIV COPIES OF REVISIONS
—_L, "` rama Report Other_
tility i Rednne Utility dscape
Page I
Topic: Grading Plans
128
The larger scale grading plans are a bit disjointed and hard to follow while the smaller scale grading plans are too small
to read. Please chose a scale that is more usable.
Please extend the grading plans to cover the area to the north of the site and tie into the existing site to the north along
Stanford Rd.
It seems that a portion of the driveway to the east of Building A could be draining unto the building, please adjust.
The high point in the east entrance off of Horsetooth seems to be shallow and flows from Horsetooth Rd could enter the
site.
The east pond grading plans uses both absolute elevations and relative elevations to a 100.00 arbitrary datum. Please
remove relative elevations from the plans.
Topic: Line G capacity
135
Line G has several locations where the water surface elevations is very close to or exceeds the ground floor elevation.
Please consider the use of larger diameter pipe to eliminate such a condition.
Topic: Sewer Line Crossing
134
Line G seems to have a sewer line crossing that is below the required 18" clearance. Please check with Wastewater as
to what minimum separation would be acceptable to them.
Topic: Storm Line Across Horsetooth
118
It seems that the proposed storm line across Horsetooth Rd could impact the existing Evergreen tree on the south side
of Horsetooth. Please show the location of that tree compared to the proposed line on the utility plan and clarify
whether that tree is to be preserved.
Topic: Storm Line Alignment
132
It seems that the storm line going from the east water quality pond to the west one is shown to be under building
envelopes. Please make sure all storm sewers are outside of building envelopes.
Topic: Water Line Crossing
133
Please show the crossing of the water line on the sanitary sewer profile of Storm Line E.
Topic: Water Quality Pond
120
It seems that the retaining walls of the water quality pond overlap an existing sewer line. Those concrete walls are
considered permanent structures and thus would not be allowed to straddle the existing sanitary line and easement.
Please provide a concrete reinforcing detal with all the appropriate dimensions for the water quality outlet boxes.
Page 2
Project Comments Sheet
Selected Departments
Department: Engineering
Date: August 28, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
August 21, 2002
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
119
The bump -outs along Stanford need to either be extended south of the southern
driveway, or reduced to fall short of the southern driveway. The present configuration is
viewed as a concern by Transportation with regards to the right turn movement into the
southern driveway and its interaction with the bikelane.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the site. A letter of intent
from the property owner not objecting to the offsite work is required to be submitted prior to any public hearing
for the project.
[8/211 An unsigned Graat of Easement document was received. Per Stormwater, the document in concept is not
acceptable. The necessary easement needs to be dedicated to the City using our standard City deed of
dedication language. Also, because the Grant of Easement was unsigned, this does not serve as a letter of
intent, which is required prior to any hearing for the project.
122
The contours and spot elevations on the overall grading plan are difficult to read and
should be shown better. The information also will not "scan" well.
123
There is an area along Stanford north of the site that is not shown on the overall or
detailed grading plan.
Dat
HECK HEWIT YOU WISH TO RECEIVE COPIES OF REVISIONS
/Plat _/ Site Drainage Report Other
—T Utility _Redline Utility ✓Landscape
Page 1
Topic: Plat
46
The Development needs to dedicate an access easement along Stanford Drive to ensure the sidewalk proposed is
in an access easement. Additional right-of-way is not necessary.
(2/20) It appears that additional access easement along Stanford Drive (and Horsetooth Road) is necessary to
ensure that all of the proposed sidewalk is in easement.
[8/21] Replace all instances of "sidewalk easement" with "access easement".
66
A minimum of 57.5' of half street right-of-way is required to be dedicated along the entire
length of the property with a consistent utility easement width, in conformance with
LCUASS. It is understood that 9' instead of the 15' of necessary utility easement is
being proposed behind the right-of-way; when all the design and utility issues are
resolved along Horsetooth, the variance request for reduction in utility easement width
will be routed to the utilities for approval.
[8/21] With design issues outstanding and issues regarding retaining wall(s) over
easements still in question, this issue is left as unresolved.
75
There may be a benefit in designating on the plat that the emergency access easement is for the
"surface level" only. There may be issues from a title company on how the emergency access
easement is represented as going through a building envelope.
(8/21 ]
Further discussion with the City Surveyor suggests revising the label as a "surface grade level". An
explanation on the plat may also be of benefit. These are more "suggestions" than requirements, the
intent is to ensure that there are no issues with title or being able to pull a building permit.
127
Building envelopes appear to encroach within easements. Building envelopes need to
be relocated outside of easements.
Topic: Sidewalk
124
The placement of the sidewalk requires a horizontal clearance of 1' and a vertical
clearance of 8' from all fixed objects. It appears that the proposed retaining wall(s) are
of issue with this standard.
Topic: Street Design
32
Directional ramps are required on new construction in accordance with LCUASS. (Standard Drawing 16-4D)
Provide the detail on the plan set.
(2/20) The response from the applicant stated that this could not be accommodated due to existing constraints.
The design engineer should provide documentation on why this cannot be accomplished. Note that because of
the right turn discussion, any previous limitations due to existing constraints may no longer be applicable.
Page 2
[8/21 ] The design engineer cited underground utilities and traffic control devices in the response letter as
justification. Site visits and follow up discussion internal to City Engineering does not share the view that these
are constraints. The "constraints" appear far enough away to allow the placement of directional ramps with no
modifccation to our standard drawings, or slight modification. Please note that since directional ramps are
considered standard, documentation on why this cannot be accomplished needs to be in the form of a variance
request.
34
A right -turn lane for westbound Horsetooth onto northbound Stanford still should be designed and constructed.
There is a community wide benefit in the construction of the right turn lane, thus this is eligible for Street
Oversizing reimbursement. The design of the right -turn lane should look at providing pedestrian refuge
between the right -turn and through lane, especially since the width of Horsetooth would require a ped refuge
under LCUASS.
(2/20) The issue of the right turn lane was discussed at the City's 2/14 Transportation Coordination Meeting. It
was viewed that the submitted justification for not designing the right turn lane was not compelling and that a
right turn lane could be designed into the project. Please note that any written documentation regarding the
designing of the right -turn lane should be provided by the design engineer (a licensed professional engineer.)
[t21 ]
The variance request is currently with Traffic Engineering.
35
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals). (It appears that a straight-
line grade from the crown of Horsetooth Road to the flowline is not being provided as shown on the grading
plan, cross -sections will help confirm or deny this.)
(2/20) The cross section sheets need to have the centerline elevations labeled, the curb and gutter
section should be distinguishable from the asphalt section, and the right-of-way should also be
shown.
9/21 ]
The cross sections need to show the sidewalk, especially with potential issues regarding its
relationship to retaining walls. Because the detail for the inflow curb and gutter with the continuous
pour bikelane is not to standard, the cross slope for the cross sections shown weren't evaluated. In
addition, the cross sections weren't evaluated because the flowline design still does not meet
standards (vertical curve, grade breaks, etc.)
36
Show centerline and flowline profiles on Horsetooth Road.
(2/20) Can the grid lines or scale be modified in order to allow for every XX+00 stationing to be on a grid line?
Only every 3rd XX+00 stationing is on a grid line.
[8/211
The response from the design engineer indicates that this modification is time intensive. In researching, other
plan sets at 30 scale do not have this issue. Please modify the drawings to reflect every XX+00 on a grid line.
While this may be viewed as time consuming from the design engineer's perspective, it results in a more time
consuming review for the review engineer.
Page 3
37
Provide the bearing and distance for the flowline on the plan view portion of the plan and profile sheet for
Horsetooth Road.
(2/20) This information isn't shown east of the driveway and only bearing (no distance) is being shown west of
the driveway.
[8/21)
This information is required on the street design and is not a waived requirement if shown on the street striping
plan.
38
15' of utility easement is required along Horsetooth per LCUASS. An approved variance request is required to
deviate from this. A variance request should be submitted to Engineering and will require approval from all the
utilities in order to reduce the utility easement down to 9'. In addition, 9' of utility easement should be provided
along Stanford Road. Again, a variance request should be submitted to Engineering and will require approval
from all the utilities in order to eliminate this easement.
[8/211 This comment is left as unresolved until all the design issues are worked out and agreed to by the
utilities. It is my understanding that utilities have expressed concern with the placement of their utilities under
retaining walls. This may require additional utility easement width to compensate.
67
The "bulb -outs" proposed on Stanford Drive may be allowed only if the gutter is
redesigned to go around and along the bulb outs, not through them. There are
maintenance concerns with the current proposal due to dirt and debris collecting
between the bulb outs and the flowline.
[8/21 ] The bump outs need to show a flowline design and how it ties into the existing
flowline along Stanford. In addition, cross sections on Stanford (as done with
Horsetooth) should be done in order to verify adequate cross slopes are being
maintained.
68
[12] The vertical curve shown is too short in length for the street classification of
Horsetooth. A K value of 110 is required, 60 is shown.
[8/21] There are vertical curves that still fall short of meeting standards.
69
[13] A vertical curve is needed for the Horsetooth proposed flowline as it approaches the
existing storm lines. A grade break is shown with a 0.6% grade going to a 1.69% grade.
[8/21]
A grade break exceeding .4% is still shown.
Page 4
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the variance to
reduce the utility easement along Horsetooth were all viewed favorably upon by the City
Engineer. Final approval of these variance requests will occur with completion of the
designs for Horsetooth and Stanford that are acceptable to the City and the utilities.
104
It appears that redirects are too abrupt on the street striping plan. See traffic comments
regarding this.
[8/21 ]
The proposed travel lane signage doesn't appear to tie in very well with the existing
signage east of the property.
121
Street patching limits need to be revised as redlined (perpendicular to the direction of
travel as well as to the edge or middle of a lane line.) The patching shown on Stanford
Drive needs to be expanded from how it is currently shown, and may need to expand
further in order to ensure proper cross slopes.
125
Show utility crossings and depth of utilities on the street plan and profile sheets.
126
The detail for the inflow curb and gutter along Horsetooth Road does not have sufficient
depth along the gutter, please revise the detail as shown on the redlines.
131
The "bump -outs" along Stanford are required to be built with vertical curb and gutter in
accordance with LCUASS. Please specify the use of vertical curb, with transitioning to
the existing driveover curb.
Topic: Structural
136
A structural engineer will be required to submit a signed and stamped letter indicating
that the emergency access area (defined by the plat) is designed to support the live and
dead loading of emergency services vehicles. This letter is required prior to the
issuance of a building permit. The structural engineer should coordinate with PFA on
the anticpated vehicles that will be staging in this area and follow up with information
from the manufacturer(s) of the vehicle(s) on the loading specific to each vehicle(s). A
follow up letter stating that the structure was constructed to meet these requirements will
also be required prior to the issuance of a certificate of occupancy. (This will also be
stated in the Development Agreement for the project.)
Topic: Utility plans
140
Page 5
Please see redlines for additional coments/clarifications.
Page 6
STAFF PROJECT REVIEW
Cilv o(Fort Collins
STANFORD DEVELOPMENT, LLC Date: 8/29/2002
c/o Cityscape Urban Design - Eldon Ward
3555 Stanford Road, Suite 105
Fort Collins, CO. 80525
Staff has reviewed your submittal for BELLA VISTA PDP, Type I (LUC), and we
offer the following comments:
ISSUES:
Department: Current Planning
Topic: General
139
Issue Contact: Steve Olt
There has been an increase in the proposed number of residential dwelling units
(excluding any B&B operation), from 70 units to 81 units, since the last plan. The
applicant's response letter does not acknowledge or discuss the reasons for the
increase in the number of dwelling units.
141
The number of proposed parking spaces for the residential uses as shown on
Sheet 2 of the revised PDP Cover Sheet would be sufficient for the mix of 1-,
2-, and 3-bedroom units as indicated in the Land Use Breakdown table.
However, the last or far -right column indicates that there may be more than 3
bedrooms in some units. The "required" 151 spaces as shown does not allow for
any dwelling units with 4 or more bedrooms.
144
The west end of Building C does not meet the "build -to" line requirements in
Sections 3.5.3(B;)(2)(a) & (b) of the Land Use Code. On the Site Plan the building
is shown to be set back 20' to 22' from the Stanford Road right-of-way and it
must be located no more than 15' from the right-of-way of that street. If
possible, how can this building satisfy the criteria for an exception to the build -
to line standard as set forth in Section 3.5.3(B)(2)(d)l of the Code?
Page 1
146
The buildings (A thru D) vary in height from 67' for Building D to 72' for
Building C. This is based on Section 3.8.17(A)(1) - Building Height Measured in
Feet in the City's Land Use Code. Buildings A, B, and D are 5 stories + a loft on
all sides; however, Building C is 5 stories + a loft on the east and north sides but
is "perceived" to be 6 stories + a loft from the south and west (street) sides.
Based on the existing conditions on surrounding properties in the C -
Commercial, E - Employment, MMN - Medium Density Mixed -Use Neighborhood,
and RL - Low Density Residential Districts, staff's position at this time is that
the project does not satisfy the criteria set forth in Section 3.8.17(A)(3) -
Contextual Height in the Land Use Code.
Topic: Plat
137
City staff requested that 6 copies of the subdivision plat be re -submitted for
review. No copies of the plat were received with the July 31, 2002 re -submittal.
Topic: Utility plans
130
Len Hilderbrand of Public Service Company of Colorado (Excel Energy) offered
the following comments:
a. No trees may be planted within 4' of gas lines. Existing gas lines are
located in the street rights -of -way.
b. Public Service Company of Colorado will need to open cut streets (East
Horsetooth Road and Stanford Road) to install gas services to each
building. Permits will be required.
C. Meters will need to be staked at the ends of buildings. The elevations will
need to show areas to meet the requirements for meter stacks.
Topic: zoning
142
As indicated by the Zoning Department, General Note 1)d)ii on the PDP Cover
Sheet (2 of 6) must be eliminated because the language could be construed to
allow a "primary" office use in the development. Home occupations are
Page 2
65
Rick Lee of the Building Department is forwarding a copy of the various codes that
they will be enforcing.
Department: Engineering Issue Contact: Marc Virata
Topic: General
28
Replace "P.U.D." with "P.D.P" on all the documents.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of
the site. A letter of intent from the property owner not objecting to the offsite work is
required to be submitted prior to any public hearing for the project.
Topic: Plat
42
Replace all occurrences of Director of Engineering with City Engineer.
43
The Plat language (Certificate of Dedication and Maintenance and Repair Guarantee
language) has been revised. Please revised as shown (electronic format of the
document is available). Ensure that the "Notice of Other Documents" language is
included in the plat: as well.
44
The Sight Distance Easement Language on the plat has also been revised. Please
revise as shown.
46
The Development needs to dedicate an access easement along Stanford Drive to
ensure the sidewalk proposed is in an access easement. Additional right-of-way is
not necessary.
58
Vacation of City easements on the plat do not require an easement vacation
certificate. However, vacation of exclusive easements outside of the City (20'
communication easement) requires a signature from the telephone company.
59
Horsetooth Road appears confusing with right-of-way on top of city and private
utilities. Please clarify.
Page 2
permitted in the MMN District, which note 1)d)i accounts for, but a "primary"
office use is not (permitted in the District.
143
General Note 1)d)iii on the PDP Cover Sheet (2 of 6) still does not restrict the
type of proposed "food service uses" to accessory uses for the purpose of
providing that service to the residents and tenants of the Bella Vista project.
Anything resembling even a small fast food operation, with the intent to serve
the general public, would be defined as a restaurant use, which is not permitted
in the MMN District.
Department: Engineering Issue Contact: Marc Virata
Topic: Genera/
119
The bump -outs along Stanford need to either be extended south of the
southern driveway, or reduced to fall short of the southern driveway. The
present configuration is viewed as a concern by Transportation with regards to
the right turn movement into the southern driveway and its interaction with the
bikelane.
Topic: Grading
45
Off site grading and construction is shown occurring along the northern
boundary of the site. A letter of intent from the property owner not objecting
to the offsite work is required to be submitted prior to any public hearing for
the project.
[8/21] An unsigned Grant of Easement document was received. Per
Stormwater, the document in concept is not acceptable. The necessary
easement needs to be dedicated to the City using our standard City deed of
dedication language. Also, because the Grant of Easement was unsigned, this
does not serve as a letter of intent, which is required prior to any hearing for
the project.
122
The contours and spot elevations on the overall grading plan are difficult to
read and should be shown better. The information also will not "scan" well.
Page 3
123
There is an area along Stanford north of the site that is not shown on the
overall or detailed'. grading plan.
Topic: Plot
46
The Development needs to dedicate an access easement along Stanford Drive to
ensure the sidewalk proposed is in an access easement. Additional right-of-way
is not necessary.
(2/20) It appears that additional access easement along Stanford Drive (and
Horsetooth Road) is necessary to ensure that all of the proposed sidewalk is in
easement.
[8/21] Replace all instances of "sidewalk easement" with "access easement".
66
A minimum of 57.5' of half street right-of-way is required to be dedicated
along the entire length of the property with a consistent utility easement
width, in conformance with LCUASS. It is understood that 9' instead of the
15' of necessary utility easement is being proposed behind the right-of-way;
when all the design and utility issues are resolved along Horsetooth, the
variance request For reduction in utility easement width will be routed to the
utilities for approval.
[8/21] With design issues outstanding and issues regarding retaining wall(s)
over easements still in question, this issue is left as unresolved.
75
There may be a benefit in designating on the plat that the emergency access
easement is for the "surface level" only. There may be issues from a title
company on how the emergency access easement is represented as going
through a building envelope.
(8/21]
Further discussion with the City Surveyor suggests revising the label as a
"surface grade level". An explanation on the plat may also be of benefit. These
Page 4
are more "suggestions" than requirements, the intent is to ensure that there
are no issues with title or being able to pull a building permit.
127
Building envelopes appear to encroach within easements. Building envelopes
need to be relocated outside of easements.
Topic: Sidewalk
124
The placement of the sidewalk requires a horizontal clearance of 1' and a
vertical clearance; of 8' from all fixed objects. It appears that the proposed
retaining wall(s) are of issue with this standard.
Topic: Street Design
32
Directional ramps are required on new construction in accordance with LCUASS.
(Standard Drawing 16-41)) Provide the detail on the plan set.
(2/20) The response from the applicant stated that this could not be
accommodated due to existing constraints. The design engineer should provide
documentation on why this cannot be accomplished. Note that because of the
right turn discussion, any previous limitations due to existing constraints may no
longer be applicable.
[8/21] The design engineer cited underground utilities and traffic control
devices in the response letter as justification. Site visits and follow up
discussion internal to City Engineering does not share the view that these are
constraints. The "constraints" appear far enough away to allow the placement
of directional ramps with no modification to our standard drawings, or slight
modification. Please note that since directional ramps are considered standard,
documentation on why this cannot be accomplished needs to be in the form of a
variance request.
34
A right -turn lane, for westbound Horsetooth onto northbound Stanford still
should be designed and constructed. There is a community wide benefit in the
construction of the right turn lane, thus this is eligible for Street Oversizing
reimbursement. The design of the right -turn lane should look at providing
Page 5
pedestrian refuge: between the right -turn and through lane, especially since the
width of Horsetooth would require a ped refuge under LCUASS.
(2/20) The issue of the right turn lane was discussed at the City's 2/14
Transportation Coordination Meeting. It was viewed that the submitted
justification for not designing the right turn lane was not compelling and that a
right turn lane could be designed into the project. Please note that any written
documentation regarding the designing of the right -turn lane should be
provided by the design engineer (a licensed professional engineer.)
[8/211
The variance request is currently with Traffic Engineering.
35
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50'
intervals). (It appears that a straight-line grade from the crown of Horsetooth
Road to the flowline is not being provided as shown on the grading plan, cross -
sections will help confirm or deny this.)
(2/20) The cross section sheets need to have the centerline elevations labeled,
the curb and gutter section should be distinguishable from the asphalt section,
and the right-of-way should also be shown.
(8/211
The cross sections need to show the sidewalk, especially with potential issues
regarding its relationship to retaining walls. Because the detail for the inflow
curb and gutter with the continuous pour bikelane is not to standard, the cross
slope for the cross sections shown weren't evaluated. In addition, the cross
sections weren't evaluated because the flowline design still does not meet
standards (vertical curve, grade breaks, etc.)
36
Show centerline and flowline profiles on Horsetooth Road.
(2/20) Can the grid lines or scale be modified in order to allow for every XX+00
stationing to be on a grid line? Only every 3rd XX+00 stationing is on a grid
line.
Page 6
[8/21]
The response from the design engineer indicates that this modification is time
intensive. In researching, other plan sets at 30 scale do not have this issue.
Please modify the: drawings to reflect every XX+00 on a grid line. While this
may be viewed as time consuming from the design engineer's perspective, it
results in a more time consuming review for the review engineer.
37
Provide the bearing and distance for the flowline on the plan view portion of the
plan and profile sheet for Horsetooth Road.
(2/20) This information isn't shown east of the driveway and only bearing (no
distance) is being shown west of the driveway.
[8/21]
This information is required on the street design and is not a waived
requirement if shown on the street striping plan.
38
15' of utility easement is required along Horsetooth per LCUASS. An approved
variance request is required to deviate from this. A variance request should be
submitted to Engineering and will require approval from all the utilities in order
to reduce the utiility easement down to 9'. In addition, 9' of utility easement
should be provided along Stanford Road. Again, a variance request should be
submitted to Engineering and will require approval from all the utilities in order
to eliminate this easement.
(8/21] This comment is left as unresolved until all the design issues are worked
out and agreed to by the utilities. It is my understanding that utilities have
expressed concern with the placement of their utilities under retaining walls.
This may require additional utility easement width to compensate.
67
The "bulb -outs" proposed on Stanford Drive may be allowed only if the gutter is
redesigned to go around and along the bulb outs, not through them. There are
maintenance concerns with the current proposal due to dirt and debris
collecting between the bulb outs and the flowline.
Page 7
[8/21] The bump outs need to show a flowline design and how it ties into the
existing flowline along Stanford. In addition, cross sections on Stanford (as
done with Horsetooth) should be done in order to verify adequate cross slopes
are being maintained.
68
[12] The vertical curve shown is too short in length for the street classification
of Horsetooth. A K value of 110 is required, 60 is shown.
[8/21] There are vertical curves that still fall short of meeting standards.
69
[13] A vertical curve is needed for the Horsetooth proposed flowline as it
approaches the existing storm lines. A grade break is shown with a 0.6% grade
going to a 1.69% grade.
(8/21]
A grade break exceeding .4% is still shown.
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along
Stanford Drive, the variance to reduce the driveway spacing from 660' to 610',
and the variance to reduce the utility easement along Horsetooth were all
viewed favorably upon by the City Engineer. Final approval of these variance
requests will occur with completion of the designs for Horsetooth and Stanford
that are acceptable to the City and the utilities.
104
It appears that redirects are too abrupt on the street striping plan. See
traffic comments regarding this.
[8/21]
The proposed travel lane signage doesn't appear to tie in very well with the
existing signage East of the property.
Page 8
121
Street patching limits need to be revised as redlined (perpendicular to the
direction of travel as well as to the edge or middle of a lane line.) The patching
shown on Stanford Drive needs to be expanded from how it is currently shown,
and may need to expand further in order to ensure proper cross slopes.
125
Show utility crossings and depth of utilities on the street plan and profile
sheets.
126
The detail for the: inflow curb and gutter along Horsetooth Road does not have
sufficient depth along the gutter, please revise the detail as shown on the
redlines.
131
The "bump -outs" along Stanford are required to be built with vertical curb and
gutter in accordance with LCUA55. Please specify the use of vertical curb,
with transitioning to the existing driveover curb.
Topic: structural
136
A structural engineer will be required to submit a signed and stamped letter
indicating that the emergency access area (defined by the plat) is designed to
support the live and dead loading of emergency services vehicles. This letter is
required prior to the issuance of a building permit. The structural engineer
should coordinate: with PFA on the anticipated vehicles that will be staging in
this area and follow up with information from the manufacturer(s) of the
vehicle(s) on the loading specific to each vehicle(s). A follow up letter stating
that the structure was constructed to meet these requirements will also be
required prior to the issuance of a certificate of occupancy. (This will also be
stated in the Development Agreement for the project.)
Topic: Utility plans
140
Please see redlines for additional comments/clarifications.
Page 9
Department: Light & Power
Topic: Landscaping
Issue Contact: Doug Martine
1
Street trees on the landscape plan must be adjusted to provide a minimum of
40 ft. clearance between trees and streetlights.
2
It is my understanding that the developer desires the electric transformer(s)
to be placed immediately adjacent to the east side of the mechanical enclosure.
This is acceptable: to L&P, but the landscaping in this area will need to be
adjusted to provide for the transformers. The size of the transformers cannot
be determined until the developer provides electric load information for each
electric service at the site.
Department: Natural Resources
Topic: Genera/
111
No Issues.
Issue Contact: Doug Moore
Department: PFA Issue Contact: Ron Gonzales
Topic: Genera/
145
Although these towers do not technically meet the height requirements
stipulated in 97UBC for the High -Rise Provisions, the PFA would request the
applicant consider installing as many of these provisions for the safety of the
occupants and the building. See 97UBC403
Topic: Plot
57
REQUIRED ACCE:55:
Due to the proposed heights of these edifices, a 30 foot wide fire lane is
required for aerial operations. This fire lane shall be visible by painting and
signage, and maintained unobstructed. A fire lane plan shall be submitted for
approval prior to installation. 97UFC901.2.2.1;901.3;901.4.2;902.2.1
Admin.Policy85-5; FCLUC 3.6.6(D)3
Page 10
ADDRESS NUMERALS
Address numerals shall be visible from the street fronting the property, and
posted with a minimum of 6 inch numerals on a contrasting background. The
property shall be addressed from Stanford Drive. An address marquis shall be
provided with 8" numerals. (Bronze numerals on brown brick are not
acceptable).97UFC901.4.4
WATER SUPPLY
Fire hydrants are required with a maximum spacing of 600 feet along an
approved roadway. Each hydrant must be capable of delivering 1500 gallons of
water per minute at a residual pressure of 20 psi. No commercial building can be
greater than 300 feet from a fire hydrant. 97UFC901.2.2.2
Knox Box Policy
Poudre Fire Authority requires a "Knox Box" to be mounted on the front of
every new building equipped with a required fire sprinkler system or fire alarm
system.
97UFC902.4PFAPOLICY88-20
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered. A fire pump may also be
required, as well as standpipes for the building and the parking garage below
grade. 97UBC
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below
grade. Stage One shall be tied to a Carbon Monoxide Detection System that
will detect carbon monoxide at 50ppm over 8 hours and/or 200ppm over 1 hour
and ventilate the garage. Stage Two shall provide ventilation for smoke removal
in the event of a car fire.
UBC1202.2.7
Department: Police
Topic: 6eneroi
Issue Contact: Joseph Gerdom
9
Lighting Plan: The Luminaire schedule and luminaire detail don't provide
sufficient information to determine exactly which lights are used in each
location. Also, unless there are wall fixtures there is inadequate illumination
Page 11
between Bldg B & C; east face of Bldg D; and north face of Bldg B. In general,
all building access points should have minimum of 1 fc.
105
Issues addressed except for: no illumination information for south faces of
Bldgs A & B
Topic: Landscaping
10
Landscape Plan: The use of Austrian Pine, cotoneaster, and ninebark along the
faces of Bldgs B, C, and D, particularly in front of public/private entrances will
obscure these areas and raise security issues. Lower growing species, lighting,
or some combination thereof would be recommended.
Department: Stormwater Utility Issue Contact: Basil Hamdan
Topic: Construction Easements
80
The proposed 24" RCP across Horsetooth Rd. will necessitate the construction
of a headwall and part of the culvert on Tract D of The Landings 1st Filing.
Prior to construction on this Tract owned by that HOA the contractor should
make sure that the HOA is notified and that the area will be properly restored.
Even though this area is in an existing drainage easement, the landings 1st Filing
HOA that maintains this area should ensure that the area is put back to an
acceptable level, equal or better than before construction.
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the
warren Lake Ditch company must sign off on these plans.
Topic: Easements
129
The drainage pan proposed on the north end of the site extends into
neighboring property. Please provide a drainage easement for that pan.
Page 12
61
An emergency access easement needs to be dedicated on the plat where PFA
specifies a fire lane is required.
Topic: Street Design
29
The Larimer County Urban Area Street Standards (LCUASS) in Section 8.2.2
specifies all lanes shall be in alignment through each intersection. Currently a 4.5'
offset is measured on the road design; no offset will be allowed for this design.
30
Because of the no offset requirement and some constraints involving the existing
storm drainage improvements across Horsetooth, the previous discussion involving
extension of the proposed median to the Horsetooth/Stanford intersection will no
longer be required. Instead, no median shall be provided on Horsetooth Road and a
pork chop island for the driveway off of Horsetooth shall be required. The design of
the "pork chop" for this access point should prohibit left turns onto Horsetooth (to the
extent reasonably feasible) while at the same time be designed to allow PFA access.
31
The access out to Horsetooth Road does not provide enough separation from the
intersection of Horsetooth Road and Stanford Drive as required under LCUASS
(660' is required, E320' is provided). Transportation Services has determined that this
separation will work with the construction of the "pork chop" island to deter left turns
out of the development.
32
Directional ramps are required on new construction in accordance with LCUASS.
(Standard Drawing 16-4D) Provide the detail on the plan set.
33
The City's Traffic Engineer has determined that the Stanford/Horsetooth intersection
would not make a suitable location for a roundabout and an alternative analysis
(typically required on arterial/collector and arterial/arterial intersections) is not
needed.
34
A right -turn lane for westbound Horsetooth onto northbound Stanford still should be
designed and constructed. There is a community wide benefit in the construction of
the right turn lane, thus this is eligible for Street Oversizing reimbursement. The
design of the right -turn lane should look at providing pedestrian refuge between the
right -turn and through lane, especially since the width of Horsetooth would require a
ped refuge under LCUASS.
Page 3
Topic: Erosion Control
117
Second Review
February 4, 2002
The plan still indicates straw bales on concrete and/or asphalt. This doesn't
work, they float. Please correct.
Your report/calculations call for mulching in certain areas of the project.
Please spell out with a note on the plan what areas are to be seeded/mulched.
Third Review
August 22, 2002
Same comments as last time.
Topic: Grading Plans
128
The larger scale grading plans are a bit disjointed and hard to follow while the
smaller scale grading plans are too small to read. Please chose a scale that is
more usable.
Please extend the grading plans to cover the area to the north of the site and
tie into the existing site to the north along Stanford Rd.
It seems that a portion of the driveway to the east of Building A could be
draining unto the building, please adjust.
The high point in the east entrance off of Horsetooth seems to be shallow and
flows from Horsetooth Rd could enter the site.
The east pond grading plans uses both absolute elevations and relative
elevations to a 100.00 arbitrary datum. Please remove relative elevations from
the plans.
Topic: Line 6 capacity
135
Page 13
Line 6 has several locations where the water surface elevations is very close to
or exceeds the ground floor elevation. Please consider the use of larger
diameter pipe to eliminate such a condition.
Topic: Sewer Line Crossing
134
Line 6 seems to have a sewer line crossing that is below the required 18"
clearance. Please check with Wastewater as to what minimum separation would
be acceptable to them.
Topic: Storm Line Across Horsetooth
118
It seems that the: proposed storm line across Horsetooth Rd could impact the
existing Evergreen tree on the south side of Horsetooth. Please show the
location of that tree compared to the proposed line on the utility plan and
clarify whether that tree is to be preserved.
Topic: Storm Line Alignment
132
It seems that the: storm line going from the east water quality pond to the west
one is shown to be under building envelopes. Please make sure all storm sewers
are outside of building envelopes.
Topic: Water Line Crossing
133
Please show the crossing of the water line on the sanitary sewer profile of
Storm Line E.
Topic: Water Quality Pond
120
It seems that the retaining walls of the water quality pond overlap an existing
sewer line. Those concrete walls are considered permanent structures and
thus would not be allowed to straddle the existing sanitary line and easement.
Please provide a concrete reinforcing detail with all the appropriate dimensions
for the water quality outlet boxes.
Page 14
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: Genera/
106
I understand this is not my call. That being said, I have serious reservations
about the mid -block crossing shown on Stanford Rd. This is in my opinion a
terrible end -around way of technically meeting Pedestrian LOS, rather than
doing it correctly.
107
Will a ramp cut be made on the west end of Stanford Rd. at the new mid -block
crossing? It is unclear from the site & utility plan. Please provide ramp cut.
108
Can we provide appropriate signage warning motorists of the mid -block
pedestrian crossing?
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: Genera/
109
Provide steel casing around proposed water main at multiple storm sewer
crossing. Include detail on detail sheet.
110
No permanent structures are allowed in sanitary sewer easement (I.e. retaining
walls, headwalls, etc.).
112
Are 1.5" water services adequate for these size of buildings? Provide flow
demand calculations for our review. Provide separate water and sewer services
for residential and commercial uses.
113
Provide grease traps for all food preparation facilities.
114
Provide concrete encasement of all sewers which cross above or within 18-
inches vertically of water lines. Clearly define this on plans. Show all water,
storm and sanitary sewer crossings in all profile views.
Page 15
115
Maintain 4 feet of separation between outside wall of meter pit and all
permanent structures.
116
It is unacceptable to have multiple underground storm sewers cross at a
sanitary sewer crossing.
Topic: Landscaping
48
Repeat Comment: Coordinate landscape design with the civil design and provide
the required landscape/utility separation distances. Correctly show all existing
and proposed water/sewer mains and services on the landscape plans. With the
tight constraints on this site we would be willing to relax our separation
requirements, however we will not allow landscaping to be placed directly on top
of our facilitates. Please consider the placement of shrubs and trees to
minimize the impact to our facilities.
Topic: Utility plans
54
Repeat Comment: Maintain 18-inches of vertical separation between all water,
sanitary sewer and storm sewer crossings.
92
Repeat Comment: Place all curb stops and meter pits adjacent to the main when
at all possible. Curb stops must be located within a utility easement. Water
and sewer services must be perpendicular to the main when possible.
94
Repeat Comment: Clearly define all water main joint deflection (I.e. Vertical,
Horizontal, Beginning, ending, etc.). Is entire length of proposed 8-inch water
main to be lowered?
Page 16
Department: Zoning Issue Contact: Peter Barnes
Topic: zoning
3
REPEAT, REPEAT COMMENT (8-6-02). The latest revision of General Note
1(d)(ii) has replaced the term "live/work office type units" with some lengthy
explanation of some sort of office use. Since the only type of office use
allowed without a Type 2 review is a home occupation office, and since General
Note 1(d)(i) lists home occupations, please just delete 1(d)(ii). The way they've
described it just complicates things and leaves open the possibility of a
disagreement over, its intent. The bottom line is that if the office use complies
with the home occupation ordinance, then it's allowed, and since note 1(d)(i)
covers home occupations, NOTHING ELSE NEEDS TO BE SAID.
REPEAT COMMENT (1-31-02). General note 1(d)(ii) lists "live/work office type
units" as a possible use. What is that? No such term. Is it the same as a home
occupation? The explanation of what this is in their 1-29-02 letter is
interesting, but it doesn't change anything. Our code contains no such use,
therefore the use is not allowed (4.5(C) prohibits any use that is not expressly
allowed). It still seems to me that what they are describing on sheet i of 6 is a
home occupation, which is permitted and is listed by them on general note
1(d)(i). This type of comment is common from Zoning whenever an applicant
lists a use that is not defined. For example, we make the same comment
relative to an applicant that lists "townhomes" as a permitted use. Since there
is no such defined term, we require them to remove it. If they really want to
allow offices in the building that are not within a dwelling unit (home
occupation), then they should do a Type 2 review in order to obtain approval for
things like offices, dry cleaners, hair salons.
6
REPEAT, REPEAT COMMENT (8-6-02) - General note 1(d)(iii) regarding small
food service uses has now been replaced by another lengthy description of a use
that I still don't think is permitted in the MMN zone. It seems to be saying
that they can have a "food service use" (no longer limited to ready -to -eat) as
long as the food preparation area is less than 1500 sf. I would interpret a
"food service use"' with a food preparation area as a RESTAURANT. There are
6000 and 7000 sf full service restaurants with about 1500 sf of food
preparation area, so what would prevent a full service restaurant from locating
in the building. There are now convenience retail stores that have Subways,
Page 17
Taco Bells, etc inside them. Those operations are not considered to be "ready -
to -eat" food products. So I don't know what they are trying to describe as a
use. THERE IS NO SUCH USE IN THE CODE AS A "FOOD SERVICE USE
BEYOND READY -TO -EAT", and they must only use terms that we have in the
Code. The only way we can come up with new terms or uses is by a Code
amendment, not be a listing on a PIP. If it operates as a restaurant as defined
in the Code, then the only way it is allowed is if it is accessory, meaning that the
restaurant must serve only the residences of the building. If that's what they
want to allow, then it should be stated just that way. If that's not what is
intended, then it's not allowed and the note must be removed. No building
permit or CO will be issued for anything that is classified as a restaurant use.
REPEAT COMMENT (1-31-02) - General note 1(d)(iii) - small food service uses
listed are not classified as accessory uses. Therefore, they are not permitted
in the MMN zone. (the only way they can be remotely "accessory" is if they
serve only the residences of the building, and are not open to the "public").
I've read the explanation in the applicant's 1-29-02 letter, but I don't agree.
For instance, would a Sushi Bar really be accessory, serving the tenants of the
building? I doubt it would remain in business very long with such a small
customer base.
The following comments and concerns were expressed at staff review on August
215t:
Transportation PI inning
1. The mid -block crossing on Stanford Road is of concern. A handicapped
ramp probably is needed on the west end of this crossing. Also, appropriate
signage must be provided.
