Loading...
HomeMy WebLinkAboutReport - Mail Packet - 12/13/2016 - City Manager Monthly Update - December 8, 2016December 8, 2016 TABLE OF CONTENTS ISSUES BEFORE COUNCIL ................................................................................................................. 3 DECEMBER 13 WORK SESSION ...............................................................................................................................3 DECEMBER 20 COUNCIL MEETING .........................................................................................................................3 DECEMBER 20 WORK SESSION ...............................................................................................................................3 DECEMBER 27 WORK SESSION ...............................................................................................................................3 JANUARY 3, 2017 COUNCIL MEETING ....................................................................................................................3 JANUARY 3 URA MEETING ......................................................................................................................................4 JANUARY 10 WORK SESSION ..................................................................................................................................4 SALES AND USE TAX COLLECTION .................................................................................................. 4 MONTHLY & YEAR TO DATE ...................................................................................................................................4 CAPITAL PROJECTS ........................................................................................................................... 4 CITYWIDE PEDESTRIAN ACCESS PROJECT ...............................................................................................................4 TIMBERLINE IMPROVEMENTS – PROSPECT TO BLACKBIRD ...................................................................................5 DOWNTOWN RIVER DISTRICT IMPROVEMENTS ....................................................................................................6 NORTH COLLEGE PEDESTRIAN GAP ........................................................................................................................6 LINCOLN CORRIDOR PROJECT – 1ST STREET TO LEMAY AVENUE ...........................................................................7 LINCOLN CORRIDOR PROJECT – POUDRE RIVER BRIDGE TO 1ST STREET ................................................................7 COLLEGE AND PROSPECT INTERSECTION IMPROVEMENTS ...................................................................................8 VINE AND LEMAY BNSF IMPROVEMENTS ..............................................................................................................8 SHARP POINT/NANCY GRAY CONNECTION ............................................................................................................9 COLORADO STATE PROJECT COORDINATION.........................................................................................................9 ELIZABETH AND SHIELDS UNDERPASS ................................................................................................................. 10 MULBERRY BRIDGE URBAN DESIGN AND LANDSCAPING ................................................................................... 11 CAPITAL PROJECTS – UTILITIES .................................................................................................... 12 SPRING CREEK SEWER IMPROVEMENTS AT TIMBERLINE ROAD ......................................................................... 12 WATER TREATMENT FACILITY CHLORINE CONTACT BASIN ................................................................................ 12 DWRF UV DISINFECTION...................................................................................................................................... 13 EAST HARMONY DUCT BANK – TIMBERLINE TO ZIEGLER – PHASE 1 .................................................................. 13 COLORADO STATE UNIVERSITY CIRCUITS AND DUCT BANK PROJECT ................................................................ 13 CARPENTER ROAD DUCT BANK PROJECT ............................................................................................................ 14 PUBLIC SAFETY UPDATE ................................................................................................................. 14 POLICE SERVICES .................................................................................................................................................. 14 POUDRE FIRE AUTHORITY ................................................................................................................................... 15 BUILDING AND PLANNING ACTIVITY .............................................................................................. 16 YEAR TO DATE COMPARISONS ............................................................................................................................ 16 PROJECTS OF NOTE-STATUS AND UPDATES ........................................................................................................ 16 PROJECTS UNDER APPEAL ................................................................................................................................... 19 PROJECTS OF NOTE-STATUS AND UPDATES ........................................................................................................ 19 SUSTAINABILITY SERVICES ............................................................................................................ 20 ENVIRONMENTAL SERVICES ................................................................................................................................ 20 SOCIAL SUSTAINABILITY ...................................................................................................................................... 20 ECONOMIC HEALTH ............................................................................................................................................. 21 PUBLIC ENGAGEMENT UPDATE ..................................................................................................... 21 CITY MANAGER’S UPDATE 3 ISSUES BEFORE COUNCIL DECEMBER 13 WORK SESSION  Occupancy Study o Review and consider project scope for jointly-funded study to review the impacts of the U+2 occupancy ordinance.  