HomeMy WebLinkAboutROBINSON PIERSAL PLAZA PUD - Filed CS-COMMENT SHEETS - 2009-03-12.. r
D
A d
7 May 85 **40 DIE]DAIR
ROBINSON PIERSAL PLAZA - Preliminary PUD 26-85A
04"�MMENTS
V
CITY OF FONT COLLINS
COMMUNITY DEVELOPMENT DEPARTMENT, PLANNING DIVISION
May 21, 1985
Mr. Ed Zdenek
ZVFK
11 Old Town Square, Suite 200
Fort Collins, CO 80524
Dear Ed:
Staff has reviewed the Master Plan and Preliminary PUD submittal for Robinson
Piersal Plaza and has the following comments. Revisions reflecting these
comments are due by noon on June 4, 1984. Items that cannot be shown on the
plans should be addressed in writing.
PUD Plan:
1. Traffic concerns are summarized in Rick Ensdorff's May 13 memo which you
have already received.
2. Access to the service area on Magnolia Street should be reworked as was
discussed at our May 20th meeting. The service area should not be in the
right-of-way. Explain how parking removed from Magnolia Street can be
accommodated.
3. Include information on the United Bank drive-thru facility in the traffic
analysis.
4. Correct inconsistencies between the site plan, master plan, and traffic
impact information.
5. Parking ramp elevations and grades should be added to the plans. It is
not clear how the parking structure works in terms of circulation and
stacking. Please clarify this graphically. Add stop signs as was
previously discussed.
6. Ramps should be heated unless you can demonstrate this is not necessary.
C 6 b
OFFICE OF COMMUNITY 300 LaPorte Ave. • P.O. Box 580 • Fort Collins, Colorado 80522 • (303)221-675
DEVELOPMENT, PLANNING DIVISION
Mr.
Ed Zdenek
'
From:
Elaine KleckneAkW
Re:
Robinson Piersal
May
23, 1985
Page
2
7.
Staff suggests the sidewalk design at corners be done like that on the
adjacent blocks (with the exception of the southwest and northwest
.
corners). Handicapped ramps should still be provided.
8.
Existing unused curb cuts should be removed/replaced.
9.
Damaged curb, gutter or sidewalk damage must be replaced.
10.
The plan calls the alley a utility easement. It should be noted as
right-of-way to be vacated.
11.
The alley must be vacated before development occurs. Existing utilities
Li
must be relocated before the vacation is finally approved.
12.
What is the triangle in the southwest corner?
13.
Sidewalks should follow curb returns at all entrances to the site.
14.
The Traffic Impact Study does not include an acceleration lane on
C�
Mulberry.
15.
All curb cuts should be concrete to the property line.
16. Provide information on the possibility of using existing storm sewer
lines. Cutting up the streets may not be necessary.
17. A 0.90' water depth on the building seems excessive. Can the structure
hold this? What happens to the displaced storm water when the
residential portion is constructed?
18. One way aisles through the parking area must be 20' wide unless overhang
occurs, in which case 22' is required.
19. 90 degree spaces must be 9' wide.
20. It isn't clear where overhang can occur. Is the edge of the parking
structure a concrete wall on either level?
21. A lower level parking plan should be provided.
22. Dimension rows of parking spaces, aisles and width of spaces.
23. Fire sprinkler water service must be sized to serve the entire complex
including the residential portion unless a separate sprinkler/standpipe
system is proposed. The sprinkler connection must be on the Remington or
Magnolia side of the building. Check if adequate flow for connection to
the 6" water line is available.
24. East -west and north -south access lanes must be designed to support a
pumper truck.
25. The Fire Department command center must be included in the first phase.
01
Mr. Ed Zdenek
From: Elaine Kleckner,+
Re: Robinson Piersal
May 23, 1985
Page 3
26. Building design review by the Poudre Fire Authority should occur before
building permit application.
27. Indicate building envelopes and show dimensions. A 2' roof overhang can
extend beyond the envelope line. More than 2' must be in the envelope.
28. All signs must comply with the Sign Code. What type of sign system will
be used for the project?
29. Show motorcycle and bicycle parking.
30. Minimum width for a landscape island is 8'.
31. A minimum 15' landscaped strip is required between the sidewalk and
parking structure.
32. Provide trees in the parking lot islands.
33. Street trees should be 3" caliper minimum.
34. Provide a landscape schedule.
35. Use DDA Design Guidelines for the streetscape to the extent possible. A
grass strip is recommended along College Avenue as well as conformity in
lighting and street furniture. This will provide consistency with the
proposed United Bank expansion.
36. Planning Objectives must be submitted. Address specific City policies
and goals and objectives as well as the point charts used.
37. A detailed development phasing schedule should be submitted. What happens
under the store until Phase 2 parking is constructed? How many spaces
could ultimately be provided?
38. More information on the structure of the grocery store is needed since
this will dictate how the future residential development will look.
39. Provide more detail on the elevations. Indicate what the exterior
materials will look like, show windows, doors, areas for signage for both
the store and parking structure. Provide an east and north elevation
also.
