I his is to inform you that your asphalt paving on streets Canterbury,
glen Haven and West Drake in Kensington South Subdivision will be completed
by November 1), 1977, weather permitting.
cc: file
11 you have any ether questions, ptease feel free to contact me.
Yours 'I ruts,
STERLING PAVING CO.
J
By: Bob Gardner
We Are An Equal Employment Opportunity Employer
ENGINEERING DIVISION
August 29, 1980
Mr. Rex s• Miller
Rex Miller Construction, Inc.
P.O. Sox 1417
Fort Collins, Colorado 80522
Dear Rex:
we are presently preparing an inventory of detention ponds in the
City to determine whether or not they have been properly constructed
and have been accepted for maintenance by the City. In doing so, we
have noted that the detention pond for Kensington South, First Filing
has not been. constructed in accordance with the approved utility
drawings.
The headwall at the outlet structure and the trickle channels have
not been installed. Also, the overall grading of the pond is not in
accordance with the utility plan. if you wish to go over these items
before you correct them, please contact Dave Stringer at our office.
If you have any questions regarding this matter, please call me.
Sincerely,
Marc Engemoen
Civil Engineer IS
cc: Dave Stringer
m
REX S.
s gg
L�1 I l'� S
`O"v'STRUC,TIC►N INC;.
„� ` ,
9-9-80
Marc I,;ngco�oen
city of Fer_t Collins
Engincering Division
P.O. Rox 580
T't. Collins, rn 80522
UcarMarc;
We are in receipt of your letter dated August 29, 1980 regarding
the detention pond for Kensington South, First Filing. Rex
asked me to notify you to the effect that the headwall and trickle
channels will he installed by the summer of 1,981. At this time
t_h(, grading will also meet the utility plan specifications. If
you do not find this reply satisfactory, please contact our office
at. 482-4743.
;Sinccr� ly,
rl( rrri_ l— Celka
Sccrclary
b;nclo:;urc
MILLER
CCMPANIES
Cit-y of Port Collins
I,,'no Ii nc(ring fk1,parti[K nL
P.O. Box 580
Dort Collins, CO 80522
AtLr: Ronnie Trfpolie
To whom it may concern;
Miller Properties Inc
PBox 2272
July 2, 1�81
This letter is to inform you of our intent to repair Lhe sect -ion of sidewalk
d�u,gcd in Front of the property located at 1343 Glen Haven Drive, Lot 38,
Kensington South Subdivision. We will repair the damage within thirty (30)
day cf the of the certificate of occupancy. At this time we ask
that you give clearance on this property . Thank you for your
cooperation.
sincerely,
Bruce E. Miller
t 3ty/ t: l Cl
MILLER
l'h
CCMNiES
City of Fort Collins
I�ngineorrinq Depart-mcnt
P.O. 1Sox 580
Fort Collins, CO 80522
Dear Sirs;
Miller Properties Inc
,trc(t N. ") Sox 2272
oct_oi-,--r b, 1981
'Tbe intent of thi:; letter is to request that Fngineerinq Clearance be given for
the property located at 1430 (;len Haven (hot 12, Kensington South, 1st Piling).
Tlir,r(, is scxnc, repair work to I)r done in the concrete sidewalk along the street.
The -,se repairs will be made within a thirty day period. We are asking that
cleararco Ix, given from your department so as to obtain a Certificate of Occupancy
from the Miildinq Tnspection Department. Your cooperation in this matter will
ix, greatly appreciated.
Sincerely,
Bruce F. Miller
I3f 7,l/tl
CIIV (Jf KJKI LVLLWO
... e: a ..
BUILDING INSPECTION
December 9, 1981
-
f .ffisi._. .b..c Sv.•X. _J 4: ..r�.r S.1 hC ....-°sr.-.r;
Mr. Bruce Miller
Miller Properties, Inc.
