Loading...
HomeMy WebLinkAboutMemo - Mail Packet - 11/8/2016 - Memorandum From Adam Jokerst Re: Halligan Water Supply Project Status Update, Third Quarter 2016Utilities electric · stormwater · wastewater · water 700 Wood Street PO Box 580 Fort Collins, CO 80522 970.221.6700 970.221.6619 – fax 970.224.6003 – TDD utilities@fcgov.com fcgov.com/utilities M E M O R A N D U M DATE: November 1, 2016 TO: Mayor Troxell and Councilmembers FROM: Adam Jokerst, Water Resources Engineer THRU: Darin Atteberry, City Manager Kevin R. Gertig, Utilities Executive Director RE: Halligan Water Supply Project Status Update, Third Quarter 2016 Bottom Line The purpose of this Third Quarter 2016 Status Update is to inform City Council on progress related to the Halligan Water Supply Project (“Halligan Project”) and to provide an update on project schedule and costs. Adjustments to the Halligan Project’s timeline and budget have occurred in the third quarter 2016, and are summarized below:  As a result of additional work required on water quality studies, the date of release for the Halligan Project’s draft Environmental Impact Statement (“EIS”) has been delayed, extending the overall schedule by approximately 5 months; the draft EIS is now scheduled to be released in late-2017. Approximately $1.1 million in additional funding is required to finalize the draft EIS. Additional funds are needed primarily to address various issues raised in comments on the Northern Integrated Supply Project (“NISP), to complete the water quality studies referenced above, and to address numerous out-of- scope analyses and study revisions requested by the Corps and other permitting agencies. Additional details on schedule and budget are provided below.  Additional permitting costs and updates to construction costs have increased the overall project budget from $44.5 million1 to $46.2 million. Substantial progress continues towards development of a draft EIS despite recent delays and cost increases. The publication of the draft EIS will be a significant milestone in the completion of the Halligan Project. Public comment on the draft EIS will give the City clarity as to which water supply alternative will be permitted, the degree of future permitting needs, and what public opposition the project may face. Furthermore, current efforts on water quality studies are likely to reduce the future costs and timeline to receive water quality permits needed for the project. 1 Staff last reported the projected budget of $44.5 million to City Council via a July 27, 2016 memorandum. City Council was provided an update of project costs during a May 12, 2015 Work Session indicating the total cost of the Halligan Project would be $46 million. The project’s budget was revised to $44.5 million in early 2016 and reported via a February 23, 2016 memorandum to City Council. DocuSign Envelope ID: F9CDF81E-660F-4523-8057-21AC05D8D511 2 Background The Halligan Project proposes to enlarge Halligan Reservoir from its existing capacity of 6,400 acre- feet to an enlarged capacity of 14,525 acre-feet, providing Utilities with 8,125 acre-feet of additional storage capacity. The purposes of the Halligan Projects are to:  Meet future water demands of the Fort Collins Utilities service area;  Provide a storage reserve for emergency water supply disruptions;  Increase drought security; and  Improve water system reliability and flexibility. In order to enlarge Halligan Reservoir, the City requires permits from the U.S. Army Corps of Engineers (“Corps”) and other federal and state agencies. Before issuing permits, the Corps will produce an EIS, which will be published for public review and comment. The EIS will provide detailed analyses of the environmental impacts of the project, along with impacts of other alternatives to enlarging Halligan. Progress Update City Staff, the Corps and its third-party consultants continued to make progress during the third quarter of 2016. Key progress achieved during the period includes:  Continued analyses of the social, economic, and environmental impacts of the Halligan enlargement and alternatives, which will be evaluated and compared in the EIS.  Finalized two additional draft technical reports, for a total of 17 completed draft reports of the approximately 27 technical reports that form the basis of the draft EIS.  Continued writing the main body of the draft EIS, a major milestone in the permitting process.  Progressed development of water quality and water temperature models, and met with CDPHE and EPA staff to gather feedback.  Collected various water quality data and installed numerous water temperature probes in Halligan Reservoir and the North Fork.  Finalized an agreement between the City and Northern Water to allow sharing of water quality models used for both the Halligan Project and the Northern Integrated Supply Project. Halligan Reservoir DocuSign Envelope ID: F9CDF81E-660F-4523-8057-21AC05D8D511 3  Prepared a quitclaim deed to the City from mining claimants on an 80-acre tract of federally owned land lying under and adjacent to the existing Halligan Reservoir.  Negotiated an interim recreational lease to the Landowners Association for Phantom Canyon Ranches, as discussed in an August 30, 2016 memorandum to City Council.  