2. This development will be responsible for the construction of a new sidewalk
off -site on the east side of Stanford Road, north to the Aspen Leaf
Apartments entry only.
Page 18
Engineering
1. There are lots of technical issues still unresolved.
2. The length of vertical curve on Stanford Road is not sufficient.
3. Reduce or expand the "bump out" along Stanford Road.
4. The patching limits for both East Horsetooth Road and Stanford Road
need to be revised.
5. A letter of intent from the adjacent property owner for drainage along the
north property line is needed before the item can go to a public hearing.
6. Show the needed additional grading at the northwest corner of the site.
7. Utility crossings are needed for East Horsetooth Road.
8. The westbound right -turn lane is not needed at this time; however, the
right-of-way necessary for a future turn lane must be dedicated at this
time.
9. The applicant was asked to re -submit copies of the subdivision plat but
none were submitted with this last round of review.
10. The applicant's engineer did not respond to some of staff's comments with
this last round of review.
Water/Wastewater
1. Maintain a minimum 10' separation between the detention area wall and the
sanitary sewer near the southwest corner of the site.
2. The water main is shown to be under multiple storm sewers and, therefore,
it must be encased.
Page 19
Light & Power
1. Some buildings are almost to the edge of the street right-of-way. All
utilities must be shown on the plans so that any potential conflicts can be
identified and addressed.
2. There will be ,just one point of service for each building.
Poudre Fire Author
1. There will be just one point of water service for fire flows for each
building.
2. Engineering should verify the structural calculations for the parking
structure based on the live and dead loads.
3. The utility plans show 4" fire services; however, 6" services are needed.
5tormwater
1. Stormwater is not sure how the utility conflicts will work.
2. The stormsewer is being shown to go under retaining walls for Buildings A
and B. This is not allowed.
3. There are trees within 5' of the stormsewer on the south side of East
Horsetooth Road. The proposed stormsewer would eliminate at least one
large Blue Spruce. Can this be done and will mitigation be required?
4. The Landscape Plan must show all existing off -site trees at the southeast
corner of the East Horsetooth Road - Landings Drive intersection and how
they will be affected.
5. The grading plans are still very confusing and difficult to read.
Page 20
Planning
1. The Landscape Plan must show all existing off -site trees that will be
affected by this development plan and indicate what is intended for each
one. Will they be retained, relocated, removed, mitigated, etc.?
2. Staff has determined that, because of the changes to the development
plan and lingering questions and concerns expressed by residents in the
area, another neighborhood information meeting should be held very soon.
Staff's opinion is that it is imperative that the developers and/or their
design consultants be present at this meeting. The Current Planning
Department will work with the applicants to schedule the meeting.
3. The current Photometric Study shows many points on the site that exceed
the maximum allowed foot-candles generated by the site lighting as set
forth in Section 3.2.4(C) of the Land Use Code. What is the reason for
this?
This completes staff comments at this time. Additional comments may be
forthcoming. This development request is subject to the 90-day revision re -
submittal (from the date of this comment letter) as set forth in Section
2.2.11(A) of the Land Use Code. Be sure and return all of your redlined plans
when you re -submit.
If you have any questions regarding these issues or any other issues related to
this project, please feel free to call me at (970)221-6341.
Yours Truly,
Steve Olt,
City Planner
Page 21
4; ) STAFF PROJECT REVIEW
C9ty of Purl Caitias
STANFORD DEVELOPMENT, LLC Date: 812912002
c% Cityscape Urban Design - Eldon Ward
3555 Stanford Road, Suite 105
Fort Collins, CO. 80525
Staff has reviewed your submittal for 9ELLA VISTA PDP, Type I (L UC), and we
offer the followiiag comments:
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: General
139
There has been an increase in the proposed number of residential dwelling units
(excluding any B&B operation), from 70 units to 81 units, since the last plan. The
applicant's response letter does not acknowledge or discuss the reasons for the
increase in the number of dwelling units.
141
The number of proposed parking spaces for the residential uses as shown on
Sheet 2 of the revised PDP Cover Sheet would be sufficient for the mix of I-,
2-, and 3-bedroom units as indicated in the Land Use Breakdown table.
However, the last or for -right column indicates that there may be more than 3
bedrooms in some units The "required" 151 spaces as shown does not allow for
any dwelling units with 4 or more bedrooms
144
The west end of Building C does not meet the "build -to " line requirements in
Sections 3.5.3(B)(2)(a) d (b) of the Land Use Code. On the Site Plan the building
is shown to be set back 20' to 22' from the Stanford Road right-of-way and it
must be located no more than 15' from the right-of-way of that street. If
possible, how can this building satisfy the criteria for an exception to the build -
to line standard as set forth in Section 3.5.3(R)(2)(d)1 of the Code?
Page I
35
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals).
(It appears that a straight-line grade from the crown of Horsetooth Road to the
flowline is not being provided as shown on the grading plan, cross -sections will help
confirm or deny this.)
36
Show centerline and flowline profiles on Horsetooth Road.
37
Provide the bearing and distance for the flowline on the plan view portion of the plan
and profile sheet for Horsetooth Road.
38
15' of utility easement is required along Horsetooth per LCUASS. An approved
variance request is required to deviate from this. A variance request should be
submitted to Engineering and will require approval from all the utilities in order to
reduce the utility easement down to 9'. In addition, 9' of utility easement should be
provided along Stanford Road. Again, a variance request should be submitted to
Engineering and will require approval from all the utilities in order to eliminate this
easement.
39
Show 150' past the limits of construction (vertically and horizontally) to show how
proposed improvements tie into existing. (Plan and profile street views, as well as
street striping.) (per LCUASS Page E4-6)
40
Can the striping for the bikelane continue further east to tie into the existing
bikelane?
41
Per LCUASS in Section 16.6.4, the maximum length of a crosswalk without a
pedestrian refuge area is 56'. This distance is being exceeded on Stanford Drive
and Horsetooth Road. Transportation Services has agreed that pedestrian refuge
on Stanford will not be required. As previously mentioned, a ped refuge should be
looked at across Horsetooth in between the right turn lane and the through lanes.
60
Because of the aforementioned need for the right -turn lane, eliminating the offset
through the intersection, and the constraint of the existing storm drainage
improvements, it is understood that the bike lane design for westbound Horsetooth
may have to be compromised. A reduced bike lane width of 6' (including gutter) with
a continuous concrete pour should be looked at as one potential compromise. It
may also be necessary for the bike lane to stop short of the intersection to
accommodate the right -turn lane. An additional option would be to look at widening
Page 4
146
The buildings (A thru D) vary in height from 67' for Building D to 72' for
Building C. This is based on Section 38.17(A)(1) - Building Height Measured in
Feet in the City'.s Land Use Code. Buildings A, R, and D are 5stories + a loft on
all sides however, Building C is 5 stories + a loft on the east and north sides but
is 'perceived" to be 6 stories + a loft from the south and west (street) sides
Based on the existing conditions on surrounding properties in the C -
Commercial, E - Employment, MMN - Medium Density Mixed -Use Neighborhood,
and RL - Low Density Residential Districts, staff 's position at this time is that
the project does' not satisfy the criteria set forth in Section 3.8.17(A)(3) -
Contextual Height in the Land Use Code,
Topic: Plat
137
City staff requested that 6 copies of the subdivision plat be re -submitted for
review. No copies of the plat were received with the July 31, 2002 re -submittal.
Topic: Utility plans
130
Len Hilderbrand of Public Service Company of Colorado (Excel Energy) offered
the following comments:
a. No trees may be planted within 4' of gas lines. Existing gas lines are
located in the street rights -of -way.
b. Public Service Company of Colorado will need to open cut streets (East
Horsetooth Road and Stanford Road) to install gas services to each
building. Permits will be required.
A note has been added to the overall utility plan indicating that permits will
be required for gas services.
C. Meters willl need to be staked at the ends of buildings. The elevations will
need to show areas to meet the requirements for meter stacks.
Topic: zoning
142
As indicated by the Zoning Department, General Note 1)d)ii on the PDPCover
Sheet (2 of 6) must be eliminated because the language could be construed to
Page 2
allow a 'primary" office use in the development. Home occupations are
permitted in the MMN District, which note I)d)i accounts for, but a 'primary"
office use is not permitted in the District.
143
6eneral Note 1)a)iii on the PDP Cover Sheet (2 of 6) still does not restrict the
type of proposed "food service uses" to accessory uses for the purpose of
providing that service to the residents and tenants of the Bella Vista project.
Anything resembling even a small fast food operation, with the intent to serve
the general public, would be defined as a restaurant use, which is not permitted
in the MMN District.
Department: Engineering Issue Contact: Marc Virata
Topic: 6eneral
The b p-outs along Stanford need to either be extended south of the
southern driveway, or reduced to fall short of the southern driveway. The
present configuration is viewed as a concern by Transportation with regards to
the right turn movement into the southern driveway and its interaction with the
bikelane.
The bump -outs along Stanford have been revised to transition between the
two access drives.
T ic. Grading
45
site grading and construction is shown occurring along the northern
boundary of the site. A letter of intent from the property owner not objecting
to the offsite work is required to be submitted prior to any public hearing for
the project.
[8/21] An unsigned Grant of Easement document was received. Per
Stormwater, the document in concept is not acceptable. The necessary
easement needs to be dedicated to the City using our standard City deed of
dedication language. Also, because the Grant of Easement was unsigned, this
does not serve as: a letter of intent, which is required prior to any hearing for
the project.
Page 3
The letter of intent will be signed and included as part of the submittal.
Th contours and spot elevations on the averallgrading plan are difficult to
read and should be shown better. The information also will not "scan" well.
Discussion with irity Staff indicated that the contours and spot elevations
are acceptable.
XTheis an area along Stanford north of the site that is not shown on the
overall or detailedgrading plan.
The plans have been revised to include the area along Stanford north of
the site indicating off -site grading.
opi . P
la
t
The evelopmeni needs to dedicate an access easement along Stanford Drive to
ensure the sidewalk proposed is in an access easement. Additional right-of-way
is not necessary.
(2/20) It appears that additional access easement along Stanford Drive (and
Horsetooth Road) is necessary to ensure that all of the proposed sidewalk is in
easement.
[8/21] Replace all instances of "sidewalk easement" with "access easement".
Revised as requested.
,mum of 57.5' of half street right-of-way is required to be dedicated
9 Y
along the entire length of the property with a consistent utility easement
width, in conformance with LCUASS. It is understood that 9' instead of the
15' of necessary utility easement is being proposed behind the right-of-way;
when all the design and utility issues are resolved along Horsetooth, the
variance request for reduction in utility easement width will be routed to the
utilities for approval.
[8/21] With design issues outstanding and issues regarding retaining wall(s)
over easements still in question, this issue is left as unresolved.
Paac 4
Per coordination with City Staff, it was agreed that dry stack walls and
landscaping could co -exist over the 9' utility easement provided utility
company's are not held responsible for landscape, walls, etc. A note has
been added to the overall utility plan, responding to this issue.
5
re may be a benefit in designating on the plat that the emergency access
easement is for the "surface level" only. There may be issues from a title
company on how the emergency access easement is represented as going
through a building envelope.
This has been reflected in the plat.
[8/211
Further discussion with the City Surveyor suggests revising the label as a
"surface grade level". An explanation on the plat may also be of benefit. These
are more "suggestions" than requirements, the intent is to ensure that there
are no issues with title or being able to pull a building permit.
The requested change in language has been revised on the plat.
127
Building envelopes appear to encroach within easements Building envelopes
need to be relocated outside of easements.
Building envelopes previously shown were general and over -sized to
accommodate bump -outs found around the perimeter of the buildings. To
simplify the play; building envelopes have been removed. In no case, do
building structures encroach within easements.
Topic: Sidewalk
The placement of the sidewalk requires a horizontal clearance of P and a
vertical clearance of 8' from all fixed objects It appears that the proposed
retaining wall(s) are of issue with this standard.
To facilitate the P horizontal clearance, retaining walls and walks have
been re -aligned. There are no instances of vertical clearance less than B'
above the sidewalk.
I Pa.e 5
Topic: Street Design
3)�
Directional ramps are required on new construction in accordance with LCUASS.
(Standard Drawing 16-40) Provide the detail on the plan set.
(2/20) The response from the applicant stated that this could not be
accommodated due to existing constraints. The design engineer should provide
documentation on why this cannot be accomplished. Note that because of the
right turn discussion, any previous limitations due to existing constraints may no
longer be applicable.
[8/21] The design engineer cited underground utilities and traffic control
devices in the response letter as justification. Site visits and follow up
discussion internal to City Engineering does not share the view that these are
constraints. The: "constraints" appear for enough away to allow the placement
of directional ramps with no modification to our standard drawings, or slight
modification. Please note that since directional ramps are considered standard,
documentation on why this cannot be accomplished needs to be in the form of a
variance request.
Directional pedestrian ramps have been provided as requested.
right -turn lane: for westbound Horsetooth onto northbound Stanford still
should be designed and constructed. There is a community wide benefit in the
construction of the right turn lane, thus this is eligible for Street Oversizing
reimbursement. The design of the right -turn lane should look at providing
pedestrian refuge between the right -turn and through lane, especially since the
width of Horsetooth would require a ped refuge under LCUASS.
(2/20) The issue of the right turn lane was discussed at the City's 2/14
Transportation Coordination Meeting. It was viewed that the submitted
justification for not designing the right turn lane was not compelling and that a
right turn lane could be designed into the project. Please note that any written
documentation regarding the designing of the right -turn lane should be
provided by the design engineer (a licensed professional engineer.)
Page 6
[8/211
The variance request is currently with Traffic Engineering.
Noted.
.Provide cross -sections on Horsetooth Road per LCUASS 3.3AC (at 50'
intervals). (It appears that a straight-line grade from the crown of Horsetooth
Road to the flowlline is not being provided as shown on the grading plan, cross -
sections will help confirm or deny this.)
(2/20) The cross section sheets need to have the centerline elevations labeled,
the curb and gutter section should be distinguishable from the asphalt section,
and the right-of-way should also be shown.
[8/211
The cross sections need to show the sidewalk, especially with potential issues
regarding its relationship to retaining walls. Because the detail for the inflow
curb and gutter with the continuous pour bikelane is not to standard, the cross
slope for the cross sections shown weren't evaluated. In addition, the cross
sections weren't evaluated because the flowline design still does not meet
standards (vertical curve, grade breaks, etc.)
The cross sections have been revised to address these concerns.
1�6
Show centerline and flowline profiles on Horsetooth Road.
(2/20) Can the grid lines or scale be modified in order to allow for every XX+00
stationing to be on a grid line? Only every 3rd XX+00 stationing is on a grid
line.
[8/211
The response from the design engineer indicates that this modification is time
intensive. In researching, other plan sets at 30 scale do not have this issue.
Please modify the drawings to reflect every XX+00 on a grid line. While this
may be viewed as time consuming from the design engineer's perspective, it
results in a more time consuming review for the review engineer.
Profile grids have been revised as requested.
Paee 7
3��
Provide the bearing and distance for the flowline on the plan view portion of the
plan and profile sheet for Horsetooth Road.
(2/20) This information isn't shown east of the driveway and only bearing (no
distance) is being shown west of the driveway.
[8/21]
This information is required on the street design and is not a waived
requirement if shown on the street striping plan.
Horizontal control for the proposed flowline alignment along Horsetooth has
been shown on the street sheet as well as the striping plan.
A8
15' of utility easement is required along Horsetooth per LCUASS. An approved
variance request is required to deviate from this. A variance request should be
submitted to Engineering and will require approval from all the utilities in order
to reduce the utility easement down to 9'. In addition, 9' of utility easement
should be provided along Stanford Road. Again, a variance request should be
submitted to Engineering and will require approval from all the utilities in order
to eliminate this easement.
[8/21] This comment is left as unresolved until all the design issues are worked
out and agreed to by the utilities. It is my understanding that utilities have
expressed concern with the placement of their utilities under retaining walls.
This may require additional utility easement width to compensate.
As per the most recent Utility Coordination Meeting, it was agreed by the
City and Utilities that as long as they were not held responsible for
replacement of landscape and structures above the easement, this would be
acceptable. It should also be noted, that to date, there are no utilities
located within this easement.
67.
The "'bulb -outs" proposed on Stanford Drive may be allowed only if the gutter is
redesigned to go around and along the bulb outs, not through them. There are
maintenance concerns with the current proposal due to dirt and debris
collecting between the bulb outs and the flowline.
Page 8
[8/21] The bump outs need to show a flowline design and how it ties into the
existing flowline along Stanford. In addition, cross sections on Stanford (as
done with Horsetooth) should be done in order to verify adequate cross slopes
are being maintained.
Refer to plan sheet 18 of 25 for plan and profile of bump -out
improvements along Stanford Road.
0
[12] The vertical curve shown is too short in length for the street classification
of Horsetooth. A K value of 110 is required, 60 is shown.
[8/21] There are vertical curves that still fall short of meeting standards.
A# vertical curves now attain a K value of 110.
[13] A vertical curve is needed for the Horsetooth proposed flowline as it
approaches the existing storm lines. A grade break is shown with a 0.6% grade
going to a 1.69% grade.
[8/21]
A grade break exceeding .4% is still shown.
A# grade break:, are now. 4% or less.
i, 71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction insight distance along
Stanford Drive, the variance to reduce the driveway spacing from 660' to 610',
and the variance to reduce the utility easement along Horsetooth were all
viewed favorably upon by the City Engineer. Final approval of these variance
requests will occur with completion of the designs for Horsetooth and Stanford
that are acceptable to the City and the utilities.
It appears that redirects are too abrupt on the street striping plan. See
traffic comments regarding this.
Page 9
[s/211
The proposed travel lane signage doesn't appear to tie in very well with the
existing signage east of the property.
The existing lanes east of the site have been revised to transition into the
proposed striping along the frontage of the site.
121
Street patching limits need to be revised as redlined (perpendicular to the
direction of travel as well as to the edge or middle of a lane line.) The patching
shown on Stanford Drive needs to be expanded from how it is currently shown,
and may need to expand further in order to ensure proper cross slopes
Street patching limits have been revised as requested.
tow utility crossings and depth of utilities on the street plan and profile
sheets
A# utility crossings are now shown in the street plan and profile.
126
'The detail for the inflow curb andgutter along Horsetooth Road does not have
sufficient depth along the gutter, please revise the detail as shown on the
redlines
As per coordination with City Staff, the inflow curb and gutter section has
been revised as requested.
1,31
The "bump -outs"' along Stanford are required to be built with vertical curb and
gutter in accordance with LCUASS. Please specify the use of vertical curb,
with transitioning to the existing driveover curb.
The bump -outs along Stanford have been revised to vertical curb and
gutter.
Topic: Structural
136
A structural engineer will be required to submit a signed and stamped letter
indicating that the emergency access area (defined by the plat) is designed to
Pane 10
support the live and dead loading of emergency services vehicles. This letter is
required prior to the issuance of a building permit. The structural engineer
should coordinate with PFA on the anticipated vehicles that will be staging in
this area and follow up with information from the manufacturer(s) of the
vehicle(s) on the loading specific to each vehicle(s). A follow up letter stating
that the structure was constructed to meet these requirements will also be
required prior to the issuance of a certificate of occupancy. (This will also be
stated in the Development Agreement for the project.)
Topic: Utility plans
140
Please see redlines for additional comments/clarifications.
Noted.
Department: Light & Power
Topic: Landscaping
Issue Contact: Doug Martine
1
Street trees on the landscape plan must be adjusted to provide a minimum of
40 ft. clearance between trees and streetlights
Z
It is my understanding that the developer desires the electric transformer(s)
to be placed immediately adjacent to the east side of the mechanical enclosure.
This is acceptable to L&P, but the landscaping in this area will need to be
adjusted to provide for the transformers The size of the transformers cannot
be determined until the developer provides electric load information for each
electric service at the site.
Department: Natural Resources
Topic: General
111
No Issues
Issue Contact: Doug Moore
Department: PFA Issue Contact: Ron Gonzales
Topic: General
145
Although these ;rowers do not technically meet the height requirements
stipulated in 97U9C for the High -Rise Provisions, the PFA would request the
Page I I
the sidewalk and create a combined bike/ped area behind the curb if the bikelane
cannot be accomplished.
62
Add the following note as reference wherever patching is shown on the plans: Limits
of street repair are approximate. Final limits to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City Street repair
standards.
Department: Light & Power Issue Contact: Doug Martine
Topic: Landscaping
1
Street trees on the landscape plan must be adjusted to provide a minimum of 40 ft.
clearance between trees and streetlights. A streetlight plan has been sent to Steve
Olt via inter -office mail.
2
It is my understanding that the developer desires the electric transformer(s) to be
placed immediately adjacent to the east side of the mechanical enclosure. This is
acceptable to L&P, but the landscaping in this area will need to be adjusted to
provide for the transformers. The size of the transformers cannot be determined
until the developer provides electric load information for each electric service at the
site.
Department: PFA
Issue Contact: Ron Gonzales
Topic: Plat
57
REQUIRED ACCESS:
Due to the proposed heights of these edifices, a 30 foot wide fire lane is required for
aerial operations. This fire lane shall be visible by painting and signage, and
maintained unobstructed. A fire lane plan shall be submitted for approval prior to
installation. 97UFC901.2.2.1;901.3;901.4.2;902.2.1 Admin.Policy85-5; FCLUC
3.6.6(D)3
ADDRESS NUMERALS
Address numerals shall be visible from the street fronting the property, and posted
with a minimum of 6 inch numerals on a contrasting background. The property shall
be addressed from Stanford Drive. An address marquis shall be provided with 8"
numerals. (Bronze numerals on brown brick are not acceptable).97UFC901.4.4
WATER SUPPLY
Fire hydrants are required with a maximum spacing of 600 feet along an approved
roadway. Each hydrant must be capable of delivering 1500 gallons of water per
Page 5
applicant consider installing as many of these provisions for the safety of the
occupants and the building. See 97UBC403
After meeting with PFA, the plans were revised to show striping indicating
fire lanes throughout the upper deck parking.
Topic: P/ot
57
REQUIRED ACCE:55:
Due to the proposed heights of these edifices, a 30 foot wide fire lane is
required for aerial operations. This fire lane shall be visible by painting and
signage, and maintained unobstructed. A fire lane plan shall be submitted for
approval prior to installation. 97UFC901.2.2.1;901.3;901.4.2;902.2.1
Admin.Policy85-5; FCLUC 3.6.6(D)3
After meeting with PFA, the plans were revised to show striping indicating
fire lanes throughout the upper deck parking.
ADDRESS NUMERALS
Address numerals shall be visible from the street fronting the property, and
posted with a minimum of 6 inch numerals on a contrasting background. The
property shall beaddressed from Stanford Drive. An address marquis shall be
provided with 8" numerals. (Bronze numerals on brown brick are not
acceptable).97UFC901.4.4
WATER SUPPLY
Fire hydrants are required with a maximum spacing of 600 feet along an
approved roadway. Each hydrant must be capable of delivering 1500 gallons of
water per minute: at a residual pressure of 20 psi. No commercial building can be
greater than 300 feet from a fire hydrant. 97UFC901.2.2.2
Hydrants shown meet the required spacing requirement, in addition, a
hydrant has been added adjacent to the upper deck parking, as requested
by PFA. Verification has been requested of City Utilities for flow rates
and residual pressure. This information is still pending.
Knox Box Policy
Poudre Fire Authority requires a "Knox Box" to be mounted on the front of
every new building equipped with a required fire sprinkler system or fire alarm
system.
97UFC902.4 PFAPOLICY88-20
Page 12
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered. A fire pump may also be
required, as well as standpipes for the building and the parking garage below
grade. 97UBC
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below
grade. Stage One shall be tied to a Carbon Monoxide Detection System that
will detect carbon monoxide at 50ppm over 8 hours and/or 200ppm over 1 hour
and ventilate the garage. Stage Two shall provide ventilation for smoke removal
in the event of a car fire.
UBC1202.2.7
Department: Police Issue Contact: Joseph Gerdom
Topic: General
9
Lighting Plan: The Luminaire schedule and luminaire detail don't provide
sufficient information to determine exactly which lights are used in each
location. Also, unless there are wall fixtures there is inadequate illumination
between Bldg B d C,' east face of Bldg D; and north face of Bldg B. In general,
all building access points should have minimum of 1 fc.
105
Issues addressed except for: no illumination information for south faces of
Bldgs A d B
Topic: Landscaping
10
Landscape Plan: The use of Austrian Pine, cotoneaster, and ninebark along the
faces of Bldgs B, C, and D, particularly in front of public/private entrances will
obscure these areas and raise security issues. Lower growing species, lighting,
or some combination thereof would be recommended.
Page 13
Department: Stormwater Utility Issue Contact: Basil Hamdan
Topic: Construction Easements
80
The proposed 24' RCP across Horsetooth Rd will necessitate the construction
of a headwall and part of the culvert on Tract D of The Landings 1st Filing.
Prior to construction on this Tract owned by that HOA the contractor should
make sure that the HOA is notified and that the area will be properly restored.
Even though this area is in an existing drainage easement, the landings 1st Filing
HOA that maintains this area should ensure that the area is put back to an
acceptable level, equal or better than before construction.
Notes have been added to the plan to ensure that the area disturbed is
left in as good or better condition than before construction.
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the
warren Lake Ditch company must sign off on these plans
Current plans and supporting documentation have been submitted to the
Warren Lake Ditch Company and signature blocks have been added to the
necessary plan sheets for their approval.
Topic: Easements
129
The drainage pan proposed on the north end of the site extends into
neighboring property. Please provide a drainage easement for that pan.
The above -noted easement has been noted on the plat.
Topic: Erosion Control
117
Second Review
February 4, 2002
The plan still indicates straw bales on concrete and/or asphalt. This doesn't
work, they float. Please correct.
All instances of straw bales on concrete have been revised to gravel bag
dikes.
Paae 14
Your report/calculations call for mulching in certain areas of the project.
Please spell out with a note on the plan what areas are to be seeded/mulched.
Due to the site plan and construction schedule, no areas will require seeding
and mulching, thus, no text or calculations /n the report call for seeding
and mulching.
Third Review
August 22, 2002
Same comments as last time.
Topic: Grading Plans
128
The larger scale grading plans are a bit disjointed and hard to follow while the
smaller scale grading plans are too small to read. Please chose a scale that is
more usable.
After discussion and meeting with City Staff, /t was agreed that the
grading plans are acceptable as presented.
Please extend the grading plans to cover the area to the north of the site and
tie into the existing site to the north along Stanford Rd.
The grading plans have been adjusted to show the area north of the site.
It seems that a portion of the driveway to the east of Building A could be
draining unto the: building, please adjust.
A proposed trench drain w//l intercept all runoff from the driveways into
the underground parking garage.
The high point in the east entrance off of Horsetooth seems to be shallow and
flows from Horsetooth Rd could enter the site.
The flows in the north flowl/ne of Horsetooth Road are nominal.
Calculations have been provided to ensure street flows will not overtop into
the Site.
The east pond grading plans uses both absolute elevations and relative
elevations to a 100,00 arbitrary datum. Please remove relative elevations from
the plans.
The grading plans in this area have been revised to prevent confusion.
Page 15
Topic: Line 6 capacity
135
Line 6 has several locations where the water surface elevations is very close to
or exceeds the ground floor elevation. Please consider the use of larger
diameter pipe to eliminate such a condition.
As discussed in a previous memo, this storm sewer primarily drains the
covered parking garage from nuisance flows, thus, the "100-yr" H6L is not
a true "100-yr H6L_ Notes have been added to help clarify this.
Topic: Sewer Line Crossing
134
Line 6 seems to have a sewer line crossing that is below the required 18"
clearance. Please check with Wastewater as to what minimum separation would
be acceptable to them.
Per a meeting with Jeff Hill, Roger Buffington and Basil Hamdan, it was
deemed that 12"' C-900 PVC for Storm Line Cr would make this crossing
acceptable.
Topic: Storm Line Across Horsetooth
118
It seems that the proposed storm line across Horsetooth Rd could impact the
existing Evergreen tree on the south side of Horsetooth. Please show the
location of that tree compared to the proposed line on the utility plan and
clarify whether that tree is to be preserved.
Tim Buchanan of the City Forestry Department has been contacted. At his
direction, tree protection notes have been added to the plans.
Topic: Storm Line Alignment
132
It seems that Ore storm line going from the east water quality pond to the west
one is shown to be under building envelopes Please make sure all storm sewers
are outside of building envelopes.
The plat no longer includes building envelopes, furthermore, Storm Line 8
has been removed from the design plans.
Page 16
Topic: Water Line Crossing
133
Please show the crossing of the water line on the sanitary sewer profile of
Storm Line E
The crossing referred to above is now shown on the plans.
Topic: Water 42uality Pond
120
It seems that the retaining walls of the water quality pond overlap an existing
sewer line. Those concrete walls are considered permanent structures and
thus would not be allowed to straddle the existing sanitary line and easement.
This issue was resolved at a meeting on September 25, 2002_ All vertical
walls have been moved outside of the sanitary sewer easements.
Please provide a concrete reinforcing detail with all the appropriate dimensions
for the water quality outlet boxes.
Reinforcement and dimensioning have been added to the outlet details.
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: General
106
I understand this is not my call. That being said, I have serious reservations
about the mid -block crossing shown on Stanford Rd. This is in my opinion a
terrible end -around way of technically meeting Pedestrian LOS, rather than
doing it correctly.
Noted.
107
Will a ramp cut be made on the west end of Stanford Rd. at the new mid -block
crossing? It is unclear from the site d utility plan. Please provide ramp cut.
A ramp cut is shown on the west side of Stanford Road for the mid -block
crossing.
Pagc 17
108
Can we provide appropriate signage warning motorists of the mid -block
pedestrian crossinys2
A pedestrian crossing sign has been added in both directions along Stanford
Road for this crossing. Refer to sheet 19 of 25.
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: General
109
Provide steel casing around proposed water main at multiple storm sewer
crossing. Include detail on detod sheet.
Steel casing and detail have been added to the ponds.
110
No permanent structures are allowed in sanitary sewer easement (I.e. retaining
walls, headwalls, etc.).
Structures and walls have been removed from the sanitary sewer easement.
112
Are 1.5" water services adequate for these size of buildingsP Provide flow
demand calculations for our review. Provide separate water and sewer services
for residential and commercial uses
Flow demands are currently being analyzed for these buildings. Once
complete, any new information will be reflected on the overall utility plan.
113
Pro vide grease traps for all food preparation facilities
There will be no food preparation on this Site.
114
Provide concrete encasement of all sewers which cross above or within 18-
inches vertically of water lines Clearly define this on plans Show all water,
storm and sanitory sewer crossings in all profile views
Concrete encasements have been added where necessary.
Pagc 18
115
Maintain 4 feet of separation between outside wall of meter pit and all
permanent structures
Four feet minimum is provided between permanent structures and outside
wall of meter pits.
116
It is unacceptable to have multiple underground storm sewers cross at a
sanitary sewer crossing.
The multiple crossings have been reduced to a single crossing.
Topic: Landscaping
48
Repeat Comment: Coordinate landscape design with the civil design and provide
the required landscape/utility separation distances. Correctly show all existing
and proposed water/sewer mains and services on the landscape plans With the
tight constraints on this site we would be willing to relax our separation
requirements, however we will not allow landscaping to be placed directly on top
of our facilitates. Please consider the placement of shrubs and trees to
minimize the impact to our facilities.
Topic: Utility plans
54
Repeat Comment: Maintain 18-inches of vertical separation between all water,
sanitary sewer and storm sewer crossings.
With exception to Storm Line G, all crossings provide for 18" of vertical
separation. Where Storm Line G intersects the existing 8" sanitary sewer,
it was agreed by City Utilities that the implementation of C-900 PVC over
the existing sewer main with high -density foam between, would be
acceptable.
92
Repeat Comment: Place all curb stops and meter pits adjacent to the main when
at all possible. Curb stops must be located within a utility easement. Water
and sewer services must be perpendicular to the main when possible.
Utility easements have been provided for the proposed curb stops. Curb
stops and meter pits have been relocated, adjacent to the main where
Page 19
possible. Water and sewer services are perpendicular to the main, in all
cases.
94
Repeat Comment: Clearly define all water main joint deflection (I.e. Vertical,
Horizontal, Beginning, ending, etc.). Is entire length of proposed 8-inch water
main to be lowered.
Water main deflections have been clarified.
Department, Zoning Issue Contact: Peter Barnes
Topic: zoning
3
REPEAT, REPEAT COMMENT (8-6-02). The latest revision of General Note
1(d)(ii) has replaced the term "live/work office type units" with some lengthy
explanation of some sort of office use. Since the only type of office use
allowed without a Type 2 review is a home occupation office, and since General
Note 1(d)(i) lists home occupations, please just delete 1(d)(ii). The way they've
described it just complicates things and leaves open the possibility of a
disagreement over its intent. The bottom line is that if the office use complies
with the home occupation ordinance, then it's allowed, and since note 1(d)(i)
covers home occupations, NOTHING ELSE NEEDS TO BE SAID.
REPEAT COMMENT (1-31-02). General note 1(d)(ii) lists "live/work office type
units" as a possible use. What is that? No such term. Is it the same as a home
occupation? The explanation of what this is in their 1-29-02 letter is
interesting, but it doesn't change anything. Our code contains no such use,
therefore the use is not allowed (4.5(C) prohibits any use that is not expressly
allowed). It still seems to me that what they are describing on sheet 1 of 6 is a
home occupation, which is permitted and is listed by them on general note
1(d)(i). This type: of comment is common from Zoning whenever an applicant
lists a use that is not defined. For example, we make the same comment
relative to an applicant that lists "townhomes" as a permitted use. Since there
is no such defined term, we require them to remove it. If they really want to
allow offices in the building that are not within a dwelling unit (home
occupation), then they should do a Type 2 review in order to obtain approval for
things like offices, dry cleaners, hair salons.
Page 20
6
REPEAT, REPEAT COMMENT (8-6-02) - General note 1(d)(iii) regarding small
food service uses has now been replaced by another lengthy description of a use
that I still don't think is permitted in the MMN zone. It seems to be saying
that they can have a "food service use" (no longer limited to ready -to -eat) as
long as the food preparation area is less than 1500 sf. I would interpret a
"food service use." with a food preparation area as a RESTAURANT. There are
6000 and 7000 sf full service restaurants with about 1500 sf of food
preparation area; so what would prevent a full service restaurant from locating
in the building. There are now convenience retail stores that have Subways,
Taco Bells, etc inside them. Those operations are not considered to be "ready -
to -eat" food products. So I don't know what they are trying to describe as a
use. THERE IS NO SUCH USE IN THE CODE AS A "FOOD SERVICE USE
BEYOND READY -TO -EAT", and they must only use terms that we have in the
Code. The only way we can come up with new terms or uses is by a Code
amendment, not be a listing on a PDP. If it operates as a restaurant as defined
in the Code, then the only way it is allowed is if it is accessory, meaning that the
restaurant must serve only the residences of the building. If that's what they
want to allow, then it should be stated just that way. If that's not what is
intended, then it's not allowed and the note must be removed. No building
permit or CO will be issued for anything that is classified as a restaurant use.
REPEAT COMMENT (1-31-02) - General note 1(d)(iii) - small food service uses
listed are not classified as accessory uses. Therefore, they are not permitted
in the MMN zone:. (the only way they can be remotely "accessory" is if they
serve only the residences of the building, and are not open to the "public").
I've read the explanation in the applicant's 1-29-02 letter, but I don't agree.
For instance, would a Sushi Bar really be accessory, serving the tenants of the
building? I doubt it would remain in business very long with such a small
customer base.
The following comments and concerns were expressed at staff review on August
2-rf:
p".�e 21
minute at a residual pressure of 20 psi. No commercial building can be greater than
300 feet from a fire hydrant. 97UFC901.2.2.2
Knox Box Policy
Poudre Fire Authority requires a "Knox Box" to be mounted on the front of every
new building equipped with a required fire sprinkler system or fire alarm system.
97UFC902.4 PFAPOLICY88-20
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered. A fire pump may also be
required, as well as standpipes for the building and the parking garage below grade.
97UBC
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below grade.
Stage One shall be tied to a Carbon Monoxide Detection System that will detect
carbon monoxide at 50ppm over 8 hours and/or 200ppm over 1 hour and ventilate
the garage. Stage Two shall provide ventilation for smoke removal in the event of a
car fire.
UBC1202.2.7
Department: Police Issue Contact: Joseph Gerdom
Topic: General
9
Lighting Plan: The Luminaire schedule and luminaire detail don't provide sufficient
information to determine exactly which lights are used in each location. Also, unless
there are wall fixtures there is inadequate illumination between Bldg. B & C; east
face of Bldg. D; and north face of Bldg. B. In general, all building access points
should have minimum of 1 fc.
Topic: Landscaping
10
Landscape Plan: The use of Austrian Pine, cotoneaster, and ninebark along the
faces of Bldg. B, C, and D, particularly in front of public/private entrances will
obscure these areas and raise security issues. Lower growing species, lighting, or
some combination thereof would be recommended.
Department: Stormwater Utility Issue Contact: Wes Lamarque
Topic: Erosion Control
15
The report table of contents doesn't have the correct page numbers for the erosion
control report.
Page 6
Transportation Planning
The mid -block crossing on Stanford Road is of concern. A handicapped romp
probably is needed on the west end of this crossing. Also, appropriate signage
must be provided!
This development will be responsible for the construction of a new sidewalk off -
site on the east side of Stanford Road, north to the Aspen Leaf Apartments
entry only.
