HomeMy WebLinkAboutFIRST CHOICE BANK OF FORT COLLINS REPLAT - Filed GC-GENERAL CORRESPONDENCE - 2003-10-30WA1 --R
WASTE
& LAND
February 7, 1994
Mr. Mike Herzig, P.E.
City of Fort Collins
281 North College
Fort Collins, Colorado 80521
2629 Redwing Rd. Suite 20( t Collins, Colorado 80526-2879
(303)226-3535
fax (303) 226-6475
RE: 1 ST CHOICE BANK - SUBMITTAL OF UTILITY DRAWINGS AND A DRAINAGE AND EROSION
CONTROL REPORT FOR THE PERMANENT BANKING FACILITY (Southeast Corner of College
Avenue and Horsetooth Road)
Dear Mike:
We are submitting, for the City's review, the Plat, Utility Drawings, the Drainage and Erosion Control
Report and the proposed APO list for the referenced project. A landscaping and site plan prepared by
the architect will be included.
The drawings in the Utility set that will show details of the widening of College Avenue, Horsetooth
Road and the Median at Horsetooth and Mitchell Drive, are incomplete awaiting additional information.
However, we understand that the City will review the Bank site drawings at this time so that portion
of the project can proceed while the planning and design work on the remainder is being completed.
The alignment of the sidewalk along Horsetooth Road is not according to City standards. An
explanation of how this and the berming and wall along Horsetooth and the west side of Mitchell Drive
evolved, follows. It will hopefully induce the City to approve this variation in standards.
By way of background, at the outset of the project we held several meetings with Stormwater Utility
to discuss the best approach to handling the runoff from the site and from College and Horsetooth.
Historically, stormwater from these locations ran east on the south side of Horsetooth eventually
ending up in Warren Lake. Along the way some of the water entered a piped system at JFK Parkway,
proceeded through the piped systems that handle the Marriot and surrounding development and then
contributed to the flooding that occurs from time to time at the intersection of Horsetooth and
Landings Drive. An obvious though costly approach was initially considered - a new storm sewer on
the south side of Horsetooth from the site to Warren Lake. This was deemed to be an unfair
imposition on infill development from the standpoint of cost. It was finally agreed that as much
stormwater as reasonably possible would be detained on site. The released runoff from the site and
the runoff from the adjacent streets would then be allowed to take the historical route to Warren Lake.
An analysis of the inlet and stub connection at the southwest corner of JFK and Horsetooth was to
be conducted to determine if any significant benefit would be realized from enlarging both so as to
divert more flow from Horsetooth gutter to the Marriot system. A prediction of the impact of increased
runoff from the developed site on the periodic flooding at Horsetooth and Landings Drive would then
be attempted and a variance requested for the impact. The need for some of these analyses was
eliminated as the final design of the drainage system evolved. This design is explained in the Drainage
and Erosion Control Report.
Consulting Engineers and Scientists
I st Choice Bank - Development Agreement Revisions05/25/95
Page 2
certain off -site improvements to Mitchell Drive and JFK Parkway that will
complete those streets and related drainage improvements described in (a)
and (b) Ibeing collectively referred to as the "Improvements" provided that the
following conditions first have been met:
(i) Funds in an amount sufficient to reimburse the developer for the
City's cost share of the improvements have been placed in an escrow
account satisfactory to developer.
(ii) Funds in an amount sufficient to reimburse the developer for the
cost shares of the improvements attributable to those owners whose
properties adjoin and will benefit from the improvements have been
placed into an escrow account satisfaetory to developer. Such cost
shares shall be determined on a proportionate front footage basis;or
other basis as mutually agreed upon by the affected property owners
and the developer.
(iii) Funds in an amount sufficient to reimburse the developer for the
cost shares of the South College Avenue and Mitchell Drive bridge
improvements (already completed by the Bank) which are attributable
to the City and to benefited property owners have been placed into
an escrow account�ga4gaett��. The cost shares for
benefited property owners shall be determined as in (ii) above.