Provided outreach to senior EPA staff on the Halligan Project, particularly related to the evaluation of greenhouse gas emissions and climate change in the federal permitting process. Staff also recently provided a presentation of the project to the Colorado Water Conservation Board’s South Platte Basin Roundtable and Metro Roundtable. Permitting Schedule The date of release for the draft EIS has been delayed approximately five months; the draft EIS is now scheduled to be released in late 2017. This delay is the result of water quality studies requested by federal and state agencies requiring more time, more resources, and more coordination with other regional permitting projects than originally anticipated. In addition, the water quality studies require approval from multiple permitting agencies including the Corps, the Environmental Protection Agency (“EPA”), and the Colorado Department of Public Health and Environment (“CDPHE”). Some delays have been caused by a lack of coordination among the various agencies. Fort Collins will require permits from the CDPHE (with oversight from the EPA) specific to water quality in order to enlarge Halligan Reservoir. Staff intend to utilize the water quality studies being developed for the draft EIS for the CDPHE permits. Therefore, although the studies are presently delaying the draft EIS, it is likely that the timeframe and cost of CDPHE permitting will be reduced. Staff is taking steps to speed the water quality study process where achievable. This past August, City Council approved a plan to share water quality models developed for the NISP permitting process. Sharing of water quality models will speed the overall water quality study schedule, as well as reduce costs and improve study defensibility. In addition, Staff is proactively collecting additional water quality data in the Halligan Reservoir and the North Fork of the Poudre River. The additional data is being collected should the validity of the water quality models be questioned in the future. As a result of the delay to the draft EIS, the overall project schedule has been extended. In particular, issuance of the Record of Decision (i.e., final permit approval by the Corps) is now expected in 2019 and completion of the project is anticipated for 2021. Other project milestones are shown in the chart below. Federal and state agencies ultimately set the permitting schedule, and thus, other delays beyond the City’s control could arise in the future. Staff will continue to DocuSign Envelope ID: F9CDF81E-660F-4523-8057-21AC05D8D511 4 monitor and encourage timely execution of the permitting process to the extent allowable, and will keep City Council apprised of any future shifts in timeline. The most recent Front Range Water Supply Report from the Corps (attached) indicates that the draft EIS will be delivered in September 2017. This report is based on outdated information; the Corps’ third-party contractors have recently released a schedule indicating the draft EIS will be released in late-2017. Schedule Delays The federal permitting timeline for the Halligan Project has been extended multiple times over the past decade. When the City first began the project, federal permitting was expected to take just two years. Ten years after the permitting process began, the City has yet to receive a draft EIS. Specific reasons for the delays are numerous, but can be condensed to just a couple broad causes:  Federal permitting has been a moving target. Permitting is not controlled by the City; rather it involves numerous federal and state agencies, whose permitting requirements have expanded over time. Revisions to permitting requirements have been caused by public scrutiny and legal challenges to other national and state water supply projects, expanded scientific understanding of various resources over the past decade, and turnover among agency staff. In some cases, the length of permitting has required that certain studies completed early in the process be redone with newer data. Furthermore, permitting studies are sequential, meaning that revising a study early in the sequence causes many other studies to require revisions as well.  There are three water supply projects in the Poudre River basin undergoing federal permitting (the Halligan Project, NISP, and Greeley’s Seaman Reservoir enlargement). Federal and state agencies desire that permitting requirements and methodology remain consistent between the projects, despite that the fact that scale of the projects are vastly different (by most measures, the Halligan Project is 1/20th the size of NISP). Maintaining consistent studies is difficult since each project is on its own timeline, which has led to study delays and revisions to studies already completed for the Halligan Project. Despite the past delays on the Halligan Project, Staff is strongly optimistic that a draft EIS will be produced in 2017. Well over half the studies and EIS text have been written, and the permitting agencies are in consensus on the methodology for the remaining studies that need to 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Federal Permitting ‐ Draft EIS Federal Permitting ‐ Final EIS Federal Permitting ‐ Permit Decision Preliminary and Final Design Construction Enlarged Halligan Operations DocuSign Envelope ID: F9CDF81E-660F-4523-8057-21AC05D8D511 5 be completed. Furthermore, there appears to be much more political pressure on the various permitting agencies, especially among state agencies, to speed and finalize the permitting process. Release of the draft EIS will be a major milestone for the project. It will give the City clarity as to which water supply alternative will be permitted, the degree of future permitting needs, and what public opposition the project may face. Project Budget Recently the Corps’ third-party contractors have requested an additional approximate $1.1 million to finalize the Halligan Project’s draft EIS. There are several reasons additional funds are needed. These include:  The third-party contractors’ current budget was developed in February 2015, prior to the NISP supplemental draft EIS being released. Comments on the NISP supplemental draft EIS required that several out-of-scope studies and revisions to completed studies be performed for the Halligan Project. Some examples include preparation of a flushing flows analysis for the North Fork of the Poudre River, and revisions to a previously completed aquatic resources technical report. Staff previously acknowledged the potential for delays to the Halligan Project as a result of comments on NISP2.  