Engineering
There are lots of technical issues still unresolved.
The length of vertical curve on Stanford Road is not sufficient.
Reduce or expand the "bump out" along Stanford Road.
The patching limits for both East Horsetooth Road and Stanford Road need to
be revised.
A letter of intent from the adjacent property owner for drainage along the
north property khe is needed before the item can go to a public hearing.
Show the needed additionalgrading at the northwest corner of the site.
Utility crossings are needed for East Horse tooth Road.
The westbound right -turn lone is not needed at this time; however, the right-
of-way necessary for a future turn lane must be dedicated at this time.
The applicant was asked to re -submit copies of the subdivision plat but none
were submitted with this lost round of review.
The applicant's engineer did not respond to some of staffs comments with this
last round of review.
Page 22
Water/Wastewater
Maintain a minimum 10' separation between the detention area wall and the
sanitary sewer near the southwest corner of the site.
The water main is shown to be under multiple storm sewers and, therefore, it
must be encased.
Light d Power
Some buildings ai-e almost to the edge of the street right-of-way. All utilities
must be shown on the plans so that any potential conflicts can be identified and
addressed.
Dry utilities utilized by this project have been added to the overall utility
plan.
There will be just one point of service for each building.
One point of service is provided per building.
Poudre Fire Authorit
There will be just one point of water service for fire flows for each building.
Services have been reduced to one per building.
Engineering should verify the structural calculations for the parking structure
based on the live and dead loads
The utility plans show 4" fire services• however, 6"services are needed.
6" fire services are now shown.
Stormwater
Stormwater is not sure how the utility conflicts will work
Page 23
The stormsewer is being shown to go under retaining walls for Buildings A and B.
This is not allowed.
The storm sewer line has been eliminated from the plans.
There are trees within 5' of the stormsewer on the south side of East
Horsetooth Rood The proposed stormsewer would eliminate at least one large
Blue Spruce. Can this be done and will mitigation be required2
The Landscape Plan must show all existing off -site trees at the southeast
corner of the East Horsetooth Road - Landings Drive intersection and how they
will be affected.
The grading plans are still very confusing and difficult to read.
It was agreed after meeting with City Staff, that the grading plans as
presented are acceptable.
Planning
The Landscape Plan must show all existing off -site trees that will be affected
by this development plan and indicate what is intended for each one. Will they
be retained, relocated, removed, mitigated, etc.?
Staff has determined that, because of the changes to the development plan and
lingering questions and concerns expressed by residents in the area, another
neighborhood information meeting should be held very soon. Staffs opinion is
that it is imperative that the developers and/or their design consultants be
present at this meeting. The Current Planning Department will work with the
applicants to schedule the meeting.
The current Photometric Study shows many points on the site that exceed the
maximum allowed foot-candles generated by the site lighting as set forth in
Section 324(C) of the Land Use Code. What is the reason for this.'
Page 24
This completes staff comments at this time. Additional comments may be
forthcoming. This development request is subject to the 90-day revision re -
submittal (from the date of this comment letter) as set forth in Section
2.2.11(A) of the Land Use Code. Be sure and return all of your redlined plans
when you re -submit.
If you have any questions regarding these issues or any other issues related to
this project, please feel free to call me at (970)221-6341.
Yours Truly,
Steve Olt,
City Planner
Page 25
REVISION
COMMENT SHEET
DATE: October 30, 2002 TO: Technical Services
PROJECT: #45-01A Bella Vista PDP - Type I (LUC)
All comments must be received by Steve Olt no later than the staff
review meeting:
ryM anG
November 20, 2002
No Continent
Problems or Concerns (see below or attached)
"PLEASE IDENTIFY YOUR REDLINES FOR FUTURE
REFERENCE'' ?,,0% A
2, P(EfiS� AESGR{e> RCL 4ou'8oa�Q
�d SC C-1",d,"'Y-licCcSS �5"'^1 l
CC, t�,�f Pla�r
HERE T YOU WISH TO RECEIVE COPIES OF RFPISIONFSignatu
Plat-
- Utifity _ Redline UW'ty —LMISW
� S o ffsi ?e .
Project Comments Sheet
Selected Departments
City of Fort Collins
Department: Engineering
Date: November 20, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
November 20, 2002
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata _
Topic: General--
149
The sidewalk that continues north of this site along Stanford appears to impact an
existing tree and landscape bed that is not reflected on the plan set. Will the tree be
relocated?
150
The cross sections on the utility plan set now show the sidewalk in this view. The cross
section on station 11+50 shows the sidewalk as sloped away from the street. This is not
per standards as the sidewalk is required to slope towards the street at 1/4" per foot.
There is a general concern about this occurrence because of the transition that takes
place, resulting in a section of sidewalk with no slope. Because the flowline grade of the
street at this section is less than 1%, there is a concern that there is not enough grade
on the sidewalk in this area. 1/4" per foot cross slope sloped to the street (for public
sidewalk) is required to be maintained on Horsetooth and Stanford, why is this proposed
otherwise?
Please provide LCUASS Standard Drawing 7-20B in the details sheet.
151
Because of the proposed placement of the permanent wall structure in the utility
easement, the City is requiring the following note be placed on the plat and will require
this same note in the Development Agreement for the project.
Upon receipt of written request from the City or any other utility agency occupying the 9-foot utility easement
along Horsetooth Road for the removal and/or replacement for utility purposes of the retaining wall, or for the
removal of any other permanent structures as shown on the Final Development Plan Documents located within
Signature Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drainage Report Other_
Utility Redline Utility Landscape
Page 1
said 9-foot utility easement, the Developer/Owner and/or its successors and assigns (hereafter the "Developer")
shall promptly comply with such request by performing the work requested. In the event that the Developer
Should fail to perform the aforesaid obligation within 60 days following receipt of said written request, then the
City or such other utility shall have the right to remove and/or replace such structures and the cost thereof shall
be borne by the Developer which cost, until paid, shall accrue interest at the rate of 8% per annum. If the
Developer shall fail to make reimbursement for such costs within 30 days of receipt of a written accounting of
cost, then, if demand for removal and/or replacement was from the City, electric service to the development
may be discontinued until payment is made; and if the request for removal and/or replacement was from another
Utility, such utility service as provided by said utility may be discontinued until payment is made. In addition,
the City and/or such other utility shall have a right of action against the Developer in damages for recovery of
any such cost incurred by the City or such other utility.
155
At the 11/13/02 neighborhood meeting it was suggested by some of the residents of the
Cove Island neighborhood that a raised median be provided that allows a storage area
for residents turning left out of Spindrift Court. In discussing this with the Traffic
Engineer, the singular median design will cause problems. If a design creating medians
is desired, a channelized "T" intersection design should be looked at as specified in
AASHTO. Keep in mind that this design would require medians on both sides of the
protective left turn pocket(s) and the medians would need to be a minimum of 4' in
width; additional right-of-way width is needed along the center area (only 12' exists
which is the bare minimum amount for a left turn lane with no medians) which would
result in longer transitions along the existing lanes. In addition, the length of the
medians in order for a channelized "T" to work would more than likely extend medians
past the 3/4 movement into Bella Vista off of Horsetooth. Further investigation of this
design should be coordinated between Northern Engineering and the City Traffic
Engineer.
158
Coordinate the name of the project, is it "Bellavista PDP" or "Bella Vista PDP"? Ensure
the title is consistent on all documents.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the site. A letter of intent
from the property owner not objecting to the offsite work is required to be submitted prior to any public hearing
for the project.
I8/21 ] An unsigned Grant of Easement document was received. Per Stormwater, the document in concept is not
acceptable. The necessary easement needs to be dedicated to the City using our standard City deed of
dedication language. Also, because the Grant of Easement was unsigned, this does not serve as a letter of
intent, which is required prior to any hearing for the project.
[ 1 1/20] Checking with Current Planning, a letter of intent was apparently not received
Topic: Plat
127
Building envelopes appear to encroach within easements. Building envelopes need to
be relocated outside of easements.
Page 2
[11/201 It appears that encroachments still exists for both walls and buildings, especially
into the sanitary sewer easement. Please bear in mind that walls along Horsetooth over
4 feet in height will require a permit from the Building and Zoning Department and they
would not issue a permit for a wall that encroaches into an easement.
Topic: Street Design
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the variance to
reduce the utility easement along Horsetooth were all viewed favorably upon by the City
Engineer. Final approval of these variance requests will occur with completion of the
designs for Horsetooth and Stanford that are acceptable to the City and the utilities.
121
Street patching limits need to be revised as redlined (perpendicular to the direction of
travel as well as to the edge or middle of a lane line.) The patching shown on Stanford
Drive needs to be expanded from how it is currently shown, and may need to expand
further in order to ensure proper cross slopes.
[11/20] The patching on Stanford Drive should be revised as redlined (see sheet 3 of
25).
156
Indicate on the detail for the monolithic vertical curb and gutter that the cross slope for
the bikelane shall be greater than or equal to the asphalt section, while being between
2-3%.
Topic: Utility plans
152
Clarify whether the striping shown on Stanford is existing or proposed.
153
It appears that there are electric facilities that should be in an utility easement
154
Portions of Building C and a wall appear to be within the existing City Sanitary Sewer
Easement. If this encroachment is allowed by City utilities, it would appear that portions
of this easement would at least have to be vacated because of the building.
Page 3
Project Comments Sheet
iz Selected Departments
Citv of Fort Collins
Department: Stormwater Utility
Date: November 22, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
November 20, 2002
Note - Please identify your redlines for future reference
Issue Contact: Basil Harridan
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the warren Lake Ditch company must sign off on
these plans.
Topic: Drainage Plan
162
Please correct the labeling of the contours south of buildings A, B and C so that they are not upside down.
Topic: Easements
129
The drainage pan proposed on the north end of the site extends into neighboring property. Please provide a drainage
easement for that pan. If the existing easement on the Strachan Subdivision First Filing is to be used, then please
provide a written approval from the owners of that property for the construction activities that are to take place within
that existing easement.
Topic: Grading
161
Please clarify what off -site grading will be done to the north of the entrance drive off of Stanford Rd., if grading is to be
done outside of ROW easements may be required.
Topic: Hearing
165
This project is ready for hearing from Stormwater's perspective as soon as letter of intent is obtained for the drainage
easement on the Aspen Leaf Apts property, and when the City forester indicates that he is satisfied with the tree
protection measures that are needed to protect the large conifer tree that is close to the storm sewer outfall into Warren
Lake.
Topic: Notes
160
Signatu a Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat x Site x Drainage Report Other
Utility Redline Utility x Landscape
Page 1
Please add notes to the plans, stating that the water quality ponds and the stormceptor are to be maintained by the
developer or HOA.
Topic: Storm Line Across Horsetooth
118
It seems that the proposed storm line across Horsetooth Rd could impact the existing Evergreen tree on the south side
of Horsetooth. Please add tee protection measures such as coonstruction fencing to the utility plans, please add tree
protection notes to the utility plans (not only the landscape plans) as directed by the City forester.
Topic: Storm Line E1
163
It seems that the publicly maintained Storm Line E1 will be crossing a landscaping planter box. Please add a note that
it is the responsibility of the developer to replace that box and the landscaping if that line would need to be dug up by
the City in the future.
Topic: Utility plans
159
Please call out the C-900 12" line as a plastic pipe on the utility plans, not an RCP
Page 2
Your plan calls for straw bale inlet filters at a number of locations. Straw bales do
not work on concrete or asphalt surfaces. When are these to be installed, after inlet
construction but prior to hard surfacing? You need to spell the intent out with notes
on the plan.
What is to protect Warren Lake during the construction of the outlet drain piping
system and the roadway (Horsetooth) construction? All of these and water quality
pond #1 seem to be outside the limits of your erosion control BMP's.
The surety is calculated incorrectly with regard to reseeding/mulching. Also, $1.30/If
on silt fencing is pretty cheap. Who does it for that, you?
Topic: General
16
Please revise the general notes section to apply to this project and the city of Fort
Collins. Please check that the benchmarks referenced are the closest to the site.
17
Please provide a signature block for the Warren Lake Owner. Please provide
construction/ drainage easements on the south side of Horsetooth Rd.
20
Please specify on the plans where maintenance responsibility changes from
property owner to City of Fort Collins.
22
The minimum pipe size is 15" according to the Storm Drainage Design Criteria or
storm sewers maintained by the City. Also, class III RCP is required under all city
streets. Please revise the storm sewer system to meet the minimum criteria.
23
All swales and ponds require a concrete pan when slopes are less than 2%. Please
revise plans.
25
Please provide pond depth markers where water is more than 3 ft. deep. Please
include the depth marker detail in the plans.
27
Please specify which pipes are pressure sealed on plans. Consider resizing pipes to
minimize pressurized areas.
Topic: Grading
18
Please maintain a maximum of 4:1 grading on site. Currently the west entrance area
and west detention ponds have slopes greater than allowed.
Page 7
I ftN Project Comments Sheet
Selected Departments
Citv of Fort Collins
Department: Water Wastewater
Date: November 25, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
November 20, 2002
Note - Please identify your redlines for future reference
Issue Contact: Jeff Hill
Topic: General
109
Steel casing on the proposed water main must extend 5 feet clear beyond storm sewer
crossings.
112
Repeat comment: Are 1.5' water services adequate for these size of buildings? Provide
flow demand calculations for our review. Provide separate water and sewer services for
residential and commercial uses.
115
Repeat Comment: Maintain 4 feet of separation between outside wall of meter pit and all
permanent structures.
L"T
It is unacceptable to havemuftiple underground storm sewers erQ�s3nitarysewer
crossing.
169
Maintain a 10 feet separation between the proposed fire hydrant/lateral and electric
transformer/main.
92
Repeat Comment: Place all curb stops and meter pits adjacent to the main when at all
possible. Curb stops must be located within a utility easement. Water and sewer services
must be perpendicular to the main when possible.
94
Water mains may not be joint deflected to a depth of 8 feet. Use fitting to lower the
proposed 8-inch water main in Horsetooth. Provide all information necessary for the
lowering.
See site, landscape and utility plans for other comments.
CHECK HERE
Date
IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drainage Report Other,
Utility Redline Utility Landscape
Page 1
Project Comments Sheet
6-z - . Selected Departments
City of Port Collins
Department: Engineering
Date: November 25, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
November 20, 2002
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
149
The sidewalk that continues north of this site along Stanford appears to impact an
existing tree and landscape bed that is not reflected on the plan set. Will the tree be
relocated?
150
The cross sections on the utility plan set now show the sidewalk in this view. The cross
section on station 11+50 shows the sidewalk as sloped away from the street. This is not
per standards as the sidewalk is required to slope towards the street at 1/4" per foot.
There is a general concern about this occurrence because of the transition that takes
place, resulting in a section of sidewalk with no slope. Because the flowline grade of the
street at this section is less than 1 %, there is a concern that there is not enough grade
on the sidewalk in this area. 1 /4" per foot cross slope sloped to the street (for public
sidewalk) is required to be maintained on Horsetooth and Stanford, why is this proposed
otherwise?
Please provide LCUASS Standard Drawing 7-20B in the details sheet.
151
Because of the proposed placement of the permanent wall structure in the utility
easement, the City is requiring the following note be placed on the plat and will require
this same note in the Development Agreement for the project.
Upon receipt of written request from the City or any other utility agency occupying the 9-foot utility easement
along Horsetooth Road for the removal and/or replacement for utility purposes of the retaining wall, or for the
removal of any other permanent structures as shown on the Final Development Plan Documents located within
Signature Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISION
Plat ✓ Site Drainage Report Other eJ ,-�`,�af<<-
/ Utility / Redline Utility Landscape
Page I
said 9-foot utility easement, the Developer/Owner and/or its successors and assigns (hereafter the "Developer")
shall promptly comply with such request by performing the work requested. In the event that the Developer
Should fail to perform the aforesaid obligation within 60 days following receipt of said written request, then the
City or such other utility shall have the right to remove and/or replace such structures and the cost thereof shall
be borne by the Developer which cost, until paid, shall accrue interest at the rate of 8% per annum. If the
Developer shall fail to make reimbursement for such costs within 30 days of receipt of a written accounting of
cost, then, if demand for removal and/or replacement was from the City, electric service to the development
may be discontinued until payment is made; and if the request for removal and/or replacement was from another
utility, such utility service as provided by said utility may be discontinued until payment is made. In addition,
the City and/or such other utility shall have a right of action against the Developer in damages for recovery of
any such cost incurred by the City or such other utility.
155
At the 11/13/02 neighborhood meeting it was suggested by some of the residents of the
Cove Island neighborhood that a raised median be provided that allows a storage area
for residents turning left out of Spindrift Court. In discussing this with the Traffic
Engineer, the singular median design will cause problems. If a design creating medians
is desired, a channelized "T" intersection design should be looked at as specified in
AASHTO. Keep in mind that this design would require medians on both sides of the
protective left turn pocket(s) and the medians would need to be a minimum of 4' in
width; additional right-of-way width is needed along the center area (only 12' exists
which is the bare minimum amount for a left turn lane with no medians) which would
result in longer transitions along the existing lanes. In addition, the length of the
medians in order for a channelized "T" to work would more than likely extend medians
past the 3/4 movement into Bella Vista off of Horsetooth. Further investigation of this
design should be coordinated between Northern Engineering and the City Traffic
Engineer.
158
Coordinate the name of the project; is it "Bellavista PDP" or "Bella Vista PDP"? Ensure
the title is consistent on all documents.
168
The raised planter bed, within the proposed access easement, (now evident on the
street design cross section sheet) is a potential concern with any future widening for a
right turn lane, as it may be in the way for a future realigned sidewalk. It is preferred
that the raised planter bed be removed. If the applicant desires it to remain,
development agreement language may need to be worked on illustrating that any future
construction of Horsetooth may result in the planter bed having to be removed at the
expense of the property owner.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the site. A letter of intent
from the property owner not objecting to the offsite work is required to be submitted prior to any public hearing
for the project.
[8/21 ] An unsigned Grant of Easement document was received. Per Stormwater, the document in concept is not
acceptable. The necessary easement needs to be dedicated to the City using our standard City deed of
dedication language. Also, because the Grant of Easement was unsigned, this does not serve as a letter of
intent, which is required prior to any hearing for the project.
Page 2
[1 1 /201 Checking with Current Planning, a letter of intent was apparently not received
Topic: Plat
127
Building envelopes appear to encroach within easements. Building envelopes need to
be relocated outside of easements.
[11/20] It appears that encroachments still exists for both walls and buildings, especially
into the sanitary sewer easement. Please bear in mind that walls along Horsetooth over
4 feet in height will require a permit from the Building and Zoning Department and they
would not issue a permit for a wall that encroaches into an easement.
Topic: Street Design
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the variance to
reduce the utility easement along Horsetooth were all viewed favorably upon by the City
Engineer. Final approval of these variance requests will occur with completion of the
designs for Horsetooth and Stanford that are acceptable to the City and the utilities.
121
Street patching limits need to be revised as redlined (perpendicular to the direction of
travel as well as to the edge or middle of a lane line.) The patching shown on Stanford
Drive needs to be expanded from how it is currently shown, and may need to expand
further in order to ensure proper cross slopes.
[11/20] The patching on Stanford Drive should be revised as redlined (see sheet 3 of
25). According to the City Engineering Pavement Manager, the street was recently
redone and a mill and inlay for this section is likely.
153
The cross slopes indicated for Horsetooth Road on the cross sections sheets do not
appear to match calculated values based on elevations and widths indicated. Despite
this, the cross slope values still appear to fall within City criteria, with the exception of
Station 10+00, which appears to fall below 2%.
156
Indicate on the detail for the monolithic vertical curb and gutter that the cross slope for
the bikelane shall be greater than or equal to the asphalt section, while being between
2-3%.
167
Please provide a detail on the details sheet indicating the area where the bikelane
terminates and leads onsite combined with the sidewalk. Design of this area should
keep in mind drainage along Horsetooth, containing the flows on the street and
preventing flows from entering the sidewalk to the extent feasible. The bike "ramp"
between the street and the sidewalk should have a curb along either side of the ramp.
Page 3
Topic: Utility plans
152
Clarify whether the striping shown on Stanford is existing or proposed.
154
Portions of Building C and a wall appear to be within the existing City Sanitary Sewer
Easement. If this encroachment is allowed by City utilities, it would appear that portions
of this easement would at least have to be vacated because of the building.
Page 4
er Project Comments Sheet
11062aiisil' Selected Departments
C itcut Iurt Collins
Department: Water Wastewater
Date: November 25, 2002
Project: BELLA VISTA PDP, TYPE 1 (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
November 20, 2002
Note - Please identify your redlines for future reference
Issue Contact: Jeff Hill
Topic: General
109
Steel casing on the proposed water main must extend 5 feet clear beyond storm sewer
crossings.
112
Repeat comment: Are 1.5" water services adequate for these size of buildings? Provide
flow demand calculations for our review. Provide separate water and sewer services for
residential and commercial uses.
115
Repeat Comment: Maintain 4 feet of separation between outside wall of meter pit and all
permanent structures.
4-W
Maintain a 10 feet separation between the proposed fire hydrant/lateral and electric
transformer/main.
92
Repeat Comment: Place all curb stops and meter pits adjacent to the main when at all
possible. Curb stops must be located within a utility easement. Water and sewer services
must be perpendicular to the main when possible.
94
Water mains may not be joint deflected to a depth of 8 feet. Use fitting to lower the
proposed 8-inch water main in Horsetooth. Provide all information necessary for the
lowering.
See site, landscape and utility plans for other comments.
/-:2- 0
Date
HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Alm Plat _ 2�- Site Drainage Report Other
'_ Utility _� Redline Utility V Landscape
Page I
December 20, 2002
Steve Olt
City of Fort Collins
Community Planning
P.O. Box 580
and Environmental Services
Fort Collins, CO 80522
Go����caa o 0
urban design, inc.
3555 stanford road, suite 105
fort Collins, Colorado 80525
(970) 226-4074
fax (970) 226-4196
e@cityscapeud.com
RE: Bella Vista PDP — November 27, 2002, PDP Review Comments
Dear Steve;
Included below are the November 27, 2002 comments received from City Staff
regarding the revised Bella Vista Project Development Plan (initially submitted
November 28, 2001; previous revisions were submitted January 29, 2002, July 31,
and October 28, 2002). Applicant responses to the City Staff comments are in a
bold "Arial" font.
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: General
The buildings in the Bella Vista project have been decreased in height somewhat from the last submittal of the
plans. However, the Shadow Analysis that was resubmitted does not reflect any less of a shadow cast onto the
Aspen Leaf Apartments to the north and cast. There appears to be a significant shadow impact to the Aspen
Leaf Apartments parking lot and two of the buildings. How does this satisfy the criteria set forth in Section
32.3(D) of the LUC?
A revised shadow analysis — reflecting the most recent reductions in building
height — is included with this submittal.
146
The buildings (A thin D) vary in height from 64' for Buildings A & B to 65'+ for Building C. Tlus is based on
Section 3.8. l7(A)(1) - Building Height Measured in Feet in the City's Land Use Code (LUC). Buildings A & B
are 5 stories + a loft on all sides; however, Building C is 5 stories + a loft on the east and north sides but is 6
stories + a loft from the south and west (street) sides. Based on the existing conditions on surrounding
properties in the C - Commercial, E - Employment, MMN - Medium Density Mixed -Use Neighborhood, and
RL - Low Density Residential Districts. staffs position at this time is that the project does not satisfy the criteria
set forth in Section I.S. 17(A)(3) - Contextual Height in the Land Use Code.
Page I
urban design, inc.
11/26/02 - City staff had previously instructed the applicant/developer to verify the actual height of the
Marriott Hotel in feet, not stories (being used as the highest "contextual height" building in the area) and
demonstrate this project's contextual compatibility with that comparative height in feet. The City's
project planner, development review engineer, and survey crew were at the Marriott Hotel on 11/26/02 to
measure the height of the building in feet. Based on heights shot by instrument on the northwest,
northeast, and southeast sides of the building, it has been determined that the hotel building is 60.5'
in height.
Prior to the second Neighborhood Meeting, we have no record of previously
being "instructed" to verify the actual height of the Marriott. While City Staff's
method of measuring the height does not exactly match LUC provisions
requiring an average of finish grades on all sides of the building; Staff's
conclusions are not greatly different (approximately V) than our revised
measurements. As per our December 13th meeting with City Staff we have
agreed upon 61' as the actual height in feet of the Marriott.
Revised building elevations meeting the agreed upon height requirements are
included with this submittal. Building 'A' has been reduced by one floor; and
the loftimezzanine levels have been eliminated from the redesigned upper
floors of the other buildings so that — except for elevator towers and some
minor ornamental elements — the maximum building heights are 61'.
It states in Section 3.8.17(A)(3) that:....The allowed "contextual" height may fall at any point between the
zone district maximum height limit and the height of a building that exists on lots that are adjacent to the
subject Iot.....The maximum building height in the MMN Zoning District is 3 stories (commonly no more
than 40' to 45' in height) and the height of the tallest building in this area is 60.5'. The 5' (+/-) difference
between the buildings in the Bella Vista project and the Marriott Hotel doestion of the LUC. The
applicant has the option to request it modification of the standard set forth in Section 4.5(E)(I)(d) of the
LUC regarding building height in the MMN District
The proposed buildings at BellaVista conform to the Contextual Height
provisions (3.8.17(A)(3) of the Land Use Code in that they include the same or
fewer stories than the six story Marriott Hotel that exists on a lot adjacent to
the subject lot; and the proposed buildings — by code - cannot be required to
have a lower maximum height than imposed by the underlying zone district
(something greater than 75'). The height of buildings "commonly" constructed
in the MMN Zone has no bearing on technical Code requirements. No
modification is needed, as the proposed buildings meet Code requirements.
Topic: Street Design
64
The latest comments from Eric Bracke of Traffic Operations are offered on a red -lined copy of the Detailed
Site Plan that is being forwarded to the applicant with this comment letter.
Page 2
CO
�Y2@Qo
urban design, inc.
While full movement at the Horsetooth Road entry drive location may be
allowed, we do not feel it should be encouraged at this location. Eric has
concurred that our current plan is acceptable.
Department: Engineering Issue Contact: Marc Virata
Topic: General
149
The sidewalk that continues north of this site along Stanford appears to impact an existing tree and landscape
bed that is not reflected on the plan set. will the tree be relocated?
The walk alignment has been adjusted.
I50
The cross sections on the utility plan set now show the sidewalk in this view. The cross section on station
11+50 shows the sidewalk as sloped away from the street. This is not per standards as tine sidewalk is required
to slope towards the street at 1/4" per fool. There is a general concern about this occurrence because of the
transition that lakes place, resulting in a section of sidewalk with no slope. Because the llowline grade of the
street at this section is less than 1%, there is a concern that there is not enough grade on the sidewalk in this
area. 1 /4" per fool cross slope sloped to the street (for public sidewalk) is required to be maintained on
Horsetooth and Stanford, why is this proposed otherwise?
Please provide LCUASS Standard Drawing 7-20B in the details sheet.
Northern Engineering is addressing this comment.
151
Because of the proposed placement of the permanent wall stricture in the utility easement, the City is requiring
the following note be placed on the plat and will require this same note in the Development Agreement for the
proiect.
Upon receipt of written request from the City or any other utility agency occupying the 9-foot utility easement
along Horsetooth Road for file removal and/or replacement for utility purposes of the retaining wall, or for the
removal of any other permanent structures as shown on the Final Development Plan Documents located within
said 9-foot utility casement. the Developer/Owner and/or its successors and assigns (hereafter the "Developer")
shall promptly comply with such request by performing tite work requested. In the event that the Developer
should fail to perform the aforesaid obligation within 60 days following receipt of said written request, then the
City or such other utility sliall have the right to remove and/or replace such structures and the cost thereof shall
be borne by the Developer which cost, until paid, shall accrue interest at the rate of 8% per annual. If the
Developer shall fail to niAc reimbursement for such costs within 30 days of receipt of a written accounting of
cost, then, if demand for removal and/or replacement was from the City, electric service to the development
ther
may be discontinued until payment is made; and if the request for removal and/or replacement was from 1,
utility, such utility service as provided by said utility may
be discontinued until payment is made. In addition,
the City and/or such other utility shall have a right of action against the Developer in damages for recovery of
any such cost incurred by the City or such other utility.
The requested note will be added.
Page 3
CO
�Yp
urban design, inc.
155
At the 11/13/02 neighborhood meeting it was suggested by some of the residents of the Cove island
neighborhood that a raised median be provided that allows a storage area for residents turning left out of
Spindrift Court. In discussing this with the Traffic Engineer, the singular median design will cause problems.
If a design creating medians is desired, a charnelized "T" intersection design should be looked at as specified in
AASHTO. Keep in mind that this design would require medians on both sides of the protective felt tum
pocket(s) and the medians would need to be a minimum of 4' in width; additional right-of-way width is needed
along the center area (only 12' exists which is the bare minimum amount for a left turn lane with no medians)
which wound result in longer transitions along the existing lanes. In addition, the length of the medians in order
fora channelized "T" to work would more than likely extend medians past (lie 3/4 movement into Bella Vista
off of Iforse(ooth. Further investigation of this design should be coordinated between Northern Engineering
and the City Traffic Engineer.
Because the design criteria noted above would require extensive off -site
demolition and reconstruction, this concept will not be pursued further.
158
Coordinate the name of the project, is it "Bellavista PDP" or "Bella Vista PDP"? Ensure the title is consistent
on all documents.
"Bellavista" is one word.
168
The raised planter bed, within the proposed access casement, (now evident on the street design cross section
sheep is a potential concern with any future widening for a right turn lane, as it may be in the way for a future
realigned sidewalk. It is preferred that the raised planter bed be removed. If the applicant desires it to remain,
development agreement language may need to be worked on illustrating that any future construction of
Horse(oolh may result in the planner bed having to be removed at the expense of the property owner.
The raised planter is important to the pedestrian environment at the corner.
The suggested language should be included in the Development Agreement.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the site. A letter of intent
from the property owner not objecting to the offsite work is required to be submitted prior to any public hearing
for the project.
18/2 11 An unsigned Grant of Easement document was received. Per Stonnwater, the document in concept is not
acceptable. The necessary easement needs to be dedicated to the City using our standard City deed of
dedication language. Also, because the Grant of Easement was unsigned, this does not serve as a letter of
intent, which is required prior to any hearing for the project.
111/201 Checking with Current Planning, a letter of intent was apparently not received
The applicants have verbal commitments from the adjacent property owner,
and are in the process of securing the needed signature.
Page 4
19
Please revise the grading plan to include top of wall and bottom of wall elevations for
all retaining walls and terraces on site. Include enough grading and spot elevations
on each level to show drainage patterns. Also, include details of retaining and pond
walls. Please include more spot elevations around buildings and in parking lots to
clarify grading and drainage. Currently some areas do not have enough information
to show how water drains. Please provide low points in both detention ponds.
Topic. Landscaping
24
Please maintain a minimum of 10ft. separation between trees and storm sewers.
There is very dense landscaping shown around the southern inlets and in the
northern swale; please check that drainage will not be affected.
Topic: Riprap
26
Please call out all riprap on plans and profiles. Is there any riprap or protection at the
outlet of Storm Sewer E?
Topic: Spillway
21
Please provide spillways and conveyance for flows from water quality ponds in case
outlet is plugged. Please provide calculations and cross sections for the spillways.
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: General
11
Please show bicycle parking as appropriate at each building near main entrances.
12
What number of HC parking spaces exist on lower level? Is there elevator access or
adequate access for ADA?
13
Provide cross -sections of Horsetooth (arterial) and Stanford (Collector), including
bike lanes to standard.
14
Provide pedestrian refuge for movement across Horsetooth. This can be done
either through the extension of the median and/or a porkchop island for the right turn
lane.
Page 8
Co�yp@o
urban design, inc.
Topic: Plat
127
Building envelopes appear to encroach within easements. Building envelopes need to be relocated outside o
easements.
111/201 It appears that encroachments still exist for both walls and buildings, especially into the salutary sewer
casanent. Please bear in mind that walls along Horsetooth over 4 feet in height will require a permit from the
Building and Zoning Department and they would not issue a pennit for a wall that encroaches into an easement.
The encroachment of the floors above the walkout basement into the sewer
easement has been resolved since the initial submittal of this project in
November of 2001. The dry -stack retaining walls in utility easements were
reviewed and agreed upon at our second utility coordination meeting.
Topic: street Design
Northern Engineering is addressing these comments.
71
Three variance requests were received regarding Bella Vista from Northern Engineering. The variance
requesting the reduction in sight distance along Stanford Drive, the variance to reduce the driveway spacing
From 660' to 610', and the variance to reduce the utility casement along Horsetooth were all viewed favorably
upon by the City Engineer. Final approval of these variance requests will occur with completion of the designs
for Horsetooth and Stanford that are acceptable to the City and the utilities.
121
Street patching limits need to be revised as redlined (perpendicular to the direction of travel as well as to the
edge or middle of a lane line.) The patching shown on Stanford Drive needs to be expanded from how it is
currently shown, and may need to expand further in order to ensure proper cross slopes.
It 1/201 The patching on Stanford Drive should be revised as redlined (see sheet 3 of 25). According to the City
Engineering Pavement Manager, the street was recently redone and a mill and inlay for this section is likely.
153
The cross slopes indicated for Horsetooth Road on the cross sections sheets do not appear to match calculated
values based on elevations and widths indicated. Despite this, the cross slope values still appear to Call within
City criteria, with the exception of Station Ill+00, which appears to fall below 2%.
156
Indicate oil the detail for the monolithic vertical curb and gutter that the cross slope for the bikelane shall be
greater than or equal to the asphalt section, while being between 2-3%.
167
Please provide a detail on the detail sheet indicating the area where the bikelane l ng Hors and leads containing
combined with the sidewalk. Design of thus area should keep in nand drainage along Horsetooth, contaitung the
"
Chows on the street and preventing flows from entering the sidewalk to the extent feasible. The bike "ramp
between the street and the sidewalk should have a curb along either side of the rarnp.
Page 5
coM(§@P
urban design, inc.
Topic: Utility plans
Northern Engineering is addressing these comments.
152
Clarify whether the striping shown on Stanford is existing or proposed.
154
Portions of Building C and a wall appear to be within the existing City Sanitary Sewer Easement. If this
encroachment is allowed by City utilities, it would appear that portions of this easement world at least have to
be vacated because of the building.
Department: Light & Power Issue Contact: Doug Martine
Topic: Electric
148
will need to see detailed drawings showing the electric services to buildings A
Light & Power Engineering
before the electric system is installed (this is NOT a condition of PDP approval).
Thank you.
Topic: Utility plans
147
Two electric transformers are shown on the utility plan north of building A. Only one transformer will e
needed at this location unless 2 different service voltages are required.
Northern Engineering is addressing this comment.
Department: PFA
Issue Contact: Ron Gonzales
Topic: Fire
157
Fire sprinkler (ire department connections shall be located on the fire lane side of all the buildings. This is to e
verified at the time of building pennit plan review.
Northern Engineering is addressing this comment.
Topic: General (these comments are being reiteratedfor general information)
57
REQUIRED ACCESS:
Due to the proposed heights of these edifices, a 30 foot wide fire lane is required for aerial operations. This fire
lane shall be visible by painting and signage, and maintained unobstructed. A fire lane plan shall be submitted
for approval prior to installation. 97UFC90L2.2.1:901.3,90L4.2;902.2.1 Adnrin.Policy85-5.FCLUC3.6.6(D)3
ADDRESS NUMERALS
Address numerals shall be visible from the street fronting the property, and posted with a minimum of 6 inch
numerals on a contrasting background. The property shall be addressed from Stanford Drive. An address
Page 6
urban design, inc
marquis shall be provided with 8" numerals. (Bronze numerals on brown brick are not
acceptable).97UFC90 L4.4
WATER SUPPLY
Fire hydrants are required with a nraxinumr spacing of 600 reel along an approved roadway. Each hydrant
must be capable of delivering 1500 gallons of water per urinute at a residual pressure of 20 psi. No commercial
building can be greater than 300 feet from a fire hydrant. 97UFC90 L2.2.2
Knox Box Policy
Poudre Fire Authority requires a "Knox Box" to be mounted on the front of every new building equipped with
a required fire sprinkler system or fire alarm system.
97UFC902.4 PFAPOLICY88-20
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire spritildered. A fire pump may also be required, as well as standpipes for
the building and the parking garage below grade. 97UBC
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below grade. Stage one shall be tied to a
Carbon Monoxide Detection System that will detect carbon monoxide at 50ppnr over 8 hours and/or 200ppm
over I hour and ventilate the garage. Stage Two shall provide ventilation for smoke removal in the event of a
car tire.
UBC1202.2 7
Department: Police
Issue Contact: Joseph Gerdont
Topic: General
105
Issues addressed except for: no illumination information for south faces of Bldgs A & B
The illumination information for the south faces of the buildings is on the
lighting plan.
Department: Storntwater Utility Issue Contact: Basil Harridan
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the Warren Lake Ditch company must
sign off on these plans.
Northern Engineering is addressing this comment.
Topic: Drainage Plan
162
Please correct the labeling of the contours south of buildings A, B and C so that they are not upside down.
Northern Engineering is addressing this comment.
Page 7
Co�Y7 P
urban design, inc.
Topic: Easements
129
The drainage pan proposed on the north end of the site extends into neighboring property. Please provide a
drainage easement for that pan. If the existing easement on the Slrachan Subdivision First Filing is to be used,
then please provide a written approval from the owners of that property for the construction activities that are to
take place within that existing casement.
Northern Engineering is addressing this comment.