40. Indicate how mechanical space is enclosed.
41. Provide sections at a larger scale through the Mulberry Street and
College Avenue frontages.
42. Indicate building heights on the elevations.
43. A noise impact study is required, as was previously discussed.
• Mr. Ed Zdenek
From: Elaine Kleckner
Re: Robinson Piersal
May 23, 1985
Page 4
44. How will the project deal with the neighborhood concern about odors from
the service area?
45. Overall reduction in energy use is an absolute and specific criterion.
Please address this.
MActur Plan
1. Water and Sewer comments that existing line sizes in Mulberry do not
appear large enough to serve the proposed use.
2. A number of existing water services on this block must be abandoned,
preferably before Remington is over-layed this summer.
3. The Police Department is concerned about security for the parking
structure. Check with them on lighting standards and provide a note on
the plans.
4. The plan should indicate where residents will enter the future building.
5. Phase 2 access is poorly located.
6. Provide more information on how the residential portion would be phased
in and how this affects the existing uses.
7. Information on Phase 2 building height and mass is needed. Although
detailed plans are not required, north -south and east -west sections
should be provided. Also, the potential building should be superimposed
on views from the Oak Street Plaza, South College Avenue, north Ft.
Collins (Country Club area),. the DMA Tower (higher level), Park Lane
Towers, and Remington, Peterson and Mathews Streets at a mid -block.
8. Have you explored the possibility of a mid -rise, stepping -down effect for
the residential portion? Staff would encourage an imaginative,
multi -level approach to depicting the future phase.
9. The Master Plan must include approximate acreage and density of each
area, number and type of residential units, estimated floor area, and
types of business and commercial uses.
10. Planning Objectives and phasing schedule are also required with a Master
Plan submittal.
Mr. Ed Zdenek
From: Elaine Klecknerr+
Re: Robinson Piersal
May 23, 1985
Page 5
I suggest we meet at your convenience to discuss these points. PMTs, colored
renderings and copies of the plans for the Board are due on June 14th.
Sincerely,
Elaine Kleckner
Planner
cc: Curt Smith, Community Development Director
Sam Mutch, Planning Director
Bonnie Tripoli, Development Coordinator
CITY OF FORT COLLINS
DEPARTMENT OF TRANSPORTATION
i 4, i
MEMORANDUM
,
TO: Sam Mutch, Planning Director
Elaine Kleckner, City Planner '` '''"
FROM: Rick Ensdorff, Traffic Engineer
DATE: June 13, 1985
RE: Robertson/Piersal Plaza
In a review of the re -submitted site plan and traffic impact
study, I would offer the following comments. These comments
pertain to issues that I feel need to be resolved before the
final approval of the site.
1. The southbound left turn bay at College Avenue and
Magnolia Street, in my opinion, is needed with the
development of this site. My concerns are that the
impacts from the design of this turn bay could be
significant. My initial analysis indicates that at a
minimum, some median landscaping would be lost and
possibly some parking stalls in the median. At this
point, all possible designs have not been looked at.
Discussions on this design concern need to continue.
2. Responsibility for construction. At the present time,
the turn bay improvement is not in the City capital
program. Negotiations need to be pursued concerning the
responsibility of funding this possible project.
3. Responsibility for Remington Street. If, in fact,
Remington Street needs to be restriped, the
responsibility for removing existing stripes and
layout/restriping needs to be determined. This includes
transitions to existing striping south of Mulberry Street
and north of Magnolia Street.
I
—uvu m)-u- - �..-j. oux aou - ron c:omns, Colorado 80522 • (303)221-6615
TRANSPORTATION
date:
rtmenl,.* ��? -
ITEM:7)'(,r�,SCLA F-I I Ea
�b
Fi n(--L
cm
\_I
CITY OF FORT COLLINS
COMMUNITY DEVELOPMENT DEPARTMENT, PLANNING DIVISION
August 26, 1985
Mr. Ed Zdenek
ZVFK Architects/Planners
Eleven Old Town Square
Suite.200
Fort Collins, CO 80524
Dear Ed:
Staff has reviewed the Final PUD submittal for Robinson Piersal Plaza, Phase
I, and the Preliminary PUD for Phase II, and has the following comments to
offer. Revisions reflecting these concerns should be submitted to the
Planning Office by noon on September 4, 1985. Items that can't be shown
graphically should be addressed in writing.
PHASE I - FINAL PUD
1. Comments from the State Highway Department are attached. A copy has also
been forwarded to the City Traffic Engineer.
2. As we discussed on August 16th, the Department of Transportation is
opposed to the new left turn onto Mulberry Street. Other issues that
require further discussion are outlined in the attached memo from Rick
Ensdorff. Conditions of the PUD submittal that have not been fully
addressed include:.
a. A design solution for the potential stacking problem at the Mulberry
Street access.
b. A design for the left -turn bay onto Magnolia (we have engineering
drawings but still need the landscape plan).
c. Developer participation in financing the left -turn bay onto Magnolia.
