HomeMy WebLinkAboutBURGER KING AT RAINTREE PUD - Filed GC-GENERAL CORRESPONDENCE - 2003-07-31Dever nent Services
Planning Department
December 22, 1989
Robert Huffsrnith
Lobar, Inc.
P. O. Box 1987
Fort Collins, CO. 80522
Dear Robert,
City staff has reviewed the Burger King at Raintree PUD Administrative
Change request. The following items requested in the administrative change
application have been approved:
- change in building elevations;
- relocation of handicapped parking stalls;
- modification to the outdoor dining area; and
- building lighting.
The request to delete the drain from the trash receptacle area and the deletion
of the walk have been denied by the Engineering Department. Engineering
staff has indicated that a change in the location of this sidewalk may be
considered, as an alternative.
The Planning Department has denied the request to change the mansard roof
materials to asphalt/fiberglass shingles and suggests that in lieu of the
originally proposed "metal shingles", a standing seam metal roof be utilized.
If relocation of the sidewalk, or a change from the roofing material of metal
shingles is proposed, a new administrative change request addressing these
and/or other items must be submitted. If you have any questions regarding
this matter, please do not hesitate to contact me.
Sincerely,
Sherry Albertson -Clark, AICP
Senior City Planner
xc: Mick Richter, Engineering
Dan Coldiron, Building Permits and Inspections
File
)00 1-Worte Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (30,) 221-hi�0