HomeMy WebLinkAboutMemo - Mail Packet - 6/20/2017 - Information From Darin Atteberry Re: Memorandum From Mike Calhoon Re: Spring Storm UpdateParks Department
413 South Bryan Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6660
970.221.6849 - fax
fcgov.com/parks
Date: June 9, 2017
To: Darin Atteberry, City Manager
Thru: Jeff Mihelich, Deputy City Manager
Wendy Williams, Assistant City Manager
From: Mike Calhoon, Director of Parks
Re: Spring Storm Update
Introduction
On May 18
th
and 19
th
Fort Collins experienced one of the five worst storm events involving tree
damage to the community. This memo provides an update on response efforts and estimated
costs. An appropriation ordinance is being prepared for the July 5
th
Council meeting.
Background
It appears that Fort Collins received more tree damage than most cities along the Front Range.
The variety of temperatures seems to be the difference in snow fall totals producing branch
breaking weights. This is the fifth major storm in the last 22 years. This storm had the potential
to be much worse if the temperatures had dropped a few more degrees between Thursday
night and Friday morning. The worst area of town appears to be on the Colorado State
University campus.
Response Update
The storm response has involved several divisions throughout the organization.
-Streets-equipment, operators and limb drop off sites.
-Forestry-corrective pruning and chipping.
-Parks-equipment and operators.
-Storm Water-equipment and operators.
-Traffic-traffic control and signage.
In addition there are three private tree companies under contract. An additional 60’ bucket
truck was rented pre-storm in anticipation of the event.
Priorities were established based on health and property threats. A running list is being
maintained in the Tree Keeper software. Currently all of the highest hazardous trees have been
pruned with many hanging limbs remaining in the canopy which are the next priority.
June 15, 2017
TO: Mayor & City Councilmembers
FROM: Darin Atteberry
FYI
/sek
Most of the areas around Old Town are now complete. Several
recreation areas including Warren, Blevins, Rolland Moore, Library and Landings Parks have
been completed. The team will be moving through Collindale Golf Course while still working on
main arterials in the next week. As we are moving through the City we are revising our
estimates for recovery down to two months.
Estimated Direct Costs (blue indicates updated estimates)
Monthly Costs
-Three Tree Companies $119,616 X 2 = $239,232
-60’ Bucket Truck Rental 3,200 X 1 = 3,200
-Traffic Control 8,000 X 2 = 16,000
Tub Grinding (Tub grinding bids are due Tuesday, June 13 at 3pm.)
-Private Trees $150,000
-Public Trees 60,000
Total Direct Costs for Three Months $468,432
Internal Costs
Parks
Redirected Costs $ 6500
Incremental Costs 147
Parks Subtotal $ 4,584
Streets
Redirected Costs $23,866
Incremental Costs 7,866
Equipment/Fuel Costs 13,336
Streets Subtotal $ 45,068
Utilities
Redirected Costs $ 1,243
Incremental Costs
Equipment/Fuel Costs 2,556
Utilities Subtotal $ 3,799
Forestry
Redirected Costs $52,000
Incremental Costs 10,500
Equipment/Fuel Costs 2,900
Forestry Subtotal $ 65,400
Internal Costs Total $ 118,851
Total Storm Costs $ 587,283
We will be providing the next update in one month. In this report we have included the
Redeployed Costs (cost of staff being diverted from regular duties), Incremental Costs (cost of
overtime due to the storm response) and Equipment/Fuel costs related to the storm response.
The number of full tree removals is small enough that the regular Forestry budget can absorb
the stump grinding and re-planting costs.
Appropriation Ordinance
Preparation of an appropriation ordinance is under way and planned to go in front of Council at
the July 5
th
meeting. This ordinance will be modeled after the 2011 appropriation request.