OFFICE OF COMMUNITY T
nFVFI nPMFNT. PLANNING DIVISION
300 LaPorte Ave. • P.O. Box 580 • Fort Collins, Colorado 80522 • (303)221-6750
G
M
M
b. Provision must be made for a grade -level command center and fire pump
room. Note its location on the plans. il
c. Contact Warren Jones on special review procedures for the parking
structure.
d. The interface between Phase I and the residential structure must be
detailed.
13. The Police Department is concerned that the parking deck design does not'
allow for natural surveillance. Contact Lee Frausel in this issue as
well as potential loitering problems.
14. At least 9' of clearance must be maintained between the first and second
parking level for emergency access.
15. Elevations on the parking deck and drives should be noted on the site
plan and elevation at parking deck.
16. Curbing must be noted be noted on the plan for landscapea areas in the
parking deck.
17. Show motorcycle parking on the plan.
18. All signs should comply with the Sign Code. You will recall that Staff
requested a detailed signage plan for the complex previously.
19. A detailed final landscape plan should be provided as soon as possible.
The highly visible areas along College and Mulberry are of particular
concern given potential utility conflicts. Also, as recommended by the
City Arborist, larger than standard size trees should be provided. A
condition of preliminary approval was that plantings be intensified
overall.
20. Pedestrian and vehicular area lighting specifications should be provided,
as was required at preliminary.
21. Structural information on Phase I should be provided as was required at
preliminary to provide an understanding of design constraints for Phase
II.
PHASE II, PRELIMINARY PUD
1. The technical concerns raised for Phase I should be noted for this
submittal also.
2. The high-rise must have a complete fire protection package including
sprinklers, alarms, fire command center and smoke removal.
3. A construction management plan should be provided for review to include
where construction equipment will be located, where vehicles will park,
r
3. The new design of the service area still appears to create some traffic
problems and extends too far into the right-of-way (36' must be
maintained). It now impacts two streets and little room for landscaping
exists. An encroachment permit must be obtained from the City by the
final document submittal date (9-19-85) to allow the service area in the
right-of-way.
4. Discussions at the preliminary stage were leading to the addition of
another lane adjacent to College Avenue on the north half of the site,
yet this has not been shown.
5. The western ramp up to the parking deck must be a minimum of 20' wide and
it appears that the arrows on the parking deck are incorrectly drawn.
:)6. Engineering has pointed out that the pedestrian access ramps and
sidewalks are incorrectly. drawn. The area between the curb and walk
�Jshould be a minimum of 6' wide.
7. Mountain Bell has a problem with vacation of the alley. Contact Bonnie
Tripoli on this.
8. John St. John of the Light and Power Utility is concerned that
deceleration lanes will conflict with overhead and underground utilities.
Overhead lines on Mulberry will have to be removed at the cost of the
developer. He has also pointed out that the design does not recognize
the duct banks on Magnolia and Remington which would cost in the range of
$150,000 per frontage to relocate. Also, provide 15' easements on all
streets.
9. The Water and Sewer Utility does not want trees planted over the existing
water lines on College and Remington.
10. Public Service points out that there is an existing gas main in the alley
that will have to be relocated. Bonnie Tripoli can provide information
from Gary Huett on where the new lines should be located. A 20' x 160'
utility easement at the southeast corner of the site should be provided.
11. A note should be added to the site plan that roof -top storm water
detention will be provided, with detailed structural plans required prior
to issuance of a building permit.
12. The Fire Department has questioned the structural adequacy of the lane
between the parking deck and the Safeway. It must be designed to support
a fully loaded pumper truck. This concern also relates to their ability
to provide emergency services for the high-rise. Other comments are as
follows:
a. The fire main size must be calculated to supply both retail and
residential uses.
.
D"". 1— 7 May 85 **e DEE DA TiNIMM—
A
Robinson Piersal Plaza MASTER PLAN
137'
C�JWTVJEN b
9
2§-85
how the adjacent street system will be impacted, how construction of the
residential phase will affect first phase operations and a phasing
schedule. There is some concern from the Planning and Zoning Board that
construction of Phase II may be quite disruptive to the area. ;
4. Show building height on the elevations. Please provide south and west
elevations.
5. Given the magnitude of the project, Staff will continue to evaluate the
building height review criteria and the appropriateness of a high-rise
structure at this location (during the first part of the week of the
26th). I'll let you know if additional information is needed.
Spring, summer and fall shadow impacts as well as different times of day
for each season would be helpful for comparative purposes. Also, a
perspective from the Magnolia/Mathews intersection should be provided.
The tower design does not provide the stepping -down effect that was
originally discussed at the Master Plan stage and this may be of some
concern to the Board. A written discussion on the design intent would be
useful to both Staff and the Planning and Zoning Board. Use of masonry
and emphasis of the entry area are positive features of the design,
however more information on exterior materials should be noted on the
plans.
6. Justification for reduction in residential parking spaces should be
provided.
7. Land use data should be provided on an 8" x 11 1/2" sheet.
PMT's and colored renderings are due by September 16th at noon and final
documents are due by September 19th. I am available to discuss these
comments at your convenience.