El Note: A water system has already been installed on the property is this
sentence necessary?
These are changes we believe are necessary to complete the agreement. Could you please
call Spiro and arrange to have him sign the temporary drainage easement. We have
provided you with all the changes o landscaping and drainage he requested. With the
aforementioned changes we stand ready to sign the development agreement.
CC: .John Drennen
Richard Gast
Col nits Plannin- and Environmt Services
Current Planning
k--tty of tort �-oluns
June 12, 1995
Teresa Jones
Colorado Department of Transportation
Region 4
1420 2nd Street
P.O. Box 850
Greeley, CO 80632
RE: SOUTH C01LEGE AVENUE/HORSETOOTH ROAD NORTHBOUND
RIGHT TURN LANE
Dear Teresa:
The City has been reviewing a development proposal for a bank at
the southeast corner of Horsetooth Road and South College Avenue
(SF 287). The City is taking this opportunity to work with the
developer to construct a northbound right turn lane at the
intersection which has been needed for some time. In addition,
after many years, the property owners in the surrounding area
have been working together to design and construct public street
connections which will help recirculate traffic off of College
Avenue. The enclosed site plan shows the existing and proposed
street system and the right turn lane.
The City will be preparing a formal access permit application for
the right turn lane construction. Prior to submittal of detailed
plans, we are requesting your review of the conceptual turn lane
configuration and proposed modification to the existing access
point between the Showtime Video property and Palmer House
Florist. As you are aware, the existing access point is not
ultimately a part of the South College Avenue Access Control
Plan. However, _t is the City's belief that maintaining the
existing access point, with some modifications to the width and
radii, does not create a significant additional impact on College
Avenue at this time. Two alternatives for the access and parking
lot configuration of Showtime Video are attached for your
information and comment. The bank and Palmer House are still
negotiating terms for the cross access shown between those
properties.
with respect to the existing Showtime Video/ Palmer House Florist
access point, there is a potential that vehicles wanting to go
westbound on Horsetooth Road try to exit out onto College Avenue
and cross the travel lanes to cret into the northbound left turn
lanes. However, with the recirculation options on Mitchell Drive
2S1 North College Avenue • P.O. Box 580 Fort Collins. CO 80522-0580 • (303) 221-0750
FAX (303) 221-6378 TDD (303) 224-6002
and J.F.K Parkway, there are opportunities for vehicles to
recirculate without getting onto College Avenue. In addition,
during peak times, the volume of traffic on College Avenue
restricts the possibility of vehicles being able to cross
multiple travel lanes. The enclosed area traffic circulation
map shows the connection of J.F.K Parkway between Boardwalk Drive
to the south and Horsetooth Road on the north. In addition,
Mitchell Drive will be connected from Bookman Drive on the south
(a signalized intersection with College Avenue) and Horsetooth
Road on the north. Lastly, the area property owners are
proposing to provide a public street connection between Mitchell
Drive and J.F.K. Parkway as shown in red on the plan.
Your review and comment on this matter prior to our final design
phase is appreciated. The City is currently reviewing plans for
construction of the Mitchell Drive and J.F.K. Parkway
connections. It is desirable to construct the right turn lane on
College Avenue concurrent with the Mitchell/J.F.K. projects.
Please contact me to discuss this matter as soon as possible. In
addition, I would like to set up a meeting to discuss the design
in detail (radii, width, variance requirements,...). Please call
me at (970) 221-6750 at your earliest convenience. Thank you.
Sincerely, p
Kerrie Ashbeck
Civil Engineer
CC: File
Matt Baker, S.I.D. Coordinator
j l
� ��- 4 J�- /--'.2WVIjTjtAt-
-{ �' « i, r A4- - Ii
IV<� V-('111q, n rytO
vw
VTIm/Y
C-vvg
4-
kc
Olo e --
,�t Itw,( x V-/(i
rA
-f' y
AZ-1
ti
'7Jte
C'r 1
'7Jte
C'r 1
Mr. Mike Herzig
1st Choice Submittal
The conceptual location of the detention pond was suggested by the surface of the undeveloped site.