Possible Charter Amendments o Consider possible Charter amendments for inclusion on the April 2017 ballot. At its July 18 meeting, the Council Election Code Committee discussed the possibility of a Charter amendment that would amend the date for the certification of the election (from three days to ten days). The additional time to certify results would permit voters the opportunity to correct deficiencies with their ballots, such as unsigned return envelopes and ballots received without a return envelope.  Council Appeal Process Amendments o Review of the background and options for improving the Council appeal process DECEMBER 20 COUNCIL MEETING  Adoption of the Larimer County IGA o Amend the Growth Management Boundary to reflect the boundary adopted by the Council and the Town of Timnath  Rennat Annexation Initiation (resolution-consent) o Initiating enclave annexation proceedings for the Rennat Annexation, 6015 South Timberline. DECEMBER 20 WORK SESSION  Broadband Strategic Plan o Provide a review of community outreach and Broadband Strategic Plan recommendation to City Council. - Summary of broadband community outreach and results - Overview of the Request for Information (RFI) for potential public private partnerships such as the wholesale or franchise model - Recap of site visits of municipal retail - Overview of economic and social impact research - Bring forward a staff recommendation and next steps DECEMBER 27 WORK SESSION JANUARY 3, 2017 COUNCIL MEETING  Land Use Code Update o Bring forward an annual package of various code revisions to the Land Use Code in order to clarify, revise, add, or otherwise amend the Code as part of a continuous improvement effort.  Possible Charter Amendments o Consider Charter Amendments for placement on the April 4, 2017 ballot.  Land Use Code Changes Related to Prairie Dog Management o Consider potential changes to a number of Land Use Code requirements related to the protection, removal, and mitigation of impacts to prairie dog colonies on development sites.  Staff Report: Regional Wasteshed Coalition o Provide a summary of the Wasteshed Coalition’s Phase I accomplishments from 2016 and a Phase II timeline for 2017. Highlights from Phase I include the production of a detailed report on regional infrastructure options for handling waste and recycling as well as broad 4 CITY MANAGER’S UPDATE public engagement. Highlights from Phase II include a more detailed analysis of infrastructure options and continued engagement with the community and regional partners.  Short Term Rentals o Provide regulatory framework for short term rentals JANUARY 3 URA MEETING  Approval of a Redevelopment Agreement with the Lyric Cinema Café o Consideration of a redevelopment agreement between the Fort Collins Urban Renewal Authority and the Lyric Cinema pertaining to a planned development located in the North College Plan Area. JANUARY 10 WORK SESSION  Electric Capacity Fees o The purpose of this agenda item is to discuss the new capacity fee model and to get direction on when the new model and fees should be implemented. Electric Capacity Fees are required for any new development and are intended to recover the costs associated with providing the infrastructure required to serve the new development. The current model was developed when there was considerable green field development within the service area so a new model is being developed with the help of a consultant which is more consistent with the anticipated redevelopment that will continue to become more common within the electric service area. City Code requires the City Manager to review such charges annually and to present the fees to the City Council no less than biennially (Sec 26-473 (b)). This agenda item will provide an overview of the new model and how it would impact some typical development fees.  Sign Code Update o Review potential amendments to the sign regulations related to electronic signs in an effort to address aesthetic and safety impacts and anticipated change in the technology; address constitutional amendments regarding signage; and, sign coverage restrictions on fuel station canopies. SALES AND USE TAX COLLECTION MONTHLY & YEAR TO DATE OCTOBER SUMMARY OVER PRIOR YEAR Month Year to Date Sales Tax Collected: 4.6% 4.7% Use Tax Collected Excluding Rebates: 12.0% -1.6% Sales and Use Tax Collected Excluding Rebates: 6.6% 3.4% Year to date, sales and use tax collections excluding rebates are up 3.4% and total $114.2 million. CAPITAL PROJECTS CITYWIDE PEDESTRIAN ACCESS PROJECT Funding Source: KFCG/BOB Funds Estimated Project Budget: $450,000 Status: On Budget, On Schedule CITY MANAGER’S UPDATE 5 Project Details:  This project provides a complete City sidewalk inventory, identifies sidewalk inadequacies, and identifies inadequate handicap accessibilities according to Americans with Disabilities Act (ADA) requirements.  37,741 accessible ramps have been identified as acceptable, substandard, or missing in accordance with the ADA requirements. Project Updates: o Upcoming project locations: Staff has completed the Pedestrian Improvement Program for 2016. The program constructed 10,513’+ of new sidewalk and 96 accessible ramp improvements. Staff is finalizing the 2017 Pedestrian Improvement Program. Communication efforts are beginning with property owners regarding missing segments and PSD regarding access to schools. o Current projects: Staff is continuing to manage projects for FCMoves and the Downtown General Improvement District. Staff is continuing to collaborate with CSU staff regarding final layout for the NRRC connection between Centre Avenue and MAX Spring Creek Station. CSU is reviewing legal implications with the lease with the GSA regarding a pedestrian easement for NRRC. More information is available at http://www.fcgov.com/engineering/pedneeds.php TIMBERLINE IMPROVEMENTS – PROSPECT TO BLACKBIRD Funding Source: Building on Basics (BOB) Estimated Project Budget: $5.0m Status: On Budget, On Schedule Project Details:  The goals of this project are to improve air quality, reduce vehicle wait time and reduce the accident rate by constructing a free-right turn and acceleration lane from eastbound Prospect to southbound Timberline; as identified in our Arterial Intersection Prioritization Study.  