Topic: Grading
161
Please clarify what off -site grading will be done to the north of the entrance drive off of Stanford Rd., if grading
is to be done outside of ROW easements may be required.
Northern Engineering is addressing this comment.
Topic: Hearing
165
This project is ready for hcalring front Stonnwater's perspective as soon as letter of intent is obtained for the
drainage easement oil the Aspen Leaf Apts. property, and when the City forester indicates that lie is satisfied
with the tree protection measures that are needed to protect the large conifer tree that is close to the storm sewer
outfall into Warren Lake.
Thank you.
Topic: Notes
160
Please add notes to the plans, staling that the water quality ponds and the storniceptor are to be maintained by
the developer or FICA.
Northern Engineering is addressing this comment.
Topic: Morm Line Across Horsc400th
119
it seems that the proposed storm line across Horsetooth Rd could impact the existing Evergreen tree on the
south side of Horsetooth. Please add tee protection measures such as construction fencing to the utility plans,
please add tree protection notes to the utility plans (not only the landscape plans) as directed by the City
forester.
Northern Engineering is addressing this comment.
Topic: Storm Line El
163
It seems that the publicly maintained Storm Line EI will be crossing a landscaping planter box. Please add a
note that it is the responsibility of the developer to replace that box and the landscaping if that line would need
to be dug up by the City in the future.
Northern Engineering is addressing this comment.
Page 8
co
urban design, inc.
Topic: Utilityplans
159
Please call out the C-900 12" line as a plastic pipe on the utility plans, not an RCP
Northern Engineering is addressing this comment.
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: General
108
The applicant should provide appropriate signage wanting motorists of the mid -block pedestrian crossing.
Northern Engineering is addressing this comment.
166
Safety concerns have arisen regarding the proposed bike path design where it diverts off of Horsetooth Road
and then crosses Stanford in the crosswalk. In order to improve safety and prevent potential accidents with right
laming vehicles please provide the following measures; I) Signs (2) along Horsetooth Road that informs both
cyclists and motor vehicles that the bike late ends - the signs should be spaced to provide sufficient tune to
acknowledge and prepare, 2) The off-street bike path surface should be treated in a manner to slow cyclists and
alert them to their new surroundings, 3) And a sign infonning cyclists that they must dismount their bike in the
crosswalk (see red lines). Furthermore, the path will serve only one way bike traffic, please narrow the width to
aid in the reduction of bilke speeds.
Northern Engineering is addressing the needed traffic signage on their Traffic
Control Plan. The off-street path alignment and width as shown reflects
previous direction by City Staff. Narrowing the width could create conflicts
with "wayward" pedestrians.
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: General
109
steel casing on the proposed water main must extend 5 feet clear beyond stone sewer crossings.
Northern Engineering is addressing this comment.
112
Repeat continent: Are 1.5" water services adequate for these size of buildings? Provide flow demand
calculations for our review. Provide separate water and sewer services for residential and commercial uses.
Northern Engineering is addressing this comment.
115
Repeat CouunenC Maintain 4 feet of separation between outside wall of meter pit and all permanent structures.
Northern Engineering is addressing this comment.
Page 9
an@@
urban design, inc.
169
Maintain a 10 feet separation between the proposed fire hydrant/lateral and electric transformer/main.
See site. landscape and utility plans for other comments.
Northern Engineering is addressing this comment.
Topic: Iltilitp plans
92
Repeat Conuucnt: Place all curb stops and meter pits adjacent to the main when at all possible. Curb stops must
be located within a utility easement. Water and sewer services must be perpendicular to the main when
possible.
Northern Engineering is addressing this comment.
94
Water mains may not be joint deflected to a depth of 8 feet. Use fitting to lower the proposed 8-inch water
main in Horsetooth. Provide all infomnatiou necessary for the lowering.
Northern Engineering is addressing this comment.
Department: Zoning
Issue Contact: Peter Barnes
Topic: Zoning
6
REPEAT, REPEAT, REPEAT COMMENT (11-1-02) - General note I(d)(h) still needs a little wordsmithurg.
On page 5 of the applicant's response letter dated 10-28-02, it states "allow food preparation as an accessory use
to a "convenience retail" use". The key words are "accessory use". However, the note on the plan should be
clarified so that there is no misunderstanding that any food preparation use is indeed accessory to the
convenience retail (i.e. they can't have a 700 S.F. tenant space with a 300 S.F. food preparation area and a few
tables, and then the only other offerings in the unit are a sunglass rack and a magazine rack, and have it then be
classified as convenience retail). It has to be clear that the principal use of the space is convenience retail - not
food preparation/restaurmt. I suggest the following wording or similar be added to the end of the sentence in
the note: "...and that the principal use of the convenience retail store is the sale of everyday goods and services
including, bill not limited to, ready -to -cat food products, groceries, over-the-counter drugs and sundries."
The actual language from the LUC definition — making the same statement as
the requested "wordsmithing" - is already included. A clear reference to that
language has also been added.
REPEAT. REPEAT COMMENT (8-6-02) - General note I (d)(iii) regarding small food service uses has now
been replaced by another lengthy description of a use that I still don't think is permitted in die MMN zone. It
seems to be saying that they can have a "food service use,, (no longer limited to ready -to -eat) as long as the food
preparation area is less than 1500 S.F.. I would interpret a "food service use" with a food preparation area as a
RESTAURANT. There are 6000 and 7000 S.F. full service restaurants with about I500 S.F. of food
preparation area, so what would prevent a full service restaurant from locating in the building. There are now
convenience retail stores Mutt have Subways, Taco Bells, etc inside them. Those operations are not considered
to be "ready -to -eat" food products. So I don't know what they are trying to describe as a use. THERE IS NO
Page 10
Qy7
urban design, inc.
SUCH USE IN THE CODE AS A "FOOD SERVICE USE BEYOND READY -TO -EAT", and they must oldv
use terms that we have in the Code. The only way we can come up with new terms or uses is by a Code
aiicndncnl, not be a listing on a PDP. If it operates as a restaurant as defined in die Code, then the only way it
is allowed is if it is accessory, meaning that the restaurant must serve only the residences of the building. If
at w,av if
allowed and tl c note ii t sllow. then it be removed �ioNobuild be stated
pennittor CO willtbetissued foiranythi ais nything l�dtisen it's not
classified
as a restaurant use.
REPEAT COMMENT (1-31-02) - General note I (d)(iii) - small food service uses listed are not classified as
accessory uses. Therefore, they are not permitted in the MMN zonetitle only way they can be remotely
"are
"accessory" is if they sce only the residences of the building and are not open to the "public"
explanation in the applicant's 1-29-02 letter, but I don't agree. For instance, would a Sushi Bar really be
rI've read the
accessory, serving the tenants of the building? I doubt it would remain in business very long with such a small
customer base.
As per our meeting on December 13th, it is our understanding that all
substantive comments have been addressed, and that the Bellavista PDP is
ready to be scheduled for a Type 1 Hearing in late January, or early February.
Please let us know as soon as possible the exact date of the scheduled
hearing, and call -to coordinate needed presentation materials.
Sincerely,
Eldon Ward, Pre int
Cityscape Urban Design, Inc.
cc: Javier Martinez Campos
Chuck McNeal
Frank Vaught
Bud Curtis
Lucia Liley
Page 11
LOAMN Project Comments Sheet
Selected Departments
Citv of Fort Collins
Depart r Wastewater
Date: January 15, 2003
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
January 15, 20'03
Note - Please identify your redlines for future reference
Issue Contact: Jeff Hill
Topic: General
112
Repeat comment: Are 1.5" water services adequate for these size of buildings?
Provide flow demand calculations for our review. Provide separate water and sewer
services for residential and commercial uses.
Topic: Utility plans
94
Water mains may not be joint deflected to a depth of 8 feet. Use fittings to lower the
proposed 8-inch water main in Horsetooth. Provide all information necessary for the
lowering. Now that the storm sewer and water main have been raised to the
bury depth of 6.5 feet, joint deflection is the preferred method of lowering. If a
fitting lowering is still to be used then provide a complete detail of the
lowering.
See site, landscape and utility plans for other comments.
Signature Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ Site Drainage Report Other_
Utility _ < Redline Utility Landscape
Page 1
MMNMMMMM�_
Project Comments Sheet
Selected Departments
Department: Stormwater Utility
Date: January 17, 2003
Project: EiELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
January 15, 2003
Note - Please identify your redlines for future reference
Issue Contact: Basil Harridan
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the warren Lake Ditch company must sign off on
these plans.
Topic: Easements
129
The drainage pan proposed on the north end of the site extends into neighboring property. Please provide a drainage
easement for that pan. If the existing easement on the Strachan Subdivision First Filing is to be used, then please
provide a written approval from the owners of that property for the construction activities that are to take place within
that existing easement.
Topic: Hearing
165
This project is ready for hearing from Stormwater's perspective as soon as letter of intent is obtained for the drainage
easement on the Aspen Leaf Apts property, and when the City forester indicates that he is satisfied with the tree
protection measures that are needed to protect the large conifer tree that is close to the storm sewer outfall into Warren
Lake.
Topic: Storm Line Across Horsetooth
118
It seems that the proposed storm line across Horsetooth Rd could impact the existing Evergreen tree on the south side
of Horsetooth. Please add tee protection measures such as coonstruction fencing to the utility plans, please add tree
protection notes to the utility plans (not only the landscape plans) as directed by the City forester.
Topic: Storm Line E1
163
It seems that the publicly maintained Storm Line E1 will be crossing a landscaping planter box. Please add a note that
it is the responsibility of the develo lace that box and the landscaping if that line would need to be dug up by
the City in the future.
.Cionnlu---------N� Dat b
C$ECK.HERE IF Y WISH TO RECEIy9XOPIES OF REVISIONS
la a ainage Report Other
tility Redline Utility Landscape
Page 1
Project Comments Sheet
S
City of Fort Collins Selected Departments
Department: Engineering
Date: January 22, 2003
Project: BE?LLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
January 15, 2003
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
150
The cross sections on the utility plan set now show the sidewalk in this view. The cross
section on station 11+50 shows the sidewalk as sloped away from the street. This is not
per standards as the sidewalk is required to slope towards the street at 1/4" per foot.
There is a general concern about this occurrence because of the transition that takes
place, resulting in a section of sidewalk with no slope. Because the flowline grade of the
street at this section is less than 1 %, there is a concern that there is not enough grade
on the sidewalk in this area. 1/4" per foot cross slope sloped to the street (for public
sidewalk) is required to be maintained on Horsetooth and Stanford, why is this proposed
otherwise?
Please provide LCLIASS Standard Drawing 7-20B in the details sheet.
[1/151 Detail 7-20B was not provided.
158
Coordinate the name of the project, is it "Bellavista PDP" or "Bella Vista PDP"? Ensure
the title is consistent on all documents.
[1/151 "Bella Vista" is still shown on the site/PDP plans.
Signature
Dote /
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _-� Site Drainage Report Other
Utility _ Redline Utility Landscape
Page 1
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: Landscaping
48
Coordinate landscape design with the civil design and provide the required
landscape/utility separation distances. Show all existing and proposed water/sewer
mains and services on the landscape plans.
Topic: Plat
47
Provide a 30 foot minimum utility easement for the existing 8-inch sanitary sewer
main which crosses this site. No buildings, retaining walls, trash enclosures, over
hangs, landscape boulders, etc my be placed or erected within the utility easements.
Topic: Utility plans
49
Call out all fittings, thrust blocks, valves, water/sewer service sizes on the overall
utility plans.
50
Maintain a 4 feet minimum separation distance between the outside wall of all meter
pits and any permanent structure (i.e. retaining walls, buildings, landscape boulders,
trash enclosures, etc.).
51
Provide separate water and sewer services for each building and each use within
each building (I.e. commercial, residential).
52
Eliminate all un-necessary bends and low angle crossings of water, sewer and storm
sewer lines.
53
Show and label all curb stops and meter pits on the overall utility plans. Clearly
identify these with size and location.
54
Clearly show and label all water, sanitary sewer and storm sewer crossings in all
utility profile views. Define any and all lowerings or adjustments. Maintain 18-inches
of vertical separation between all water, sanitary sewer and storm sewer crossings.
55
Will an irrigation tap be required within this site?
Page 9
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the site. A letter of intent
from the property owner not objecting to the offsite work is required to be submitted prior to any public hearing
for the project.
[8/21 ] An unsigned Grant of Easement document was received. Per Stormwater, the document in concept is not
acceptable. The necessary easement needs to be dedicated to the City using our standard City deed of
dedication language. Also, because the Grant of Easement was unsigned, this does not serve as a letter of
intent, which is required prior to any hearing for the project.
[11/201 Checking with Current Planning, a letter of intent was apparently not received
Topic: Street Design
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the variance to
reduce the utility easement along Horsetooth were all viewed favorably upon by the City
Engineer. Final approval of these variance requests will occur with completion of the
designs for Horsetooth and Stanford that are acceptable to the City and the utilities.
167
Please provide a detail on the details sheet indicating the area where the bikelane
terminates and leads onsite combined with the sidewalk. Design of this area should
keep in mind drainage along Horsetooth, containing the flows on the street and
preventing flows from entering the sidewalk to the extent feasible. The bike "ramp"
between the street and the sidewalk should have a curb along either side of the ramp.
[1/15] This information was not apparently provided.
171
A detail will need to be addled for the truncated dome design on the general details sheet (for ADA compliance). See the
redlines for the detail.
Topic: Utility plans
154
Portions of Building C and a wall appear to be within the existing City Sanitary Sewer
Easement. If this encroachment is allowed by City utilities, it would appear that portions
of this easement would at least have to be vacated because of the building.
Page 2
r. STAFF PROJECT REVIEW
Cily of Fort Collins
STANFORD DEVELOPMENT, LLC Date: 1/28/2003
c/o Cityscape Urban Design/Eldon Ward
3555 Stanford Road, Suite 105
Fort Collins, CO. 80525
Staff has reviewed your re -submittal for BELLA VISTA PDP, TYPE I (LUC), and we offer the
following comments:
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: Street Design
63
Len Hilderbrand of Excel Energy (PSCO) offered the following comments:
PSCO has a 2" MW existing gas main along the west boundary of the project and a 4" FB gas
main existing along the south edge of the property. Both gas mains lay in the street right-of-
way. No trees may be planted within T of gas lines.
The plans show a 12" storm sewer proposed in areas of PSCO's gas lines. Any relocation of
existing gas lines would be at the developer's expense.
Gas meters would be clustered together @ the ends of buildings, with 2 gas service lines per
building.
Topic: Utility plans
130
Len Hilderbrand of Public Service Company of Colorado (Excel Energy) offered the following
comments:
a. No trees may be planted within 4' of gas lines. Existing gas lines are located in the street
rights -of -way.
b. Public Service Company of Colorado will need to open cut streets (East Horsetooth Road and
Stanford Road) to install gas services to each building. Permits will be required.
C. Meters will need to be staked at the ends of buildings. The elevations will need to show areas
to meet the requirements for meter stacks.
Department: Engineering Issue Contact: Marc Virata
Topic: General
150
The cross sections on the utility plan set now show the sidewalk in this view. The cross section on
station 1 1+50 shows the sidewalk as sloped away from the street. This is not per standards as the
sidewalk is required to slope towards the street at 1/4" per foot. There is a general concern about this
occurrence because of the transition that takes place, resulting in a section of sidewalk with no slope.
Because the flowline grade of the street at this section is less than 1%, there is a concern that there is
Page 1
not enough grade on the sidewalk in this area. 1/4" per foot cross slope sloped to the street (for public
sidewalk) is required to be maintained on Horsetooth and Stanford, why is this proposed otherwise?
Please provide LCUA.SS Standard Drawing 7-20B in the details sheet.
[1/15] Detail 7-20B was not provided.
158
Coordinate the name of the project, is it "Bellavista PDP" or "Bella Vista PDP"? Ensure the title is
consistent on all documents.
[1/15] "Bella Vista" is still shown on the site/PDP plans
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the site. A letter
of intent from the property owner not objecting to the offsite work is required to be submitted prior to
any public hearing for the project.
[8/21 ] An unsigned Grant of Easement document was received. Per Stormwater, the document in
concept is not acceptable. The necessary easement needs to be dedicated to the City using our
standard City deed of dedication language. Also, because the Grant of Easement was unsigned, this
does not serve as a letter of intent, which is required prior to any hearing for the project.
[11/20] Checking with Current Planning, a letter of intent was apparently not received
Topic: Street Design
71
Three variance requests were received regarding Bella Vista from Northern Engineering. The
variance requesting the reduction in sight distance along Stanford Drive, the variance to reduce the
driveway spacing from 660' to 610', and the variance to reduce the utility easement along Horsetooth
were all viewed favorably upon by the City Engineer. Final approval of these variance requests will
occur with completion of the designs for Horsetooth and Stanford that are acceptable to the City and
the utilities.
167
Please provide a detai'I on the details sheet indicating the area where the bikelane terminates and leads
onsite combined with the sidewalk. Design of this area should keep in mind drainage along
Horsetooth, containing; the flows on the street and preventing flows from entering the sidewalk to the
extent feasible. The bike "ramp" between the street and the sidewalk should have a curb along either
side of the ramp.
[1/15] This information was not apparently provided.
171
A detail will need to be added for the truncated dome design on the general details sheet (for ADA
compliance). See the redlines for the detail.
Page 2
Topic: Utility plans
154
Portions of Building C and a wall appear to be within the existing City Sanitary Sewer Easement. If
this encroachment is allowed by City utilities, it would appear that portions of this easement would at
least have to be vacated because of the building.
Department: Light & Power Issue Contact: Doug Martine
Topic: Electric
148
Light & Power Engineering will need to see detailed drawings showing the electric services to
buildings A & B before the electric system is installed (this is NOT a condition of PDP approval).
Topic: Utilityplans
147
Two electric transformers are shown on the utility plan north of building A. Only one transformer
will be needed at this location unless 2 different service voltages are required.
Department: PFA Issue Contact: Ron Gonzales
Topic: Fire
157
Fire sprinkler fire department connections shall be located on the fire lane side of all the buildings.
This is to be verified at the time of building permit plan review.
Topic: General
145
Although these towers do not technically meet the height requirements stipulated in 97UBC for the
High -Rise Provisions. the PEA would request the applicant consider installing as many of these
provisions for the safety of the occupants and the building. See 97UBC403
Topic: Plat
57
REQUIRED ACCESS:
Due to the proposed heights of these edifices, a 30 foot wide fire lane is required for aerial operations.
This fire lane shall be visible by painting and signage, and maintained unobstructed. A fire lane plan
shall be submitted for approval prior to installation. 97UFC901.2.2.1;901.3;901.4.2;902.2.1
Admin.Policy85-5; FCLUC 3.6.6(D)3
ADDRESS NUMERALS
Address numerals shall be visible from the street fronting the property, and posted with a minimum of
6 inch numerals on a contrasting background. The property shall be addressed from Stanford Drive.
An address marquis shall be provided with 8" numerals. (Bronze numerals on brown brick are not
acceptable).97UFC901.4.4
WATER SUPPLY
Fire hydrants are required with a maximum spacing of 600 feet along an approved roadway. Each
hydrant must be capable of delivering 1500 gallons of water per minute at a residual pressure of 20
psi. No commercial building can be greater than 300 feet from a fire hydrant. 97UFC901.2.2.2
Knox Box Policy
Poudre Fire Authority requires a "Knox Box" to be mounted on the front of every new building
equipped with a required fire sprinkler system or fire alarm system.
Page 3
97UFC902.4 PFAPOI-ICY88-20
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered. A fire pump may also be required, as well as
standpipes for the building and the parking garage below grade. 97UBC
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below grade. Stage One shall
be tied to a Carbon Monoxide Detection System that will detect carbon monoxide at 50ppm over 8
hours and/or 200ppm over 1 hour and ventilate the garage. Stage Two shall provide ventilation for
smoke removal in the event of a car fire.
UBC 1202.2.7
Department: Stormwater Utility
Topic: Ditch Company Approval
87
Issue Contact: Basil Harridan
Prior to allowing additional discharge from this site into Warren Lake, the Warren Lake Ditch
company must sign off on these plans.
Topic: Easements
129
The drainage pan proposed on the north end of the site extends into neighboring property. Please
provide a drainage easement for that pan. If the existing easement on the Strachan Subdivision First
Filing is to be used, then please provide a written approval from the owners of that property for the
construction activities that are to take place within that existing easement.
Topic: Hearing
165
This project is ready for hearing from Stormwater's perspective as soon as letter of intent is obtained
for the drainage easement on the Aspen Leaf Apts. property, and when the City forester indicates that
he is satisfied with the tree protection measures that are needed to protect the large conifer tree that is
close to the storm sewer outfall into Warren Lake.
Topic: Stone Line Across Horsetooth
118
It seems that the proposed storm line across Horsetooth Rd could impact the existing Evergreen tree
on the south side of Horsetooth. Please add tee protection measures such as construction fencing to
the utility plans, please; add tree protection notes to the utility plans (not only the landscape plans) as
directed by the City forester.
Topic: Storm Line El
163
It seems that the publicly maintained Storm Line E 1 will be crossing a landscaping planter box.
Please add a note that it is the responsibility of the developer to replace that box and the landscaping
if that line would need to be dug up by the City in the future.
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: General
108
Can we provide appropriate signage warning motorists of the mid -block pedestrian crossing?
Page 4
166
Safety concerns have arisen regarding the proposed bike path design where it diverts off of
Horsetooth Road and then crosses Stanford in the crosswalk. In order to improve safety and prevent
potential accidents with right turning vehicles please provide the following measures; 1) Signs (2)
along Horsetooth Road that informs both cyclists and motor vehicles that the bike lane ends - the
signs should be spaced to provide sufficient time to acknowledge and prepare, 2) The off-street bike
path surface should be treated in a manner to slow cyclists and alert them to their new surroundings,
3) And a sign informing cyclists that they must dismount their bike in the crosswalk (see red lines).
Furthennore, the path will serve only one way bike traffic, please narrow the width to aid in the
reduction of bike speeds.
170
Regarding comment # 166. I realize that the site design reflects earlier staff comments, but
subsequent analysis from bike/pedestrian planners have resulted in safety concerns. Hence the
request for redesign of this piece. Please contact Tom Reiff in Transportation Planning at (970) 416-
2040 for further information.
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: General
112
Repeat comment: Are 1.5" water services adequate for these size of buildings? Provide flow
demand calculations for our review.
Topic: Utilityplans
94
Water mains may not be joint deflected to a depth of 8 feet. Use fittings to lower the proposed 8-inch
water main in Horsetooth. Provide all information necessary for the lowering. Now that the storm
sewer and water main have been raised to the bury depth of 6.5 feet, joint deflection is the preferred
method of lowering. If a fitting lowering is still to be used then provide a complete detail of the
lowering.
Items #45 (Engineering), #165 (Stormwater), and #170 (Transportation Planning) appear to be
the primary deterrents to scheduling this item for an administrative public hearing. Once
addressed and resolved to the City's satisfaction we can schedule a hearing date. If you have any
questions regarding these issues or any other issues related to this project, please feet free to call me
at (970) 221-6341.
Yours Truly,
Steve Olt,
City Planner
Page 5
Project Comments Sheet
Selected Departments
Department: Transportation Planning
Date: March 12, 2003
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
March 12, 2003
Note - Please identify your redlines for future reference
Issue Contact: Tom Reiff
Topic: General
Number: 176
Created: 3/12/2003
Follow - Up Comment to # 170 (3-12-03) Concerns have arisen from Engineering
regarding the potential for blind pedestrians to wonder out onto the bike path and
Horsetooth Road. Please make the following corrections to address this issue. 1.
Instead of having the bike path continue directly in line with the access ramp and the
crosswalk, swing the path northward to intersect with the sidewalk at or near 90
degrees (see red Hines). Then the area vacated by the path can be used to clearly
mark the sidewalk and bike path with landscaping (see red lines). This will also
require the proposed raised planter to shift eastward. 2. Please remove the walkway
connection to the bike path from the building's main south entrance to physically
separate the bike path and sidewalk. 3. It is important that the concrete pour where
the on street bike lane transitions to the off street path be constructed flush with NO
lip or seam that may cause a cyclists to lose balance or control of their bike. See red
lines for additional comments.
Signature Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ Site Drainage Report Other_
Utility __ Redline Utility Landscape
Page I
Project Comments Sheet
Selected Departments
City of Fort Collins
Department: Water Wastewater
Date: March 16, 2003
Project: BE?LLA VISTA PDP, TYPE I (LUC)
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
March 12, 2003
Note - Please identify your redlines for future reference
Issue Contact: Roger Buffington
Topic: Utility plans
Number: 178 Created: 3/16/2003
Sheet 15: How much clearance is between the storm and sanitary (outside of pipe
to outside of pipe)? Can storm be raised? May need detail showing method of
protecting the sanitary depending on the clearance.
Issue Contact: Jeff Hill
Topic: Utility plans
Number: 94
Created: 2/22/2002
Repeat comment 3/16/03: Water mains may not be joint deflected to a depth of 8
feet. Use fittings to lower the proposed 8-inch water main in Horsetooth. Provide all
information necessary for the lowering. Now that the storm sewer and water main
have been raised to the bury depth of 6.5 feet, joint deflection is the preferred
method of lowering. If a fitting lowering is still to be used then provide a complete
detail of the lowering.----------- It is unclear whether joint deflection is being used at
this crossing. It was our understanding that the storm sewer would be raised
eliminating the need for lowering the water main, but the profile looks the same as
last round of review. Please clarify
Signature
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drainage Report Other
Utility Redline Utility Landscape
Page 1
Project Comments Sheet
Selected Departments
Department: Stormwater Utility
Date: March 17, 2003
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
March 12, 2003
Note - Please identify your redlines for future reference
Issue Contact: Basil Harridan
Topic: Drainage Reports
Number: 180 Created: 3/17/2003
Please provide three signed and atamped copies of the drainage report, including plans in the back for approval.
Topic: Easements
Number: 165 Created: 11 /20/2002
Please provide a copy of the drainage easement on Aspen Leaf Apts property for our records,if this easement has been
secures. The easement will be needed prior to approval of final plans.
Topic: Utility plans
Number: 179 Created: 3/17/2003
Please add detail of storm/sanitary sewer crossing on storm line G. Provide as much clearance as possible.
CHECK HERE IF YOU WISH
at Site
Utility _ Redline Utility
3/17-(03
Dat
TORE IVE COPIES OF REVISIONS
Drainage Report Other_
Landscape
Page 1
Project Comments Sheet
(06�- Selected Departments
City of Fort Collins
Department: Engineering
Date: March 21, 2003
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
March 12, 2003
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
Number: 158 Created: 11 /19/2002
Coordinate the name of the project, is it "Bellavista PDP" or "Bella Vista PDP"? Ensure the title is
consistent on all documents.
[1/15] "Bella Vista" is still shown on the site/PDP plans.
[2/20] repeat comment (site/landscape plans differ from utility/plat).
Number: 181 Created: 3/21 /2003
The letter of intent was received and is acceptable. Copies of the actual signed easement, (recorded at
the county with reception numbers) is required prior to the submittal of mylars. Please indicate the
reception number(s) for the easement on the plat. Also, please remove the City Acceptance provision
from the document, as it is a private easement agreement between two parties outside of the City.
Topic: Street Design
Number: 71 Created: 2/18/2002
Three variance requests were received regarding Bella Vista from Northern Engineering. The
variance requesting the reduction in sight distance along Stanford Drive, the variance to reduce the
driveway spacing from 660' to 610', and the variance to reduce the utility easement along Horsetooth
were all viewed favorably upon by the City Engineer. Final approval of these variance requests will
occur with completion of the designs for Horsetooth and Stanford that are acceptable to the City and
the utilities.
[2/27] The three variance requests were approved by the City Engineer and can be indicated as such
on General Note #58. No additional notice or follow up will be made, unless requested.
Al
narure/ Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drainage Report y Other
Utility Redline Utility Landscape '
Page 1
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: November 28, 2001 TO: Engineering Pavement
PROJECT: #45-01A Bella Vista PDP - Type I (LUC)
All comments must be received by Steve Olt no later than the staff
review meeting:
December 26, 2001
Note- Please identify your redlines for fieture reference
rl) e
C'rC'C°r-l�-. y
i
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _Site _Drainage Report _Other
Utility _Redline Utility _Landscape
56
Provide a manhole adjustment and a concrete encasement detail with the next
submittal.
See the site, landscape and utility plans for other comments.
Department: Zoning Issue Contact: Peter Barnes
Topic: General
3
General note 1(d)(ii) lists "live/work office type units" as a possible use. What is
that? No such term. Is it the same as a home occupation?
4
General note 2 references Section 2.8.17. There is no such section. I assume they
mean 3.8.17 (A)(3). If so, then Planning needs to determine if the 4 to 6 stories is
the appropriate "contextual height". Some of the walls of buildings are almost 90'
tall. In my opinion, "contextual height" as used in 3.8.17(A)(3) implies a similar
height in feet as well as in stories. For instance, a 6 story building on one lot may
only be 70' tall, and that doesn't mean that it's therefore ok to have a 6 story building
on an adjacent lot that is 90' tall when the maximum height allowed in the MMN zone
is 3 stories (4.5(E)(1)(d). How tall is the Marriott in terms of feet?
5
General note 13 - wood gates are not advisable
6
General note 1(d)(iii) - small food service uses listed are not classified as accessory
uses. Therefore, they are not permitted in the MMN zone. (the only way they can
be remotely "accessory" is if they serve only the residences of the building, and are
not open to the "public".
7
General note 1(C)(ii) - B&B's would not be allowed. Such a use is a use that is
conducted in a private house, not in a condo building.
Topic: Landscaping
8
The surface level parking lot is required to have interior parking lot landscaping.
(Sections 3.2.1(E)(5) and 3.2.2(M)(1). Does the parking underneath the surface lot
preclude interior landscaping? If so, then a modification will be required to
3.2.2(M)(1) since there is no alternative compliance provision to that section and
since there is no automatic exemption for a surface lot on top of an underground lot.
The lot does have some landscaping that could qualify as interior, but not enough.
Page 10
- STAFF PROJECT REVIEW
C;tv"r tort c"us
Stanford Development, LLC Date: 3/25/2003
c/o Cityscape Urban Design - Eldon Ward
3555 Stanford Road, Suite 105
Fort Collins, CO. 80525
Staff has reviewed your submittal for BELLA VISTA PUP, TYPE I (LUC), and we offer
the following comments:
ISSUES:
Department: Engiineering Issue Contact: Marc Virata
Topic: Genera/
Number: 158 Created: 11/19/2002
Coordinate the name of the project, is it "Bellavista PDP" or "Bella Vista PDP" or
"BellaVista PDP"? Ensure that the title is consistent on all documents.
(1/15] "Bella Vista' is still shown on the site/PDP plans.
[2/20] repeat comment (site/landscape plans differ from utility/plat).
Number: 181 Created: 3/21/2003
The letter of intent was received and is acceptable. Copies of the actual signed
easement, (recorded at the county with reception numbers) is required prior to the
submittal of mylars. Please indicate the reception number(s) for the easement on the
plat. Also, please remove the City Acceptance provision from the document, as it is a
private easement agreement between two parties outside of the City.
Topic: Street Design
Number: 71 Created: 2/18/2002
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance; to reduce the driveway spacing from 660' to 610', and the variance
to reduce the utility easement along East Horsetooth Road were all viewed favorably
upon by the City Engineer. Final approval of these variance requests will occur with
completion of the designs for Horsetooth Road and Stanford Road that are acceptable
to the City and the utilities.
[2/27] The three variance requests were approved by the City Engineer and can be
indicated as such on General Note #58. No additional notice or follow up will be made,
unless requested.
Page I
Department: Stormwater Utility Issue Contact: Basil Hamdan
Topic: Drainage Reports
Number: 180 Created: 3/17/2003
Please provide three signed and stamped copies of the drainage report, including plans
in the back for approval.
Topic: Easements
Number:165 Created:1112012002
Please provide a copy of the drainage easement on the Aspen Leaf Apartments
property for our records, if this easement has been secures. The easement will be
needed prior to approval of final plans.
Topic: Utility plans
Number: 179 Created: 3/17/2003
Please add detail of storm/sanitary sewer crossing on storm line G. Provide as much
clearance as possible.
Department: Transportation Planning Issue Contact: Tom Reiff
Topic: General
Number:176 Created:3/12/2003
Follow - Up Comment to # 170 (3-12-03) Concerns have arisen from Engineering
regarding the potential for blind pedestrians to wonder out onto the bike path and East
Horsetooth Road. Please make the following corrections to address this issue: 1.
Instead of having the bike path continue directly in line with the access ramp and the
crosswalk, swing the path northward to intersect with the sidewalk at or near 90
degrees (see red lines). Then the area vacated by the path can be used to clearly mark
the sidewalk and bike path with landscaping (see red lines). This will also require the
proposed raised planter to shift eastward. 2. Please remove the walkway connection to
the bike path from the building's main south entrance to physically separate the bike
path and sidewalk. 3. It is important that the concrete pour where the on street bike
lane transitions to the off street path be constructed flush with NO lip or seam that
may cause a cyclists to lose balance or control of their bike. See red lines for
additional comments..
Department: Water Wastewater Issue Contact: Roger Buffington
Topic: Utility plans
Number:178 Created:3/16/2003
Sheet 15: How much clearance is between the storm and sanitary (outside of pipe to
outside of pipe)? Can storm be raised? May need detail showing method of protecting
the sanitary depending on the clearance.
Page 2
Department: Washer Wastewater Issue Contact: Jeff Hill
Topic: Utility plans
Number: 94 Created: 2/22/2002
Repeat comment 3 /16/03: Water mains may not be joint deflected to a depth of 8
feet. Use fittings to lower the proposed 8-inch water main in East Horsetooth Road.
Provide all information necessary for the lowering. Now that the storm sewer and
water main have been raised to the bury depth of 6.5 feet, joint deflection is the
preferred method of lowering. If a fitting lowering is still to be used then provide a
complete detail of the lowering. It is unclear whether joint deflection is being used at
this crossing. It was our understanding that the storm sewer would be raised
eliminating the need for lowering the water main, but the profile looks the same as last
round of review. Please clarify
This item has been scheduled for an administrative public hearing on the evening of
Thursday, April 10, 2003, in the City Council chambers. The hearing will begin
promptly at 5:30 p.m. and the Bella Vista PDP is second on the agenda (following the
Maple Hill PDP).
Please submit to the City the number of copies of all documents as shown on the
attached Revision Routing Sheet as soon as possible. Be sure and return all of the red -
lined plans when you submit.
If you have any questions regarding these issues or any other issues related to this
project, please feel free to call me at (970)221-6341.
Yours Truly,
Aukoy,
Steve Olt
City Planner
Page 3
sq Project Comments Sheet
Selected Departments
Citvot Fort Collins
.`.���
Department: Sbormwater Utility
Date: Angust 12, 2003
Project:
BELLA VISTA PROJECT DEVELOPMENT PLAN, FINAL COMPLIANCE
#45-01 A/B
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
8/6/03
Note - Please identify your redlines for future reference
Issue Contact: Basil Harridan
Topic: Utility plans
Number: 186 Created: 8/12/2003
Please look into alternative pipe material such as ductile iron pipe for the storm sewer crossing over the water line in
Horsetooth Road, as the encasement is a concern to the City Engineering Department due to the shallowness of that
storm line.
C
v
Sib na! Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drainage Report Other_
Utility Redline Utility Landscape
Page 1
Project Comments Sheet
Selected Departments
City of FortCol of tins
���
Department: Engineering
Date: August 14, 2003
Project:
BELLA VISTA PROJECT DEVELOPMENT PLAN, FINAL COMPLIANCE
#45-01A/B
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
Number: 158 Created: 11/19/2002
Coordinate the name of the project, is it "Bellavista PDP" or "Bella Vista PDP"? Ensure the title is consistent on all
documents.
[t/t 51 "Bella Vista" is still shown on the site/PDP plans.
[2/201 repeat comment (site/landscape plans differ from utility/plat).
[8/6] The utility plans now specify the project as "Bellavista F.D.P.". The preference is to leave the title as P.D.P as it
matches the plat and other documents. Better yet, remove the FDP/PDP designation all together. There may be some
future confusion as to why the plans would say FDP as no other documents have this in the title.
Number: 181 Created: 3/21/2003
The letter of intent was received and is acceptable. Copies of the actual signed easement, (recorded at the
county with reception numbers) is required prior to the submittal of mylars. Please indicate the reception
number(s) for the easement on the plat. Also, please remove the City Acceptance provision from the document,
as it is a private easement agreement between two parties outside of the City.
[8/6] As the actual easement has not been received, the comment is left as unresolved.
Topic: Utility plans
Number: 182 Created: 8/5/2003
Please remove the truncated dome detail shown on Sheet 22A. The City's Engineering Department has decided to
forego requiring the construction of these as constructability and ADA compliance issues are being worked out.
Number: 184 Created: 8/5/2003
The use of concrete encasement for the storm pipe above the water line on Horsetooth is an Engineering concern with
regards to maintaining cover over the top of the storm pipe. Please look at using ductile iron pipe instead of RCP to
eliminate the use of encasement. Please also include a note on the plans that the pavement engineer shall address the
shallowness of this storrnwater pipe crossing Horsetooth Road as part of the pavement design report.
_y r
Signature Dn e
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat / Site Drainage Report / Other
Utility _ Redline Utility Landscape
Page t
NORTHERN
ENGINEERING
N'l SERVICES, INC.
