HomeMy WebLinkAboutRAINTREE COMMERCIAL PUD PHASE II - Filed GC-GENERAL CORRESPONDENCE - 2009-03-12CITY OF FORT COLLINS
ENGINEERING SERVICES
May 16, 1986
Mr. Mike Carver
Taranto, Stanton & Tagge Consulting Engineers
748 Whalers Way
Fort Collins, CO 80525
Dear Mike:
This letter is to confirm the conversations that we have had regarding the
deceleration lane off of Horsetooth Road for the 7-11 Convenience Store at
Cunningham Corner. On May 2 I shot the lip elevation of the new curb installed
by Loveland Excavation and the elevation of the existing edge of asphalt on
Horsetooth Road to see if the minimal slope of 1.1% (as shown on the plan)
existed between the curb and gutter and the existing edge of asphalt. It was
determined that the new pavement if installed would not have the minimal slope
and would in fact have a reverse slope in some places.
After reviewing the elevation shots submitted by you, it appears that the
curb and gutter installed by Loveland Excavation was installed to the plan
grade.
The alternate red -lined plan that you submitted to the City Planning Department
using concrete in place of asphalt will be acceptable to the City under the
following conditions:
I. That the contractor installing the concrete pavement shall take extreme
care in finishing the concrete so as to not create water ponds in the
finished slab.
2. That the City Inspection Department be notified of the construction of
the concrete pavement.
Thank you for your help in this matter.
Sincerely,
Rick Richter
Construction Inspector
4
vb ?�Ys,z.-i'i
ENGINEERING SERVICES
cc: Southland Corporation
Loveland Excavation
Lobar, Inc.
Cunningham Corner Construction
300 LaPorte Ave. • P.O. Box 580 • Fort Collins, Colorado 80522 9
(303) 221-6605