The 2005 ballot language stated this project will expand Timberline Road to four (4) lane arterial standards including:  Travel lanes, sidewalks, bike lanes and landscaped medians.  Improvements to the Prospect and Timberline intersection and all its approaches to add additional turn lanes.  The project will add a sidewalk connection for southbound Timberline from Prospect to Blackbird.  The project is likely a Two Phase project (Phase One – Roadway work 2016, Phase Two – Great Western Maintenance and Signal Improvements).  Construction is expected to begin in the spring of 2016. Project Updates:  Mountain Constructors installed full depth toplift asphalt pavement south of the Railroad tracks on Timberline Road and continued working on medians, sidewalks and porkchop islands.  As December moves forward, traffic congestion will lighten as upcoming work can mostly be done outside of live lanes of traffic on southbound Timberline Road south of Prospect. 6 CITY MANAGER’S UPDATE  December work will include sanitary sewer upgrades for the CSU stadium on northbound Timberline Road, median installation south of the railroad tracks on Timberline Road and sidewalk installation along Timberline Road.  There will be a point where the project needs to be winterized and fully reopened for the winter. Spring 2017 work will focus on landscaping the Timberline center medians. More information is available at http://www.fcgov.com/engineering/prospect-timberline.php DOWNTOWN RIVER DISTRICT IMPROVEMENTS Funding Source: Federal Grants/Local Funds/DDA Funds Estimated Project Budget: $1.4M Status: On Budget, On Schedule Project Details:  The goals of this project are to provide various design and construction improvements within the Downtown River District.  The project has completed two design projects to date. The project is now focused on developing a preliminary engineering design for improvements along Jefferson Street between College Avenue and the Mountain/Lincoln Intersection. Project Updates:  Staff has initiated the preliminary engineering design phase. The design is based on improvements outlined in the Jefferson Street Intergovernmental Agreement (IGA) with the Colorado Department of Transportation (CDOT).  Improvements include converting a section of Jefferson Street from four lanes to three lanes, a raised, landscaped median, urban design elements, and drainage improvements. An on-street bike lane will not be included as part of the project.  Staff continues coordination with various stakeholders in an effort to better understand existing utilities, planned utility improvements, developments, and other services provided within the Jefferson Street Improvements project’s vicinity.  Upcoming months will see continued utility coordination, public engagement, environmental investigations, and refined plan development. NORTH COLLEGE PEDESTRIAN GAP Funding Source: CMAQ Grant/URA Contribution/Pedestrian Program Funds Estimated Project Budget: $900,000 Status: On Budget, On Schedule Project Details:  The primary goal of this project is to complete a gap in pedestrian infrastructure from Highway 1 to the south side of the Larimer & Weld Canal.  This project will construct a pedestrian connection crossing the Larimer & Weld Canal extending north to SH 1 (Terry Lake Rd). The project impacts a federal highway, CITY MANAGER’S UPDATE 7 and is located outside the City limits but within the Growth Management Area. Project Updates:  Larimer County and the City applied for, and were awarded, an additional $810,000 in federal grant funding for the project. The additional funding enables multimodal improvements on both sides of the road.  Staff is meeting regularly with Larimer County and the Colorado Department of Transportation in order to determine feasibility and potential funding for the construction of full roadway improvements within the project limits.  At this time, discussions do not include reconstruction of the existing roadway bridge. LINCOLN CORRIDOR PROJECT – 1ST STREET TO LEMAY AVENUE Funding Source: General Fund Reserves, Street Oversizing Fund, previously committed developer local street obligations, savings from Woodward interim improvements Estimated Project Budget: $6.5m Status: On Budget, On Schedule Project Details:  This phase of the overall Lincoln corridor plan includes improvements along Lincoln Avenue between 1st Street and Lemay Avenue.  Subsequent phases include improvements to the Poudre River Bridge and improvements along Lincoln Avenue to Jefferson Street.  Project intent is to create a multi-modal design along Lincoln Avenue that will include creating a street with a unique identity, improving the mobility, safety, and experience for bicyclists, pedestrians, transit users, and vehicles, and creating an environment where local businesses can thrive. Project Updates:  Placement of concrete curb and gutter, sidewalk, driveways, and pavement construction along south side of Lincoln ongoing, as well as electrical and irrigation lines.  South side of Lincoln construction is winding down, cleaning up to prepare for Winter.  North side of Lincoln construction is being planned – will start in Feb 2017. LINCOLN CORRIDOR PROJECT – POUDRE RIVER BRIDGE TO 1ST STREET Funding Source: BOB 2.0 Estimated Project Budget: $5.4m Status: On Budget, On Schedule Project Details:  This phase of the overall Lincoln corridor plan includes replacement of the Poudre River bridge and road between the bridge and 1st Street.  Project intent is to add to the ongoing Lincoln Corridor project creating a street with a unique identity, improving the mobility, safety, and experience for bicyclists, pedestrians, transit users, and vehicles, to include an enhanced bridge that will meet the intent of the overall project. Project Updates:  Bid packages have been received. Staff will negotiate the bridge award in December.  Staff will discuss bridge closure and ped/bike detour routes with local businesses and neighborhood residents in December.  Bridge closure and construction start projected for January 2017. 8 CITY MANAGER’S UPDATE COLLEGE AND PROSPECT INTERSECTION IMPROVEMENTS Funding Source: Mid-Budget Approval of 2016 Capital Projects Fund Estimated Project Budget: $2.7 M Status: On Budget, On Schedule Project Details:  The Colorado State University (CSU) Medical Center project at the northwest corner of this intersection, presented an opportunity for the City to address other existing deficiencies which were identified in the 2011 Arterial Intersection Prioritization Study.  