September It, 2003
Mr. Steve Olt
City of Fort Collins
281 North College Avenue
Fort Collins, Colorado 80522-0580
RE: Bella Vista PDP
Response to City comments
Steve,
This letter is in response to the City Comments we received dated August 14, 2003
regarding the BellaVista PDP project in Fort Collins, Colorado:
No. 158 — The client and project team would like to leave the title as BellaVista PDP
No. 181 — The easement will be provided by the owner
No. 182 — Detail has been removed
No. 184 — Ductile Iron Pipe has been specified for this section of storm sewer. In
addition, we added a note on the plan and profile sheet stating that the pavement
engineer will need to take into account the shallow nature of that particular stretch
of storm sewer.
No. 186 — Similar to 184, see response above.
In addition, we received an Email from Eric Braake to Mark Varata, and made the
following corrections:
"Diamond" symbols were removed from the bike lanes
Removed "through" stencils from the striping plan
I hope that this addresses all of the remainder of the City's concerns. We are sending
mylars to the City for signatures. Please feel free to contact me if you have any additional
questions.
Roger A urP.E.
Project Engineer
420 SOUTH HOWES, SUITE 202 / FORT COLLINS, COLORADO 80521 / 970 221 4158 / FAX 970.221.4159
This completes staff comments at this time. Additional comments will be
forthcoming. This development request is subject to the 90-day revision re -
submittal as set forth in Section 2.2.11(A) of the Land Use Code. Be sure and
return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this
project, please feel free to call me at (970) 221-6341.
Yours Truly,
C,
Steve Olt,
Project Planner
Pale I I
�P ALBERS, DRExEL & POHLY, INc.
1860 Industrial Circle, Suite D # Longmont • Colorado • 80501
January 28, 2002
Mr. Daryl Sigler
Northern Engineering Services
420 S. Howes St., Suite 202
Ft. Collins, CO 80521
Re: Bella Vista PDP — Final Plat
Response to City Comments
Dear Daryl:
Telephone: (303) 682-1131 . Fax: (303) 682-1149
Via Fax & Email 970-221-4159
Following are our responses to the various comments made by the City of Ft. Collins:
(28) Replace "PUD" with "PDP" on all documents.
All occurrences of "PUD" were replaced with "PDP
(42) Replace all occurrences of Director of Engineering with City Engineer.
All occurrences of "Director of Engineering" have been replaced with "City Engineer"
(43) The Plat language (Certificate of Dedication and Maintenance and Repair Guarantee
language) has been revised. Please revise as shown (electronic format of the document is
available). Ensure that the "Notice of Other Documents" language is included in the plat as
well.
The "Certificate of Dedication" and "Maintenance and Repair Guarantee" language have been
revised per documents enclosed with the City of Fort Collins' Engineering Department's
Project Comments Sheet, dated December 26, 2001.
(44) The Sight Distance Easement Language on the plat has also been revised. Please revise as
shown.
The "Sight Distance Easement" language has been revised per documents enclosed with the
City of Fort Collins' Engineering Department's Project Comments Sheet, dated December 26,
2001.
(46) The Development needs to dedicate an access easement along Stanford Drive to ensure the
sidewalk proposed is in an access easement. Additional Right-of-way is not necessary.
An 'Access and Sidewalk Easement" has been delineated on the plat.
A Full Service Land Surveying Company
Boundary • Title • Geodetic • Topographic • Engineering Layout • Subdivision Platting • Environmental
�I !p ALBERS, DREXEL & POHLY, INC.
Bella Vista PDP — Final Plat
Response to City Comments
(58) Vacation of City easements on the plat do not require an easement vacation certificate.
However, vacation of exclusive easements outside of the City (20' communication easement)
requires a signature from the telephone company.
The Vacation Certificate for the City easements was removed from the final plat.
A vacation and signature block for the local telephone company has been added to the plat.
(59) Horsetooth Road appears confusing with Right-of-way on top of city and private utilities.
Please clarify.
The plat correctly depicts various easements within the Right-of-way for Horsetooth Road.
Also, the communications and City electric easements do overlap. Apparently, through the
acquisition of additional road right-of-way over the years, easements formerly not within the
road right-of-way are now within the current road right-of-way.
(61) An emergency access easement needs to be dedicated on the plat where PFA specifies a fire
lane is required.
An Emergency Access Easement has been delineated on the plat per drawing supplied to
ADP on January 28, 2002 by Northern Engineering, Inc.
Other Comments
(1) Comments regarding graphic appearance of plat.
Line weights of text were corrected.
(2) How was the 50 feet of Horsetooth Road dedicated?
The Client's title to the subject parcel is to the North Right-of-way Line of Horsetooth Road
and fixes its mathematical position at 50 feet from section line. The North 20 feet of the South
50 feet was dedicated to the City of Ft. Collins by deed recorded July 9, 1992, as Reception
No. 92039565 as shown on this final plat. The Right-of-way for Horsetooth Road adjacent to
the subject parcel on its east and west sides were dedicated on the final plats of Strachan
Subdivision, First and Third Filings. Our research thus far has not identified the specific
document that dedicated the South 30 feet.
Please feel free to call me of you have any questions.
Regards
ALBERS, DREXEL & POHLY, INC.
Frank N. Drexel, PLS
President
-2-
1-Ze-02: 5: 28PM: NORTHERNENG
Ol/Loi LUOL 11:4/ jvSbtzllg7
ALibtKS DKEXEL HUHLY
:9702214159
# 2/ 2
PAGE 01/02
ALBERS, DREXEL & POHLY INC.
1860 Industrial Circle, Suite D . Longmont . Colorado . 80501
January 28, 2002
Mr. Daryl Sigler
Northern Engineering Services
420 S. Howes St., Suite 202
Ft. Collins, CO 80521
Re: Bella Vista PDP — Final Plat
Response to City Comments
Dear Daryl:
Telephoner (303) 682-1131 . Fax. (303) 6824149
Via Fax & Email 970-221-4159
Following are our responses to the various comments made by the City of Ft. Collins:
(28) Replace "PUD" with "PDP" on all documents.
All occurrences of "PUD" were replaced with PDP"
(42) Replace all occurrences of Director of Engineering wlth City Engineer.
i
All occurrences of "Director of Engineering" have been replaced with "City Engineer"
(43) The Plat language (Certificate of Dedication and Maintenance and Repair Guarantee
language) has been revised. Please revise as shown (electronic format of the document is
available). Ensure tliat the "Notice of Other Documents" language is included in the plat as
well.
The "Certificate of Dedication" and "Maintenance and Repair Guarantee" language have been
revised per documents enclosed with the City of Fort Collins' Engineering Department's
Project Comments Sheet, dated December 26, 2001,
(44) The Sight Distance Easement Language on the plat has also been revised. Please revise as
shown.
The "Sight Distance Easement" language has been revised per documents enclosed with the
City of Fort Collins' Engineering Department's Project Comments Sheet, dated December 26,
2001.
(46) The Development needs to dedicate an access easement along Stanford Drive to ensure the
sidewalk proposed is in an access easement. Additional Right-of-way is not necessary.
An "Access and Sidewalk Easement" has been delineated on the plat.
A Full Service Land Surveying Company
Boundary . Title • Geodetic - Topographic • Engineering Layout . Subdivision Platting . Environmental
0
Brit
January 28, 2002
Daman Holland
Cityscape Urban Design
3555 Stanford Road, Suite 105
Fort Collins, Co 80525
RE: BELLA VISTA
Dear Daman,
Integrity
Skill
Imagination
I have reviewed the Staff Project Review dated 1/10/2002. The following are Merit
Electric's response to those comments:
Topic: Generall
9. Comment: The Luminaire schedule and luminaire detail don't provide
sufficient information to determine exactly which lights are used in each
location. Also, unless there are wall fixtures there is inadequate illumination
between Bldg. B & C; east face of Bldg. D; and north face of Bldg. B. In
genera!, all building access points should have minimum of 1 fc.
Res ores& The labeling and notes on the luminaire detail sheet have been
revised to more clearly identify fixture types. The photometry of the fixtures is
dependent on the optical reflector and is independent of the hood and
luminous elements. Therefore, the architectural features can be selected
without affecting the photometric performance of the fixture.
The layout of the pedestrian poles between buildings B & C has been revised
and additional poles have been added in front of buildings A, B, and D to
provide adequate light levels to building access points.
Should you have any questions about the above items or need further clarification,
please give me a call.
Thank You,
Chris Weaver
Cc: Bob Mechels — Vaught Frye Architects
4700 lnnocution DiiNc, Snitc D-1 Fort Collins, Colorado 80525 (970) 266.8100 b[etro (303) 443-8100 Fax (970) 266.1640
January 29, 2002
Steve Olt
City of Fort Collins
Community Planning and
P.O. Box 580
Fort Collins, CO 80522
Environmental Services
COKYPC o
urban design, inc
3555 stanford road, suite 105
fort collins, colorado 80525
(970) 226-4074
fax (970) 226-4196
e@cityscapeud.com
RE: Bella Vista PDP — January 10, 2002, PDP Review Comments
Dear Steve,
Included below are the comments received from City Staff regarding the Bella
Vista Project Development Plan (submitted November 28, 2001). An explanation (in
italics) of how issues have been addressed follows each comment.
COMMENTS:
Len Hilderbrand of Excel Energy (PSCO) offered the following comments:
PSCO has a 2" MW existing gas main along the west boundary of the project and
a 4" FB gas main existing along the south edge of the,property. Both gas mains
lay in the street right-of-way. No trees may be planted within 4' of gas lines.
The tree lawn has been designed to maintain 4' minimum clearance as
requested.
The plans show a 12" storm sewer proposed in areas of PSCO's gas lines. Any
relocation of existing gas lines would be at the developer's expense.
The storm drain does not conflict with the gas lines.
3. Gas meters would be clustered together @ the ends of buildings, with 2 gas
service lines per building.
Meters will be clustered as required.
Eric Bracke of Traffic Operations offered the following comments:
1. The proposed raised median is insufficient. A median should be constructed
to "match" the west leg.
The City Engineering Department has informed us that this comment is no
longer valid, and that no raised median is to be constructed.
G:\WP\9o00\9600\9601 P DP -RESPONSE 1 A. doc
o
urban design, inc.
2. The westbound right -turn should be included @ East Horsetooth Road and
Stanford Roadl. This developer is not generating the need; however, the right -turn
lane should be included in the design.
* (In addition to the responses below, see the attached Memorandum from
Matt Delich).
The extensive existing drainage structures and other utility installations
existing, at the intersection preclude a right -turn lane at this location, due to
both vertical and horizontal conflicts.
♦ The existing storm vault (top of structure) elevation is .95' higher than
the Horsetooth Road flowline.
♦ Research indicates that the pipes within the structure are at the top of
the box, which eliminates the option of lowering the lid to
accommodate a right turn lane over the box.
♦ The two existing curb inlets at the intersection would conflict with a
new right turn lane.
♦ A right turn lane pushed further north into the site would:
i Eliminate the proposed water quality pond which is proposed at the
only location where it can affect the quality of storm water from the
entire frontage of Horsetooth Road and Stanford Road;
➢ Conflict with the existing traffic signal control box;
Conflict with the existing traffic signal pole and street light; and
Could pose something of a hazard for through, northbound traffic,
due to the unusual location of the turn lane intersection with
Stanford.
♦ Evaluation by our Traffic Engineer indicates that:
While a right -turn lane is warranted, based on LCUASS Figure 8-
04, the existing physical constraints must be recognized.
y While not specifically discussed in LUCA SS, right -turn lanes
improve both operation and safety at intersections by removing
right turns from the through traffic lane. This is particularly relevant
at unsignalized intersections where it is desired that the through
traffic on the major street not be significantly slowed by right -turning
vehicles. However, at signalized intersections, this becomes less
important, since the traffic on the major street (Horsetooth Road)
will be slowing due to the signal at this intersection. Approximately
40% of the time during the peak hours, traffic on Horsetooth Road
will be approaching a red light. Further, it was demonstrated in the
Transportation Impact Study that acceptable operation will be
achieved without the westbound right -turn lane.
Elimination of the right -turn lane will not be detrimental to the public
health, welfare, and safety. The City of Fort Collins has many
signalized intersections with similar traffic volumes without the
existence of a right -turn lane.
G:\W P\9000\9600\9601 P DP -RESPONSE 1 A. d oc
Go����caa o 0
urban design, inc.
Due to the physical constraints and the above stated traffic issues, it is
respectfully requested that the westbound right -turn lane on Horsetooth Road
approaching Stanford Road not be a requirement of the Bella Vista development.
The westbound left -turn lane @ East Horsetooth Road and Landings Drive
should be 12' wide, not 11'. The thru lanes @ 1 V wide are OK.
Lane widths have been adjusted as needed.
Please contact Eric, at 224-6062, if you have questions about his comments.
Rick Lee of the Building Department is forwarding a copy of the various codes that they
will be enforcing.
Department: Engineering Issue Contact: Marc Virata
Topic: General
40
Replace "P.U.D." with "P.D.P" on all the documents.
PDP labels have been corrected.
Topic: Grading
41
Offsite grading and construction is shown occurring along the northern boundary of the
site. A letter of intent from the property owner not objecting to the offsite work is
required to be submitted prior to any public hearing for the project.
The applicants are in the process of securing the needed letter of intent.
Topic: Plat
42
Replace all occurrences of Director of Engineering with City Engineer
The Plat will reflect this change throughout.
43
The Plat language (Certificate of Dedication and Maintenance and Repair Guarantee
language) has been revised. Please revised as shown (electronic format of the
document is available). Ensure that the "Notice of Other Documents" language is
included in the plat as well.
The Plat language will be corrected as needed.
44
The Sight Distance Easement Language on the plat has also been revised. Please
revise as shown.
The Plat language will be corrected as needed.
G:\W P\9000\9600\9601 PDP-RESPONSE 1 A. doc
conry@ o
urban design, inc.
46
The Development needs to dedicate an access easement along Stanford Drive to
ensure the sidewalk proposed is in an access easement. Additional right-of-way is not
necessary.
The needed easement has been added to the Plat.
58
Vacation of City easements on the plat do not require an easement vacation certificate.
However, vacation of exclusive easements outside of the City (20' communication
easement) requires a signature from the telephone company.
It is our understanding that the 20' easement in question is now within the
Horsetooth Road right-of-way, and no vacation is necessary.
59
Horsetooth Road appears confusing with right-of-way on top of city and private utilities.
Please clarify.
The location of the right-of-way has been clarified on the Plat and plans.
61
An emergency access easement needs to be dedicated on the plat where PFA specifies
a fire lane is required.
The needed emergency access easement has been added.
Topic: Street Design
29
The Larimer County Urban Area Street Standards (LCUASS) in Section 8.2.2 specifies
all lanes shall be in alignment through each intersection. Currently a 4.5' offset is
measured on the road design; no offset will be allowed for this design.
Lanes have been revised to align at the intersection, and maintain the existing
curb and gutter.
30
Because of the no offset requirement and some constraints involving the existing storm
drainage improvements across Horsetooth, the previous discussion involving extension
of the proposed median to the Horsetooth/Stanford intersection will no longer be
required. Instead, no median shall be provided on Horsetooth Road and a pork chop
island for the driveway off of Horsetooth shall be required. The design of the "pork
chop" for this access point should prohibit left turns onto Horsetooth (to the extent
reasonably feasible) while at the same time be designed to allow PFA access.
The design of Horsetooth Road has been revised as requested.
31
The access out to Horsetooth Road does not provide enough separation from the
intersection of Horsetooth Road and Stanford Drive as required under LCUASS (660' is
G:\WP\9000\9600\9601 PDP-RESPONSE1A.doc
PROJECT
COMMENT SHEET
Current Planning
DATE: November 28, 2001 TO: Technical Services
PROJECT: #45-01A Bella Vista PDP - Type I (LUC)
All comments must be received by Steve Olt no later than the staff
review meeting:
,�Alj
December 26, 2001
Note- Please identify your redlines for future reference
1, 60amp 4, � l.t_-GgC Z' asE ,
?, �r1n/7a4�S TEXT /5 700 (��c7 Tf/E vu1mr3��s ACE Lf%QE�tl LEGIAtFl
ll GOvrec I� �✓+^�
�i. lex�' It�e waicl%i' IS T00 heauy, MgKy q�eaS
1 d ut��Pss
be Me,��. pjc,- W;Ll Viol ke
? t" ow w4s 1 I`Q- SOl e-� IzorSelno�� �a. decticCT�� >
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _Site _Drainage Report Other
_Utility _Redline Utility _Landscape
Cj�y7 ( o 0
urban design, inc.
required, 620' is provided). Transportation Services has determined that this separation
will work with the construction of the "pork chop" island to deter left turns out of the
development.
We have maintained the location of the drive centerline.
32
Directional ramps are required on new construction in accordance with LCUASS.
(Standard Drawing 16-4D) Provide the detail on the plan set.
The City standard directional ramp is not possible at this corner, due to existing
Infrastructure in place, however we have expanded the previous ramp to better access
the new crosswalks at Horsetooth and Stanford.
33
The City's Traffic Engineer has determined that the Stanford/Horsetooth intersection
would not make a suitable location for a roundabout and an alternative analysis
(typically required on arterial/collector and arterial/arterial intersections) is not needed.
Thank you.
34
A right -turn lane for westbound Horsetooth onto northbound Stanford still should be
designed and constructed. There is a community wide benefit in the construction of the
right turn lane, thus this is eligible for Street Oversizing reimbursement. The design of
the right -turn lane should look at providing pedestrian refuge between the right -turn and
through lane, especially since the width of Horsetooth would require a ped refuge under
LCUASS.
As indicated above, vertical and horizontal conflicts with extensive existing
drainage and utility improvements preclude construction of a right turn lane at this
location.
35
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals). (It
appears that a straight-line grade from the crown of Horsetooth Road to the flowline is
not being provided as shown on the grading plan, cross -sections will help confirm or
deny this.)
The requested cross sections are included in the Utility Plans.
36
Show centerline and flowline profiles on Horsetooth Road.
Northern Engineering will show profiles as required.
37
Provide the bearing and distance for the flowline on the plan view portion of the plan
and profile sheet for Horsetooth Road.
G:\WP\9000\9600\9601 PDP-RESPONSE 1 A. doc
urban design, inc.
Northern Engineering has shown this information on their plans
38
15' of utility easement is required along Horsetooth per LCUASS. An approved
variance request is required to deviate from this. A variance request should be
submitted to Engineering and will require approval from all the utilities in order to reduce
the utility easement clown to 9'. In addition, 9' of utility easement should be provided
along Stanford Road. Again, a variance request should be submitted to Engineering
and will require approval from all the utilities in order to eliminate this easement.
Northern Engineering is submitting the Variance Request.
39
Show 150' past the limits of construction (vertically and horizontally) to show how
proposed improvements tie into existing. (Plan and profile street views, as well as
street striping.) (per LCUASS Page E4-6)
Northern Engineering has shown the additional limits on their plans
40
Can the striping for the bikelane continue further east to tie into the existing bikelane?
That is the intent of our plans.
41
Per LCUASS in Section 16.6.4, the maximum length of a crosswalk without a pedestrian
refuge area is 56'. This distance is being exceeded on Stanford Drive and Horsetooth
Road. Transportation Services has agreed that pedestrian refuge on Stanford will not
be required. As previously mentioned, a ped refuge should be looked at across
Horsetooth in between the right turn lane and the through lanes.
With the above comment that no raised median is to be constructed, pedestrian
refuge is limited to the T painted median area between the west bound left turn lane
and the east bound travel lanes. Even if a right turn lane were feasible, a pedestrian
refuge between the right turn lane would still result in a street crossing of over 56'.
60
Because of the aforementioned need for the right -turn lane, eliminating the offset
through the intersection, and the constraint of the existing storm drainage
improvements, it is understood that the bike lane design for westbound Horsetooth may
have to be compromised. A reduced bike lane width of 6' (including gutter) with a
continuous concrete pour should be looked at as one potential compromise. It may also
be necessary for the bike lane to stop short of the intersection to accommodate the
right -turn lane. An additional option would be to look at widening the sidewalk and
create a combined bike/ped area behind the curb if the bikelane cannot be
accomplished.
G:\WP\9000\9600\9601 PD P-RESPONSE 1 A. doc
C OKM@C o
urban design, inc.
A revised plan for bike lanes is included with these plans. The west bound bike
lane is proposed to remain on the street until the approach to the intersection and the
existing lane alignment forces the bikeway to transition onto an oversized walk.
62
Add the following note as reference wherever patching is shown on the plans: Limits of
street repair are approximate. Final limits to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City Street repair standards.
Northern Engineering is adding the note as needed.
Department: Light & Power Issue Contact: Doug Martine
Topic: Landscaping
1
Street trees on the landscape plan must be adjusted to provide a minimum of 40 ft.
clearance between trees and streetlights. A streetlight plan has been sent to Steve Olt
via inter -office mail.
Street trees have been adjusted as necessary.
2
It is my understanding that the developer desires the electric transformer(s) to be placed
immediately adjacent to the east side of the mechanical enclosure. This is acceptable
to L&P, but the landscaping in this area will need to be adjusted to provide for the
transformers. The size of the transformers cannot be determined until the developer
provides electric load information for each electric service at the site.
Landscape areas have been adjusted as needed. Further coordination will occur
as needed as construction documents are finalized.
Department: PFA Issue Contact: Ron Gonzales
Topic: Plat
57
REQUIRED ACCESS:
Due to the proposed heights of these edifices, a 30 foot wide fire lane is required for
aerial operations. This fire lane shall be visible by painting and signage, and maintained
unobstructed. Afire lane plan shall be submitted for approval prior to installation.
97UFC901.2.2.1,901.3,901.4.2;902.2.1 Admin.Policy85-5; FCLUC 3.6.6(D)3
The above ground level of the parking structure has been modified to allow 30'
fire lane areas on one side of each building. It is our understanding that other
circulation areas may remain at 20' or 24' as proposed.
ADDRESS NUMERALS
Address numerals shall be visible from the street fronting the property, and posted with
a minimum of 6 inch numerals on a contrasting background. The property shall be
G:\W P\9000\9600\9601 P DP -RESPONSE 1 A. doc
Co�7g@@o
urban design, inc.
addressed from Stanford Drive. An address marquis shall be provided with 8"
numerals. (Bronze numerals on brown brick are not acceptable).97UFC901.4.4
A note indicating addressing requirements has been added.
WATER SUPPLY
Fire hydrants are required with a maximum spacing of 600 feet along an approved
roadway. Each hydrant must be capable of delivering 1500 gallons of water per minute
at a residual pressure of 20 psi. No commercial building can be greater than 300 feet
from a fire hydrant. 97UFC901.2.2.2
Northern Engineering is confirming hydrant spacing and fire flows
Knox Box Policy
Poudre Fire Authority requires a "Knox Box" to be mounted on the front of every new
building equipped with a required fire sprinkler system or fire alarm system.
97UFC902.4 PFAPOLICY88-20
So noted.
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered. Afire pump may also be required,
as well as standpipes for the building and the parking garage below grade. 97UBC
Notes to this effect have been added to the plans. Further coordination will occur
as construction documents are completed
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below grade.
Stage One shall be tied to a Carbon Monoxide Detection System that will detect carbon
monoxide at 50ppm over 8 hours and/or 200ppm over 1 hour and ventilate the garage.
Stage Two shall provide ventilation for smoke removal in the event of a car fire.
UBC1202.2.7
Notes to this effect have been added to the plans. Further coordination will occur
as construction documents are completed
Department: Police Issue Contact: Joseph Gerdom
Topic: General
9
Lighting Plan: The Luminaire schedule and luminaire detail don't provide sufficient
information to determine exactly which lights are used in each location. Also, unless
there are wall fixtures there is inadequate illumination between Bldg. B & C; east face of
Bldg. D; and north face of Bldg. B. In general, all building access points should have
minimum of 1 fc.
A revised lighting plan is included with these plans.
G:\W P\9000\9600\9601 P DP -RESPONSE 1 A doc
C'�Y7 § O 0
urban design, inc.
Topic: Landscaping
10
Landscape Plan: The use of Austrian Pine, cotoneaster, and ninebark along the faces of
Bldg. B, C, and D, particularly in front of public/private entrances will obscure these
areas and raise security issues. Lower growing species, lighting, or some combination
thereof would be recommended.
We have reviewed the landscape plan, and noted that adequate security lighting
is to be provided at building entrances.
Department: Stormwater Utility Issue Contact: Wes Lamarque
Topic: Erosion Control
15
The report table of contents doesn't have the correct page numbers for the erosion
control report.
The report table of contents has been revised to correctly reference all pages.
Your plan calls for straw bale inlet filters at a number of locations. Straw bales do not
work on concrete or asphalt surfaces. When are these to be installed, after inlet
construction but prior to hard surfacing? You need to spell the intent out with notes on
the plan.
Gravel bag inlet filters will replace straw bales as the BMP of choice. The gravel
bags will be effective both before and after hard surfacing.
What is to protect. Warren Lake during the construction of the outlet drain piping system
and the roadway (Horsetooth) construction? All of these and water quality pond #1
seem to be outside the limits of your erosion control BMP's.
Silt fencing and a gravel bag check dam have been added near the
reconstructed headwall to protect Warren Lake during construction.
The surety is calculated incorrectly with regard to reseeding/mulching. Also, $1.3O/lf on
silt fencing is pretty cheap. Who does it for that, you?
Proper unit prices are now included in the surety calculations for both reseeding
and silt fencing.
Topic: General
16
Please revise the general notes section to apply to this project and the city of Fort
Collins. Please check that the benchmarks referenced are the closest to the site.
The general notes have been updated for this project and location.
G:\WP\9000\9600\9601 PDP-RESPONSE1A.doc
Co�Y7PQ o
urban design, inc
17
Please provide a signature block for the Warren Lake Owner. Please provide
construction/ drainage easements on the south side of Horsetooth Rd.
There is already an existing easement for the proposed improvements at the
headwall. No additional easements or approval blocks are needed. Enclosed is a copy
of the Utility Easement Dedication for the First Replat of The Landings First Filing. (Rec.
# 366979, Book 2051, Page 0546), dated 06122180.
20
Please specify on the plans where maintenance responsibility changes from property
owner to City of Fort Collins.
The plans now clearly specify which storm sewer is to remain private and which
storm sewer is to be maintained by the City of Fort Collins.
22
The minimum pipe size is 15" according to the Storm Drainage Design Criteria or storm
sewers maintained by the City. Also, class III RCP is required under all city streets.
Please revise the storm sewer system to meet the minimum criteria.
All storm sewer to be maintained by the City of Fort Collins is at least 15"
diameter. Also, all storm sewer located under City streets is Class 111 RCP.
23
All swales and ponds require a concrete pan when slopes are less than 2%. Please
revise plans.
A concrete trickle pan has been added to Swale D.
25
Please provide pond depth markers where water is more than 3 ft. deep. Please include
the depth marker detail in the plans.
WQ Pond 1 has a pond depth marker specified, and the detail is also included.
27
Please specify which pipes are pressure sealed on plans. Consider resizing pipes to
minimize pressurized areas.
Storm sewer lines requiring water-tight/pressure-sealed gaskets have been
clearly noted on the plans. All storm sewer lines have been sized to convey the 100-
year flows without surface ponding.
Topic: Grading
18
Please maintain a maximum of 4:1 grading on site. Currently the west entrance area
and west detention ponds have slopes greater than allowed.
G:\WP\9000\9600\9601 PDP-RESPONSE1A.doc
urban design, inc.
WQ Pond 2 has 3:1 side slopes. This pond will not be maintained by the City of
Fort Collins. Furthermore, it will not be sod -grass, but rather native grasses requiring
less mowing. All maintenance will be performed by the local homeowners association.
Also, an erosion control blanket has been proposed for slope stability until permanent
vegetation has been established.
19
Please revise the grading plan to include top of wall and bottom of wall elevations for all
retaining walls and terraces on site. Include enough grading and spot elevations on
each level to show drainage patterns. Also, include details of retaining and pond walls.
Please include more spot elevations around buildings and in parking lots to clarify
grading and drainage. Currently some areas do not have enough information to show
how water drains. Please provide low points in both detention ponds.
The requested detail has been added to the grading plan.
Topic: Landscaping
24
Please maintain a minimum of 1 Oftseparation between trees and storm sewers. There
is very dense landscaping shown around the southern inlets and in the northern swale,
please check that drainage will not be affected.
10' separation is maintained between trees and City maintained storm sewers.
The minor area inlet drain system behind the walk along Horsetooth Road is to be
maintained by the H.O.A.
Topic: Riprap
26
Please call out all riprap on plans and profiles. Is there any riprap or protection at the
outlet of Storm Sewer E?
Riprap is now called -out on the storm sewer plan and profiles. The existing
riprap at the outfall of Storm Sewer Line E is also shown on the plans.
Topic: Spillway
21
Please provide spillways and conveyance for flows from water quality ponds in case
outlet is plugged. Please provide calculations and cross sections for the spillways.
Spillways (emergency overflow weirs) have been provided for both ponds.
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: General
11
Please show bicycle parking as appropriate at each building near main entrances.
G:\W P\9000\9600\9601 PD P-RESPONSE 1 A. d oc
UYpQ o
urban design, inc.
Bike rack locations have been noted on the revised plans.
12
What number of HC parking spaces exist on lower level? Is there elevator access or
adequate access for ADA?
Elevator access and the 8 HC spaces provided on the lower level are noted.
13
Provide cross -sections of Horsetooth (arterial)
lanes to standard.
and Stanford (Collector), including bike
Cross sections are provided on sheet 6. As per the Engineering comments, some
compromises to normal standards are necessary due to existing conditions.
14
Provide pedestrian refuge for movement across Horsetooth. This can be done either
through the extension of the median and/or a porkchop island for the right turn lane.
As per the direction we received from Engineering, pedestrian refuge is provided
at the painted median between the west bound left turn lane and the eastbound travel
lanes.
Belated Comment (received January 25, 2002)
Requiring Bella Vista to complete the sidewalk connection on the east side of Stanford.
This comment is in conflict with the direction we received earlier from
Transportation Planning. The adjacent Aspen Leaf Apartments has a minimal
pedestrian walkway system, which (as approved by the City of Fort Collins) includes
connecting walkways only within the center of the site. These walks dead in into the
asphalt parking lots, forcing resident pedestrians to walk in parking areas and
landscaped areas to reach any of the surrounding streets. While there are existing
walks along Monroe and Stover, my extensive personal experience with the Aspen Leaf
site indicates that these public walks are not used, largely because cutting through the
Aspen Leaf site — by walking in the parking areas and the central building access walks
— is a more direct route to area destinations. This will also be true of any pedestrian
destinations 1 Bella 'Vista; and the connecting walk previously agreed with City Staff, and
proposed by this applicant works better with the "real' pedestrian circulation pattern in
Aspen Leaf, while a new walk along Stanford will not integrate with the actual
pedestrian circulation in the area.
Because a retro-fitted walk on the east side of Stanford would be expensive to
construct; will disrupt existing landscaping; and will not provide easier access to the
Bella Vista site or other area destinations, we do not agree with the belated request to
construct this off -site walk. It is not reasonable to require this development to correct a
past mistake by the City and an earlier developer. Similar requirements have not been
made of other recent developers. (For example the King Soopers at Harmony and JFK
G:\W P\9000\9600\9601 PDP-RESPONSE 1 A. d oc
urban design, inc.
did not have to build walkways in the Fairway Estates subdivision; or even make
connections back to Boardwalk along Harmony).
Department: Waiter Wastewater Issue Contact: Jeff Hill
Topic: Landscaping
48
Coordinate landscape design with the civil design and provide the required
landscape/utility separation distances. Show all existing and proposed water/sewer
mains and services on the landscape plans.
Utilities are shown, and coordinated with landscaping as requested.
Topic: Plat
47
Provide a 30 foot minimum utility easement for the existing 8-inch sanitary sewer main
which crosses this site. No buildings, retaining walls, trash enclosures, over hangs,
landscape boulders, etc my be placed or erected within the utility easements.
As per the decision at the January 9th Utility Coordination Meeting, the easement
will remain at 20' with the understanding that the existing sewer main will be encased in
concrete; it will be confirmed that the existing line is not a clay tile material, and minor
building encroachments 17' or more above finish grade will be allowed. Repair and
replacement of landscape and hardscape plaza elements required as a result of any
future requirement to excavate the adjacent portion of the sewer line will be the
responsibility of the property owner/H.O.A.
Topic: Utility plans
49
Call out all fittings, thrust blocks, valves, water/sewer service sizes on the overall utility
plans.
Northern Engineering has addressed these comments
50
Maintain a 4 feet minimum separation distance between the outside wall of all meter pits
and any permanent structure (I.e. retaining walls, buildings, landscape boulders, trash
enclosures, etc.).
To the extent practical, meter pits will be located as requested. Further
coordination will occur as construction documents are completed.
51
Provide separate water and sewer services for each building and each use within each
building (I.e. commercial, residential).
The required number of services will be provided
G:\WP\9000\9600\9601 PDP-RESPONSE1A.doc
urban design, inc.
52
Eliminate all un-necessary bends and low angle crossings of water, sewer and storm
sewer lines.
Bends and low angle crossings have been minimized to the extent practical
53
Show and label all curb stops and meter pits on the overall utility plans. Clearly identify
these with size and location.
Northern Engineering has addressed these comments
54
Clearly show and label all water, sanitary sewer and storm sewer crossings in all utility
profile views. Define any and all lowerings or adjustments. Maintain 18-inches of
vertical separation between all water, sanitary sewer and storm sewer crossings.
Northern Engineering has addressed these comments.
55
Will an irrigation tap be required within this site?
No. Irrigation is intended to be taken off one or more of the domestic services to
the buildings.
56
Provide a manhole adjustment and a concrete encasement detail with the next
submittal.
Northern Engineering has addressed these comments
See the site, landscape and utility plans for other comments.
Rather than greatly reducing the landscape plantings, a note obligating
landscape repair and replacement by the H.O.A. has been added so that 10' clearance
from service lines is not required.
Department: Zoning Issue Contact: Peter Barnes
Topic: General
3
General note 1(d)(ii) lists "live/work office type units" as a possible use. What is that?
No such term. Is it the same as a home occupation?
Live/Work is a type of mixed -use dwelling concept, wherein a work (non-
residential) space is accessory or incidental to the primary residential uses in the same
structure. In this case, the non-residential use may be a home occupation, or any other
Type 1 use allowed in the MMN District. Although the term "live/work" is not in the Fort
Coffins Land Use Code, it is a common planning term in current practice, and
represents a desirable mixed -use concept.
G:\WP\9000\9600\9601 P DP -RESPONSE IA. d oc
Project Comments Sheet
Selected Departments
Citv of Fort Collins
Department: Stormwater Utility
Date: December 24, 2001
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
December 26, 2001
Note - Please identify your redlines for future reference
Issue Contact: Wes Lamarque
Topic: Erosion Control
15
The report table of contents doesn't have the correct page numbers for the erosion control report.
Your plan calls for straw bale inlet filters at a number of locations. Straw bales do not work on concrete or asphalt
surfaces. When are these to be installed, after inlet construction but prior to hard surfacing? You need to spell the
intent out with notes on the plan.
What is to protect Warren Lake during the construction of the outlet drain piping system and the roadway (Horsetooth)
construction? All of these and water quality pond #1 seem to be outside the limits of your erosion control BMP's.
The surety is calculated incorrectly with regard to reseeding/mulching. Also, $1.30/If on silt fencing is pretty cheap.
Who does it for that, you?
Topic: General
16
Please revise the general notes section to apply to this project and the city of Fort Collins. Please check that the
benchmarks referenced are the closest to the site.
17
Please provide a signature block for the Warren Lake Owner. Please provide construction/ drainage easements on the
south side of Horsetooth Rd.
20
Please specify on the plans where maintenance responsibility changes from property owner to City of Fort Collins.
22
The minimum pipe size is 15" according to the Storm Drainage Design Criteria on storm sewers maintained by the City.
Also, class III RCP is requ d under all city streets. Please revise the storm sewer system to meet the minimum
criteria. 'W' yl-( /Z/ Z Z� /ry
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
y _ Plat _ X Site X Drainage Report _ Other Ve-,Vwsy
Utility _ Redline Utility X_ Landscape «, SkK o tt
n o r�v'n
Page 1
�lg(actn.g
urban design, inc.
4
General note 2 references Section 2.8.17. There is no such section. I assume they
mean 3.8.17 (A)(3). If so, then Planning needs to determine if the 4 to 6 stories is the
appropriate "contextual height". Some of the walls of buildings are almost 90' tall. In
my opinion, "contextual height" as used in 3.8.17(A)(3) implies a similar height in feet as
well as in stories. For instance, a 6 story building on one lot may only be 70' tall, and
that doesn't mean that it's therefore ok to have a 6 story building on an adjacent lot that
is 90' tall when the maximum height allowed in the MMN zone is 3 stories (4.5(E)(1)(d).
How tall is the Marriott in terms of feet?
According the Land Use Code, "Height may be measured according to any [not
all] of several methods." Building Height limitations in various zoning districts are stated
in terms of the number of stories. Section 3.8.17 (A)(3) refers to Contextual Height in
relation to the "zone district maximum height", which is regulated according to the
number of stories. The difference in height from ground floor to "the highest point of the
roof surface or structure" between the Marriott and the tallest proposed building at Bella
Vista is approximately 12'. Making the Bella Vista building shorter by using a flat roof,
or by changing the plan to four, identical five story buildings would result in a less
attractive project, while the reduction in height would be imperceptible.
5
General note 13 - wood gates are not advisable.
So noted.
6
General note 1(d)(iii) - small food service uses listed are not classified as accessory
uses. Therefore, they are not permitted in the MMN zone. (the only way they can be
remotely "accessory" is if they serve only the residences of the building, and are not
open to the "public".