P. 0. Box 2272 re
Fort Collins, CO 80522
Dear Bruce:
1430 Glen Haven Drive
Sidewalk Repair
It has come to my attention that a 30-day, Temporary Certificate of Occupancy
was issued for the above residence on October 19, 1981 conditional upon the
adjacent public sidewalk and surrounding pavement being repaired. As of this
date, our office has not received clearance from the Engineering Division in-
dicating that the necessary repair has been done.
I understand furl 'her that your office has been apprised of this matter by a
phone call from our office on two separate occasions with no corrective
action taken.
City subdivision regulations specifically require that all such public im-
provements be completed prior to issuance of a Certificate of Occupancy.
Because the Temporary Certificate has expired, the occupants of the above
residence are no longer authorized to remain there. Therefore, if the
required sidewalk repairs are not completed within five days of this notice,
proceedings to vacate the above residence will be initiated as agreed to by
your firm when the Temporary Certificate was issued.
Sincerely,
-
Felix C; Lee
Deputy Chief Building Official
FCL/dlh
cc: Dave Stringer, Chief Construction Inspector
Residents of 1430 Glen Haven Drive
P.O. Box 580. Fort Collins. Colorado 80522
ENGINEERING DIVISION
April 13, 1982
Rex S. Miller Construction, Inc.
3833 Spruce Drive
Fort Collins, Colorado 80526
Ph
Dear Mr. Miller:
I am sure you are aware that the detention pond, for Kensington South,
First Filing has still not been constructed in accordance with the
approved utility drawings. The headwall at the outlet structure and
the trickle channels have not been installed, and the overall grading
is not in accordance with the utility plan.
I brought this matter to your attention in a letter dated August 29,
1980, a copy of which is attached. You advised me in a letter dated
September 9, 1980, also attached, that the necessary work would be
completed by the summer of 1981. As we are now approaching the 1982
construction season, I wonder if you are planning to bring this matter
to a conclusion.
484-4220 Ext. 728
I realize that the present slump in the building industry has affected
your construction schedule, and that is difficult to estimate when
construction will pick up again. But I am sure you can appreciate the
concern of the homeowners in Kensington South who have endured the nui-
sance the pond creates:in its present condition for the past three years.
Please advise me at your earliest convenience when we can anticipate
the completion of this pond. Your cooperation in this matter would be
greatly appreciated. If you have any questions, please do not hesitate
to call me.
Sincerely,
4"7 5Wle/f-1—
Marc Engemoen
Civil Engineer IT
Attachments
FLATIRON
CONCRETE CONSTRUCTION CO.
941 RIVERSIDE DRIVE, FORT COLLIN S, COLORADO 80524 • PHONE (303)484-9262
Reply to: P. O. Box 504, Fort Collins. Colorado 80522
August 3, 1983
City of Fort Collins
P.O. Box 580
Fort Collins CO 80522
P,ttn: Dave Stringer Re: Detention Pond Swale
& Headwall @ Kensington South
Dear Dave:
Flatiron Concrete Construction has been contracted
with Rex Miller to build the concrete swale and headwall
at the Kensington South Detention Pond. Work will begin
immediately.
SKW/jd
Sincerely,
Steven K. Wood, Superintendent
Flatiron Concrete Construction Co.
FOUNDATIONS & FLATWORK
CURBIGUTTER
CITY OF FORT COI TINS
ENGINEERING SERVICES
July 7, 1983
Mr. Rex S. Miller
Rex Miller Construction, Inc.
P.O. Box 1417
Fort Collins, Colorado 80522
Re: Kensington South Subdivisions
Dear Rex:
Some weeks ago you met with Marc Engemoen and myself to discuss the detention
system in the Kensington South lst Filing as it relates to building permits.
In our meeting you indicated the remaining improvements to the detention
system would be completed as soon as possible. In turn, the City agreed not
to withhold building permits in the Kensington South Subdivisions because of
the drainage system.
To date the City has released building permits for homes on Hastings,
Canterbury and Knottingham streets. However, work towards completing
the drainage system has not yet started.
The City has operated in good faith towards its portion of the agreement and
now requests the drainage system be completed.