The goals of the project are to address safety, operational, and congestion issues primarily focused on Prospect Road by: o Adding turn lane capacity to existing turn lanes o Constructing new turn lanes and medians on Prospect Road o Improving bicycle and pedestrian facilities  The City and Colorado State will work collaboratively on the intersection improvements, with each entity funding their own design and construction obligations. Project Updates:  Council approved design option 2 on Second Reading at the November 1 meeting. Staff is moving forward with ROW acquisition on the residential properties in accordance with Option 2. The majority of commercial property ROW has been acquired.  Project is moving towards 90% design in early December. Construction is planned to start mid-February 2017, and staff is working on communication and outreach plan. Will have detailed construction phasing and traffic control plan mid-December and will have open house in mid-January to message construction impacts.  Staff is coordinating design and construction with CSU Medical Center schedule. CSU will begin construction in February 2017 in coordination with the City in order to minimize disruption to the public. The construction is being closely coordinated to limit the impacts and shorten the overall duration of construction. More information available at: http://www.fcgov.com/engineering/college-prospect.php VINE AND LEMAY BNSF IMPROVEMENTS Funding Source: Keep Fort Collins Great (KFCG) Estimated Project Budget: $1.0 M Status: On Budget, On Schedule Project Details:  The existing Vine and Lemay intersection, which includes the Burlington Northern Santa Fe (BNSF) Railway crossing, is severely congested with limited options to expand through or turn lane capacity due to land use constraints. CITY MANAGER’S UPDATE 9  Lemay Avenue realignment and intersection improvements have been prioritized as the City’s #1 Transportation Capital Improvement Project  The realignment has been on the City’s Master Street Plan since the mid-1980’s  The project area is included within the City’s Mountain Vista Subarea Plan which was created as a long-term planning vision for the northeast section of Fort Collins  The improvements will construct a new roadway and intersection slightly northeast of the existing Vine and Lemay intersection. The new intersection will be realigned Lemay and Suniga Road.  The City is investigating a number of interim and ultimate solutions that include new at-grade intersections or overpass/underpass of the BNSF Railway and existing Vine Drive Project Updates:  Staff hosted a Neighborhood Meeting for Alta Vista residents on November 16, 2016 at the City Streets Facility. More information is available at http://www.fcgov.com/engineering/vine-lemay.php SHARP POINT/NANCY GRAY CONNECTION Funding Source: Street Oversizing Estimated Project Budget: $1 M Status: On Schedule Funding Source: Street Oversizing Estimated Project Budget: $1 M Status: On Schedule for Late 2017 Construction Project Details:  The City Master Street Plan identifies Sharp Point Drive and Nancy Gray Avenue connected across the Great Western Railroad tracks.  City Staff has identified the connection as a priority due to recent developments to the south.  City Staff is in the process of preparing an application for a new at-grade crossing of the Great Western tracks to the Public Utilities Commission (PUC). Once approved by the PUC, Staff will continue coordination with Great Western in order to facilitate design, crossing agreements and construction.  Construction dates are tentative as timeline depends on PUC approval and railroad coordination. Project Updates:  Staff is currently working with Great Western to finalize the PUC application.  Staff is working on the utility and roadway design to have it shovel ready, pending Great Western’s schedule. COLORADO STATE PROJECT COORDINATION Funding Source: Colorado State Estimated Project Budget: None 10 CITY MANAGER’S UPDATE Status: On Schedule Project Details:  Prospect and Center bicycle and pedestrian underpass, along with Center Avenue improvements between Bay Farm and Lake  Elizabeth and Shields bicycle and pedestrian underpass, and at-grade intersection improvements  Laurel / Washington and Laurel / Sherwood pedestrian enhancements  Whitcomb sidewalk improvements (east side) Prospect to Lake  Whitcomb sanitary sewer line (stadium flow)  College and Lake (northbound left turn lane improvements)  Lake and Center intersection improvements  Lake Street bicycle and pedestrian improvements  Game Day Operations Plan Project Updates:  Prospect and Center underpass – to be completed mid-November 2016  Elizabeth and Shields underpass o Right-of-way negotiations are complete o The voluntary SPAR process received a unanimous approval on November 10, 2016 at the Planning and Zoning Board hearing.  Laurel Street pedestrian improvements – Washington completed August 2016; Sherwood to be completed September 2016  Whitcomb sidewalk improvements – completed August 2016, landscaping installation this fall  Lake and Center intersection – requires further study of vehicle, bike, and pedestrian counts with the opening of Aggie Village North and the Center underpass o Intersection improvements to be completed in summer 2017  Lake Street bike and pedestrian improvements o Substantially complete – street overlay and restriping scheduled for summer 2017  Game Day Operations Plan – further refinement this fall More information available at http://source.colostate.edu/construction-and-parking/ ELIZABETH AND SHIELDS UNDERPASS Funding Source: Colorado State University Estimated Project Budget: $10.0 M Status: On Budget, On Schedule Project Details:  The City and Colorado State University (CSU) have been working in partnership for years to improve bicycle and pedestrian safety amid continued and projected population growth along the West Elizabeth corridor. CSU is making a series of improvements as a commitment by the University to improve safety and make the campus more accessible.  The project aligns with multiple CSU and City planning efforts, such as: West Central Area Plan (2015), CSU Parking and Transportation Master Plan (2014), City Bicycle Master Plan (2014), City Student Housing Action Plan (2013), City Arterial Intersection Prioritization Study (2012), and the City Transportation Master Plan (2011). All of these planning efforts identified the need for improvements at the Elizabeth and Shields intersection with recurring themes of: enhanced safety, separation of travel modes, and reducing the number of conflict points and crashes.  