At a Novernber 2 Id meeting with City Planning Staff, we were assured that small
food services uses would be considered as accessory uses. This was the basis for our
request for MMN zoning rather than a combination of zones that would have allowed a
greater mix of uses.
7
General note 1(C)(ii) - B&B's would not be allowed. Such a use is a use that is
conducted in a private house, not in a condo building.
We can find nothing in the Land Use Code that precludes B&B's from being
located in a condominium building. B&Bs are clearly allowed in the MMN District, while
"private houses" are allowed only on lots of less than 6,000 square feet. Such "private
houses" would not be conducive to a six bedroom B&B.
G 1W P\9000\9600\9601 PDP-R ESP ON S E 1 A. d oc
co
�Y2�§Qo
urban design, inc.
Topic: Landscaping
8
The surface level parking lot is required to have interior parking lot landscaping.
(Sections 3.2.1(E)(5) and 3.2.2(M)(1). Does the parking underneath the surface lot
preclude interior landscaping? If so, then a modification will be required to 3.2.2(M)(1)
since there is no alternative compliance provision to that section and since there is no
automatic exemption for a surface lot on top of an underground lot. The lot does have
some landscaping that could qualify as interior, but not enough.
The revised plan meets the 6% interior landscape area requirement. We would
be interested to know how the Mason Street Parking Garage meets this standard. Our
office provided the landscape plans for that project. During the review of the Mason
Street Parking Garage, no one ever suggested that the above mentioned sections of the
Code would be applicable, and — to my knowledge - no modification was required.
The following comments were expressed at Staff Review on December 26, 2001:
Natural Resources:
The plans are showing only one trash enclosure location. This does not seem to
be enough for the development program that is proposed.
A second trash enclosure has been added.
Engineering:
Off -site grading on the property to the north will be required. A letter of intent
from that property owner will be needed prior to scheduling this item for a public
hearing and the actual off -site easement from the property owner will be needed
at the time of final compliance review.
(See above)
2. Additional street right-of-way for Stanford Road is not needed; however, the
public sidewalk must be located in a public access easement.
(See above)
3. The East Horsetooth Road design that was part of the PDP submittal is not
sufficient. It does not meet the City's street design standards and requirements.
A variance request will be needed.
Northern Engineering has addressed this comment.
4. The 9' wide utility easement as shown along East Horsetooth Road needs to be
15' wide. The applicant may submit a variance request for the easement width.
(See above)
G\WP\9000\9600\9601PDP-RESPONSE1Adoc
urban design, inc.
5. The necessary westbound right -turn lane on East Horsetooth Road will have an
impact on the building placement in this development.
(See above)
6. There is a 660' minimum separation requirement between the access onto East
Horsetooth, Road and Stanford Road. The distance as shown is about 610'. The
applicant may submit a variance request for the minimum separation.
(See above)
7. The applicant has to do a roundabout study for the intersection of East
Horsetooth Road and Stanford Road.
(See above)
8. Pedestrian refuge islands are needed in both East Horsetooth Road and
Stanford Road.
(See above)
9. The street striping as proposed does not meet the City's standards.
(See above)
10. There is a requirement that the utility plans show conditions at least 100' past the
limits of construction for this project.
Northern Engineering has addressed this comment
11. Adequate drainage in the medians in the streets must be provided.
(See above)
12. It is important that a utility coordination meeting be held.
A Utility Coordination Meeting was held on January 9rn
13. A big issue ..... the Poudre Fire Authority has a requirement for a 30' wide
emergency access on -site through this project because of the proposed
height of the buildings.
As per my discussions with Ron Gonzales, 30' fire lane areas have been
provided on one side of each building.
14. The length of the straight section of the access drive from Stanford Road into the
parking garage is not long enough.
Because the access drive from Stanford into the parking garage is "in only" no
straight section is needed. The condition is not unlike a "free right" turn at a
street intersection.
15. There may be a problem with the placement of the parking garage gates.
G:\W P\9000\9600\9601 PDP-RESPONSE 1 A. doc
o
urban design, inc.
There are automatic overhead doors planned at the entrances to the parking
garage. We are not aware of any problems with their locations.
Planning:
1. This development proposal, with the uses as identified on the Site Plan, is
considered to be a Type I, administrative review project. However, depending on
how the proposed commercial/retail uses are defined in the 22,000 square feet of
non-residential floor area, and if any modifications to standards are deemed to be
necessary, the proposal could be subject to a Type II, Planning & Zoning Board
review.
As noted on the PDP it is the applicants' intent to limit uses to those allowed as Type 1
in the MMN District, including the accessory uses as agreed with Planning Staff on
November 2"d. We do not believe that modifications to the Code are needed.
2. The proposed small food service uses, Item iii) under Accessory Uses in the
General Notes, may be of concern. If there are several very small users, as staff
and the developer have previously discussed, then these food services could be
considered to be accessory uses. However, if a single restaurant were to occupy
the bulk of the defined food service space (up to 4,500 square feet) then there
would be a problem associated with the list of permitted uses in the MMN District.
Restaurants are not a permitted use in this district.
Standard, "sit-down" franchise restaurants are typically 6,000 to 8,000 square feet. It is
our intent to establish a limit to the size that would — from a practical point of view —
essentially preclude those larger restaurants. The lack of ample customer parking on
the site (further limited by the required 30' fire lanes) also makes this project un-
attractive to any larger food service operations. The result of a similar discussion
regarding a residential, mixed -use plan in Loveland resulted in a limit of 4,000 square
feet on any individual "restaurant, pub, coffee shop, or similar use". It must be
remembered that allowing some reasonable food service operation is key to the "social
gathering" or "neighborhood center" function that is appropriate at this location. This
site and the surrounding residential areas have no real "centers" as envisioned in City
Plan. We should not be trying to preclude Bella Vista from filling this need. With these
revisions, we are limiting accessory, "small food service" operations to a maximum of
3600 sq. ft. per food service use.
3. The proposed live/work office uses, Item ii) under Accessory Uses in the General
Notes, is a good idea; however, offices (per say) are listed as a Type Il, Planning
& Zoning Board review use in the MMN District.
We have revised the land use notes to limit office uses to Home Occupations. Other
"work" areas allowed under the "live/work" concept at this location are limited to Type 1
uses in the MMN District.
G:\W P\9000\9600\9601 PD P-RESPONSE 1 A. d oc
urban design, inc.
4. Specific elevations for Building D were not part of the original development
submittal. This building is of most concern regarding how it meets the standards
set forth in Section 3.5.3(B) Relationship of Buildings to Streets, Walkways and
Parking in the LUC. Stanford Road is a 2-lane collector street (less than full
arterial) and all mixed -use and commercial buildings must be within 15' of the
right-of-way (ROW) for this street. None of Building D is at or within 15' of the
ROW. There are patios and a sidewalk along the west side of the building, but do
they truly satisfy the criteria set forth in Section 3.5.3(13)(2)(d) of the LUC?
Additional Building D elevations are included with these revisions. As per our meeting
with Planning Staff on November 21d, Building D meets #.5.3 (B)(d) I., which states that
"Exceptions to the build -to line standards shall be permitted in order to form an outdoor
space such as a plaza, courtyard, patio or garden between the building and the
sidewalk..." Our plans include landscaping, low walls and other similar improvements
along the sidewalk designed for pedestrian interest, and visual continuity.
5. A discussion of how this project satisfies Section 3.2.1(E)(5) Parking Lot Interior
Landscaping should be done involving the developers, their consultants, City
Planning, and City Zoning. It is understood that the "surface" parking lot for the
commercial/retail uses is above an underground parking garage; however, there
may be ways to incorporate landscaping in this area.
Our revised plans meet the 6% interior landscape area requirement. Areas of shading
are addressed through the provision of trellis structures. It should be noted that the City
of Fort Collins — to my knowledge — has not applied "parking lot" landscape
requirements to the upper, uncovered, deck levels of other "parking structures" in the
review process. it continues to be unclear why this project should be held to a different
standard. City Plan clearly intended to encourage structured parking, while
enforcement of the Code appears to actively discourage that approach.
6. Section 3.2.1(E)(5)(e) of the LUC states that parking bays shall extend no more
than 15 parking spaces without an intervening tree, landscape island, or
landscape peninsula. There are 20 uninterrupted parking spaces in the bay along
the north side of Building B. As part of the interior landscaping discussion this
concern should be addressed.
We have added a landscape island. (also, see above).
7. While reviewing the Shadow Analysis Plan and Streetscape & Building
Elevations Plans against the criteria set forth in Section 3.5.1(G) Building Height
Review of the LUC, several comments have arisen:
a. Regarding Views, are there still desirable views of the foothills from the
residential areas north and south of East Horsetooth Road that will be
affected by this development? Are there views of Warren Lake from
properties north of East Horsetooth Road that will be affected? Section
G:\WP\9000\9600\9601 PDP-RESPONSE1 A. doc
o
urban design, inc.
3.5.1(G)(1)(b)2 of the LUC requires that a visual analysis of views be
submitted for review.
There are no existing views of the foothills or of Warren Lake that will be affected
by this development. Vaught'Frye is providing additional view analysis for your
review.
b. There would appear to be several areas of concern regarding Light and
Shadow on adjacent properties, mostly at the 9:00 a.m. and 3:00 p.m.
times as shown on the Shadow Analysis Plan. Most significant is the
potential affects on buildings and parking lots to the west, across Stanford
Road.
No existing, occupied structures are affected. The only existing building affected
by the 9:00 or 3:00 December 21st shadows is the small storage/maintenance
building at the, Aspen Leaf Apartments. A future building on the Marriott
expansion portion of the Marriott lot west of Stanford may be affected as the
existing Marriott affects the Arena Office Buildings to the west of the hotel.
C. Due to the placement of these buildings and their relationship to
surrounding properties, it does not appear that "Privacy" should be an
issue.
We agree
d. Regarding Neighborhood Scale, it would be appropriate for the
developer/applicant to submit a more detailed written narrative than what
has been presented in Section 9) of the Statement of Planning Objectives
in support of the buildings heights and massing. The City still has some
"contextual" concerns regarding this issue. Understanding the "Contextual
Height' definition in Section 3.8.17(A)(3) of the LUC, there is still some
discussion needed about where this site is situated relative to the taller
buildings (such as the Marriott Hotel) in the area.
Additional written and graphic materials are in process.
8. The Building Elevations Plans should indicate, to some degree, the building
materials and colors being proposed as set forth in Section (2) of the PDP
submittal requirements. Also, what will the elevations of the buildings interior to
the site look like? Typically, elevations for all 4 sides of buildings should be
submitted.
Vaught*Frye is providing the additional architectural information requested.
G:\WP\9000\9600\9601 PDP-RESPONSE1A.doc
C OX72@@ o
urban design, inc.
9. There may be additional Planning comments on red -lined plans that are being
forwarded to the applicant.
No significant additional comments were reflected on the red -lines we have received.
Sincerely,
Eldon Ward
Cityscape Urban Design, Inc.
cc: Chuck McNeal, Stanford Development, LLC
Javier Martinez Campos, Stanford Development, LLC
Frank Vaught, Vaught ` Frye Architects
Bud Curtis, Northern Engineering
Matt Delich
G:\WP\9000\9600\9601 PDP-RESPONSE1A.doc
REVISION
COMMENT SHEET
DATE: January 30, 2002 TO: Engineering
PROJECT: #45-01A Bella Vista PDP - Type I (LUC)
All comments must be received by Steve Olt no later than the staff
review meeting:
February 20, 2002
El No Comment
❑ Problems or Concerns (see below or attached)
"PLEASE IDENTIFY YOUR REDLINES FOR FUTURE
REFERENCE**
Date: __Signature:_
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ Site _ Eminage Report Other
Utility Redlinc Utility Landscape
Marc Virata --Bella Vista Utili Plans Pa e 1
g
From: Eric: Bracke
To: Cam McNair; Dave Stringer; Kathleen Reavis; Mar...
Date: Tue, Feb 5, 2002 11:41 AM
Subject: Bella Vista Utility Plans
I just reviewed the Belle Vista Utility Plans and provide the following comments:
1. Horsetooth Road:
- on the east end of the project, they are showing 3.E' t ike lanes and 10.6' travel lanes. This is a 40 mph
facility and these lane widths are not acceptable to Traffic Engineering. I would settle for 6' bike lanes ( if
TP agrees) and 11.5' travel lanes.
-The redirect taper for westbound traffic is shown at '40'. Again, this is a 40 mph facility and using the
standard WS^2/60 calculation, the taper should be 320'.
-The eastbound bike lane at Landings needs to start at the pc, not 25' east of the taper to begin the bike
lane A cyclist is likely to get "squished" under this design.
- I definitely remember the discussion at TC regarding the need for a WB right turn lane - based on our
standards and not the TIS or LOS requirements. It is still not shown.
2. Stanford
- a 10' right turn lane is not acceptable
- have them get rid of the 4' painted median and use 2' for the SB right turn, 1' for the SB thru, and 1' for
the SB left turn.
Kind Regards,
Eric L. Bracke, P.E.
Traffic Engineer
City of Fort Collins
970-224-6062
ebracke@fcgov.com
urban design. inc.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the
site. A letter of intent from the property owner not objecting to the offsite work is
required to be submitted prior to any public hearing for the project.
Topic: Plat
46
The Development needs to dedicate an access easement along Stanford Drive to
ensure the sidewalk proposed is in an access easement. Additional right-of-way is not
necessary.
(2/20) It appears that additional access easement along Stanford Drive (and Horsetooth Road)
is necessary to ensure that all of the proposed sidewalk is in easement.
66
A minimum of 57.5' of half street right-of-way is required to be dedicated along the
entire length of the property with a consistent utility easement width, in conformance
with LCUASS. It is understood that 9' instead of the 15' of necessary utility easement is
being proposed behind the right-of-way; when all the design and utility issues are
resolved along Florsetooth, the variance request for reduction in utility easement width
will be routed to the utilities for approval.
75
There may be a benefit in designating on the plat that the emergency access easement
is for the "surface level" only. There may be issues from a title company on how the
emergency access easement is represented as going through a building envelope.
Topic: Sidewalk
99
The grading plan appears to show that inlets with straw bales will be in close proximity
or perhaps even overlapping with the street sidewalks. These straw bales need to be
outside of the sidewalk section. Perhaps a different erosion control measure can be
used if the straw bales are encroaching into the sidewalk for a period of time.
Topic: Street Design
32
Directional ramps are required on new construction in accordance with LCUASS.
(Standard Drawing 16-4D) Provide the detail on the plan set.
(2/20) The response from the applicant stated that this could not be accommodated due to
existing constraints. The design engineer should provide documentation on why this cannot be
accomplished. Note that because of the right turn discussion, any previous limitations due to
existing constraints may no longer be applicable.
34
A right -turn lane for westbound Horsetooth onto northbound Stanford still should be
designed and constructed. There is a community wide benefit in the construction of the
right turn lane, thus this is eligible for Street Oversizing reimbursement. The design of
the right -turn lane should look at providing pedestrian refuge between the right -turn and
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
23
All swales and ponds require a concrete pan when slopes are less than 2%. Please revise plans.
25
Please provide pond depth markers where water is more than 3 ft. deep. Please include the depth marker detail in the
plans.
27
Please specify which pipes are pressure sealed on plans. Consider resizing pipes to minimize pressurized areas.
Topic: Grading
18
Please maintain a maximum of 4:1 grading on site. Currently the west entrance area and west detention ponds have
slopes greater than allowed.
19
Please revise the grading plan to include top of wall and bottom of wall elevations for all retaining walls and terraces on
site. Include enough grading and spot elevations on each level to show drainage patterns. Also, include details of
retaining and pond walls. Please include more spot elevations around buildings and in parking lots to clarify grading
and drainage. Currently some areas do not have enough information to show how water drains. Please provide low
points in both detention ponds.
Topic: Landscaping
24
Please maintain a minimum of loft, separation between trees and storm sewers. There is very dense landscaping
shown around the southern inlets and in the northern swale; please check that drainage will not be affected.
Topic: Riprap
26
Please call out all riprap on plans and profiles. Is there any riprap or protection at the outlet of Storm Sewer E?
Topic: Spillway
21
Please provide spillways and conveyance for flows from water quality ponds in case outlet is plugged. Please provide
calculations and cross sections for the spillways.
Page 2
cc
n@ o
urban design, inc.
through lane, especially since the width of Horsetooth would require a ped refuge under
LCUASS.
(2/20) The issue of the right turn lane was discussed at the City's 2/14 Transportation
Coordination Meeting. It was viewed that the submitted justification for not designing the right
turn lane was not compelling and that a right turn lane could be designed into the project.
Please note that any written documentation regarding the designing of the right -turn lane should
be provided by the design engineer (a licensed professional engineer.)
35
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals). (It
appears that a straight-line grade from the crown of Horsetooth Road to the flowline is
not being provided as shown on the grading plan, cross -sections will help confirm or
deny this.)
(2/20) The cross section sheets need to have the centerline elevations labeled, the curb and
gutter section should be distinguishable from the asphalt section, and the right-of-way should
also be shown.
36
Show centerline and flowline profiles on Horsetooth Road.
(2/20) Can the grid lines or scale be modified in order to allow for every XX+00 stationing to be
on a grid line? Only every 3rd XX+00 stationing is on a grid line.
37
Provide the bearing and distance for the flowline on the plan view portion of the plan
and profile sheet for Horsetooth Road.
(2/20) This information isn't shown east of the driveway and only bearing (no distance) is being
shown west of the driveway.
60
Because of the aforementioned need for the right -turn lane, eliminating the offset
through the intersection, and the constraint of the existing storm drainage
improvements, it is understood that the bike lane design for westbound Horsetooth may
have to be compromised. A reduced bike lane width of 6' (including gutter) with a
continuous concrete pour should be looked at as one potential compromise. It may also
be necessary for the bike lane to stop short of the intersection to accommodate the
right -turn lane. An additional option would be to look at widening the sidewalk and
create a combined bike/ped area behind the curb if the bikelane cannot be
accomplished.
(2/20) With the right turn lane still being an outstanding issue, the proposed design of the
westbound bike lane will not be commented on by Engineering at this time. It is still considered
ideal that the bike lane is continuous to the intersection.
62
Add the following note as reference wherever patching is shown on the plans: Limits of
street repair are approximate. Final limits to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City Street repair standards.
(2/20) Ensure that this note is referenced to the work along Stanford as well.
67
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
urban design, inc
The "bulb -outs" proposed on Stanford Drive may be allowed only if the gutter is
redesigned to go around and along the bulb outs, not through them. There are
maintenance concerns with the current proposal due to dirt and debris collecting
between the bulb outs and the flowline.
68
[12] The vertical curve shown is too short in length for the street classification of
Horsetooth. A K value of 110 is required, 60 is shown.
69
[13] A vertical curve is needed for the Horsetooth proposed flowline as it approaches
the existing storm lines. A grade break is shown with a 0.6% grade going to a 1.691/c
grade.
70
[13] Fix the vertical elevation labeling on this sheet for the profile view.
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the variance
to reduce the utility easement along Horsetooth were all viewed favorably upon by the
City Engineer. Final approval of these variance requests will occur with completion of
the designs for Horsetooth and Stanford that are acceptable to the City and the utilities.
72
[13] The 2.55% shown on this sheet appears to actually calculate to 4.2% with the
elevations and stationing shown.
77
The Traffic Engineer has noted that the center turn lane should be continuous from the
intersection to the Cove Island development and continuing east. The Traffic Engineer
notes that a 3/4 movement to allow left turns into the site could be designed (with
painted medians) in conjunction with the porkchop island to facilitate right turns out of
this driveway.
78
The cross section sheets show the additional road width to be 4% or even greater.
Because a saw cut is being shown to the centerline for most of Horsetooth, a
continuous straight line grade needs to be maintained along the entire north half of the
roadway where the sawcut is shown. For the additional width between stations 10+00
and 11+00, (where the roadway is not being sawcut to centerline), this new portion of
roadway is limited to 3%.
79
A grade break is shown on Sheet [12] that exceeds .40%. A vertical curve would be
required based on this design.
98
Provide spot elevations at the Horsetooth and Stanford intersection in accordance with
LCUASS Standard Detail 7-32B.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
o
urban design, inc.
100
The submitted "Street Cross Sections" from the site planner is not appropriate to be
submitted as a document along with the site and landscape development plan
documents. Street cross sections are to be shown on the utility plan set and will be
established based upon an approved design for the roadway(s).
101
Angle points along the flowine appear to be shown along Horsetooth, please revise and
use curves as shown in LCUASS 7.4.1.
104
It appears that redirects are too abrupt on the street striping plan. See traffic comments
regarding this.
Topic: Utility plans
76
The drawings retarding the storm system across Horsetooth originally approved by the
City showed an inlet being tied to the easternmost pipe, the submitted plans show that
the inlet is tied to the westernmost pipe.
Applicant Response:
1) General
a) The access ramp design is now reconciled on both the site plan and utility plans.
b) General note #4 has been revised to reflect adopted City Policy.
2) Grading
a) A letter of intent is being provided as requested.
3) Plat
a) Access easements for all public walks will be provided upon resolution of the
alignment:3 of the affected walks.
b) The minimum right-of-way is now indicated, along with a utility easement
adiacent to Horsetooth Road.
c) The emergency easement is noted for the "surface level" only as suggested.
4) Sidewalk
a) Erosion control and walk locations have been reconciled on the revised plans.
5) Street Design revisions are reflected in the utility plans and addressed in the
response letter from Northern Engineering.
6) Utility Plans revisions are reflected in the utility plans and addressed in the response
letter from Northern Engineerinq
Department: PFA Issue Contact: Ron Gonzales
Topic: Plat
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered. A fire pump may also be required,
as well as standpipes for the building and the parking garage below grade. 97UBC
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
urban design, inc.
The response letter from Cityscape stated that notes to this effect have been added to
the plans. Please indicate where the notes are.
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below grade.
Stage One shall be tied to a Carbon Monoxide Detection System that will detect carbon
monoxide at 50ppm over 8 hours and/or 200ppm over 1 hour and ventilate the garage.
Stage Two shall provide ventilation for smoke removal in the event of a car fire.
U BC 1202.2.7
The response letter from Cityscape stated that notes to this effect have been added to the
plans. Please indicate where the notes are.
Applicant Response:
a) Notes regarding sprinkler requirements fire pumps standpipes and 2-stage
ventilation have been added to the PDP General Notes (#'s 23 and 24)
Department: Police Issue Contact: Joseph Gerdom
Topic: General
9
Lighting Plan: The Luminaire schedule and luminaire detail don't provide sufficient
information to determine exactly which lights are used in each location. Also, unless
there are wall fixtures there is inadequate illumination between Bldg B & C; east face of
Bldg D; and north face of Bldg B. In general, all building access points should have
minimum of 1 fc.
Topic: Landscaping
10
Landscape Plan: The use of Austrian Pine, cotoneaster, and ninebark along the faces of
Bldgs B, C, and D, particularly in front of public/private entrances will obscure these
areas and raise security issues. Lower growing species, lighting, or some combination
thereof would be recommended.
Applicant Response:
A revised light�nq plan has been provided indicating locations of wall mounted
fixtures for security lighting. The provision of adequate lighting — rather than reduced
landscaping — is the preferred security measure.
Department: Stormwater Utility Issue Contact: Basil Harridan
Topic: Construction Easements
80
The proposed 24" RCP across Horsetooth Rd. will necessitate the construction of a
headwall and part of the culvert on Tract D of The Landings 1 st Filing. Prior to
construction on this Tract owned by that HOA the contractor should make sure that the
HOA is notified and that the area will be properly restored. Even though this area is in
\\SERVER\Server_D\WP\9000\9600\9601 PDP-RESPONSE3.doc
CXM@Q o
urban design, inc.
an existing drainage easement, the landings 1 st Filing HOA which maintains this area
should ensure that the area is put back to an acceptable level, equal or better than
before construction.
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the Warren Lake
Ditch company must sign off on these plans.
Topic: Drainage Report
83
Please provide street capacity calculations for Horsetooth Road for the area that is
being widened by this project. Since Horsetooth is a major arterial the standards call for
no curb overtopping in the 10-year storm and one lane open in the 100 -year storm.
Please provide sizing calculations for the proposed Stormceptor.
Please provide sizing calculations for the proposed spillways on ponds 1 and 2.
Topic: Erosion Control
86
Please submit an erosion control plan that meets the standards of the City of Fort
Collins. The submitted materials do not meet our minimum standards. Contact Bob
Zakely for further directions.
Please provide a better detail for the proposed erosion control fabric for Pond 2.
Provide a seed mix for the native grass proposed in this pond.
Topic: Grading
85
The proposed offsite grading on the northwest corner of the site will require an off -site
grading easement from the adjacent property owner.
Please provide a detail of the retaining walls that are not part of the proposed buildings.
There are still some areas in the upper level parking that do not seem to drain properly.
Please revise and add spot elevations. The proposed patio area to the west of Building
B has a low point with no proposed drainage outlet.
Topic: Landscaping
90
Several inlets on private property might be affected by the dense vegetation proposed
around these. Please revise landscaping plans to ensure proper drainage from these
areas even though they will be owned and maintained by the Bella Vista HOA.
Topic: Off -site Grading Easement
88
The swale on the north side of the property as well as some grading takes place on
private property (Strachan 1 st Filing Subdivision) . The plans show that this easement
will be granted b,y separate document. A letter of intent will be required prior to PDP
hearing and a final easement is needed prior to Final Compliance.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
urban design, inc.
Topic: Plat
89
Please connect drainage easement in driveway to off -site drainage easement on the
plat.
Topic: Roof Drainage
91
Please show on the plans how the roof drains are getting to the proposed water quality
ponds.
Topic: Tree Removal
81
The construction of the 24" pipe across Horsetooth Rd. could impact the existing 8"
Blue Spruce on the south side of Horsetooth. The note that was added to the plan calls
for the contractor to determine in the field whether this tree can be saved. This is not
acceptable. The City will not allow the contractor to remove this tree at his own
discretion. Please REMOVE this note as the City will not allow this tree to be removed
and provide plans that will preserve the tree in place.
Topic: Utility plans
82
This is a repeat comment: The proposed storm sewer coming from the Stormceptor
and tying into the! line along Horsetooth is currently shown as a 12"RCP. The minimum
allowed size in the ROW is a 15" line please correct. The 15" City line should extend to
the edge of the ROW (back of walk), this part of the line should be public and separated
from the private '12" line that would extend back to the Stormceptor by a manhole.
Please make sure that storm line G has enough cover at the point it exits into Horsetooth Road.
the minimum cover requirement is 1-foot below subgrade.
The proposed storm sewer on Horsetooth Rd. seems to be very close to several
existing utilities especially at the east end of the line. The line seems to be jammed
within 4' of an existing sanitary manhole and close to existing telephone and gas lines.
Such small separations are not acceptable please revise plans. The line also seems to
be under the proposed curb and gutter. A meeting with strormwater and wastewater as
well as other utilities is recommended to discuss the pipe alignment issue.
Please specify an ASTM Standard C443 gasketed joint for all pressurized storm lines.
The existing 5-foot inlets on the corner of Horsetooth and Stanford are shown to be
remaining in place on the Utility plans, while the calcs included in the drainage report
check for the sizing these inlets and the plans show that these might need to be
relocated and reconstructed with the widening of Horsetooth Rd. Please clarify. Will
the existing inlets be moved ?
If a right turn lane is called for on Horsetooth and Stanford then the existing junction box
vault should be designed to handle traffic loads and the elevation of this box should be
checked.
Applicant responses are included in the revised utility plans and response letter
provided by Northern Engineering.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
cXn@ o
urban design, inc.
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: Sidewalk
73
Applicant needs to provide off -site sidewalk connection on Stanford from their site north
to Monroe.
Based on the City's pedestrian LOS standards within the Land Use Code (LUC) and
Larimer County Urban Area Street Standards (LCUASS) the minimum LOS for
pedestrians is not met. Contrary to Mr. Delich's response, the proposed development is
actually located within the area types classified as "transit corridor" and "school walking
area". Therefore, all pedestrian LOS elements must meet LOS B, except for the visual
interest and amenities as stated within the LCUASS and the TIS provided. The
LCUASS further explains that all "destination areas" within a quarter mile (1,320 feet)
must be identified within the TIS for analysis. All locations are identified within the TIS
with the exception of the medium density residential land use to the north, which is
located on the NE corner of the Monroe and Stanford intersection. This "destination
area" does not meet the minimum LOS for "directness" as measured on the street grid
system, and thus, the minimum pedestrian LOS for "continuity" due to the lack of a
sidewalk along Stanford between the proposed development and the identified
intersection.
In addition, the LUC states in Section 3.2.2 C.7 "Offsite Access to Pedestrian and Bicycle
Destinations", that "offsite pedestrian or bicycle facility improvements may be required in order
to comply with the requirements of Section 3.2.2 (E) (1) (Parking Lot Layout) and Section 3.4
(Transportation Level of Service Requirements).
84
Proposed mid -block pedestrian crossing shown on Stanford looks problematic due to
curve. This is a Traffic Engineering call however.
Applicant Response:
As agreed at our June le meeting, the revised plans additional analysis from Matt
Delich demonstrate that the minimum LOS is met without provision of the off -site
sidewalk along Stanford, adjacent to the Aspen Leaf Apartments. It was also agreed
that the proposed mid -block pedestrian crossing on Stanford is acceptable with the
design revisions shown on the current PDP.
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: Landscaping
48
Repeat Comment: Coordinate landscape design with the civil design and provide the
required landscape/utility separation distances. Correctly show all existing and
proposed water/sewer mains and services on the landscape plans. With the tight
constraints on this site we would be willing to relax our separation requirements,
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
o
urban design,inc.
however we will not allow landscaping to be placed directly on top of our facilitates.
Please consider the placement of shrubs and trees to minimize the impact to our
facilities.
Topic: Utility plans
54
Repeat Comment: Maintain 18-inches of vertical separation between all water, sanitary
sewer and storm sewer crossings.
92
Place all curb stops and meter pits adjacent to the main when at all possible. Curb
stops must be located within a utility easement.
93
Provide a minimum of 10 feet of separation between storm sewer manholes and
sanitary sewer mains.
94
Clearly define all water main joint deflection (I.e. Vertical, Horizontal, Beginning, ending,
etc.).
95
Clearly show that the valve box located on the south side of Horsetooth will not end up
half in and half out of the vertical curb.
96
After much consideration and discussion within the utility, it has been determined that
placing concrete around the existing sanitary sewer main will only hamper any attempt
to excavate the sewer in the future if required. Please remove all notes from this plan
set which refers to encasing the existing sanitary sewer main. It has also been
determined that the existing sanitary sewer is PVC and in good condition, so no
replacement will be required.
97
The only allowable substitution for concrete encasement of sewer mains is to use a 20
foot length of D.I.P. or C-900 PVC pipe. Clearly define any substitution of concrete
encasement.
Applicant responses are included in the revised utility plans and response letter
Provided by Northern Engineering and shown on the revised Landscape Plans
with this PDP.
Department: Zoning Issue Contact: Peter Barnes
Topic: zoning
3
REPEAT COMMENT (1-31-02). General note 1(d)(ii) lists "live/work office type units" as
a possible use. What is that? No such term. Is it the same as a home occupation?
The explanation of what this is in their 1-29-02 letter is interesting, but it doesn't change
anything. Our code contains no such use, therefore the use is not allowed (4.5(C)
prohibits any use that is not expressly allowed). It still seems to me that what they are
\\SERVER\Server_D\WP\9000\9600\9601 PDP-RESPONSE3.doc
co�YP@o
urban design, inc.
describing on sheet 1 of 6 is a home occupation, which is permitted and is listed by
them on general mote 1(d)(i). This type of comment is common from Zoning whenever
an applicant lists a use that is not defined. For example, we make the same comment
relative to an applicant that lists "townhomes" as a permitted use. Since there is no
such defined term, we require them to remove it. If they really want to allow offices in
the building that are not within a dwelling unit (home occupation), then they should do a
Type 2 review in order to obtain approval for things like offices, dry cleaners, hair
salons.
4
REPEAT COMMENT (1-31-02). With regards to my original comment below, I am glad
to see that they have corrected the code section reference number. I find their
explanation in their 1-29-02 letter regarding contextual height to be interesting,
However, I believe they are missing my point. I agree that height can be measured
either in stories or feet. But since the section they reference deals with establishing a
contextual height, it is important that such height be reflected in terms of "feet" not
"stories". Since the height of a story can vary from one buidling to another, City staff
needs to have the height of the applicable buildings indicated to us in "feet" in order to
determine if the proposed height is "contextual". As I stated originally, indicating that a
Bella Vista building may be 6 stories, says nothing to us about how it relates to the
height of the Marriott since one 6 story building can be considerably shorter or taller
than another 6 story building. That's why I asked the question "How tall is the Marriott
in terms of feet"? They have explained the difference in feet in their 1-29-02 letter, now
they have to put that information on the plan.
(12-18-01) - General note 2 references Section 2.8.17. There is no such section. I assume
they mean 3.8.17 (A)(3). If so, then Planning needs to determine if the 4 to 6 stories is the
appropriate "contextual height". Some of the walls of buildings are almost 90' tall. In my
opinion, "contextual height" as used in 3.8.17(A)(3) implies a similar height in feet as well as in
stories. For instance, a 6 story building on one lot may only be 70' tall, and that doesn't mean
that it's therefore ok to have a 6 story building on an adjacent lot that is 90' tall when the
maximum height allowed in the MMN zone is 3 stories (4.5(E)(1)(d). How tall is the Marriott in
terms of feet?
6
REPEAT COMMENT (1-31-02) - General note 1(d)(iii) - small food service uses listed
are not classified) as accessory uses. Therefore, they are not permitted in the MMN
zone. (the only way they can be remotely "accessory" is if they serve only the
residences of the building, and are not open to the "public"). I've read the explanation in
the applicant's 1-29-02 letter, but I don't agree. For instance, would a Sushi Bar really
be accessory, serving the tenants of the building? I doubt it would remain in business
very long with such a small customer base.
7
REPLY (1-31-02). OK, I'll agree with B&B's being allowed. Editorial note - The
applicant has suggested that private houses on lots less than 6000 s.f. would not be
conducive to a six bedroom B&B. I would suggest that such a private house would be
more conducive to a B&B than would a 2 or 3 bedroom condo.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
urban design, inc.
(original comment). General note 1(C)(ii) - B&B's would not be allowed. Such a use is a
use that is conducted in a private house, not in a condo building.
Applicant Response:
a) The term Live/Work has been dropped.
b) The measurement of "contextual height" at this PDP is in feet — and considers
"perceived height" - per the Code Interpretation by the Planning Director. While
the five story buildings in the revised submittal are limited to 65' (the height of the
six story Marriott) the perceived height is somewhat less due to the extensive
use of pitched roofs on the proposed buildings. A six story building on this site
could be perceived to be of less height than the Marriott, even if the actual
maximum height in feet were greater than 65'.
c) Food service is now limited by the LUC definition of Convenience Retail, and
accessory food preparation areas as commonly found in Convenience Retail
uses.
d) Condominium units including B&B's may include more than 3 bedrooms.
aaaaaaaaaaaaaa as aaaa aaaaaaaaw��s.s..'��x++�+�rts.�x�xs.t+�+fs.� f �txfs.s.� w�� si r.� s.� w.'x+.rw r.+awwx�w.ttr..t�t wax
The following cornments were expressed at Staff Review on February 20, 2002:
Engineering:
1. The East Horsetooth Road design is still of concern. A westbound right -turn lane is
needed. It is warranted based on City street standards.
2. The striping as shown on East Horsetooth Road is unsafe.
3. The center left -turn lane is unneeded.
4. There are issues with the cross sections on East Horsetooth Road. They are not to
City standards.
5. Dedicate 57.5' of street right-of-way all the way to the east property line.
6. Flowlines need to be on the outside of the proposed bulb -outs on Stanford Road.
7. The 3 variance requests from Northern Engineering are still being reviewed.
8. There should be an emergency access easement on the surface parking only and
this should be noted on the subdivision plat.
Stormwater:
1. Storm water from this site will have to go into Tract D of Cove Island, to the south.
A storm drainage easement may be needed from them.
2. The proposed 12" storm sewer from the parking area needs to be a 15" pipe.
3. The storm sewer in East Horsetooth Road needs to be out from under the curb &
gutter.
4. There are lots of tree and storm sewer conflicts.
\\SERVER\Server D\WP\9000\9600\9601 PDP-RESPONSE3.doc
6 Project Comments Sheet
Ali' Selected Departments
City of Fort Collins
Department: Water Wastewater
Date: December 27, 2001
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
December 26, 2001
Note - Please identify your redlines for future reference
Issue Contact: Jeff Hill
Topic: Landscaping
48
Coordinate the landscape design with the civil design and provide the required
landscape/utility separation distances. Show all existing and proposed water/sewer
mains and services on the landscape plans.
Topic: Plat
47
Provide a 30 foot minimum utility easement for the existing 8-inch sanitary sewer
main which crosses this site. No buildings, retaining walls, trash enclosures, over
hangs, landscape boulders, etc may be placed or erected within the utility
easements.
Topic: Utility plans
49
Call out all fittings, thrust blocks, valves, water/sewer service sizes on the overall
utility plans.
50
Maintain a 4 feet minimum separation distance between the outside wall of all meter
pits and any permanent structure (Le. retaining walls, buildings, landscape boulders,
trash enclosures, etc.).
51
./z-z7 vi
Muturu U D¢te
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
;! Plat _ '< Site Drainage Report Other
Utility Redline Utility Landscape
Page 1
urban design, inc.