The existing site drained naturally to its northeast corner and the proposed configuration and grading
of site roads and parking areas around the new bank building substantiated the conclusion that this
was the best point from which to drain the detention pond to the Horsetooth Road gutter by gravity.
The berm and wall were placed to maximize the on -site volume available for detention. Preliminary
drawings of this intended design were reviewed with City personnel on several occasions. The location
of the sidewalk, at one time on top of the berm, now lowered next to the wall, and the widened
sidewalk at the corner of Horsetooth and Mitchell, resulted from these sessions.
It is important to note that the stormwater detention system, as designed, allows a release rate to be
held to or less than historical runoff from a 2 year storm so the development of the site does not
increase runoff to down stream facilities. The anticipated request for a variance for an increase in
flooding at the intersection of Horsetooth and Landings Drive will not be required.
Thank you for your attention to this matter. Please call if you have any questions
Sincerely,
WATER, WASTE & LAND, INC.
c.e N
M urice H. Lutkin, P.E.
Manager, Civil Engineering Division
x/c: Glen Schlueter
CommL y Planning and Environmentai :rvices
J Planning Department
City of Fort Collins
July 22, 1994
Maurice H. Lutkin, P.E.
Water, Waste & Land
2629 Redwing Road
Suite 200
Fort Collins, CO 80526
Dear Maurice:
The following is a summary of my notes from our meeting on
Tuesday, July 19, 1994 regarding the First Choice Bank site at
the corner of South College and Horsetooth:
• The property is in the HB, Highway Business zoning
district. The proposed uses and office building is a
use by right in this district.
• The Code does not address the siting of a temporary
facility therefore it is treated like a permanent
structure for all development review. The temporary
structure must follow all Code requirements such as
setbacks and parking. Special care must be taken in
siting the temporary structure to ensure it maintains
the appropriate setbacks as the improvements associated
with the permanent building are being constructed.
• This parcel requires platting before a building permit
can be issued. As we discussed, it will be possible to
plat just for the area involved in the temporary bank
operation then replat at a later date to include the
entire property. This plat will be processed as a
Minor Subdivision and will be processed through the
Development Review Center. The typical review time is
four to six weeks depending on the complexity of the
project.
• If you only plat for the area of the temporary
structure, you will only need to prepare a site plan
for the area the temporary structure sits on.
• No access will be permitted from Horsetooth Road, even
for the temporary facility. Access will need to be
provided from Mitchell Drive. Tom Vosburg from the
Transportation Department will be working with you to
determine the access location and the required
281 North C lleee Avenue • P.O Boy ;80 • Fort Collins. CO 8052241580 • (303) 221-670
F
temporary improvements to Mitchell Drive for opening
the temporary facility.
o A right turn lane will be required from Horsetooth onto
Mitchell with the connection of Mitchell Drive. This
will need to be shown on the site plan. You will also
need to provide the design for the intersection of the
temporary Mitchell Drive with Horsetooth to include
measures that limit access to right in, right out, left
in only.
• Engineering is preparing to go to condemnation to take
possession of the "Hiller" portion of the Mitchell
Drive right-of-way at the intersection of Horsetooth
and Mitchell. They intend to request immediate
possession so it should not delay permanent
construction of Mitchell. This still requires City
Council approval.
• All review of detention and stormwater issues are being
coordinated with Glenn Schlueter of the Stormwater
Utility.
• The: dedication of the right-of-way for Mitchell Drive
will be required at the time of the initial plat. All
other required dedications will occur at the time of
replat.
• while the City will apply for the State Highway permit
for the turn lane on College Avenue, the applicant will
need to show it on the site plan and construct it. The
City will reimburse in accordance with the City Code
for its construction from the street oversizing fund.