Sincerely, /
Elaine Kleckner
Planner
CC: Linda Hopkins, Acting Community Development Director
Rick Ensdorff, City Traffic Engineer
Bonnie Tripoli, Development Coordinator
M
n
CITY OF FORT COLLINS
COMMUNITY DEVELOPMENT DEPARTMENT, PLANNING DIVISION
September 30, 1985
Mr. Ed Zdenek
ZVFK Architects/Planners
Eleven Old Town Square, Suite 200
Fort Collins, CO 80522
Dear Ed:
The following is a summary of the Staff concerns on the Robinson
Piersal Plaza project, as discussed on. August 16, and our
comments as a result of further review of the project. Many
of these items were mentioned in my Interdepartmental Review
summary letter, dated August 26, 1985.
1. The
still
design of the southbound left turn
on to Magnolia is
an
issue. On September 26th the DDA
indicated that they
were not
in favor of decreasing the width of the existing planter
bed in
The City
College Avenue to accomodate the
Forester believes it can be done but
turning movement.
the
substantial. Rick Ensdorff has also solicited
cost would be
input from
Transfort,
Fort Town, and the City Engineer on
this but I don't
know what
their responses were. Rick will be
out of town until
October 7th, but I suggest we meet with him as soon as possible
after his
return to explore other options. We
must also discuss
developer
participation in financing the
College Avenue
improvements.
2. Location of the water line had not been determined at the
meeting on the 26th. Engineering has reviewed the most recent
set of plans and will be talking to your engineer shortly.. I
don't anticipate problems with the College Avenue alignment.
3. A revocable permit is required for the loading zone. After
further discussion of this with the Assistant City Attorney, it
was determined that the request will be sent to City Council
after final P&Z approval.
4. The building design,
College Avenue presents a
believes a strong statement
do feel the impact of the
Avenue should be softened
Avenue for,;he high-rise should
with hi gh-ri se
very hard, urban
is appropriate
building mass
somewhat. A
be provided.
directly adjacent to
edge. Although Staff
at this location, we
as viewed from College
setback from College
OFFICE OF COMMUNITY
ncvcn nn.ecnir ni nniniinir_ nnncinni
300 LaPorte Ave. • P.O. Box 580 • Fort Collins, Colorado 80522 • (303)221-6750
n
n
Page 2
Ed Zdenek
5. In terms of landscaping, loss of it (trees) in the parking
deck is a concern. More detail is needed on the final plan.
Indicate the type of paving material for the plaza spaces. Use
of tree grates on College Avenue should be specified. Staff does
not feel comfortable with extensive use of Red Oak since it has
not 'been particularly successful in the Fort Collins area.
Selection of a more. "tried and true" species is recommended. Use
of additional evergreen trees should be considered along the
service area, and at the Mulberry/Remington corner for a more
dramatic landscape statement. And finally, with the change in
the high-rise footprint, the rooftop landscape area will require
revision.
6. A basic construction management plan should be provided, as
was previously requested. Several P&Z Board members have
specifically requested information on how the surrounding area
would be affected with and without phasing of the project.
7. Phasing of the project is a separate issue and of great
concern to the P&Z Board. At this point in time, I believe that
it is the consensus of the group that the project should not be
phased. This is primarily due to the concern that the Phase I
design by itself cannot stand on its own and is not the highest
and best use of the site. Other Board concerns about phasing
include construction management and potential disruption of the
surrounding area.
8. A condition of preliminary approval was that you document
structural information on the Safeway Store so that Staff and the
Board can understand the design constraints associated with
development on top of the structure.
9. Please provide the background and information source for your
parking analysis. If only 30% of the units are to be used as
elderly housing, we may need to reevalute the 0.5 space per unit
ratio.
10. Details on lighting and signage must be included on the plans
as a condition of P&Z Board approval. Attention to detail in this
respect could make the Board more comfortable with a phased
approach.
11. Information on type and color of exterior materials should be
noted on the plans.
n
n
Page 3
Ed Zdenek
12. Provide the perspective of the service area that we
discussed. You will recall that the appearance of this area was
of particular concern to the neighborhood. A higher masonry wall
should be considered to adequately screen the area.
13. We appreciate your desire to contribute to "art in public
places". Lets discuss this further before the P&Z hearing.
14. Note building height on all elevations.
15. The bus stop location should be shown on the plan (mid -way on
the half -block with the parking structure). Provision of the
appropriate pedestrian amenities and landscape revisions should
be included.
16. There appear to sidewalk design/utility location conflicts on
the corner of Mulberry and Remington.
I am available to meet on these items at your convenience.
Revisions should be submitted by October 9th. PMI's, colored
renderings and full-size copies for the Board are due on the 21st
and final documents are due on the 24th.
Sincerely,
Elaine Kleckner
Planner
cc: Linda Hopkins
Rick Ensdorff
Bonnie Tripoli
Developrif nt Services
Planning Department
Citv of Fort Collets
June 5, 1989
MEMORANDUM
TO: Gary Diede, Director of Engineering Services
✓Mike Herzig, Development Coordinator
Rick Ensdorff, Director of Transportation Services
Peter Barnes, Zoning Administrator
Pern Goldy, Cumberland Companies
Tod Bruteig, Cumberland Companies
Ed Zdenek, ZVFK Architects
Burt Pedri, Safeway Manager
FROM: Joe Frank, Assistant Planning Director/.