In addition, after the pond's completion a letter from your engineer to the
Storm Drainage Utility, certifying the drainage system has been constructed
to the lines and grades shown on the Kensington South 1st Filing Utility Plans
as approved by the City Engineer must be submitted.
If the drainage system is not completed by July 31, 1983, the City Engineer's
office will withhold all building permits in the Kensington South Subdivisions.
All permits requested from now to the July 31st date will be handled on an
individual basis.
I regret the :inconvenience this may cause you, but the Kensington developments
have expam.ed to the point where completion of the pond is necessary.
0 A ��` y vG I
David Stringer'�
Chief Construction Inspector
cc: Mick Mercer
Tom Bays
James H. Stewart and Associates, Inc.
Consulting Engineers and Surveyors
214 North Howes Street
P.O. Box 429
Fort Collins, Colorado 80522
(303) 482 9331
March 28, 1984
Mr. David Stringer
City of Fort Collins
P.O. Box 580
Fort Collins, Colorado 80522
Dear Dave:
Laboratory:
301 Lincoln Court
P.O. Box 429
Fort Collins, Colorado 80522
(303)484-6309
This is to inform you that we have examined the detention pond on Tract "A",
Kensington South, First Filing. The concrete pan was straightened and has
been completed. Some finish grading was required to ensure the bottom of
the pond drains to the pan. The volume of the pond was not significantly
decreased; however, its actual volume was much greater than the volume re-
quired at the time the pond was designed.
The pond appears to be built as designed and will function as it is supposed
to. If you have any questions regarding the pond, please call.
Sincerely,
JAMES H. STEWART AND ASSOCIATES, INC.
Richard A. Rutherford, P.E. & L.S.
Secretary/Treasurer
ME
cc: Rex Miller
CITY OF FORT COLLINS
STORM WATER LIT ILI TY
April 2, 1984
Mr. Rex Miller
3833 Spruce Lane
Fort Collins, Colorado
Re: Detention Pond in Tract A, Kensington South, lst
Dear Mr. Miller,
I have received a letter from Dick Rutherford of James H. Stewart & Associates,
Inc. dated March 28, 1984. This letter was addressed to Dave Stringer, Chief
Construction Inspector, and indicates that certain work has been completed on
the detention pond in Tract A. From what I understand this work was necessary
prior to final acceptance of the pond by the City.
Please be informed that before the City can accept the pond for perpetual
maintenance an "as built" survey showing detailed cross sections of the pond
will be necessary. These cross sections are needed to verify pond volume
and check bottom elevations to see if there is adequate slope to insure the
bottom of the pond drains to the pan. After these cross sections are received,
reviewed and approved, a final site inspection will be completed prior to
final acceptance. If, after the site inspection we are satisfied with the
construction of the pond, you will be notified in writing of the City's
acceptance for perpetual maintenance.
Please call me if you have any questions.
Sincerely,
v(�kC' 6. LJazrQ-
Philip G. Waite, Civil Engineer II
Storm Drainage Division`/
cc: Dave Stringer "
Chief Construction Inspector
REX S.
CONSTRUCTION, INC.
P.O. BOX 1417, PORT COLLINS, COLO. 80522
November 22, 1977
City of Fort Collins
Engineering Department
300 Laporte Avenue
Fort Collins, CO 80521
Gentlemen:
Re: Paving of Drake Road
Following is a list of charges to the City of Fort Collins for
the above paving.
r,.
4130 cu„ yds. of 6" sub base at $1.18 $4,873.40
2710 cu.-yds. of 2" asphalt overlay 4,742.50
342.95 tons of road base (north side) at $3.60 1,234.62
Sub grade prep 692.15
Total charge to City of Fort Collins: $11,542.67
Sincerely,
R.S.M. DEVELOPMENT COMPANY
By:
Presidentk
cd
CITY OF FURT COLLINS
STORM WAFFR UTILITY
April 5, 1984
Mr. Rex Miller
3833 Spruce Lane
Fort Collins, CO 80526
Re: Kensington South 1st Filing
Dear Mr. Miller,
As you requested I am sending you this letter to verify the Tract A, Kensington
South 1st Filing has been in the past and will be in the future used for a
detention facility for this development.