The Elizabeth and Shields intersection has 50,000 vehicles per day, an increase of 20% in traffic volumes since 2009. Peak hour volumes (morning, midday, and afternoon) generate 170 bicyclists and 140 pedestrians per hour. More than 2,000 bicyclists per day are crossing Shields at Elizabeth, an increase of 40% since 2009. This intersection has a “higher than CITY MANAGER’S UPDATE 11 expected” crash rate. The grade separated crossing for bicyclists and pedestrians will reduce the number of conflict points and intersection crash rating Project Updates:  Staff is working with the CSU Design/Build team on Utility Relocations and Structure selection for the underpass.  CSU has completed the right-of-way acquisition needed from the Campus West Shops o The voluntary SPAR process received a unanimous approval on November 10, 2016 at the Planning and Zoning Board hearing.  Construction is scheduled to begin in early December 2016. The project will be completed in August 2017. The project team is currently working on construction phasing, lane drop scenarios, and a 4 week closure of Shields Street expected to occur in the spring of 2017.  City and CSU staff will present a pre-construction open house event on December 7, 2016 from 6-8 pm at the Bob Davis Hall at Moby Arena More information is available at http://source.colostate.edu/construction-and-parking/shields- underpass-proposal/ MULBERRY BRIDGE URBAN DESIGN AND LANDSCAPING Funding Source: City of Fort Collins Estimated Project Budget: $750,000 Status: On Budget, On Schedule Project Details:  This project will complete the landscaping and urban design improvements along the section of Mulberry Street between Lemay Avenue and Riverside Avenue to a level consistent with City standards.  Planned improvements will coordinate and be consistent with recently constructed improvements on Lemay Avenue north of Mulberry Street, along the Poudre River Trail, and developments within the project’s general vicinity. Project Updates:  The project is substantially complete. Remaining work includes the placement of planter pots in the medians. This work is anticipated to occur in early December 2016 and is weather dependent.  The installation of the median planter pots will require daytime lane closures. More information available at: http://www.fcgov.com/engineering/mulberryenhancement.php 12 CITY MANAGER’S UPDATE CAPITAL PROJECTS – UTILITIES SPRING CREEK SEWER IMPROVEMENTS AT TIMBERLINE ROAD Funding Source: Wastewater, but will be refunded per CSU Stadium IGA Estimated Project Budget: $665,500 Status: On Schedule Project Details:  Access agreements in place  Shoring construction complete Upcoming Work:  Construction will begin in early December WATER TREATMENT FACILITY CHLORINE CONTACT BASIN Funding Source: Water Estimated Project Budget: $9,243,000 Status: On Schedule Project Details:  All concrete walls complete  Upper decking complete  Plant shutdown 11-2-16 to cut in 36” cap, went well Upcoming Work:  Install perimeter drain and begin rough grade drainage in December  Replace existing 36” into west reservoir February 2017 Construction shoring system Installed connection between 72” and 60” pipes CITY MANAGER’S UPDATE 13 DWRF UV DISINFECTION Funding Source: Wastewater Estimated Project Budget: $5,900,000 Status: On Budget, On Schedule Project Details:  Construction work order executed and PO issued  Construction kickoff meeting held  Initial UV submittal comments returned to the manufacturer Upcoming Work:  Site mobilization and clearing  Completion of temporary construction easement from PRPA  Continue review of submittals EAST HARMONY DUCT BANK – TIMBERLINE TO ZIEGLER – PHASE 1 Funding Source: Development Fees Estimated Project Budget: $4,000,000 Status: On Budget, On Schedule Project Details:  Three Phase Project  Phase One: Install new vaults adjacent to Harmony Substation  Phase Two: 1.1 miles of duct bank installation from Timberline Substation to Ziegler  Phase Three: 1.1 Miles of duct bank from Ziegler to Strauss  Cabin  Design, route identification, and project coordination permits.  Locates, pot holing, excavation and construction  Duct bank, vault, conduit, and cable installation Project Updates:  Design, route identification is 100% complete on Phases 1 and 2; 50% complete on Phase 3  Construction anticipated to resume March 2017  Due to utility conflicts, the Phase 3 section is being redesigned to go in the roadway COLORADO STATE UNIVERSITY CIRCUITS AND DUCT BANK PROJECT Funding Source: Development Fees Estimated Project Budget: $2,804,340 Status: On Budget, On Schedule Project Details: 3D view of Duron System Vault Installation 14 CITY MANAGER’S UPDATE  2.2 miles of duct bank and two new circuits  Design, easements, and project coordination  Locates and pot holing, excavation, and construction  Duct bank, vault and conduit installation, and cable pulling  Electric termination and energizing Project Updates:  Construction is 100% complete  The circuit in this duct bank is 90% complete  Boring is complete  All seven vaults are installed  Cherry Street duct bank from College to Howes is awaiting permits and access easements  Howes/Laurel duct bank is complete  The railroad permit for Vine Drive duct bank from Linden Substation has been submitted CARPENTER ROAD DUCT BANK PROJECT Funding Source: 2016 Duct Bank Budget Estimated Project Budget: 2,000,000 Status: Delayed until 2017 Project Details:  2.6 miles of duct bank  Boring  Complete Excavation  Potholing and locates Project Updates:  No change this month  Work continues around easements and/or temporary construction easements.  