Transportation Planning:
1. The off -site sidewalk along the east side of Stanford Road, going to the north, is
needed. This proposal fails the Pedestrian Level of Service portion of the TIS
without it.
2. The proposed mid -block pedestrian crossing on Stanford Road, on the curve, is not
in a good location for safety reasons.
Water/Wastewater:
1. Water/Wastewater is still reviewing the plans. A meeting with the applicant &
developer is needed.
Applicant response:
The above comments were resolved at our meeting of June 10`", and/or with the
revised PDP and utility plans.
Planning:
1. The proposed small food service uses, Item iii) under Accessory Uses in the
General Notes, are of concern. If there are several very small users (up to 1,500
square feet in size), as staff and the developer have previously discussed, then
these food services could be considered to be accessory uses. However, if a single
restaurant were to occupy the bulk of the defined food service space (up to 3,600
square feet as shown on the Site Plan) then there would be a problem associated
with the list of permitted uses in the MMN District. Restaurants are not a permitted
use in this district.
2. The proposed livelwork office uses, Item ii) under Accessory Uses in the General
Notes, is a good idea; however, offices (per say) are listed as a Type II, Planning &
Zoning Board review use in the MMN District. What assurance is there that the
office users will not be separate from residents?
3. While reviewing the Shadow Analysis Plan and Streetscape & Building Elevations
Plans against the criteria set forth in Section 3.5.1(G) Building Height Review of the
LUC, several comments have arisen:
a. Regarding Views, are there still desirable views of the foothills from the
residential areas north and south of East Horsetooth Road that will be
affected by this development? Are there views of Warren Lake from
properties north of East Horsetooth Road that will be affected? Section
3.5.1(G)(1)(b)2 of the LUC requires that a visual analysis of views be
submitted for review.
b. There would appear to be several areas of concern regarding Light and
Shadow on adjacent properties, mostly at the 9:00 a.m. and 3:00 p.m. times
as shown on the Shadow Analysis Plan. Most significant is the potential
affects on buildings and parking lots to the west, across Stanford Road.
c. Regarding Neighborhood Scale, the City still has some "contextual" concerns
regarding this issue. Understanding the "Contextual Height' definition in
Section 3.8.17(A)(3) of the LUC, there is still some discussion needed about
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
o
urban design, inc.
where this site is situated relative to the taller buildings (such as the Marriott
Hotel) in the area. How tall, in feet, is the hotel and is one building in excess
of 3 stories in height in a larger surrounding area sufficient to justify 4
buildings that exceed the maximum allowable height in the proposed zoning
district for this site?
d. Typically, elevations for all 4 sides of buildings should be submitted. What do
the building ends look like?
Applicant response:
1) Food Service uses are now limited to the LUC definition of Convenience Retail, and
limited food preparation areas - as an accessory use - as commonly found in many
existing convcsnience retail stores.
2) The term Live/work has been eliminated and limited to Home Occupations, with the
level of flexibility allowed by condominium ownership. The enforcement of home
occupation u:rers not being separate from residents will be no different here than at
other locations in Fort Collins.
3) Additional building elevations view information and shadow analysis information are
included in V iught'Frye's revised plans.
Additional information is also attached for Staff consideration, including:
Alternative building elevations indicating the Applicants' preferred approach to a
mix of 4 and 6 story buildings (averaging 65' in height): as opposed to the
Proposed olan - that has resulted from the Planning Director's interpretation that
contextuai height is measured in feet - including all buildings at 5 stories (65'
maximum) in height.
r Three-dimensional views comparing the actual and "perceived" heights of the
Marriott and proposed Bella Vista buildings.
Additional neighborhood context/architectural compatibility information will be
forthcoming.
Sincerely,
Eldon Ward
Cityscape Urban Design, Inc.
cc: Chuck McNeal
Javier Martinez Campos
Frank Vaught
Daryl Sigler
Matt Delich
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
Project Comments Sheet
Selected Departments
.MMMMMMMM�_
Department: Stormwater Utility
Date: February 20, 2002
Project: BIELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
February 20, 2002
Note - Please identify your redlines for future reference
Issue Contact: Basil Hamdan
Topic: Construction Easements
80
The proposed 24" RCP across Horsetooth Rd. will necessitate the construction of a headwall and part
of the culvert on Tract D of The Landings 1st Filing. Prior to construction on this Tract owned by that
HOA the contractor should make sure that the HOA is notified and that the area will be properly
restored. Even though this area is in an existing drainage easement, the landings 1 st Filing HOA that
maintains this area should ensure that the area is put back to an acceptable level, equal or better
than before construction.
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the Warren Lake Ditch
Company must sign off on these plans.
Topic: Drainage Report
83
Please provide street capacity calculations for Horsetooth Road for the area that is being widened by
this project. Since Horsetooth is a major arterial the standards call for no curb overtopping in the 10-
year storm and one lane open in the 100 -year storm.
Please provide sizing calculations for the proposed Stormceptor.
Please provide sizing calculations for the proposed spillways on ponds 1 and 2.
Topic: Erosion Control
86
Please submit an erosion control plan that meets the standards of the City of Fort Collins. The
submitted materials do not meet our minimum standards. Contact Bob Zakely for further directions.
kDD2
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ V Site 1-4rainage Report Other
!/Utility _ L�edline Utility !=-U—andscape
C[:/JofLtAEW :61C.
Page 1
�C: 1tARC Vi¢I'w
Please provide a better detail for the proposed erosion control fabric for Pond 2. Provide a seed mix
for the native grass proposed in this pond.
Topic: Grading
85
The proposed offsite grading on the northwest corner of the site will require an off -site grading
easement from the adjacent property owner.
Please provide a detail of the retaining walls that are not part of the proposed buildings.
There are still some areas in the upper level parking that do not seem to drain properly. Please
revise and add spot elevations.
The proposed patio area to the west of Building B has a low point with no proposed drainage outlet.
Topic: Landscaping
90
Several inlets on private property might be affected by the dense vegetation proposed around these.
Please revise landscaping plans to ensure proper drainage from these areas even though they will be
owned and maintained by the Bella Vista HOA.
Topic: Off -site Grading Easement
88
The swale on the north side of the property as well as some grading takes place on private property
(Strachan 1 st Filing Subdivision). The plans show that this easement will be granted by separate
document. A letter of intent will be required prior to POP hearing and a final easement is needed
prior to Final Compliance.
Topic: Plat
89
Please connect drainage easement in driveway to off -site drainage easement on the plat.
Topic: Roof Drainage
91
Please show on the plains how the roof drains are getting to the proposed water quality ponds.
Topic: Tree Removal
81
The construction of the 24" pipe across Horsetooth Rd. could impact the existing 8" Blue Spruce on
the south side of Horsetooth. The note that was added to the plan calls for the contractor to
determine in the field whether this tree can be saved. This is not acceptable. The City will not allow
the contractor to remove this tree at his own discretion. Please REMOVE this note as the City will not
allow this tree to be removed and provide plans that will preserve the tree in place.
Topic: Utility plans
82
This is a repeat comment: The proposed storm sewer coming from the Stormceptor and tying into the
line along Horsetooth is currently shown as a 12"RCP. The minimum allowed size in the ROW is a
15 line please correct. The 15' City line should extend to the edge of the ROW (back of walk); this
part of the line should be public and separated from the private 12" line that would extend back to the
Stormceptor by a manhole.
Please make sure that storm line G has enough cover at the point it exits into Horsetooth Road. The
minimum cover requirement is 1-foot below subgrade.
Page 2
The proposed storm sewer on Horsetooth Rd. seems to be very close to several existing utilities
especially at the east end of the line. The line seems to be jammed witting 4' of an existing sanitary
manhole and close to Existing telephone and gas lines. Such small separations are not acceptable
please revise plans. The line also seems to be under the proposed curb and gutter. A meeting with
strormwater and wastewater as well as other utilities is recommended to discuss the pipe alignment
issue.
Please specify an ASTM Standard C443 gasketed joint for all pressurized storm lines.
The existing 5-foot inlets on the corner of Horsetooth and Stanford are shown to be remaining in
place on the Utility plans, while the talcs included in the drainage report check for the sizing these
inlets and the plans show that these might need to be relocated and reconstructed with the widening
of Horsetooth Rd. Please clarify. Will the existing inlets be moved?
If a right turn lane is called for on Horsetooth and Stanford then the existing junction box vault should
be designed to handle traffic loads and the elevation of this box should be checked.
Page 3
Project Comments Sheet
Selected Departments
Department: Water Wastewater
Date: February 22, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
February 20, 2002
Note - Please identify your redlines for future reference
Issue Contact: Jeff Hill
Topic: Landscaping
48
Repeat Comment: Coordinate landscape design with the civil design and provide the
required landscape/utility separation distances. Correctly show all existing and
proposed water/Sewer mains and services on the landscape plans. With the tight
constraints on this site we would be willing to relax our separation requirements,
however we will not allow landscaping to be placed directly on top of our facilitates.
Please consider the placement of shrubs and trees to minimize the impact to our
facilities.
Topic: Utility plans
54
Repeat Comment: Maintain 18-inches of vertical separation between all water,
sanitary sewer and storm sewer crossings.
92
Place all curb stops and meter pits adjacent to the main when at all possible. Curb
stops must be located within a utility easement.
93
Provide a minimum of 10 feet of separation between storm sewer manholes and
sanitary sewer mains.
94
Clearly define all water main joint deflection (i.e. Vertical, Horizontal, Beginning,
ending, etc.).
95
Clearly show that the valve box located on the south side of Horsetooth will not end
up half in and half out of the vertical curb.
Suture
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ ! Site Drainage Report Other_
Utility _ Redline Utility Landscape
Page 1
96
After much consideration and discussion w�thin the utility, it has been determined
that placing concrete around the existing sanitary sewer main will only hamper any
attempt to excavate the sewer in the future f required. Please remove all notes
from this plan set which refers to encasing the existing sanitary sewer main. It has
also been determined that the existing sanitary sewer is PVC and in good condition,
so no replacement will be required.
97
The only allowable substitution for concrete encasement of sewer mains is to use a
20 foot length of D.I.P. or C-900 PVC pipe. Clearly define any substitution of
concrete encasement.
See Site, Landscape and Utility plans for other comments.
Page 2
Project Comments Sheet
S
City of Fort Colains elected Departments
Department: Engineering
Date: February 26, 2002
Project: BELLA VISTA PDP, TYPE I (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
February 20, 2002
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
102
The site plan shows some sort of access ramp across one of the proposed bump outs
along Stanford Drive. This is not reflected on the utility drawings.
103
Remove General Note #4 on the site plan.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the site.
A letter of intent from the property owner not objecting to the offsite work is required to be
submitted prior to any public hearing for the project.
Topic: Plat
46
The Development needs to dedicate an access easement along Stanford Drive to ensure the sidewalk proposed is
in an access easement. Additional right-of-way is not necessary.
(2/20) It appears that additional access easement along Stanford Drive (and Horsetooth Road) is necessary to
ensure that all of the proposed sidewalk is in easement.
66
A minimum of 57.5' of half street right-of-way is required to be dedicated along the entire
length of the property with a consistent utility easement width, in conformance with
LCUASS. It is understood that 9' instead of the 15' of necessary utility easement is
Signature Date
L HECK HE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
flat _ SiW Drainage Report Other
/Utility ,/Redline UtilityLandscape
Page 1
being proposed behind the right-of-way; when all the design and utility issues are
resolved along Horsetooth, the variance request for reduction in utility easement width
will be routed to the utilities for approval.
75
There may be a benefit in designating on the plat that the emergency access easement is
for the "surface level" only. There may be issues from a title company on how the
emergency access easement is represented as c.oing through a building envelope.
Topic: Sidewalk
99
The grading plan appears to show that inlets with straw bales will be in close proximity
or perhaps even overlapping with the street sidewalks. These straw bales need to be
outside of the sidewalk section. Perhaps a different erosion control measure can be
used if the straw bales are encroaching into the sidewalk for a period of time.
Topic: Street Design
32
Directional ramps are required on new construction in accordance with LCUASS. (Standard Drawing 16-4D)
Provide the detail on the plan set.
(2/20) The response from the applicant stated that this could not be accommodated due to existing constraints.
The design engineer should provide documentation on why this cannot be accomplished. Note that because of
the right turn discussion, any previous limitations due to existing constraints may no longer be applicable.
34
A right-tum lane for westbound Horsetooth onto northbound Stanford still should be designed and constructed.
There is a community wide benefit in the construction of the right turn lane, thus this is eligible for Street
Oversizing reimbursement. The design of the right -turn lane should look at providing pedestrian refuge
between the right -turn and through lane, especially since the width of Horsetooth would require a ped refuge
under LCUASS.
(2/20) The issue of the right turn lane was discussed at the City's 2/14 Transportation Coordination Meeting. It
was viewed that the submitted justification for not designing the right turn lane was not compelling and that a
right turn lane could be designed into the project. Please note that any written documentation regarding the
designing of the right-tum lane should be provided by the design engineer (a licensed professional engineer.)
35
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals). (It appears that a straight-
line grade from the crown of Horsetooth Road to the flowline is not being provided as shown on the grading
plan, cross -sections wil I help confirm or deny this.)
(2/20) The cross section sheets need to have the centerline elevations labeled, the curb and gutter
section should be distinguishable from the asphalt section, and the right-of-way should also be
shown.
36
Show centerline and flowline profiles on Horsetooth Road.
Page 2
(2120) Can the grid lines or scale be modified in order to allow for every XX+00 stationing to be on a grid line?
Only every 3rd XX+00 stationing is on a grid line.
37
Provide the bearing and distance for the flowline on the plan view portion of the plan and profile sheet for
Horsetooth Road.
(2/20) This information isn't shown east of the driveway and only bearing (no distance) is being shown west of
the driveway.
60
Because of the aforementioned need for the right -turn lane, eliminating the offset through the intersection, and the constraint of the existing storm drainage
improvements, it is understood that the bike lane design for westbound Horsetooth may have to be compromised. A reduced bike lane width of 6' (including
gutterl with a continuous concrele pour should be looked at as one potential compromise. It may also be necessary for the bike lane to stop short of the
intersection to accommodate the right turn lane. An additional option would be to look at widening the sidewalk and create a combined bikelped area
behind the curb if the bikelane cannot be accomplished.
(2120) With the right turn lane still being an outstanding issue, the proposed design of the westbound bike lane will not be commented on by Engineering at
this time. It is still considered ideal that the bike lane is continuous to the intersection.
62
Add the following note as reference wherever patching is shown on the plans: Limits of street repair are approximate. Final limits to be determined in the
field by the City Engineering Inspector. All repairs to be in accordance with City Street repair standards.
(2120) Ensure that this note is referenced to the work along Stanford as well.
67
The "bulb -outs" proposed on Stanford Drive may be allowed only if the gutter is
redesigned to go around and along the bulb outs, not through them. There are
maintenance concerns with the current proposal due to dirt and debris collecting
between the bulb outs and the flowline.
68
[12] The vertical Curve shown is too short in length for the street classification of
Horsetooth. A K value of 110 is required, 60 is shown.
69
[13] A vertical curve is needed for the Horsetooth proposed flowline as it approaches the
existing storm lines. A grade break is shown with a 0.6% grade going to a 1.69% grade.
70
[13] Fix the vertical elevation labeling on this sheet for the profile view.
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the variance to
reduce the utility easement along Horsetooth were all viewed favorably upon by the City
Page 3
Provide separate water and sewer services for each building and each use within
each building (i.e. commercial, residential).
52
Eliminate all un-necessary bends and low angle crossings of water, sewer and storm
sewer lines.
53
Show and label all curb stops and meter pits on the overall utility plans. Clearly
identify these with size and location.
54
Clearly show and label all water, sanitary sewer and storm sewer crossings in all
utility profile views. Define any and all lowerings or adjustments. Maintain 18-inches
of vertical separation between all water, sanitary sewer and storm sewer crossings.
55
Will an irrigation tap be required within this site?
56
Provide a manhole adjustment and a concrete encasement detail with the next
submittal.
See the site, landscape and utility plans for other comments.
Page 2
Engineer. Final approval of these variance requests will occur with completion of the
designs for Horsetooth and Stanford that are acceptable to the City and the utilities.
72
[13] The 2.55% shown on this sheet appears to actually calculate to 4.2% with the
elevations and stationing shown.
77
The Traffic Engineer has noted that the center turn lane should be continuous from the
intersection to the Cove Island development and continuing east. The Traffic Engineer
notes that a 3/4 movement to allow left turns into the site could be designed (with painted
medians) in conjunction with the porkchop island to facilitate right turns out of this driveway
78
The cross section sheets show the additional road width to be 4% or even greater.
Because a saw cut is being shown to the centerline for most of Horsetooth, a continuous
straight line grade needs to be maintained along the entire north half of the roadway
where the sawcut its shown. For the additional width between stations 10+00 and
11+00, (where the roadway is not being sawcut to centerline), this new portion of
roadway is limited to 3%.
79
A grade break is shown on Sheet [12] that exceeds .40%. A vertical curve would be
required based on this design.
98
Provide spot elevations at the Horsetooth and Stanford intersection in accordance with
LCUASS Standard Detail 7-32B.
100
The submitted "Street Cross Sections" from the site planner is not appropriate to be
submitted as a document along with the site and landscape development plan
documents. Street cross sections are to be shown on the utility plan set and will be
established based upon an approved design for the roadway(s).
101
Angle points along the flowine appear to be shown along Horsetooth, please revise and
use curves as shown in LCUASS 7.4.1.
104
It appears that redirects are too abrupt on the street striping plan. See traffic comments
regarding this.
Topic: Utility plants
76
The drawings regarding the storm system across Horsetooth originally approved by the City
showed an inlet being tied to the easternmost pipe, the submitted plans show that the inlet is
tied to the westernmost pipe.
Page 4
STAFF PROJECT REVIEW
City' of Port Collins
Stanford Development, LLC
c/o Cityscape Urban Design, Inc.
3555 Stanford Road, Suite 105
Fort Collins, CO. £30525
Date: 3/6/2002
Staff has reviewed your submittal for BELLA VISTA PDP, TYPE I (LUC), and we
offer the following comments:
ISSUES:
Department: Current Planning
Topic: Street Design
Issue Contact: Steve Olt
64
Eric Bracke of Traffic Operations offered the following comments:
1. East Horsetooth Road
a. On the east end of the project the plans are showing 3.5' wide bike
lanes and 10.6' wide travel lanes. This is a 40 m.p.h. street and these
lane widths are not acceptable to Traffic Engineering. Eric will settle for
6' wide bike lanes (if Transportation Planning agrees) and 11.5' wide
travel lanes.
b. The redirect taper for westbound traffic is shown at 140'. Again, this is
a 40 m.p.h. street and using the standard WSA2/60 calculation, the
taper should be 320'.
C. The eastbound bike lane at Landings Drive needs to start at the pc, not
25' east of the taper to begin the bike lane. A bicyclist is likely to get
"squished" under this design.
d. Stafi's discussion at Transportation Coordination reaffirmed the need
for a westbound right -turn lane based on City standards, not the TIS or
LOS requirements. The right -turn lane still is not shown.
2. Stanford Road
a. A 10' wide right -turn lane is not acceptable.
Pale I
b. Please get rid of the 4' painted median and use 2' for the southbound
right -turn, 1' for the southbound through, and 1' for the southbound left -
turn.
Please contact Eric, at 224-6062, if you have questions about his comments.
Department: Enc�ineering Issue Contact: Marc Virata
Topic: General
102
The site plan shows some sort of access ramp across one of the proposed bump
outs along Stanford Drive. This is not reflected on the utility drawings.
103
Remove General Note #4 on the site plan.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of
the site. A letter of intent from the property owner not objecting to the offsite work is
required to be submitted prior to any public hearing for the project.
Topic: Plat
46
The Development needs to dedicate an access easement along Stanford Drive to
ensure the sidewalk proposed is in an access easement. Additional right-of-way is
not necessary.
(2/20) It appears that additional access easement along Stanford Drive (and
Horsetooth Road) is necessary to ensure that all of the proposed sidewalk is in
easement.
66
A minimum of 57.5' of half street right-of-way is required to be dedicated along the
entire length of the property with a consistent utility easement width, in conformance
with LCUASS. It is understood that 9' instead of the 15' of necessary utility
easement is being proposed behind the right-of-way; when all the design and utility
issues are resolved along Horsetooth, the variance request for reduction in utility
easement width will be routed to the utilities for approval.
75
Pa.c 2
There may be a benefit in designating on the plat that the emergency access
easement is for the "surface level" only. There may be issues from a title company
on how the emergency access easement is represented as going through a building
envelope.
Topic: Sidewalk
99
The grading plan appears to show that inlets with straw bales will be in close
proximity or perhaps even overlapping with the street sidewalks. These straw bales
need to be outside of the sidewalk section. Perhaps a different erosion control
measure can be used if the straw bales are encroaching into the sidewalk for a
period of time.
J �I haq CheCI ctG/"5 GR' p/OGGieG� n thl5 CCnCi7'Cn,
Topic: Street Design
32
Directional ramps are required on new construction in accordance with LCUASS.
(Standard Drawing 16-4D) Provide the detail on the plan set.
(2/20) The response from the applicant stated that this could not be accommodated
due to existing constraints. The design engineer should provide documentation on
why this cannot be accomplished. Note that because of the right turn discussion,
any previous limitations due to existing constraints may no longer be applicable.
-h
v,flie {,c, :✓ 7;%;' G, er he o` ;G;Tolr, and
lFl� A ✓ 00/h, d��' f0 ih< vk ji 1,^�J v' ICCaI OnS, % G lC ily7 5;'Gnd v_-, G(i',l CCn(/ClfP1
/ocoflonS,
34
A right -turn lane for westbound Horsetooth onto northbound Stanford still should be
designed and constructed. There is a community wide benefit in the construction of
the right turn lane, thus this is eligible for Street Oversizing reimbursement. The
design of the right -turn lane should look at providing pedestrian refuge between the
right -turn and through lane, especially since the width of Horsetooth would require a
ped refuge under LCUASS.
The right four h'CG4 /5 no lcnger regiree by Sfaf`, Gs
cietem inee at eefinq with Gifv Sfa`f on June 10 2002.
(2/20) The issue of the right turn lane was discussed at the City's 2/14
Transportation Coordination Meeting. It was viewed that the submitted justification
for not designing the right turn lane was not compelling and that a right turn lane
could be designed into the project. Please note that any written documentation
regarding the designing of the right -turn lane should be provided by the design
engineer (a licensed professional engineer.)
Page 3
35
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals).
(It appears that a straight-line grade from the crown of Horsetooth Road to the
flowline is not being provided as shown on the grading plan, cross -sections will help
confirm or deny this.)
(2/20) The cross section sheets need to have the centerline elevations labeled, the
curb and gutter section should be distinguishable from the asphalt section, and the
right-of-way should also be shown.
I 47/l7M.'ro G`055 _-�-C//O(/5,
36
Show centerline and flowline profiles on Horsetooth Road.
/i011 'Nnd %'!�Wi'^e t'.'(c ,F _- G(e ^:Ovin G- ^G�f Oi f/!e /�O/ 700/h NOGa P/GrS,
(2/20) Can the grid lines or scale be modified in order to allow for every XX+00
stationing to be on a grid line? Only every 3rd XX+00 stationing is on a grid line.
l ✓i! l 'r "' '_ i i r:'li ,: 1011"01 ✓✓ `/"^ G:,'(5 '0 U'ene(GTe cr05_'
��h �n ; !�- b✓ hcn�, r�� !ire :nien�ive
37
Provide the bearing and distance for the flowline on the plan view portion of the plan
and profile sheet for Horsetooth Road.
7hl_, irhOff,urI on aG e he ^d On the �h circ rG:
(2/20) This information isn't shown east of the driveway and only bearing (no
distance) is being shown west of the driveway.
60
Because of the aforementioned need for the right -turn lane, eliminating the offset
through the intersection, and the constraint of the existing storm drainage
improvements, it is understood that the bike lane design for westbound Horsetooth
may have to be compromised. A reduced bike lane width of 6' (including gutter) with
a continuous concrete pour should be looked at as one potential compromise. It
may also be necessary for the bike lane to stop short of the intersection to
accommodate the right -turn lane. An additional option would be to look at widening
the sidewalk and create a combined bike/ped area behind the curb if the bikelane
cannot be accomplished. N/11
(2/20) With the right turn lane still being an outstanding issue, the proposed design
of the westbound bike lane will not be commented on by Engineering at this time. It
is still considered ideal that the bike lane is continuous to the intersection. N/A
Page 4
62
Add the following note as reference wherever patching is shown on the plans: Limits
of street repair are approximate. Final limits to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City Street repair
standards.
Thies note has been added /o the general notes on plans where pafchinq occurs.
(2/20) Ensure that this note is referenced to the work along Stanford as well.
67
The "bulb -outs" proposed on Stanford Drive may be allowed only if the gutter is
redesigned to go around and along the bulb outs, not through them. There are
maintenance concerns with the current proposal due to dirt and debris collecting
between the bulb outs and the flowline.
he r cwl' P r�r� J<'?� �a i; �_��{ �f h D05i' VP �lC%�/ jC the O f�i,�Je Olr il'e v'Ul �J'CUiS,
68
[12] The vertical curve shown is too short in length for the street classification of
Horsetooth. A K value of 110 is required, 60 is shown.
69
[13] A vertical tune is needed for the Horsetooth proposed flowline as it approaches
the existing storm lines. A grade break is shown with a 0.6% grade going to a
1.69% grade.
70
[13] Fix the vertical elevation labeling on this sheet for the profile view.
Done
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the
variance to reduce the utility easement along Horsetooth were all viewed favorably
upon by the City Engineer. Final approval of these variance requests will occur with
completion of the designs for Horsetooth and Stanford that are acceptable to the
City and the utilities.
72
[13] The 2.55% shown on this sheet appears to actually calculate to 4.2% with the
elevations and stationing shown.
%hi,, ha5 been correcfee.
Page 5
77
The Traffic Engineer has noted that the center turn lane should be continuous from
the intersection to the Cove Island development and continuing east. The Traffic
Engineer notes that a 3/4 movement to allow left turns into the site could be
designed (with painted medians) in conjunction with the porkchop island to facilitate
right turns out of this driveway.
78
The cross section sheets show the additional road width to be 4% or even greater.
Because a saw cut is being shown to the centerline for most of Horsetooth, a
continuous straight line grade needs to be maintained along the entire north half of
the roadway where the sawcut is shown. For the additional width between stations
10+00 and 11+00„ (where the roadway is not being sawcut to centerline), this new
portion of roadway is limited to 3%.
n F'! i lC ihr_ r Cate. l //'. " :=F CtiC^5. lnGllCGtln^ ,7rGD05e� C(O%5 5/ope5 /J_, we .cn 2- e f57
79
A grade break is shown on Sheet [12] that exceeds .40%. A vertical curve would be
required based on this design.
l nl c, l5 5ro'wr;,,
98
Provide spot elevations at the Horsetooth and Stanford intersection in accordance
with LCUASS Standard Detail 7-32B.
Jhown On i Jer ;', o` nn an„ rro;'-le 5 eet
100
The submitted "Street Cross Sections" from the site planner is not appropriate to be
submitted as a document along with the site and landscape development plan
documents. Streel cross sections are to be shown on the utility plan set and will be
established based upon an approved design for the roadway(s).
e- o F r y r %rvo/
v She l lCr oo ec//on of or efcofh hoae,
101
Angle points along the flowine appear to be shown along Horsetooth, please revise
and use curves as shown in LCUASS 7.4.1.
t'o/7[on/Gl tIowt r' C;;Nv`, "1,-rCl :�/StCCt�' ;POCG ^G'✓e jven /e'✓15�C t0 %����� rhr7il,
104
It appears that redirects are too abrupt on the street striping plan. See traffic
comments regarding this.
The entire /ane qeo etry or 7or5efooth is re i ea in�icGtinq ore appropriate redirects,
Page 6
Topic: Utility plans
76
The drawings regarding the storm system across Horsetooth originally approved by
the City showed an inlet being tied to the easternmost pipe, the submitted plans
show that the inlet is tied to the westernmost pipe.
Jpon `iefd ve caiion, ' e; fef ee5 fie info fhe.ve,te,fy pipe
Department: PFA
Topic: Plat
Issue Contact: Ron Gonzales
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered. A fire pump may also be
required, as well as standpipes for the building and the parking garage below grade.
97UBC
The response letter from Cityscape stated that notes to this effect have been added
to the plans. Please indicate where the notes are.
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below grade.
Stage One shall be tied to a Carbon Monoxide Detection System that will detect
carbon monoxide at 50ppm over 8 hours and/or 200ppm over 1 hour and ventilate
the garage. Stage Two shall provide ventilation for smoke removal in the event of a
car fire.
U BC 1202.2.7
The response letter from Cityscape stated that notes to this effect have been added
to the plans. Please indicate where the notes are.
Department: Police Issue Contact: Joseph Gerdom
Topic: General
9
Lighting Plan: The Luminaire schedule and luminaire detail don't provide sufficient
information to determine exactly which lights are used in each location. Also, unless
there are wall fixtures there is inadequate illumination between Bldg B & C; east face
of Bldg D; and north face of Bldg B. In general, all building access points should
have minimum of 1 fc.
Pa,,t 7
Topic: Landscaping
10
Landscape Plan: The use of Austrian Pine, cotoneaster, and ninebark along the
faces of Bldgs B, ., and D, particularly in front of public/private entrances will
obscure these areas and raise security issues. Lower growing species, lighting, or
some combination thereof would be recommended.
Department: Stormwater Utility Issue Contact: Basil Harridan
Topic: Construction Easements
80
The proposed 24" RCP across Horsetooth Rd. will necessitate the construction of a
headwall and part of the culvert on Tract D of The Landings 1 st Filing. Prior to
construction on this Tract owned by that HOA the contractor should make sure that
the HOA is notified and that the area will be properly restored. Even though this
area is in an existing drainage easement, the landings 1st Filing HOA which
maintains this area should ensure that the area is put back to an acceptable level,
equal or better than before construction.
Topic: Ditch Company Approval
M
Prior to allowing additional discharge from this site into Warren Lake, the warren
Lake Ditch company must sign off on these plans.
We _o^panv 1sGeVierinqp;�ul /oW4afe hoof not
recr ved a rep pone, Since our n1/10/
Topic: Drainage Report
83
Please provide street capacity calculations for Horsetooth Road for the area that is
being widened by this project. Since Horsetooth is a major arterial the standards call
for no curb overtopping in the 10-year storm and one lane open in the 100 -year
storm.
Please provide sizing calculations for the proposed Stormceptor.
Please provide sizing calculations for the proposed spillways on ponds 1 and 2.
Page 9
Topic: Erosion Control
86
Please submit an erosion control plan that meets the standards of the City of Fort
Collins. The submitted materials do not meet our minimum standards. Contact Bob
Zakely for further directions.
Please provide a better detail foir the proposed erosion control fabric for Pond 2.
Provide a seed mix for the native grass proposed in this pond.
f hL- Crosion Gonfrol Flan has bnfn Uplafee, defai/ Gnd 4rylGnj q�ass eel
rdx.
Topic: Grading
85
The proposed offsite grading on the northwest corner of the site will require an off -
site grading easement from the adjacent property owner.
C ' /nIP^I no, v^c-e ,�-CL'rec7 C./ %h< or, �i,,c �e ^;!�ni GOd Will Z rrC'
Please provide a detail of the retaining walls that are not part of the proposed
buildings.
i`r.�e al/iMC7 Y✓Gll=5 W/// 6e ,lP'Gllv,j 3V ;✓ 1550Gncc of Ge bUlleL^O
per/7%f.
There are still some areas in the upper level parking that do not seem to drain
properly. Please revise and add spot elevations. The proposed patio area to the
west of Building B has a low point with no proposed drainage outlet.
the (IfOdIn, /U/r ni W =r)oWn G/ rr- �G ✓✓/fh o-,7if 5/iC7 ce'iGI/On5 l0 ;-,7o(P Ci'fadv Ve'/fV
�; Girage pcitf�m�
Topic: Landscaping
90
Several inlets on private property might be affected by the dense vegetation
proposed around these. Please revise landscaping plans to ensure proper drainage
from these areas even though they will be owned and maintained by the Bella Vista
HOA.
Page 9
6aProject Comments Sheet
Selected Departments
City of Fort Collins
Department: Engineering
Date: January 4, 2002
Project: BELLA VISTA PDP, TYPE i (LUC)
All comments must be received by STEVE OLT in Current Planning no later than the
staff review meeting:
December 26, 2001
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
28
Replace "P.U.U." with "PAP" on all the documents.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the site.
A letter of intent from the property owner not objecting to the offsite work is required to be
submitted prior to any public hearing for the project.
Topic: Plat
42
Replace all occurrences of Director of Engineering with City Engineer.
43
The Plat language (Certificate of Dedication and Maintenance and Repair Guarantee
language) has been revised. Please revised as shown (electronic format of the document is
available). Ensure that the "Notice of Other Documents" language is included in the plat as
well.
44
The Sight Distance Easement Language on the plat has also been revised. Please revise
as shown.
46
The Development needs to dedicate an access easement along Stanford Drive to ensure
the sidewalk proposed is in an access easement. Additional right-of-way is not necessary.
Signature i Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ Site Drainage Report Other_
Utility Redline Utility Landscape
Page 1
Topic: Off -site Grading Easement
88
The swale on the north side of the property as well as some grading takes place on
private property (Strachan 1 st Filing Subdivision) . The plans show that this
easement will be granted by separate document. A letter of intent will be required
prior to PDP hearing and a final 'easement is needed prior to Final Compliance.
e'ti c( of intent i rCythccri Pq.
Topic: Plat
89
Please connect drainage easement in driveway to off -site drainage easement on the
plat.
r hi5 will be 5/;own on, /he pial,
Topic: Roof Drainage
91
Please show on the plans how the roof drains are getting to the proposed water
quality ponds.
/` r_`` (l0 the / ^✓e,'Glll Utlll`v plan �J( rOG,' G�,rGM Co, ''eCtlOr/5 t0 5/O!r) 52we( or 5urfacc
Topic: Tree Removal
81
The construction of the 24" pipe across Horsetooth Rd. could impact the existing 8"
Blue Spruce on the south side of Horsetooth. The note that was added to the plan
calls for the contractor to determine in the field whether this tree can be saved. This
is not acceptable. The City will not allow the contractor to remove this tree at his
own discretion. Please REMOVE this note as the City will not allow this tree to be
removed and provide plans that will preserve the tree in place.
ha /,/ ✓el t�F ; aele�e� lhai f,he exi5�, 55pruce free will have lG be removed, The note
here. ceen (el�ewee' ,`! %� /ne Clans,
Topic: Utility plans
82
This is a repeat comment: The proposed storm sewer coming from the Stormceptor
and tying into the line along Horsetooth is currently shown as a 12"RCP. The
minimum allowed size in the ROW is a 15" line please correct. The 15" City line
should extend to the edge of the ROW (back of walk), this part of the line should be
public and separated from the private 12" line that would extend back to the
Stormceptor by a manhole.
Page 10
Please make sure that storm line G has enough cover at the point it exits into
Horsetooth Road. the minimum cover requirement is 1-foot below subgrade.
l''7F r)i vif '_,{irr.:;r/✓G 'r pP C,'Q Dew?U�C1(aGlvO iol'7INII/'li'^U/n COV�,'l5 D✓OVIdP_�,
The proposed storm sewer on Horsetooth Rd. seems to be very close to several
existing utilities especially at the east end of the line. The line seems to be jammed
within 4' of an existing sanitary manhole and close to existing telephone and gas
lines. Such small separations are not acceptable please revise plans. The line also
seems to be under the proposed curb and gutter. A meeting with strormwater and
wastewater as well as other utilities is recommended to discuss the pipe alignment
issue.
Afler heeling wish Gify Uri/ifies, it was agreed to reloco/c Phis sfor li e loser to fhe
cove, 0, l or iocfh, thus reau ng corer/icis.
Please specify an ASTM Standard C443 gasketed joint for all pressurized storm
lines.
6aekefed�oinfs are calle,j ouf on stow/ sewer prc,'iles; where required.
The existing 5-foot inlets on the corner of Horsetooth and Stanford are shown to be
remaining in place on the Utility plans, while the calcs included in the drainage report
check for the sizing these inlets and the plans show that these might need to be
relocated and reconstructed with the widening of Horsetooth Rd. Please clarify. Will
the existing inlets be moved ?
l he cxlj ,Ilnq inlcl t, /'lll be r"Glfralliicj In ',7iGCe.
If a right turn lane is called for on Horsetooth and Stanford then the existing junction
box vault should be designed to handle traffic loads and the elevation of this box
should be checked.
N/A
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: Sidewalk
73
Applicant needs to provide off -site sidewalk connection on Stanford from their site
north to Monroe.
Based on the City's pedestrian LOS standards within the Land Use Code (LUC) and
Larimer County Urban Area Street Standards (LCUASS) the minimum LOS for
pedestrians is not met. Contrary to Mr. Delich's response, the proposed
development is actually located within the area types classified as "transit corridor"
and "school walking area". Therefore, all pedestrian LOS elements must meet LOS
B, except for the visual interest and amenities as stated within the LCUASS and the
TIS provided. The LCUASS further explains that all "destination areas" within a
quarter mile (1,320 feet) must be identified within the TIS for analysis. All locations
are identified within the TIS with the exception of the medium density residential land
use to the north, which is located on the NE corner of the Monroe and Stanford
intersection. This "destination area" does not meet the minimum LOS for
"directness" as measured on the street grid system, and thus, the minimum
pedestrian LOS for "continuity" due to the lack of a sidewalk along Stanford between
the proposed development and the identified intersection.