RE: Summary of Meeting Regarding Robigsdn-Piersal Plaza
On Friday, June 2, 1989, representatives of the City, Safeway and the devel-
opers of the Robinson-Piersal Plaza project met to discuss a number of out-
standing issues. The following is a summary of the issues and recommend-
ations for their resolution.
1. Issue: Location of traffic signal pole in sidewalk at the corner of
Mulberry and College avenues.
Problem: Obstructs passage of pedestrians.
Solution: The relocation of the pole would cost about $6,000. Since pedes-
trian volumes are relatively low, staff does not feel the situation warrants
the cost of relocation. There appears to be sufficient clearance to handle
current and near future pedestrian traffic.
Staff will continue to monitor the situation and if a problem occurs the
sidewalk area could be widened in the future to allow a minimum three foot
clearance (an additional 1 1/2' foot of sidewalk is needed). If widening is
needed, the additional cost of widening the sidewalk would be borne by the
developer.
2. Issue: Slope of landscaped area between sidewalk and parking garage
along College Avenue, Mulberry Street and Remington Street.
Problem: Slope is too steep and may create a safety problem.
6A_ fn&J<_aS
Lal'orre Avenue • P.O. Boy ;mil • Fort Collins, CO ,ti(152_2-0580 �O;1
Solution: The developers representatives and City staff walked the site on
Friday and identified certain improvements that were needed as follows:
a. The
landscape wall along Mulberry Street will be raised to allow a
gradual
slope. The wall will be raised to allow a maximum
more
I foot difference
between
the top elevation
of the wall (measured from
the side of the wall
closest
to the sidewalk)
and the public sidewalk.
Additional fill dirt
will be
provided to level
out the slope. A one -foot
shelf will be graded
next to
the sidewalk. The
landscaping will need to be
removed and replanted
to accomplish the raising of
the wall.
b. Portions of the sloped area along Remington Street and College Avenue
will need additional fill. Also, a one -foot shelf will be graded next to
the sidewalk. Some or all of the landscaping will need to be removed and
replanted.
Ed Zdenek stated he would have a design solution for City approval by
Tuesday, June 6.
3. Issue: Handicapped ramps on Mulberry and Magnolia streets.
Problem: Too steep.
Solution:: The handicapped ramp at the westerly loading area access
point will be reconstructed to City standard. The applicant's represent-
ative and City staff met on site to discuss the ramp at the Mulberry Street
entrance. Several alternative designs were discussed. The ramp will need
to be reconstructed. The applicants should provide a design showing the
final alternative for City approval prior to construction.
4. Issue: Sidewalk along College Avenue between curb cut and Mulberry
Street.
Problem: Too narrow.
Solution: There is relatively low pedestrian volumes along this stretch
of College Avenue. Staff will continue to monitor situation. If a problem
occurs, sidewalk will need to be widened and trees put in grates. The cost
(approximately $5,000) will be at expense of City, because the current
installation meets City standards.
5. Issue: Loading area in the main driveway in front of Safeway.
Problem: Retail shops are loading off College Avenue.
Solution::
The loading situation was explained.
The main
driveway in
front of
Safeway is capable of handling fire trucks and other
large loading
vehicles.
City will not allow loading off College
or Magnolia.
The loading
zone at
the rear of Safeway is "public" i.e. for
the use of all
tenants in
the Plaza. Developer needs to work with tenants.
Applicants
will monitor
the need
for a painted loading zone in private driveway. If one is needed,
the location and proposed signing will need to be
submitted to
the City for
approval.
`mar'
6. Issue: "No loading" zone signs on Magnolia.
Problem: PUD condition required installation of signs. They have been taken
down and replaced with "no parking" signs.
Solution: City will install "no loading, standing.." signs in addition to
no parking signs on Magnolia in accordance with the PUD site plan.
7. Issue: Storm drainage,
Problem: Storm drainage rooftop outlet at the northwest corner of the building
currently drains onto sidewalk. This is not acceptable.
Solution: The contractor will provide a design solution for City approval
which outlets this pipe into the underground storm drainage system. One
solution is to take the pipe through the Safeway building an then outlet into
drainage system. The existing outlet fixture onto plaza will be plugged.
8. Issue: Bus stop.
Problem: Bus stop on College Avenue was not installed per PUD plans.
Solution: Contractor will install bus stop per City specifications. City
will let developer know the needed design of the bus stop.
9. Issue: Storm Drainage.
Problem: The developers have changed some outlets and flow areas from
approved plans. These changes have not been approved by the City.
Solution: Bill Vanhorn will provide a revised storm drainage report
for City review and approval. Ed Zdenek or Tod Bruteig will contact Van -
horn.
10. Issue: Plaza.
Problem: Chipped concrete in plaza area needs repaired.
Solution: Chips in sidewalk where sawcut occurred needs repair. Epoxy
grout would be acceptable. Contractor needs to provide specifications for
grout for City approval.