Completing due diligence in order to ask for an alignment from Natural Areas  This project will be delayed until 2017 pending the alignment PUBLIC SAFETY UPDATE POLICE SERVICES Police Investigate Two Homicides On November 19, Officers were dispatched to the location and found a deceased adult male in an abandoned building. Matthew Tatti and Anthony Horne were later arrested on charges of First Degree Murder for their involvement. Vault Installation Easement Required with Natural Areas CITY MANAGER’S UPDATE 15 On November 21, police responded to a reported stabbing on Parker Street. The victim was transported to the hospital and later died as a result of his injuries. David Matthew Strunk was arrested on charges of First Degree Murder for his involvement. Prostitution Sting Results in Multiple Arrests Ten men were arrested or cited on charges of patronizing a prostitute during an undercover operation conducted by the FCPS Neighborhood Enforcement Team. Prostitution is often connected with sex trafficking, illegal drug usage and sales, and violent crimes. FCPS hopes to reduce those issues by making Fort Collins a difficult market for soliciting or selling sexual services. Police plan to continue enforcement efforts at various locations around Fort Collins and will keep adapting their approach as this underground marketplace evolves. Police Investigate Several Crashes Resulting in Serious Bodily Injury On November 22, police were notified of a woman who was run over by a tractor trailer near the intersection of Harmony and Ziegler Roads. The 85-year-old pedestrian was waiting at a bus stop and appeared to have stepped into the road to look for the bus due to arrive. The driver of the tractor trailer was backing into the construction zone and was unable to see the woman. The pedestrian was transported to the hospital with serious injuries. On November 25, officers investigated a three-car collision at Willox Lane and College Avenue. Juan Lara-Medina was arrested on charges of Vehicular Assault, Failing to Remain at an Accident Scene, and Driving Under the Influence. Two victims sustained minor injuries and a third was transported to the hospital with serious injuries. Suspect Arrested for Sex Assault, Attempting to Hit Police Vehicles On November 23, police responded to a call regarding a sex assault with a weapon in the 4400 block of College Avenue. When officers arrived, they located a vehicle matching a description of the suspect’s truck. The suspect fled in his vehicle when officers tried to contact him. With the assistance of Larimer County Sheriff’s Office and Colorado State Patrol, Fort Collins officers followed the vehicle. The suspect attempted to hit several patrol vehicles during the incident, then crashed his truck at the intersection of Harmony Rd and Snow Mesa Rd and fled on foot. Officers apprehended him several minutes later in the nearby area of 2500 East Harmony Rd. The suspect was not injured, nor were officers. Jessie Frias was arrested on charges of 2nd Degree Kidnapping, Sexual Assault with a Deadly Weapon, 2nd Degree Assault with a Deadly Weapon and Vehicular Eluding. POUDRE FIRE AUTHORITY Nov. 9 - Investigators determined the cause of the fire at Old Town Fort Collins’ Ranch-Way Feeds to be accidental. Embers were generated during the pellet-making process and started the fire in a cooler in what's called the hopper assembly. There were no reported injuries, and everyone in the building evacuated. Nov. 14 – The Poudre Valley Fire Protection District Board of Directors and Poudre Fire Authority said thank you to Earlie Thomas for his years of service, as a director and board chair, from Jan. 1, 2011, to Sept. 26, 2016. The board was also excited to welcome its newest Director James Gentry, who took his oath of office. The organizations look forward to Director Gentry's insights and work in years to come. 16 CITY MANAGER’S UPDATE Nov. 26 - Four young adults were displaced from their Fort Collins house following an early-morning fire. One resident was transported to Poudre Valley Hospital for treatment of smoke inhalation. PFA investigators determined the fire was accidental, due to an overloaded circuit and improper wiring. A member of Poudre Fire Authority’s Customer Assistance Response Team (CART), responded to the fire to connect the displaced residents with resources, including the Red Cross, a restoration company and Larimer Humane Society. The team member also found them a place to stay for the night at Homewood Suites. FUTURE EVENT – Members of the City Council and public are invited to a grand-opening event for PFA’s new Station 8, at 4800 Signal Tree Drive in Timnath. The event is on January 28, 2017, from 9 a.m. to 1 p.m., with opening remarks at 10 a.m. There will be station tours, a history display, children’s activities and lunch, for which cash donations will be accepted. PFA will widely advertise the event in coming weeks. BUILDING AND PLANNING ACTIVITY YEAR TO DATE COMPARISONS 2015 YTD 2016 YTD % Change Development Project Submittals Rec’d 311 342 271 326 -2.25% -4.68% Conceptual/Preliminary Design Reviews/Staff Reviews Performed 168 208 234 284 +39.29% +36.54% Building Permits Issued 7,026 8,195 5,478 6,768 -22.03% -17.41% Building Permit Valuations ($M) $411.74 $516.78 $375.52 $500.99 -8.80% -3.06% Building Inspections Performed 25,239 30,769 23,613 29,123 -6.44% -5.35% Plan Reviews Performed 1,810 2,107 1,991 2,432 +10% +15.42% Overall development review revenues are $1,206,495 $1,326,871 over projection for 2016 as of October November 30th with Development Review over by $914,882 $1,063,778 and Engineering Development Review over by $291,612 $263,094. PROJECTS OF NOTE-STATUS AND UPDATES Development/Planning Projects of Note Status/Updates CITY MANAGER’S UPDATE 17 Stanford and Lot 4 (five multi-family buildings and the swimming pool) located midway along Stanford. No violations reported recently. I-25/392 Interchange Corridor Activity Center (CAC) design standards Revisions to the I25/SH 392 Interchange Corridor Activity Center design standards were adopted by City Council on September 6, and the Windsor Town Board on October 24. Amendments to the IGA will be finalized with additional review by staff, to be considered for adoption by both jurisdictions in early 2017. Lincoln Corridor Plan – Neighborhood Project Implementation Of the ten funded neighborhood projects, seven are complete and three are ongoing (neighborhood artwork, Streets Facility park enhancements, and brewery wayfinding). The final committee meeting was November 2, with additional community events planned for 2017 with the full implementation of the neighborhood artwork and park improvements. Proposed Outdoor Vendor Requirements On November 15 Council adopted on Second Reading of the Ordinances for new outdoor vendor requirements. The new changes will go into effect on January 15, 2017. Neighborhood Connections  Second pilot program meeting November 14. o Meeting included program expectations from Josh Weinberg and Clay Frickey o Introduction to working with groups by Patsi Maroney o Dr. Martin Carcasson discussed facilitative leadership techniques  23 residents from 20 neighborhoods throughout the community applied to serve as representatives for their neighborhood. o Since the first meeting of neighborhood representatives, staff has met with or helped facilitate initial neighborhood meetings in five of the 20 pilot neighborhoods. o Current level of neighborhood engagement and interest in the pilot program varies widely. Examples include:  Residents of the Old Town West neighborhood looking to move beyond occasional block parties and exchanges on Nextdoor to establishing regularly scheduled neighborhood meetings.  