HomeMy WebLinkAboutFIRST INTERSTATE BANK DRIVE THRU FACILITY PUD - Filed GC-GENERAL CORRESPONDENCE - 2003-10-30L. W."Bill" Riddell
Senior Vice President -Banking Division
July 11, 1980
Mr. Robert Smith
Storm Drainage Engineer
City of Fort Collins
300 LaPorte Ave.
Fort Collins, CO 80521
Dear Mr. Smith:
FIRST
NATIONAL
BANK
205 West Oak, Fort Coll i ns. Coloratlo 80521
Telephone 482-4861
Please accept this letter as First National Bank's request for a
variance of the City's storm drainage retention requirements on
our drive -up facility located at 201 West Olive Street in Fort
Collins.
The First National Bank is in the process of relocating the
entrance to this facility from Mason to Howes Street. In our
efforts to gain maximum utility of this site, we have discovered
that the 4500 cubic feet storm water retention curbing requirement
will be a burden and hardship on the operation of this facility
during the winter months.
In order to satisfy the retention requirement it will be necessary
to construct a curb approximately 72' long and 12" high along our
main driveway. While this curbing will serve as a ponding agent
it will also seriously hamper our ability to remove snow efficient-
ly and economically. Further, since this site is also used as an
employee parking lot we are concerned about pedestrian safety and
the danger of them slipping on the ice when the water becomes
frozen.
Consequently we are asking that the retention requirement be re-
duced from 4500 cubic feet to 13-1500 cubic feet. Further, we are
also seeking permission to move this water into the City system
An Affiliate of•; Western Bancorporation
Mr. Robert Smith
July 11, 1980
Page Two
via Mason Street and the alley to the South of our property. We do
not feel this arrangement will have an adverse impact on the property
in the area. (See attached sheets for flow data.)
Your favorable consideration of this request will be appreciated.
Please advise if you require additional data or information.
Respectfully submitted,
L.W."Bill" Riddell
LWR:cm
Attachment
Clly(N 1010 )IIINS
ENGINEERING DIVISION
July 16, 1980
P.O. Box 580, Fort Collins, Colorado
Mr. L. W. "Bill" Riddell
First National Bank
205 West Oak
Fort Collins, Colorado
Dear Sir:
The following is in response to your request to alter the
parking facilities for the First National Drive -up Bank
and the employee parking area,
The City is in agreement with your request subject to the
following conditions,
484-4220 Ext. 728
1 - Details must be shown on the drawing for the outlet
from the detention area and asphalt ridge to be
placed in the alley.
2 - Drainage flow paths must be shown on the drawing.
3 - The plan must be signed by the Assistant City Engineer -
Development, and a reproducible of the final plan shall
become a part of the Cityts records.
Any access flow above the detention pond in the employee parking
area will overflow into the drive -up detention area.
If I can be of further assistant on the matter, please advise.
Sincerely,
f
Robert W. Stn th
Assistant City Engineer •- Drainage
U/ cc: Mauri Rupel
PARSONS &
Ir-'1- ASSOCIATES
CONSULTING ENGINEERS
January 27, 1993
Mr. Glen D. Schlueter
Stormwater Utility�f�
City of Fort Collins ��i`t -�/J' f�yco✓%U✓r G>ti�frfEr
235 Mathews Street
Fort Collins, Colorado 80524 "C&V �ivr v q/
RE: First Interstate Bank Drive-Thru Facility - Stormwater CertificationrL__
Our Project Number: 92.13 NEE
Dear Glen:
We have completed a field review and field survey of the Stormwater improvements built as part of
the First Interstate Bank Drive-Thru Facility. This project was completed on a 2.067 acre site at the
southwest corner of Boardwalk Drive and the JFK Parkway.
This Follow up letter addresses three areas that we discussed to finalize this project.
1) The erosion control measures are installed and complete per our plans.
2) The riprap area at Pond "B" has been reshaped and is complete and drains south per
field shots.
3) The debris and excess dirt pile have been removed. Note: there are small topsoil areas
that will be smoothed and blended along with the sprinkler installation backfill to finish
ground elevation for sodding.
As a result of our field review, I feel that the drainage improvements are in substantial conformance
with the reports and plans approved by the City of Fort Collins for this development.
Please feel free to contact me should you have additonal questions.
SinceYJrely�,
Mike Cole
Engineer
MC/gbl
cc: Paul Hoffman, The Neenan Company