11. Issue: Regulatory signs at the curb cuts on Remington Street and Col-
lege Avenue.
Problem: The existing vehicle directional signs block pedestrian passage.
Solution: Signs will be mounted on single poles by contractor.
12. Issue: Loading zone at rear of store.
Problem: The storage of materials is blocking use of loading area. Also, the
PUD site plan was conditioned that no storage be visible from public rights -of -
way.
*4 '
Solution: Safeway and the developers agreed to remove all storage from
the loading area. It will be relocated to the interior of the store or to
another appropriate location.
13. Issue: Storage in pedestrian area in front of stores.
Problem: Storage blocks pedestrian passage. PUD plan stipulated no storage,
display or sell of goods in this area.
Solution: Safeway and developers agreed to remove all storage and display
of goods from pedestrian areas.
14. Issue: 4 parking spaces that back out onto main driveway in front of
Safeway.
Problem: Unsafe condition for automobile parking.
Solution: It was agreed that these spaces may be used
for
cart sto-
rage, motorcycle parking or bicycles.
Safeway asked that this
space
be used
for temporary storage and display of
goods for a maximum of
two
times per
year (spring bedding plants and x-mas
trees) for a maximum
of three weeks
per occurrence. The Planning Staff
will evaluate this request
and
get back
to Safeway and developers.
15. Issue: Ramp area to lower parking deck.
Problem: Signing of height and traffic control.
Solution: A signing plan has been reviewed and approved by the City's Traf-
fic Engineer. All signs must comply with sign code.
16. Issue: Underground parking deck.
Problem: Circulation.
Solution: A plan for a one-way system has been reviewed and approved by
the City's Traffic Engineer. This plan should be submitted as administrations
change.
17. Issue: Public parking spaces in parking structure.
Problem: Need to clarify use with developers and tenants.
Solution: 30 public parking spaces were designated on -site to offset loss
of public parking on Magnolia and Remington streets. These spaces are two hour
parking now, but could be used for long term in the future, depending on
need. There may be opportunity to move long term parking to lower level.
These spaces will need to be maintained. The situation was discussed at
length with the developer.
18. Issue: Designated employee parking.
Problem: Safeway wants to remove designated employee parking from parking
structure.
Solution: Leave designated employee parking spaces in structure as
shown on the site plan for now. Reevaluate situation in future in terms of
overall downtown parking issue. The spaces may be shifted around if needed.
However, the total number of employee spaces needs to remain the same. If
spaces are relocated, a parking plan must be submitted to the City for
review and approval.
19. Issue: Storm Drainage.
Problem: Extra concrete at inlets block storm drainage flows.
Solution: Contractor will chip out excess concrete.
20. Issue: Landscape median at College and Magnolia.
Problem: Tiles at nose of median not installed.
Solution: Contractor will install missing tiles.
21. Issue: General clean-up of site.
Problem: Some areas of site need to have construction mess cleaned up.
Solution: Final clean-up of site will occur after all landscaping is
installed.
22. Issue: Paving of College, Mulberry and Magnolia streets.
Problem: Asphalt falling apart since the developers initially paved the
streets.
Solution: Contractor will grind and pave streets in June, 1989.
23. Issue: Loading Zone area at rear of Safeway.
Problem: Water dripping from compactor area across sidewalk and into gutter
is unacceptable.
Solution: The Safeway representative felt the problem occurred because of a
leaking water faucet. Also, some stock persons were dumping ice into the
compactor. This has been corrected. Safeway and the City will continue to
monitor the situation.
M
MEMORANDUM
TO: Elaine Kleckner, City Planner
FROM: Rick Ensdorff, Traffic Engineer
DATE: May 13, 1985
RE: Robinson-Piersal Plaza
I have reviewed both the traffic impact study and the proposed preliminary
site plan for this proposal and I offer the following comments. They are
broken down into two areas. One, regarding the traffic impact analysis and
second, the proposed site plan impacts. I feel that this proposal, in
particular the traffic impact study, was done in a very short time span,
which I think contributed to the lack of information that now exists.
1. Traffic Impact Study Analysis
The following items need to be addressed for a traffic impact analysis
of this site to be completed:
A. There is no signal timing analysis at all included in this study.
At this time College Avenue and Mulberry Street intersection is a
very major traffic signalized intersection in the City of Fort
Collins. This site will have a significant impact on the operation
of this traffic signal. A signal timing analysis needs to be done
in regards to this intersection as well as signal progression on
both Mulberry Street and College Avenue in regards to this site.
B. The intersection of College Avenue and Magnolia Street has been
assumed in this study to have no impact on this site. I would not
agree with this statement. A major flaw in this assumption is that
southbound vehicles on College Avenue would use a left turn at
Olive Street over to Remington Street to access the site. We also
do not allow a left turn at Olive Street for southbound College
Avenue. It shows a very superficial analysis of the surrounding
traffic operations.
C. Although a decision on the future roadway needs in the downtown
area has not been determined, it is unacceptable for this project
to not plan to allow for future changes, such as the widening of
Mulberry Street or a possible one-way couple on Magnolia Street and
Mulberry Street. It is stated in the traffic impact study that
because the decision has not been made, nothing would be done along
those lines. That is not acceptable.