During our discussion at the site this afternoon I indicated that once the Storm
Drainage Division receives, reviews and approves the "as built" cross section
information a final site inspection will be completed. If after the site
inspection, the Storm Drainage Division is satisfied with the work, a letter of
acceptance will be sent to you and the City will assume responsibility for
perpetual maintenance.
As we agreed upon, the area to be included in the cross sections is that portion
of the pond east and approximately 10 feet west of the new concrete trickle pan
installed from the south inlet to the pond. Also that portion of the north end
of the pond from the top of sidewalk on Drake to the toe of the slope along all
of the area that was filled. As I indicated, the Storm Drainage Division
requires that all new detention ponds to be maintained by the City must have at
least a 20 bottom slope. However, based on your indication that there is not
enough fill material to satisfy this requirement, a 1.5% bottom slope for that
portion of the pond that is being regraded to drain to the pan will be
acceptable.
Please call if you require additional information or have any further questions.
Sincerely,
4P, -4 6. 6,,Jbz�l
Philip G. Waite
Civil Engineer II,. Storm Drainage Division
cc: Subdivision file /
Construction Inspection ✓
,' (J1} I,A IJ(. f I H U 17 I Y rJU l ., F',, r, l,,,,
CITY OF FORT COLLINS
ENGINEERING SERVICES
Date: April 11, 1985
Allision Construction
1000 Driftwood Drive
Fort Collins, CO 80525
Dear Sir:
We have on file in our office a letter of guarantee for
2720 Nottingham in the Kensington South
subdivision. In this letter you agreed to make necessary repairs for
Engineering clearance. To date, these repairs have not been completed.
Please notify this office when these repairs are being made. If I can be
of any assistance to you, please contact me at 221-6605.
Si rely,
Dave Stringer
Chief Construction Inspector
f h1GWFERINL SF.. R�/Ir;F v �'Ylr) I ipnrle Avr (l Doy SH(I . {nii tIs. (:t,' _ do
r-
RE i S.
LIM
CONSTRUCTION, INC.
P.O. IIOX 1417, POIt'I' ( 0IA,INS, COLO. 90522
November 30, 1977
Mr. Tom Jones
Traffic Engineer
City of Fort Collins
300 Laporte Ave.
Fort Collins, CO 80521
Dear Mr. Jones:
We would like to order street signs for the first filing of
Kensington South Subdivision. The following signs will be
necessary in the immediate future.
1. W. Drake Road & Dunbar Avenue
2. Dunbar Avenue & Glen Haven Drive
3. Hastings Drive & Dunbar Avenue
4. W. Drake Road & Canterbury Drive
5. Canterbury Drive & Glen Haven Drive
Enclosed is a copy of the first filing plat showing the
intersections indicated above.
If I can be of any further assistance, please call me at
221-4002.
Sincerely,
REX S. MILLER CONSTRUCTION, INC.
By: ".
President
cd
Enclosure
Post Office So. 580
Fort Collins, Colotodo 80521
January 9, 1978
Rex Miller
Po Box 1417
Fort Collins, Colorado
To Whom It May Concern:
Tal.phons 303 484.4220
It is standard policy for the City of Fort Collins to accept for perpetual
maintenance those public right-of-way constructions which have been approved
by the City and which have passed all required guarantee periods. This includes
the water mains, sanitary sewer mains, storm sewer mains, street pavements,
street lights, and street signs in the Kensington South lst Subdivision
DMP: cs
Sincerely,
Donald M. Parso
City Engineer
TIME CENTER OF THE WORLD
Asphalt Paving • Contracting • Sand & Gravel
inlay li. 1978
Rex Willer
300 C;lenhaVon Drive
Dort Collins, Colo80521
)cer Sir,
(III, ISIIII I:
P. 0. Box 2187 1800 North Taft Hill Road
Fort CnIhns, Colorado 30522
(303) 482-7854
These are the 1978 asphall pnxino nrico, for Ken�lnpton South Snh-
Soil steritant, 6" base & 2" asphalt mat $3.35,Y(l
Soil sterilant, 3" subbase, 6" base & 2" mat $4.10/yd
'Thank you for giving us the opportunity to install your asphalt paving,
we look forward to being of service to you in 1978.
if you have any further questions, please feet free to contact me.