• The review of the utility plans by the Development
Review Engineers will be critical to maintaining the
desired timeline. The typical review period has been
ten to twelve weeks depending on the number of
revisions required. This time period includes the
review of utility plans as well as the preparation of a
development agreement. A development agreement will be
required for the temporary structure as well as for the
permanent building. Collateral will be required to
guarantee the completion of Mitchell Drive, the ditch
culvert, Horsetooth Road improvements and other
improvements that may be identified during the review
process.
11
r
I trust the meeting was helpful to you and your client
the submittal requirements for the temporary facility
and you understand that the review timelines involved
the City's requirements are met. Should you have any
please contact me.
Sincerely,
�t as J
Robert E. Blanchard, AICP
Chief Planner -
cc: Mike Herzig, Development Review Engineer
Kerrie Ashbeck, Development Review Engineer
Tom Vosburg, Transportation Planner
Glenn Schlueter, Stormwater Engineer
Dan Coldiron, Zoning Inspector
I hope
are clear
in ensuring
questions,
��i vv c � ■ c t.
May 2, 1995
Mr. Basil Harridan
City of Fort Collins
Stormwater Utility
235 Mathews
Fort Collins, Colorado 80522
RE: 1ST CHOICE BANK - PROVISIONS FOR DRAINAGE BETWEEN THE NORTH EDGE OF
SHOWTINIE VIDEO PROPERTY AS IT PRESENTLY EXISTS AND THE CULVERT COVERING
LARIMER COUNTY CANAL N0 2.
Dear Basil:
Enclosed is a revised print of Drawing 4 For the 1 st Choice Bank project. You will note that there
has been a revision to the proposed drainage system at the referenced location. This change will
be on the soon -to -be -circulated mylars and we hope you can expedite your review and approval
of this revision so as not to delay mylar signatures.
The prints you recently reviewed for the 1 st Choice Bank project contained provision for a cross -
access roadway between the Bank and Showtime including appropriate grading, drainage
modifications and paving in Showtime's parking lot to cover the needs of traffic and runoff. This
would have made the area operable until the remainder of Showtime's parking lot could be
constructed in its yet -to -be -determined -final -form sometime in the future.
For various reasons, no work will now take place in Showtime's parking lot until College Avenue
is widened, if then lit is presently planned to include the design of lot modifications in the contract
we have with the City to widen Collage Avenue, however, whether actual construction will ever
take place remains to be seen). Accordingly, it is now necessary to make provisions, which may
be either temporary or permanent, to collect the Showtime parking lot drainage and the
precipitation that falls on Showtime property between the north side of the building and the
culvert. The finished elevation of the curbs on top of the culvert is 5031.5, the bottom inside
elevation of the canal is 5024, the finished floor of the Showtime building is 5030.5 and the low
point in the parking lot 5028.62.
The proposed solution for parking lot drainage consists of three 18" ADS in -line drains teed in
series to 12" pvc piping :vhich in turn will drain into the canal as the runoff from the Showtime
parking lot did before. The top of the drains would be set at 5028.5 and the 1 2" discharge pipe
through the wall of the cuivert set at invert elevation 5026.0. Canal No 2 is designed to carry a
maximum irrigation flow sr 155 cfs and under provisions detailed as part of the Heart SID, to carry
an additional flow of 85 cfs - runoff from a 100 year storm. The depth of flow — the culvert at
the 1 at Choice Bank site under latter conditions would approximare 5' or a high :eater elevation
of 5029. The depth under full irrigation flow .vowd aoproximate 3'6" or a hign .eater elevation
2629 3 Roo„ quite 200 =urn Cailins. Cnlor,,an 30526, Ph. 970 226-3535 =_x 370 226 6475
Reno Eiko bYnnamucca Ehyl.vood Pieasammin —ucson
V evada Aavaan Nevada rado Cahforma Arrzona
Mr. Basil Hamdan
Drainage Change
bk&Ad_
\T/ W%f CZ-211, i C%..
of 5027.5. Under the combination of full irrigation flow and runoff from a 100 year storm, water
would pond in the Showtime parking lot as it would have under pre -culvert conditions. Since Canal
No. 2 can only receive water from the Poudre during spring runoff it appears that the chance of
combined flow is reduced.