Robinson-Piersal Plazkwoomments
May 13, 1985 - Page 2
M
D. Traffic counts used for this study are 1983, as well as turning
movements in 1985. A concern is that the volumes for this project
be as up-to-date as possible. If it can be shown that the turning
movements reflect current overall traffic by comparison maybe peak
hours to the 1983 peak hours, thjat is acceptable. If not, current
traffic counts need to be taken. The site plan indicates that at
the time of final PUD, certain design questions will be answered,
such as the turn bays and the installation of the median on
Mulberry Street. This is not acceptable. It is very questionable
that these facilities can be designed to meet our standards, and
they need to be addressed at the preliminary stage so there is not
an assumption through the process that they will be allowed.
E. Certain assumptions are made in this traffic generation concerning
the existing Safeway store such as its relocated traffic and the
amount of passer-by traffic. I think some of those assumptions are
not necessarily valid. An understanding of what might happen on the
old Safeway site and what redistribution of traffic to the new
Safeway site is reasonable. To grossly assume that 20-30% of the
traffic could be attributed is somewhat confusing and needs to be
defined better. Back to back left turn bays on Remington Street
north of Mulberry Street are unacceptable. Currently, this
operation is not in existence in the City of Fort Collins and I
feel that it is a radical change from the existing patterns of
left -turn lanes. It is being proposed primarily because this would
be the only way that the left turn stacking can be accommodated. I
do not feel that it is an acceptable option.
F. There seems to be a signficant conflict between the site plan
submitted and its geometric proposals and some of the proposals
that are included in the traffic study. Obviously, these have to be
resolved.
2. Site Plan Analysis
A. There is insufficient information on the parking garage layout, its
.operation, its stacking and how the ramps work.
B. On Remington Street exit, approximately 40 feet is allowed for
stacking of vehicles. I do not feel this is adequate. I question
the drive -through in front of the store between Remington Street
and College Avenue. I question it on two factors; One, its
potential opportunity for cut -through traffic between these two
streets and the amount of traffic which will be using this
facility, and; Two, its impact on the operation of the grocery
store.
C. At
this time, without further analysis, it is unacceptable to
reduce the width of any of the surrounding street system. This
includes College Avenue, Remington Street, Magnolia Street and
Robinson-Piersal Plazomments
May 13, 1985 - Page 3
E5
Mulberry Street. The proposed utility plan indicates curb bulges
and reduces width on all these facilities. Until an overall
decision is made on the needed street operation needs, these kinds
of proposals are unacceptable. The distances of the proposed
deceleration lanes need to be justified. As an example, the
deceleration lane from Remington Street into the Remington access
of the grocery store proposes a 38-40 foot transition and a 75 foot
deceleration lane. If in fact deceleration lanes are needed, this
is totally unacceptable. If we are talking about right turn bays,
then possibly something in the vicinity of 120-150 feet might be
acceptable. The same type of comment goes for the proposed
deceleration/acceleration lane on Mulberry Street. Again, the
distances are inadequate for deceleration lanes. Right -turn bays
and their distances need to be determined by need. The operation of
the service area on Magnolia Street needs to be explained and how
this will work. Again, the future operation of this street, and
the next twenty years operation of this street needs to be
analyzed.
D. This plan is proposing to remove parking from the south side of
Magnolia Street. Where is the parking that is being removed going
to be relocated? Parking currently is being used by adjacent
property owners and businesses.
In summary, the above items indicate a significant concern from a traffic
standpoint. More work needs to be done on the traffic impact study to
justify this proposal, in both areas, the surrounding street system as
well as sight analysis. I propose that during the week of May 20th, a
meeting with the applicant be held to define the issues and determine the
course of action.
n
M
CITY OF FORT COLLINS
COMMUNITY DEVELOPMENT DEPARTMENT, PLANNING DIVISION
May 15, 1985
Mr. Ed Zdenek
ZVFK Architects and Planners
11 Old Town Square, Suite 200
Fort Collins, CO 80524
Dear Ed;
We have received preliminary comments on the Robinson-Piersal Plaza PUD
from the City Traffic Engineer. Since a substantial amount of additional
information and corrections are needed, I am attaching a copy of those
comments now. We need two additional copies of the Traffic Impact as soon
as possible, too. You can expect additional comments on the project based
on Staff's Interdepartmental Review next week.
Also, I wanted to remind you that we will need a noise impact study to
address general traffic impacts as a result of the store as well as the
sound generated at the loading area.
Sincerely,.
Elaine Kleckner
Planner
EK/kb
CC: Sam Mutch, Planning Director
Rick Ensdorff, City Traffic Engineer
DEVELOPMENT, PLANNING DIVISION
n
M
MEMORANDUM
TO: Elaine Kleckner, City Planner
FROM: Rick Ensdorff, Traffic Engineer
DATE: May 13, 1985
RE: Robinson-Piersal Plaza
I have reviewed both the traffic impact study and the proposed preliminary
site plan for this proposal and I offer the following comments. They are
broken down into two areas. One, regarding the traffic impact analysis and
second, the proposed site plan impacts. I feel that this proposal, in
particular the traffic impact study, was done in a very short time span,
which I think contributed to the lack of information that now exists.