Neighbors in “North Fort”/North College corridor getting a head start on collaborating with the City on a sub-area plan update for the area through targeted engagement with the diverse populations currently residing in the area.  Buckingham neighborhood residents looking to open new lines of communication in the neighborhood regarding safety, changing demographics, traffic, and the built environment.  Representatives of Miramont Village HOA wanting to create a link between Climate Action 18 CITY MANAGER’S UPDATE Plan implementation strategies at a neighborhood scale.  Working with Martin Carcasson/CSU Center for Public Deliberation to develop leadership/participatory democracy curriculum – bought him out of one of his classes so he can give us focused time and effort o Exploring opportunities with the Kettering Foundation will be part of this o Researching best practices and most current ideas around neighborhood democracy o Exploring programs available through existing organizations and partnering o Will result in actual curriculum and plan Oakridge Crossing Oakridge Crossing is a proposed mixed-use project located in the Oakridge Business Park containing 110 affordable senior multifamily units and approximately 5,100 square feet of office space. The project was approved by the Planning and Zoning board at their July hearing and final plans are currently under review by City staff. Old Town Neighborhood Plan and Design Guidelines Staff will be presenting a draft plan to the public and boards and commissions beginning in November. The plan will come before City Council for adoption on February 21, 2017. Additional outreach opportunities will be available this Fall. For more information on the project please visit the project webpage at http://fcgov.com/otnp. Smoking Ordinance Expansion Options Signage: o Approximately 147 signs have been installed around the Downtown area; additional 25 on various outdoor patios. There are an additional 24 signs installed outside of the Downtown in areas such as Library Park or blocks what contain City buildings. o Considering removal of blue Smoke Free in FC signs and moving towards the more regulatory ones. Education: o Code Compliance is now doing regular patrols throughout the Downtown during the week. Enforcement: o Focus for the first year (through December, 2016) is on education and outreach with little emphasis on writing tickets; however, some (23) have been written. Next Steps: o Update memo given to Council on December 1. o Plan to continue education/outreach efforts. o Plant to continue partnering with Larimer County Health Department to find additional ways to get cessation information to people. o Would like to re-evaluate o Lifting no-smoking restrictions in the Downtown area in late evening. o Providing designated smoking areas throughout CITY MANAGER’S UPDATE 19 the Downtown area. Electronic Plan Review First Reading of the Electronic Plan Review Appropriation Ordinance was passed on July 5, 2016. It was approved at the Second Reading on July 19, 2016. Staff is working towards implementation, with an emphasis on completing the electronic building permit review process first. Historic Preservation Code Review o Request for Proposal for consultant to carry out comprehensive review of historic preservation codes to be issued early December 2016 o Community stakeholders have been identified and are in process of being confirmed; stakeholders will meet 1-2 times each month for curation of project o To jump-start the project, Clarion Associates was hired to research two key issues, Area of Adjacency and Demolition by Neglect; final report and recommendations will be submitted December 2016. PROJECTS UNDER APPEAL The appeal for the Brick Stone Apartments on Harmony was heard by City Council on December 6. Two notices of appeal were received on November 10, 2016, for the Landmark Apartments Expansion. A City Council hearing is tentatively scheduled for January 31, 2017. PROJECTS OF NOTE-STATUS AND UPDATES I-25 Improvements: Numerous local and regional efforts are underway to accelerate planned improvements to the I-25 corridor between SH-14 (Mulberry) and SH-402 (south end of Loveland): o The City of Fort Collins included in the recommended 2017-2018 budget a commitment of $2.25 million in local funds to be used as local match for I-25 improvements. o City Council authorized the Mayor to enter into an Intergovernmental Agreement (IGA) with Larimer County on October 4 to appropriate additional local funds (estimated Fort Collins share of $2.25 million) for I-25 improvements for the next five years, equal to the amount of increase in local share of County mill levy funds (Road and Bridge) received by the City of Fort Collins each year. o Colorado Department of Transportation (CDOT) received an award of $15 million in federal grant funds (Transportation Investments Generating Economic Recovery – TIGER) to be used for I-25 improvements in Northern Colorado. This award, plus prior funding commitments and local match of $25 million, have accelerated I-25 improvements in Northern Colorado by fifteen years. o CDOT is currently building a southbound climbing lane on I-25 at Berthoud Hill to help alleviate congestion caused by traffic volumes and heavy truck traffic. The project is substantially complete; final pavement overlay and landscaping to occur spring 2017. o CDOT began reconstruction of the Crossroads Boulevard/I-25 bridge to provide 20 CITY MANAGER’S UPDATE o Improvements Project. This $237 million project will construct a third managed lane in each direction from SH-7 (Mulberry) to SH-402 (Loveland), will replace the Poudre River and Kendall Parkway bridges, and make improvements to two other bridges. Construction is anticipated to begin in 2017 and be complete by end of 2020. o City of Fort Collins has launched an I-25 related webpage providing links to projects, plans and programs http://www.fcgov.com/transportation/i25.php o City Staff is exploring funding partnership opportunities with CDOT, other local agencies and private interests to include the Prospect/I-25 interchange in the overall North I-25 Improvements Project.  