The proposed solution for the area between the north side of the Showtime building and the culvert
consists of a buried pipe line that picks up the two roof leaders on that side of the building and
conveys the flow to the open portion of Canal No.2 just west of the Mitchell Avenue bridge.
Before the culvert was constructed the roof drains were piped directly into the canal. ADS in -line
drains will be installed at intervals along this pipe line to take care of the small amount of runoff
from the grass covered ground surface la maximum of 20' wide).
Spiro Palmer's approval of the proposed work and the granting of a drainage easement for the
affected areas is anticipated.
Your expeditious review and approval of this last-minute change will be appreciated.
Sincerely,
WESTEC, Inc.
Ma rice H. Lutkin, P.E.
Manager, Civil Engineering Division
x/c Mike Herzig 1
NVATER
IV X%' ,% 5 1' is Project
& LAND Tcsk:
,-C��txj -77,-�e5- �¢.KIrvC? C�JT
Cc'ct.,c,e ; 'l L 4 L _ I
Checked 8/:
Dcte
lebxroo-�- /4,:� x iZo -f- -3cx 70 = D. SS.Oc
CIO a fT Coo = A 0 v- 3So r
/. o X
/B /� � A�5
/rv- [,� L�2A/,J
rC/AS O•
(,/� �l(J � o�� `Q
J (f,
/r
, / -2- cFs =�> 74-7 �/, / "; � .
&Oit-L- o6-417— USE /Z/, /N GaSc
T/
c�J,on1 GE / nl Q�6 LOT lwE % a CDu6r� .FIVE Wl�/AJC-
I
i
I
I
y0 X :/ICJ - I -j�OU=
r�,v
i
�/ o o �/�� �/�2,-. � G�Jo��� o✓syc l=/�cr�rnJ �
L) 1R�-c�-� To Co c�J �o�tTl one cF c-Aniocr)
%I
BLACKFOX
COALVERCLI L REAL EST. I TF GROUR LLC
To:
From:
Date:
Subject:
Dear Mike:
Mike Hera <Clof Fort Collins
Tom Peterson, AICP - Blackfox Commercial Real Estate Group, LLC
May 25, 1995
I st Choice Bank - Development Agreement Revisions
As discussed, we have some suggested language for the Development Agreement based
on our review of your draft of 5/23/95.
1. 1st line delete, "building permit" and substitute "certificate of occupancy".
he utility lines are for the most part already constructed. A fire hydrant had
G�a^ already been installed adjacent to the temporary bank facility. ; � r, (
/ _
CI% �� C L Y ✓Y�
4th line delete. "base course" and substitute' weaving course", We want
to be able to occupy the building if we ge caught by w' weather.
E. You may wish to add language covering electrical and traffic control
IVO vaults as well as light standards which we assume the city will need to install.
�JT. C. 1. 4th line delete, "any" and substitute "final".
1 Oth line delete, "any" and substitute "the final".
I CI 1st line after "shall" add concurrently with the footage and founciation
permit".
Alp _-;�, 4th line delete, "building permit" and substitute 'certificate of occupancy".
11. D1 5th line, a sentence should be added to read "city will reimburse the
ryp developer for all street oversizing improvementslas se f_,Qrth_in the traffic stua}I
for the project (pg. H2)".
s
D2 13th line, after "security" add "letter of credit satisfactory to developer.V
D3 5th line delete, "first" and substitute "final". Add sentence "Developer
may past a letter of credit to ensure completion of said improvements.
D4 Add the following section: The developer agrees to act as
general contractor in contracting for the construction of (a) the north bound
right turn lane on South College Avenue, including off -site portions of such
turn lane, and related improvements tot he south of this development, and (b)