1. Traffic Impact Study Analysis
The following items need to be addressed for a traffic impact analysis
of this site to be completed:
A. There is no signal timing analysis at all included in this study.
At this time College Avenue and Mulberry Street intersection is a
very major traffic signalized intersection in the City of Fort
Collins. This site will have a significant impact on the operation
of this traffic signal. A signal timing analysis needs to be done
in regards to this intersection as well as signal progression on
both Mulberry Street and College Avenue in regards to this site.
B. The intersection of College Avenue and Magnolia Street has been
assumed in this study to have no impact on this site. I would not
agree with this statement. A major flaw in this assumption is that
southbound vehicles on College Avenue would use a left turn at
Olive Street over to Remington Street to access the site. We also
do not allow a left turn at Olive Street for southbound College
Avenue. It shows a very superficial analysis of the surrounding
traffic operations.
C. Although a decision on the future roadway needs in the downtown
area has not been determined, it is unacceptable for this project
to not plan to allow for future changes, such as the widening of
Mulberry Street or a possible one-way couple on Magnolia Street and
Mulberry Street. It is stated in the traffic impact study that
because the decision has not been made, nothing would be done along
those lines. That is not acceptable.
Robinson-Piersal Plaza ",mments
May 13, 1985 - Page 2
E5
D. Traffic counts used for this study are 1983, as well as turning
movements in 1985. A concern is that the volumes for this project
be as up-to-date as possible. If it can be shown that the turning
movements reflect current overall traffic by comparison maybe peak
hours to the 1983 peak hours, thjat is acceptable. If not, current
traffic counts need to be taken. The site plan indicates that at
the time of final PUD, certain design questions will be answered,
such as the turn bays and the installation of the median on
Mulberry Street. This is not acceptable. It is very questionable
that these facilities can be designed to meet our standards, and
they need to be addressed at the preliminary stage so there is not
an assumption through the process that they will be allowed.
E. Certain assumptions are made in this traffic generation concerning
the existing Safeway store such as its relocated traffic and the
amount of passer-by traffic. I think some of those assumptions are
not necessarily valid. An understanding of what might happen on the
old Safeway site and what redistribution of traffic to the new
Safeway site is reasonable. To grossly assume that 20-30% of the
traffic could be attributed is somewhat confusing and needs to be
defined better. Back to back left turn bays on Remington Street
north of Mulberry Street are unacceptable. Currently, this
operation is not in existence in the City of Fort Collins and I
feel that it is a radical change from the. existing patterns of
left -turn lanes. It is being proposed primarily because this would
be the only way that the left turn stacking can be accommodated. I
do not feel that it is an acceptable option.
F. There seems to be a signficant conflict between the site plan
submitted and its geometric proposals and some of the proposals
that are included in the traffic study. Obviously, these have to be
resolved.
2. Site Plan Analysis
A. There is insufficient information on the parking garage layout, its
operation, its stacking and how the ramps work.
B. On Remington Street exit, approximately 40 feet is allowed for
stacking of vehicles. I do not feel this is adequate. I question
the drive -through in front of the store between Remington Street
and College Avenue. I question it on two factors; One, its
potential opportunity for cut -through traffic between these two
streets and the amount of traffic which will be using this
facility, and; Two, its impact on the operation of the grocery
store.
C. At this time, without further analysis, it is unacceptable to
reduce the width of any of the surrounding street system. This
includes College Avenue, Remington Street, Magnolia Street and
Robinson-Piersal Plaza " mments
May 13, 1985 - Page 3 �4W
Mulberry Street. The proposed utility plan indicates curb bulges
and reduces width on all these facilities. Until an overall
decision is made on the needed street operation needs, these kinds
of proposals are unacceptable. The distances of the proposed
deceleration lanes need to be justified. As an example, the
deceleration lane from Remington Street into the Remington access
of the grocery store proposes a 38-40 foot transition and a 75 foot
deceleration lane. If in fact deceleration lanes are needed, this
is totally unacceptable. If we are talking about right turn bays,
then possibly something in the vicinity of 120-150 feet might be
acceptable. The same type of comment goes for the proposed
deceleration/acceleration lane on Mulberry Street. Again, the
distances are inadequate for deceleration lanes. Right -turn bays
and their distances need to be determined by need. The operation of
the service area on Magnolia Street needs to be explained and how
this will work. Again, the future operation of this street, and
the next twenty years operation of this street needs to be
analyzed.
D. This plan is proposing to remove parking from the south side of
Magnolia Street. Where is the parking that is being removed going
to be relocated? Parking currently is being used by adjacent
property owners and businesses.
In summary, the above items indicate a significant concern from a traffic
standpoint. More work needs to be done on the traffic impact study to
justify this proposal, in both areas, the surrounding street system as
well as sight analysis. I propose that during the week of May 20th, a
meeting with the applicant be held to define the issues and determine the
course of action.