Sincerely Yours,
STLP1,1W PAVING CO.
By: Bob Garfncr
We Are An Equal Employment Opportunity Employer
Asphalt Paving • Contrartiny • Sand & Gravel
July Zl, 1978
Bob Zackley,
City of For( Collins,
r.0. liox 580,
Fort Collins, Colo 80522.
Dear, Bob,
P_ 0- Box 2187 1800 North Taft Hill Road
Fort Collins, Colorado 80522
(303) 482 7854
I his is to inform you that Sterling Paving Co. does have a contract for
asphalt paving Dunbar, Hastings and Sutton Court in Kensington Subdivision, with
kex Miller Construction Co. of Port Collins, Colorado.
cc: file
these streets are to be completed by November 1, 1978.
Sincerely Yours,
S"IFRLING PAVING CO.
By: Bob Gardner
We Are An Equal Employment Opportunity Employer
CITY OF FORT COI, I.INS P,O. BOX 580 FORM COLLINS, COLORADO 80522 PH (303) 484-4220 EXT. 305
ENGINEERING SERVICES DEPARTMENT
October 17, 1978
Rex Miller Construction Company
1300 Glen Haven Drive
P.O. Box 1417
Ft. Collins, CO 80522
Re 7.0' Concrete Walk & Bikeway,
Drake Road
Kensington South Subdivision
Dear Sir:
on June 9, 1978 the 7.0' concrete walk and bikepath was
constructed on the south side of Drake Road between Dunbar
Avenue and Canterbury Drive. It has since been noted that
the landscaping has not been completed per plan as shown
on Section A -A, Sheet 15 of 15 of Kensington South Utility
Plans. It has been observed that the drainage Swale between
the vertical curb and gutter and the 7.0' walk has not been
graded to meet the top of walk or the back of curb, thus
allowing undermining of the north edge of the walk in
numerous areas.
This landscaping should be completed as soon as possible
to prevent any further erosion in these areas and to minimize
the structural damage taking place on the north edge of the walk.
The 7.0' walk and bikeway will not be accepted by the City
until the landscaping is completed.
very truly yours,
Rodney 1R. Albers
Constriction Inspector
PA/cm
100% Recycled Bond
CIlY(M IMAI (UIIINS f.0. lioX 5so, f A U)I_II N b COLOR,1 DO50�_2 I'llpO3) IS1-422O
I NGINI. I_IM(, DIVISION
November 2, 1979
Mr. Pat walker
F&F Concrete Construction
941 Riverside
Fort Collins, Colorado
Dear Pat:
A survey of the Cedar Village and Kensington South subdivisions
indicates several areas of concrete curb and gutter installed by
your company which retain water because of improper construction.
These areas are listed on the attached sheet. As you know, you
are 1-C'SpOnsitl0 for poor workmanship and materials for a period
of two years from the date you install new concrete.
Please be advised that you should make all necessary repairs
to the listed areas within the next 30 days. Failure to do so
could result in action being taken on your cement contractor's bond
to have necessary corrections made.
Sincerely,
G�
Bob Zakely
Chief Construction Inspector
LXT. 728
REX ' se
Y FEE
CONSTRUCTION, INC.
P.O. BOX 1417, FORT COLLINS, COLO. 80522
9-9-80
Marc Engemoen _
City of Fort Collins
Engineering Division
P.O. Box 580
Ft. Collins, CO 80522
Dear Marc;
We are in receipt of your letter dated August 29, 1980 regarding
the detention pond for Kensington South, First Filing. Rex
asked me to notify you to the effect that the headwall and trickle
channels will be installed by the summer of 1981. At this time
the grading will also meet the utility plan specifications. If
you do not find this reply satisfactory, please contact our office
at 482-4743.
Sincerely,