Since February 2015, the Corps and other cooperating agencies have requested numerous out-of-scope analyses, EIS format changes, and large-scale revisions to past studies. For example, the EPA and CDPHE have requested substantial revisions to water quality mass-balance modeling, and the Corps has mandated revisions and reformatting of EIS materials for compliance with Section 508 of the Rehabilitation Act.  When written, the third-party contractors’ current budget anticipated completing the draft EIS in mid-2016. Given the new scheduled release date of late-2017, extra funds are needed to cover an additional 15 months of administrative duties. This budget request results in an 8% increase to the projected final cost of permitting the Halligan Project. In addition to revising permitting costs, Staff has updated construction costs for enlarging Halligan Dam using standard dam construction cost indices; a full update to the dam’s opinion of probable cost was not performed. Rising construction costs have driven up the estimated construction cost by nearly $500,000. As a result of the additional budget required to complete the draft EIS as well as the update to construction costs, the overall project budget has been increased from $44.5 million to $46.2 million. The table below provides an accounting of past, future, and total project costs. Uncertainty exists for several line items. For example:  Construction costs are based on preliminary designs. Detailed site investigations and final design may require additional contingency, and material and labor prices could rise.  Mitigation costs are assumed to be 10% of construction costs; mitigation efforts will not be finalized until permitting is complete. 2 As stated in the Agenda Item Summary for Resolution 2015-082 (September 1, 2015) regarding City comments on the NISP supplemental draft EIS, “Please note that the comments provided on NISP to the Corps could lead to potentially significant delays and increased costs to the City’s Halligan Water Supply Project, since changes to the analysis of NISP as a result of these and other comments will likely be required for both projects.” DocuSign Envelope ID: F9CDF81E-660F-4523-8057-21AC05D8D511 6  Permitting costs assume that a permitting decision will be made in 2019, that the EIS will require minor to moderate revisions between the draft and final versions, and that EIS will generate all information needed for other federal and state permitting requirements. Expenses ($M) To Date1 Future Total Acquisition $3.3 $0.5 $3.8 Permitting & Mitigation $10.5 $6.7 $17.2 Construction - $23.3 $23.3 Debt Service2 $1.9 - $1.9 Total $15.7 $30.5 $46.2 Estimated Final Ratepayers Cost ($M) To Date Future Total Project Costs $15.7 $30.5 $46.2 Less Reimbursements3 ($4.5) ($0.1) ($4.6) Total4 $11.2 $30.4 $41.6 Appropriations ($M) To Date Future Total Past Appropriations $37.4 - $37.4 Required Future Appropriation - $8.8 $8.8 Total $37.4 $8.8 $46.2 1) Costs through September 2016. 2) Debt service payments from 2004 to 2014 were allocated as Halligan project expenses. All future debt service payments will not be accounted as a project cost. 3) Reimbursements were received from former project partners (NPIC and the Tri-Districts) between 2005 and 2014; miscellaneous reimbursements will be collected from the City of Greeley and from rents in the future. 4) Final ratepayer cost includes debt service and deducts reimbursements. The table above indicates the need for an additional $8.8 million in new appropriations for the Halligan Project. Future appropriations for the Halligan Project, if approved, will be sourced from Water Enterprise Fund reserves. Revenue for the Water Enterprise Fund is sourced from water rates and development fees. In particular, revenue collected from cash-in-lieu payments for raw water requirements and commercial water surcharges are accrued to the Water Rights Reserve Fund. The Water Rights Reserve Fund is a component of the Water Enterprise Fund, and funds water supply development projects such as the Halligan Project. Staff does not anticipate increasing rates or fees specifically for the Halligan Project. However, as presented in the Utilities’ Strategic Financial Plan to the Council Finance Committee in April DocuSign Envelope ID: F9CDF81E-660F-4523-8057-21AC05D8D511 7 and June, rate increases and debt issuances will be necessary to fund future capital improvements. The $8.8 million of additional appropriation for the Halligan Project will be included among the future capital improvements identified in the Utilities’ Strategic Financial Plan. In addition, Staff is presently investigating updates to raw water requirements, and intends to present proposed changes to City Council in 2017. CC: Water Board DocuSign Envelope ID: F9CDF81E-660F-4523-8057-21AC05D8D511