In addition, the Ll1C states in Section 3.2.2 C.7 "Offsite Access to Pedestrian and
Bicycle Destinations", that "offsite pedestrian or bicycle facility improvements may be
required in order to comply with the requirements of Section 3.2.2 (E) (1) (Parking
Lot Layout) and Section 3.4 (Transportation Level of Service Requirements).
84
Proposed mid -block pedestrian crossing shown on Stanford looks problematic due
to curve. This is a Traffic Engineering call however.
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: Landscaping
48
Repeat Comment: Coordinate landscape design with the civil design and provide the
required landscape/utility separation distances. Correctly show all existing and
proposed water,/sewer mains and services on the landscape plans. With the tight
constraints on this site we would be willing to relax our separation requirements,
however we will not allow landscaping to be placed directly on top of our facilitates.
Please consider the placement of shrubs and trees to minimize the impact to our
facilities.
Topic: Utility plains
54
Repeat Comment: Maintain 18-inches of vertical separation between all water,
sanitary sewer and storm sewer crossings.
W/W excepllon lc 5forr, Line '6', We rinlrruri separa{ion is provided, We fc- eclfully
reauesl a waiver -0or /he ini u 5epara}icn require enl, where Lire '6' cros es fhe
exisfinq o sanilary ewer, f lemafives to lhis have ceen explored with no success,
92
Place all curb stops and meter pits adjacent to the main when at all possible. Curb
stops must be located within a utility easement.
This requirer�enf i not posih/e wr'fh the end/ess conf/icfs Thai exist for Phis proposal.
We respechrully request a waiver yoro fhis require enl. P/ear review the currenl layoul
and respond.
Pao*e 12
93
Provide a minimum of 10 feet of separation between storm sewer manholes and
sanitary sewer mains.
7hi-� ha-, one.
94
Clearly define all water main joint deflection (i.e. Vertical, Horizontal, Beginning,
ending, etc.).
fig shown en fhe cuerall ufilify plan
95
Clearly show that: the valve box located on the south side of Horsetooth will not end
up half in and half out of the vertical curb.
/ /7/., ��cnF//Cl hG5 been e;'//"MC7e,7, Jee 1/ie GVvra!�l / plan,
96
After much consideration and discussion within the utility, it has been determined
that placing concrete around the existing sanitary sewer main will only hamper any
attempt to excavate the sewer in the future if required. Please remove all notes
from this plan set which refers to encasing the existing sanitary sewer main. It has
also been determined that the existing sanitary sewer is PVC and in good condition,
so no replacement will be required.
97
The only allowable substitution for concrete encasement of sewer mains is to use a
20 foot length of D.I.P. or C-900 PVC pipe. Clearly define any substitution of
concrete encasement.
CncG / e;;t /� ncl propc;e<i Gf
Department: Zoning Issue Contact: Peter Barnes
Topic: zoning
3
REPEAT COMMENT (1-31-02). General note 1(d)(ii) lists "live/work office type units"
as a possible use. What is that? No such term. Is it the same as a home
occupation? The explanation of what this is in their 1-29-02 letter is interesting, but
it doesn't change anything. Our code contains no such use, therefore the use is not
allowed (4.5(C) prohibits any use that is not expressly allowed). It still seems to me
that what they are describing on sheet 1 of 6 is a home occupation, which is
permitted and is listed by them on general note 1(d)(i). This type of comment is
common from Zoning whenever an applicant lists a use that is not defined. For
example, we make the same comment relative to an applicant that lists "townhomes"
as a permitted use. Since there is no such defined term, we require them to remove
it. If they really want to allow offices in the building that are not within a dwelling unit
(home occupation), then they should do a Type 2 review in order to obtain approval
for things like offices, dry cleaners, hair salons.
Page 13
4
REPEAT COMMENT (1-31-02). With regards to my original comment below, I am
glad to see that they have corrected the code section reference number. I find their
explanation in their 1-29-02 letter regarding contextual height to be interesting,
However, I believe they are missing my point. I agree that height can be measured
either in stories or feet. But since the section they reference deals with establishing
a contextual height, it is important that such height be reflected in terms of "feet" not
"stories". Since the height of a story can vary from one buidling to another, City staff
needs to have the height of the applicable buildings indicated to us in "feet" in order
to determine if the proposed height is "contextual". As I stated originally, indicating
that a Bella Vista building may be 6 stories, says nothing to us about how it relates
to the height of the Marriott since one 6 story building can be considerably shorter or
taller than another 6 story building. That's why I asked the question "How tall is the
Marriott in terms of feet"? They have explained the difference in feet in their 1-29-02
letter, now they have to put that information on the plan.
(12-18-01) - General note 2 references Section 2.8.17. There is no such section. I
assume they mean 3.8.17 (A)(3). If so, then Planning needs to determine if the 4 to
6 stories is the appropriate "contextual height Some of the walls of buildings are
almost 90' tall. In my opinion, "contextual height" as used in 3.8.17(A)(3) implies a
similar height in feet as well as in stories. For instance, a 6 story building on one lot
may only be 70' tall, and that doesn't mean that it's therefore ok to have a 6 story
building on an adjacent lot that is 90' tall when the maximum height allowed in the
MMN zone is 3 stories (4.5(E)(1)(d). How tall is the Marriott in terms of feet?
6
REPEAT COMMENT (1-31-02) - General note 1(d)(iii) - small food service uses
listed are not classified as accessory uses. Therefore, they are not permitted in the
MMN zone. (the only way they can be remotely "accessory" is if they serve only the
residences of the building, and are not open to the "public"). I've read the
explanation in the applicant's 1-29-02 letter, but I don't agree. For instance, would a
Sushi Bar really be accessory, serving the tenants of the building? I doubt it would
remain in business very long with such a small customer base.
7
REPLY (1-31-02). OK, I'll agree with B&B's being allowed. Editorial note - The
applicant has suggested that private houses on lots less than 6000 s.f, would not be
conducive to a six bedroom B&B. I would suggest that such a private house would
be more conducive to a B&B than would a 2 or 3 bedroom condo.
(original comment). General note 1(C)(ii) - B&B's would not be allowed. Such a use
is a use that is conducted in a private house, not in a condo building.
The following comments were expressed at Staff Review on February 20, 2002:
Page 14
Engineering:
The East Horsetooth Road design is still of concern. A westbound right -turn
lane is needed. It is warranted based on City street standards.
AVA
2. The striping as shown on East Horsetooth Road is unsafe.
UeG e /e`er fo }he revise,/ sfripinq plan for `urlher review,
3. The center left -turn lane is unneeded.
4. There are issues with the cross sections on East Horsetooth Road. They are
not to City standards.
U G055 CtlOnS half Deen re'✓l=e// Gr;C '^ee` Gliy CTii e/l G.
5. Dedicate 57.5' of street right-of-way all the way to the east property line.
"/' UU.I✓✓', hO5 ✓ee:'%'O t0 r^er' f�^o ^'/n !"i�/`� U✓l4%Y; J,� n7,FO GW/G'e/ lO
u��o r�o4Gte the " u'ure" wesfhoun CY or eieofh� nigh} Turn lane. See Flat,
6. Flowlines need to be on the outside of the proposed bulb -outs on Stanford
Road.
T hi ha-, b:Q done,
7. The 3 variance requests from Northern Engineering are still being reviewed.
8. There should be an emergency access easement on the surface parking only
and this should be noted on the subdivision plat.
7 his is Uc&n on the plat,
Stormwater:
1. Storm water from this site will have to go into Tract D of Cove Island, to the
south. A storm drainage easement may be needed from them.
tlllly eta e✓"entenCCl^pG5'`5 the Greta o concern reCC(AZG 1N/7,h the
� r
ounty on June UU /��O ,ror the f;i51 Fey/a} of 1he Landings FUD„ Firsf Fitinq,
2. The proposed 12" storm sewer from the parking area needs to be a 15" pipe.
This has been ,Jofe,
3. The storm sewer in East Horsetooth Road needs to be out from under the curb
& gutter.
Uforrl ;ewe; if� no longer p/op0;e4 under the curb GU qu}ter.
Pace 15
4. There are lots of tree and storm sewer conflicts.
T nip is now ne�clvea
Transportation Planning:
1. The off -site sidewalk along the east side of Stanford Road, going to the north, is
needed. This proposal fails the Pedestrian Level of Service portion of the TIS
without it.
2. The proposed mid -block pedestrian crossing on Stanford Road, on the curve, is
not in a good location for safety reasons.
Water/Wastewater:
Water/Wastewater is still reviewing the plans. A meeting with the applicant &
developer is needed.
Planning:
1. The proposed small food service uses, Item iii) under Accessory Uses in the
General Notes, are of concern. If there are several very small users (up to
1,500 square feet in size), as staff and the developer have previously
discussed, then these food services could be considered to be accessory uses.
However, if a single restaurant were to occupy the bulk of the defined food
service space (up to 3,600 square feet as shown on the Site Plan) then there
would be a problem associated with the list of permitted uses in the MMN
District. Restaurants are not a permitted use in this district.
2. The proposed live/work office uses, Item ii) under Accessory Uses in the
General Notes, is a good idea: however, offices (per say) are listed as a Type II,
Planning & Zoning Board review use in the MMN District. What assurance is
there that the office users will not be separate from residents?
3. While reviewing the Shadow Analysis Plan and Streetscape & Building
Elevations Plans against the criteria set forth in Section 3.5.1(G) Building Height
Review of the LUC, several comments have arisen:
a. Regarding Views, are there still desirable views of the foothills from the
residential areas north and south of East Horsetooth Road that will be
affected by this development? Are there views of Warren Lake from
properties north of East Horsetooth Road that will be affected? Section
3.5.1(G)(1)(b)2 of the LUC requires that a visual analysis of views be
submitted for review.
Page 16
b. There would appear to be several areas of concern regarding Light and
Shadow on adjacent properties, mostly at the 9:00 a.m. and 3:00 p.m.
times as shown on the Shadow Analysis Plan. Most significant is the
potential affects on buildings and parking lots to the west, across Stanford
Road.
C. Regarding Neighborhood Scale, the City still has some "contextual'
concerns regarding this issue. Understanding the "Contextual Height'
definition in Section 3.8.17(A)(3) of the LUC, there is still some discussion
needed about where this site is situated relative to the taller buildings
(such as the Marriott Hotel) in the area. How tall, in feet, is the hotel and is
one building in excess of 3 stories in height in a larger surrounding area
sufficient to justify 4 buildings that exceed the maximum allowable height
in the proposed zoning district for this site?
d. Typically, elevations for all 4 sides of buildings should be submitted. What
do the building ends look like?
This completes staff comments at this time. Additional comments may be
forthcoming. This development request is subject to the 90-day revision re -
submittal (from the date of this comment letter) as set forth in Section
2.2.11(A) of the Land Use Code. Be sure and return all of your redlined plans when
you re -submit.
If you have any questions regarding these issues or any other issues related to this
project, please feel free to call me at (970) 221-6341.
Yours Truly,
Steve Olt,
Project Planner
Paae 17
COKYW o
urban design, inc.
July 31, 2002
Steve Olt
City of Fort Collins
Community Planning and Environmental Services
P.O. Box 580
Fort Collins, CO 130522
RE: Bella Vista PDP — March 6, 2002, PDP Review Comments
Dear Steve,
3555 stanford road, suite 105
fort collins, colorado 80525
(970) 226-4074
fax (970) 226-4196
e@cityscapeud.com
Included below are the March 6, 2002 comments received from City Staff
regarding the revised Bella Vista Project Development Plan (initially submitted
November 28, 2001; previous revisions were submitted January 29, 2002). Applicant
responses to the City Staff comments are in italics and underlined:
Department: Current Planning Issue Contact: Steve Olt
Topic: Street Design
64
Eric Bracke of Traffic Operations offered the following comments:
1. East Horsetooth Road
a. On the east end of the project the plans are showing 3.5' wide bike lanes
and 10.6' wide travel lanes. This is a 40 m.p.h. street and these lane
widths are not acceptable to Traffic Engineering. Eric will settle for 6' wide
bike lanes (if Transportation Planning agrees) and 11.5' wide travel
lanes.
b. The redirect taper for westbound traffic is shown at 140'. Again, this is a
40 m.p.h. street and using the standard WS^2/60 calculation, the taper
should be 320'.
C. The eastbound bike lane at Landings Drive needs to start at the pc, not
25' east of the taper to begin the bike lane. A bicyclist is likely to get
"squished" under this design.
d. Staf's discussion at Transportation Coordination reaffirmed the need for a
westbound right -turn lane based on City standards, not the TIS or LOS
requirements. The right -turn lane still is not shown.
2. Stanford Road
a. A 10' wide right -turn lane is not acceptable.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
EOM@Q o
urban design, inc.
b. Please get rid of the 4' painted median and use 2' for the southbound
right -turn, 1' for the southbound through, and 1' for the southbound left -
turn.
Please contact Eric, at 224-6062, if you have questions about his comments.
Applicant Response:
a) The "unacceptable" widths of bike lanes and travel lanes dimensioned at the east
end of the site are the existing off -site condition as striped by the City, and are
not part of this applicant's proposal. They are however the widths from which
we must ,begin the transition to the proposed lane widths. Also, the posted speed
on Horsetooth drops from 40 mph to 35 mph near the easterly end of the subject
Property. Our revised striping plan matches the existing striping to the west of
the Stanford Road intersection tapering to meet the existing condition at the east
Property ljne.
b) The taper has been revised to match the posted speed.
c) As per City Staffs earlier direction we are no longer proposing any modification
to the existing east bound bike lanes (on the fully improved south side of
Horsetooth Road). There will continue to be no eastbound bike lane west of
Spindrift, as per the existing condition.
d) As discussed at our meeting of June le, the westbound right turn lane is
impractical due to the numerous horizontal and vertical utility and drainage
conflicts, and the overwhelming negative impacts on this small site. It is the
consensus opinion that the enormous sum of City money required to construct
this turn lane would be better spent at other locations. As indicated in our last
submittal the intersection will function at an acceptable level without this
additional lane. We have designed the site so that — in the unlikely event this
intersection is reconstructed to include a west -bound right turn lane — the location
of the walk and street trees will not conflict.
2) Stanford Road
a) The "unacceptable" 10' right -turn lane previously indicated, simply illustrated the
width of the existing turn lane when the original submittal of this PDP was made.
Our revised striping plan increases the width to 12'.
b) The revised stripping plan eliminates the 4' painted median as requested.
Department: Engineering Issue Contact: Marc Virata
Topic: General
102
The site plan shows some sort of access ramp across one of the proposed bump outs
along Stanford Drive. This is not reflected on the utility drawings.
103
Remove General Note #4 on the site plan.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
58
Vacation of City easements an the plat do not require an easement vacation certificate. However, vacation of exclusive easements outside of the City 120'
communication easement) requires a signature from the telephone company.
59
Horsetooth Road appears confusing with right -of way on tap of city and private utilities. Please clarify.
61
An emergency access easement needs to be dedicated an the plat where PFA specifes a fire lane is required.
Topic: Street Design
29
The Larimer County Urban Area Street Standards ILCUASSI in Section 8.2.2 specifies all lanes shall be in alignment through each intersection. Currently a
4.5' offset is measured on the road design; no offset will be allowed for this design.
30
Because of the no offset requirement and some constraints involving the existing storm
drainage improvements across Horsetooth, the previous discussion involving extension of
the proposed median to the Horsetooth/Stanford intersection will no longer be required.
Instead, no median shall be provided on Horsetooth Road and a pork chop island for the
driveway off of Horsetooth shall be required. The design of the "pork chop" for this access
point should prohibit left turns onto Horsetooth (to the extent reasonably feasible) while at
the same time be designed to allow PFA access.
31
The access out to Horsetooth Road does not provide enough separation from the
intersection of Horsetooth Road and Stanford Drive as required under LCUASS (660' is
required, 620' is provided). Transportation Services has determined that this separation will
work with the construction of the "pork chop" island to deter left turns out of the
development.
32
Directional ramps are required on new construction in accordance with LCUASS. (Standard
Drawing 16-4D) Provide the detail on the plan set.
33
The City's Traffic Engineer has determined that the Stanford/Horsetooth intersection would
not make a suitable location for a roundabout and an alternative analysis (typically required
on arterial/collector and arterial/arterial intersections) is not needed.
34
A right -turn lane for westbound Horsetooth onto northbound Stanford still should be
designed and constructed. There is a community wide benefit in the construction of the right
turn lane, thus this is eligible for Street Oversizing reimbursement. The design of the right -
turn lane should look at providing pedestrian refuge between the right -turn and through lane,
especially since the width of Horsetooth would require a ped refuge under LCUASS.
35
Page 2
urban design, inc.
Topic: Grading
45
Offsite grading and construction is shown occurring along the northern boundary of the
site. A letter of intent from the property owner not objecting to the offsite work is
required to be Submitted prior to any public hearing for the project.
Topic: Plat
46
The Development needs to dedicate an access easement along Stanford Drive to
ensure the sidewalk proposed is in an access easement. Additional right-of-way is not
necessary.
(2/20) It appears that additional access easement along Stanford Drive (and Horsetooth Road)
is necessary to ensure that all of the proposed sidewalk is in easement.
66
A minimum of 57.5 of half street right-of-way is required to be dedicated along the
entire length of the property with a consistent utility easement width, in conformance
with LCUASS. It is understood that 9' instead of the 15' of necessary utility easement is
being proposed behind the right-of-way, when all the design and utility issues are
resolved along Florsetooth, the variance request for reduction in utility easement width
will be routed to the utilities for approval.
75
There may be a benefit in designating on the plat that the emergency access easement
is for the "surface level" only. There may be issues from a title company on how the
emergency access easement is represented as going through a building envelope.
Topic: Sidewalk
99
The grading plan appears to show that inlets with straw bales will be in close proximity
or perhaps even overlapping with the street sidewalks. These straw bales need to be
outside of the sidewalk section. Perhaps a different erosion control measure can be
used if the straw bales are encroaching into the sidewalk for a period of time.
Topic: Street Design
32
Directional ramps are required on new construction in accordance with LCUASS.
(Standard Drawing 16-4D) Provide the detail on the plan set.
(2/20) The response from the applicant stated that this could not be accommodated due to
existing constraints. The design engineer should provide documentation on why this cannot be
accomplished. Note that because of the right turn discussion, any previous limitations due to
existing constraints may no longer be applicable.
34
A right -turn lane for westbound Horsetooth onto northbound Stanford still should be
designed and constructed. There is a community wide benefit in the construction of the
right turn lane, thus this is eligible for Street Oversizing reimbursement. The design of
the right -turn lane should look at providing pedestrian refuge between the right -turn and
\\SERVER\Server D\WP\9000\9600\9601 PDP-RESPONSE3.doc
CO�M@ a o
urban design, inc.
through lane, especially since the width of Horsetooth would require a ped refuge under
LCUASS.
(2/20) The issue of the right turn lane was discussed at the City's 2/14 Transportation
Coordination Meeting. It was viewed that the submitted justification for not designing the right
turn lane was not compelling and that a right turn lane could be designed into the project.
Please note that any written documentation regarding the designing of the right -turn lane should
be provided by the design engineer (a licensed professional engineer.)
35
Provide cross -sections on Horsetooth Road per LCUASS 3.3.4.0 (at 50' intervals). (It
appears that a straight-line grade from the crown of Horsetooth Road to the flowline is
not being provided as shown on the grading plan, cross -sections will help confirm or
deny this.)
(2/20) The cross section sheets need to have the centerline elevations labeled, the curb and
gutter section should be distinguishable from the asphalt section, and the right-of-way should
also be shown.
36
Show centerline and flowline profiles on Horsetooth Road.
(2/20) Can the grid) lines or scale be modified in order to allow for every XX+00 stationing to be
on a grid line? Only every 3rd XX+00 stationing is on a grid line.
37
Provide the bearing and distance for the flowline on the plan view portion of the plan
and profile sheet for Horsetooth Road.
(2/20) This information isn't shown east of the driveway and only bearing (no distance) is being
shown west of the driveway.
60
Because of the aforementioned need for the right -turn lane, eliminating the offset
through the intersection, and the constraint of the existing storm drainage
improvements, it is understood that the bike lane design for westbound Horsetooth may
have to be compromised. A reduced bike lane width of 6' (including gutter) with a
continuous concrete pour should be looked at as one potential compromise. It may also
be necessary for the bike lane to stop short of the intersection to accommodate the
right -turn lane. An additional option would be to look at widening the sidewalk and
create a combined bike/ped area behind the curb if the bikelane cannot be
accomplished.
(2/20) With the right turn lane still being an outstanding issue, the proposed design of the
westbound bike lane will not be commented on by Engineering at this time. It is still considered
ideal that the bike lane is continuous to the intersection.
62
Add the following note as reference wherever patching is shown on the plans: Limits of
street repair are approximate. Final limits to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City Street repair standards.
(2/20) Ensure that this note is referenced to the work along Stanford as well.
67
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
urban design, inc.
The "bulb -outs" (proposed on Stanford Drive may be allowed only if the gutter is
redesigned to go around and along the bulb outs, not through them. There are
maintenance concerns with the current proposal due to dirt and debris collecting
between the bulb outs and the flowline.
68
[12] The vertical curve shown is too short in length for the street classification of
Horsetooth. A K: value of 110 is required, 60 is shown.
69
[13) A vertical curve is needed for the Horsetooth proposed flowline as it approaches
the existing storm lines. A grade break is shown with a 0.6% grade going to a 1.69%
grade.
70
[13] Fix the vertical elevation labeling on this sheet for the profile view.
71
Three variance requests were received regarding Bella Vista from Northern
Engineering. The variance requesting the reduction in sight distance along Stanford
Drive, the variance to reduce the driveway spacing from 660' to 610', and the variance
to reduce the utility easement along Horsetooth were all viewed favorably upon by the
City Engineer. Final approval of these variance requests will occur with completion of
the designs for Horsetooth and Stanford that are acceptable to the City and the utilities.
72
[13] The 2.55% shown on this sheet appears to actually calculate to 4.2% with the
elevations and stationing shown.
77
The Traffic Engineer has noted that the center turn lane should be continuous from the
intersection to the Cove Island development and continuing east. The Traffic Engineer
notes that a 3/4 movement to allow left turns into the site could be designed (with
painted medians) in conjunction with the porkchop island to facilitate right turns out of
this driveway.
78
The cross section sheets show the additional road width to be 4% or even greater.
Because a saw cut is being shown to the centerline for most of Horsetooth, a
continuous straight line grade needs to be maintained along the entire north half of the
roadway where the sawcut is shown. For the additional width between stations 10+00
and 11+00, (where the roadway is not being sawcut to centerline), this new portion of
roadway is limited to 3%.
79
A grade break is shown on Sheet [12] that exceeds .40%. A vertical curve would be
required based on this design.
98
Provide spot elevations at the Horsetooth and Stanford intersection in accordance with
LCUASS Standard Detail 7-32B.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
CXM@@ o
urban design, inc.
100
The submitted "Street Cross Sections" from the site planner is not appropriate to be
submitted as a document along with the site and landscape development plan
documents. Street cross sections are to be shown on the utility plan set and will be
established based upon an approved design for the roadway(s).
101
Angle poinis along the flowine appear to be shown along Horsetooth, please revise and
use curves as shown in LCUASS 7.4.1.
104
It appears that redirects are too abrupt on the street striping plan. See traffic comments
regarding this.
Topic: Utility plans
76
The drawings regarding the storm system across Horsetooth originally approved by the
City showed an inlet being tied to the easternmost pipe, the submitted plans show that
the inlet is tied to the westernmost pipe.
Applicant Response:
1) General
a) The acce;>s ramp design is now reconciled on both the site plan and utility plans.
b) General note #4 has been revised to reflect adopted City Policy.
2) Grading
a) A letter of intent is being provided as requested.
3) Plat
a) Access easements for all public walks will be provided upon resolution of the
alignments of the affected walks.
b) The min ?um right-of-way is now indicated, along with a utility easement
adjacent to Horsetooth Road.
c) The emergency easement is noted for the "surface level' only as suggested.
4) Sidewalk
a) Erosion control and walk locations have been reconciled on the revised plans
5) Street Design revisions are reflected in the utility plans and addressed in the
response letter from Northern Engineering.
6) Utility Plans =visions are reflected in the utility plans and addressed in the response
letter from Northern Engineering
Department: PPA
Issue Contact: Ron Gonzales
Topic: Plat
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered. A fire pump may also be required,
as well as standpipes for the building and the parking garage below grade. 97UBC
\\SERVER\Server_D\WP\9000\9600\9601 PDP-RESPONSE3.doc
urban design, inc.
The response letter from Cityscape stated that notes to this effect have been added to
the plans. Please indicate where the notes are.
Ventilation System:
A 2-stage ventilation system shall be provided for the parking garage below grade.
Stage One shall be tied to a Carbon Monoxide Detection System that will detect carbon
monoxide at 50ppm over 8 hours and/or 200ppm over 1 hour and ventilate the garage.
Stage Two shall provide ventilation for smoke removal in the event of a car fire.
UBC1202.2.7
The response letter from Cityscape stated that notes to this effect have been added to the
plans. Please indicate where the notes are.
Applicant Response:
a) Notes regarding sprinkler requirements fire pumps standpipes and 2-stage
ventilation have been added to the PDP General Notes (#'s 23 and 24)
Department: Police Issue Contact: Joseph Gerdom
Topic: General
9
Lighting Plan: The Luminaire schedule and luminaire detail don't provide sufficient
information to determine exactly which lights are used in each location. Also, unless
there are wall fixtures there is inadequate illumination between Bldg B & C; east face of
Bldg D; and north face of Bldg B. In general, all building access points should have
minimum of 1 fc.
Topic: Landscaping
10
Landscape Plan: The use of Austrian Pine, cotoneaster, and ninebark along the faces of
Bldgs B, C, and D, particularly in front of public/private entrances will obscure these
areas and raise security issues. Lower growing species, lighting, or some combination
thereof would be recommended.
Applicant Response:
A revised lighting plan has been provided indicating locations of wall mounted
fixtures for security lighting. The provision of adequate lighting — rather than reduced
landscaping — is the preferred security measure.
Department: Stormwater Utility Issue Contact: Basil Hamdan
Topic: Construction Easements
80
The proposed 24" RCP across Horsetooth Rd. will necessitate the construction of a
headwall and part of the culvert on Tract D of The Landings 1 st Filing. Prior to
construction on this Tract owned by that HOA the contractor should make sure that the
HOA is notified and that the area will be properly restored. Even though this area is in
\\SERVER\Server_D\WP\9000\9600\9601 PDP-RESPONSE3.doc
Ca�Y2(§C o
urban design, inc.
an existing drainage easement, the landings 1st Filing HOA which maintains this area
should ensure that the area is put back to an acceptable level, equal or better than
before constructiion.
Topic: Ditch Company Approval
87
Prior to allowing additional discharge from this site into Warren Lake, the Warren Lake
Ditch company must sign off on these plans.
Topic: Drainage Report
83
Please provide street capacity calculations for Horsetooth Road for the area that is
being widened by this project. Since Horsetooth is a major arterial the standards call for
no curb overtopping in the 10-year storm and one lane open in the 100 -year storm.
Please provide sizing calculations for the proposed Stormceptor.
Please provide sizing calculations for the proposed spillways on ponds 1 and 2.
Topic: Erosion Control
86
Please submit an erosion control plan that meets the standards of the City of Fort
Collins. The submitted materials do not meet our minimum standards. Contact Bob
Zakely for further directions.
Please provide ai better detail for the proposed erosion control fabric for Pond 2.
Provide a seed mix for the native grass proposed in this pond.
Topic: Grading,
85
The proposed offsite grading on the northwest corner of the site will require an off -site
grading easement from the adjacent property owner.
Please provide a detail of the retaining walls that are not part of the proposed buildings.
There are still some areas in the upper level parking that do not seem to drain properly.
Please revise and add spot elevations. The proposed patio area to the west of Building
B has a low point with no proposed drainage outlet.
Topic: Landscaping
90
Several inlets on private property might be affected by the dense vegetation proposed
around these. Please revise landscaping plans to ensure proper drainage from these
areas even though they will be owned and maintained by the Bella Vista FICA.
Topic: Off -site Grading Easement
88
The swale on the north side of the property as well as some grading takes place on
private property (Strachan 1 st Filing Subdivision) . The plans show that this easement
will be granted by separate document. A letter of intent will be required prior to PDP
hearing and a final easement is needed prior to Final Compliance.
\\SERVER\Servef_D\WP\9000\9600\9601 PDP-RESPONSE3.doc
urban design, inc.
Topic: Plat
89
Please connect drainage easement in driveway to off -site drainage easement on the
plat.
Topic: Roof Drainage
91
Please show on the plans how the roof drains are getting to the proposed water quality
ponds.
Topic: Tree Removal
81
The construction of the 24" pipe across Horsetooth Rd. could impact the existing 8"
Blue Spruce on the south side of Horsetooth. The note that was added to the plan calls
for the contractor to determine in the field whether this tree can be saved. This is not
acceptable. The City will not allow the contractor to remove this tree at his own
discretion. Please REMOVE this note as the City will not allow this tree to be removed
and provide plans that will preserve the tree in place.
Topic: Utility plans
82
This is a repeat comment: The proposed storm sewer coming from the Stormceptor
and tying into the line along Horsetooth is currently shown as a 12"RCP. The minimum
allowed size in the ROW is a 15" line please correct. The 15" City line should extend to
the edge of the ROW (back of walk), this part of the line should be public and separated
from the private 12" line that would extend back to the Stormceptor by a manhole.
Please make sure that storm line G has enough cover at the point it exits into Horsetooth Road.
the minimum cover requirement is 1-foot below subgrade.
The proposed storm sewer on Horsetooth Rd. seems to be very close to several
existing utilities especially at the east end of the line. The line seems to be jammed
within 4' of an existing sanitary manhole and close to existing telephone and gas lines.
Such small separations are not acceptable please revise plans. The line also seems to
be under the proposed curb and gutter. A meeting with strormwater and wastewater as
well as other utilities is recommended to discuss the pipe alignment issue.
Please specify an ASTM Standard C443 gasketed joint for all pressurized storm lines.
The existing 5-foot inlets on the corner of Horsetooth and Stanford are shown to be
remaining in place on the Utility plans, while the talcs included in the drainage report
check for the sizing these inlets and the plans show that these might need to be
relocated and reconstructed with the widening of Horsetooth Rd. Please clarify. Will
the existing inlets be moved ?
If a right turn lane is called for on Horsetooth and Stanford then the existing junction box
vault should be designed to handle traffic loads and the elevation of this box should be
checked.
Applicant responses are included in the revised utility plans and response letter
provided by Northern Engineering.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
o
urban design, inc.
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: Sidewalk
73
Applicant needs to provide off -site sidewalk connection on Stanford from their site north
to Monroe.
Based on the City's pedestrian LOS standards within the Land Use Code (LUC) and
Larimer County Urban Area Street Standards (LCUASS) the minimum LOS for
pedestrians is not met. Contrary to Mr. Delich's response, the proposed development is
actually located within the area types classified as "transit corridor" and "school walking
area". Therefore, all pedestrian LOS elements must meet LOS B, except for the visual
interest and amenities as stated within the LCUASS and the TIS provided. The
LCUASS further explains that all "destination areas" within a quarter mile (1,320 feet)
must be identified within the TIS for analysis. All locations are identified within the TIS
with the exception of the medium density residential land use to the north, which is
located on the NE corner of the Monroe and Stanford intersection. This "destination
area" does not meet the minimum LOS for "directness" as measured on the street grid
system, and thus, the minimum pedestrian LOS for "continuity" due to the lack of a
sidewalk along Stanford between the proposed development and the identified
intersection.
In addition, the LUC states in Section 3.2.2 C.7 "Offsite Access to Pedestrian and Bicycle
Destinations", that "offsite pedestrian or bicycle facility improvements may be required in order
to comply with the requirements of Section 3.2.2 (E) (1) (Parking Lot Layout) and Section 3.4
(Transportation Level of Service Requirements).
84
Proposed mid -block pedestrian crossing shown on Stanford looks problematic due to
curve. This is a Traffic Engineering call however.
Applicant Response:
As agreed at our June 10t" meeting, the revised plans additional analysis from Matt
Delich demonstrate that the minimum LOS is met without provision of the off -site
sidewalk along Stanford, adjacent to the Aspen Leaf Apartments. It was also agreed
that the proposed mid -block pedestrian crossing on Stanford is acceptable with the
design revisions shown on the current PDP.
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: Landscaping
48
Repeat Comment: Coordinate landscape design with the civil design and provide the
required landscape/utility separation distances. Correctly show all existing and
proposed water/sewer mains and services on the landscape plans. With the tight
constraints on this site we would be willing to relax our separation requirements,
\\SERVER\Server_D\WP\9000\9600\9601 PDP-RESPONSE3.doc
urban design, inc.
however we will not allow landscaping to be placed directly on top of our facilitates.
Please consider the placement of shrubs and trees to minimize the impact to our
facilities.
Topic: Utility plans
54
Repeat Comment: Maintain 18-inches of vertical separation between all water, sanitary
sewer and storm sewer crossings.
92
Place all curb stops and meter pits adjacent to the main when at all possible. Curb
stops must be located within a utility easement.
93
Provide a minimum of 10 feet of separation between storm sewer manholes and
sanitary sewer mains.
94
Clearly define all water main joint deflection (I.e. Vertical, Horizontal, Beginning, ending,
etc.).
95
Clearly show that the valve box located on the south side of Horsetooth will not end up
half in and half out of the vertical curb.
96
After much consideration and discussion within the utility, it has been determined that
placing concrete around the existing sanitary sewer main will only hamper any attempt
to excavate the sewer in the future if required. Please remove all notes from this plan
set which refers to encasing the existing sanitary sewer main. It has also been
determined that the existing sanitary sewer is PVC and in good condition, so no
replacement will be required.
97
The only allowable substitution for concrete encasement of sewer mains is to use a 20
foot length of D.I. P. or C-900 PVC pipe. Clearly define any substitution of concrete
encasement.
Applicant responses are included in the revised utility plans and response letter
provided by Northern Engineering, and shown on the revised Landscape Plans
with this PDP.
Department: Zoning Issue Contact: Peter Barnes
Topic: zoning
3
REPEAT COMMENT (1-31-02). General note 1(d)(ii) lists "live/work office type units" as
a possible use. What is that? No such term. Is it the same as a home occupation?
The explanation of what this is in their 1-29-02 letter is interesting, but it doesn't change
anything. Our code contains no such use, therefore the use is not allowed (4.5(C)
prohibits any use that is not expressly allowed). It still seems to me that what they are
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc
o
urban design, inc.
describing on sheet 1 of 6 is a home occupation, which is permitted and is listed by
them on general note 1(d)(i). This type of comment is common from Zoning whenever
an applicant lists a use that is not defined. For example, we make the same comment
relative to an applicant that lists "townhomes" as a permitted use. Since there is no
such defined term, we require them to remove it. If they really want to allow offices in
the building that are not within a dwelling unit (home occupation), then they should do a
Type 2 review in order to obtain approval for things like offices, dry cleaners, hair
salons.
4
REPEAT COMMENT (1-31-02). With regards to my original comment below, I am glad
to see that they have corrected the code section reference number. I find their
explanation in their 1-29-02 letter regarding contextual height to be interesting,
However, I believe they are missing my point. I agree that height can be measured
either in stories or feet. But since the section they reference deals with establishing a
contextual height, it is important that such height be reflected in terms of "feet" not
"stories". Since the height of a story can vary from one buidling to another, City staff
needs to have the height of the applicable buildings indicated to us in "feet" in order to
determine if the proposed height is "contextual". As I stated originally, indicating that a
Bella Vista building may be 6 stories, says nothing to us about how it relates to the
height of the Marriott since one 6 story building can be considerably shorter or taller
than another 6 story building. That's why I asked the question "How tall is the Marriott
in terms of feet"'' They have explained the difference in feet in their 1-29-02 letter, now
they have to put that information on the plan.
(12-18-01) - General note 2 references Section 2.8.17. There is no such section. I assume
they mean 3.8.17 (A)(3). If so, then Planning needs to determine if the 4 to 6 stories is the
appropriate "contextual height". Some of the walls of buildings are almost 90' tall. In my
opinion, "contextual height" as used in 3.8.17(A)(3) implies a similar height in feet as well as in
stories. For instance, a 6 story building on one lot may only be 70' tall, and that doesn't mean
that it's therefore ok to have a 6 story building on an adjacent lot that is 90' tall when the
maximum height allowed in the MMN zone is 3 stories (4.5(E)(1)(d). How tall is the Marriott in
terms of feet?
6
REPEAT COMMENT (1-31-02) - General note 1(d)(iii) - small food service uses listed
are not classified as accessory uses. Therefore, they are not permitted in the MMN
zone. (the only way they can be remotely "accessory" is if they serve only the
residences of the building, and are not open to the "public"). I've read the explanation in
the applicant's 1-29-02 letter, but I don't agree. For instance, would a Sushi Bar really
be accessory, serving the tenants of the building? I doubt it would remain in business
very long with such a small customer base.
7
REPLY (1-31-02). OK, I'll agree with B&B's being allowed. Editorial note - The
applicant has suggested that private houses on lots less than 6000 s.f. would not be
conducive to a six bedroom B&B. I would suggest that such a private house would be
more conducive to a B&B than would a 2 or 3 bedroom condo.
\\SERVER\Server D\WP\9000\9600\9601PDP-RESPONSE3.doc