City Council passed Resolution 2016-087 affirming its intention to participate financially in the Prospect-I-25 interchange project as part of the North I-25 Improvements Project. SUSTAINABILITY SERVICES ENVIRONMENTAL SERVICES The sun is shining a bit more brightly on the roof of Trinity Lutheran Church just in time for the holiday season. While that glare could be divine intervention, it’s more likely the 198-panel, 53.5 kW roof- mounted photovoltaic system installed this fall as part of a longstanding commitment to energy efficiency and sustainability. The project will supply about 70 percent of the church’s power and help the community achieve its goals to reduce emissions 20 percent by 2020. Watch a brief video about the project. The City of Fort Collins has been named one of 10 participating cities in the City Energy Project, a national network of communities that are sharing best practices and providing concrete tools to help commercial buildings cut their energy use. The project is expected to save Fort Collins residents and businesses as much as $11 million annually on their energy bills by 2030. More information on the City Energy Project. New Belgium Brewing and Odell Brewing Co. – two companies that are committed to creating low- carbon business operations - are collaborating with the City to help connect their employees to City sustainability programs that can improve their health, comfort and efficiency at home. o The program, called HomeWise, is designed to make it easy for people employed in Fort Collins to learn about and participate in Utilities efficiency programs, water-saving measures and other conservation programs offered through the City. o The City is working with the Vermont Energy Investment Corp. to pilot the project, which will also help employees understand how their energy use, water consumption, and transportation choices compare against others, identify their interests and encourage engagement in City programs . SOCIAL SUSTAINABILITY The City of Fort Collins, the faith community and other non-profit organizations are recruiting volunteers for a new pilot program called "A Safe Place to Rest" that will provide additional and flexible shelter this winter. The program is based on a Nashville, Tenn., program called "Room In the Inn" that brings the entire community together on a nightly basis to donate shelter space. For more information about A Safe Place to Rest contact Holly LeMasurier: hlemasurier@fcgov.com or volunteer for the program. CITY MANAGER’S UPDATE 21 The City of Fort Collins Human Relations Commission has announced the recipients of the 2016 Human Relations Award who were honored at a ceremony on Tuesday, December 6. The recipients are:  Youth – Julio Flores  Adult – Janet Freeman  Senior – Kitty Kent  Organization – FoCo Café  Police and Emergency Services – Mike Chavez ECONOMIC HEALTH Mayor Wade Troxell and Small Business Administration Region VIII Administrator Betsy Markey visited small businesses in Downtown Fort Collins on Saturday after Thanksgiving to highlight the importance of shopping at locally owned businesses during Small Business Saturday. The Mayor also presented a proclamation about Small Business Saturday at the November 15 regular City Council meeting to community business leaders representing the North and South Fort Collins Business Associations, the Downtown Business Association and the Larimer Small Business Development Center. Read the proclamation at http://www.fcgov.com/business/ PUBLIC ENGAGEMENT UPDATE December Highlight: Community Issues Forum Topics:  Revenue Diversification  Broadband Strategic Plan  Road to 2020 November 17th at Lincoln Center Attendance: 60+ Materials included: redesigned Energy-saving Checklist; Personal Assessment Worksheet to help set goals; interactive myth buster exercise for energy savings and efficiency; presentations and small group discussions on all topics; review of broadband options; and more. 22 CITY MANAGER’S UPDATE Project & Engagement Recap: Broadband Telephone Town Hall: New outreach tool reaching over 1300 total attendees on Nov. 14th Super Issues Meeting: Topics were Revenue Diversification, Broadband and Entertainment Districts on Nov. 30th. Short Term Rentals: Over 30 attendees on Dec. 1st, staff planning small stakeholder groups Transfort Strategic Planning (questionnaire and focus groups): Additional targeted outreach to youth ages 12 to 18 Good News Item! The City has purchased an Interpretation Equipment System including two interpreter headsets and 20 receiver ear pieces. The equipment is available for any City employees to check out through CPIO and allows two additional languages to be simultaneously presented at any event. Upcoming Outreach* - December  Elizabeth/Shields Public Meeting – December 7 at Moby Arena  CityWorks Alumni Forum: Dark Sky Initiative walking tour and lighting scenario - December 8, Colorado River Community Room, 222 Laporte  Downtown/Old Town Neighborhoods Plans  Draft Plan Coffee Chats (all dates 9am-11am). Dates and times could change, please check http://www.fcgov.com/planning/downtown/ for the most up-to-date information.  Thursday, December 8 | The Crooked Cup, 147 W. Oak Street #101  Friday, December 9 | Harbinger Coffee, 505 S. Mason Street  Saturday, December 10 | Dazbog Coffee, 401 Mason Court #105 *Please note this is just a sampling of upcoming Public Engagement opportunities, for a full list of events, please visit: http://www.fcgov.com/events/ Downtown Plan The public comment deadline for the draft Plan is December 11. Staff has presented the draft plan to public and boards and commissions this fall and will bring the final document to City Council on February 21, 2017 for adoption. Foothills Mall Redevelopment Residential construction is fully underway. The first phase includes Lot 6 (Community Building and one multi-family building) on the southernmost edge of the site along