Loading...
HomeMy WebLinkAboutMemo - Mail Packet - 7/26/2016 - Memorandum From Adam Jokerst Re: Halligan Water Supply Project Update, Second Quarter 2016Utilities electric · stormwater · wastewater · water 700 Wood Street PO Box 580 Fort Collins, CO 80522 970.221.6700 970.221.6619 – fax 970.224.6003 – TDD utilities@fcgov.com fcgov.com/utilities M E M O R A N D U M DATE: July 15, 2016 TO: Mayor Troxell and Councilmembers FROM: Adam Jokerst, P.E., Water Resources Engineer THROUGH: Darin Atteberry, City Manager Kevin R. Gertig, Utilities Executive Director RE: Halligan Water Supply Project Status Update, Second Quarter 2016 Bottom Line The purpose of this Second Quarter 2016 Status Update is to inform City Council on progress related to the Halligan Water Supply Project (HWSP) and to provide an update on project schedule and costs. Substantial progress is being made towards publication of a draft Environmental Impact Statement for the project in 2017. Background The HWSP proposes to enlarge Halligan Reservoir from its existing capacity of 6,400 acre-feet to an enlarged capacity of 14,525 acre-feet, providing Utilities with 8,125 acre-feet of additional storage capacity. The purpose of the HWSP is to:  Meet future water demands of the Fort Collin Utilities service area;  Provide a storage reserve for emergency water supply disruptions;  Increase drought security; and  Improve water system reliability and flexibility. In order to enlarge Halligan Reservoir, the City requires permits Halligan Dam from Downstream DocuSign Envelope ID: BAC4E11A-8262-4561-B647-88F4A82F40A0 2 from the U.S. Army Corps of Engineers (Corps) and other federal and state agencies. Before issuing permits, the Corps will produce an EIS, which will be published for public review and comment. The EIS will provide detailed analyses of the environmental impacts of the project, along with impacts of other alternatives to enlarging Halligan. Progress Update City Staff, the Corps and its third-party consultants continued to make progress during the second quarter of 2016 in the federal permitting process. Key progress achieved during the period includes:  Continued analyses of the social, economic, and environmental impacts of the Halligan enlargement and alternatives, which will be evaluated and compared in the EIS.  Finalized six draft technical reports, for a total of 15 completed draft reports of the approximately 27 technical reports that form the basis of the draft EIS.  Continued writing the main body of the draft EIS, a major milestone in the permitting process.  Completed construction of a mass-balance water quality model for the North Fork of the Poudre River.  Prepared an agreement between the City and Northern Water to allow sharing of water quality models used for both the HWSP and the Northern Integrated Supply Project. The agreement will be brought for City Council consideration in August 2016.  Quantified wetland areas in the Halligan project area that will be impacted by the enlargement. Areas where wetlands could be re-established following construction are presently being inventoried.  Prepared an agreement and license between the City and mining claimants on an 80-acre tract of federally owned land lying under and adjacent to the existing Halligan Reservoir to allow right-of-way authorization from the Bureau of Land Management.  Addressed numerous issues related to the City’s landownership at Halligan Reservoir: researched land titles and landownership boundaries, issued a revocable recreational license to the Landowners Association for Phantom Canyon Ranches, and developed a draft easement for certain roads to the reservoir. North Fork Elevation and Cross Section Data DocuSign Envelope ID: BAC4E11A-8262-4561-B647-88F4A82F40A0 3 Permitting Schedule Fort Collins entered the federal permitting process in 2006, and expects that a draft of the EIS will be released in mid-2017. Other project milestones are shown in the timeline below. No changes to the project’s schedule have been made since the last Status Update to Council. Project Costs The following table provides a summary of the costs for the Halligan project through June 2016. The acquisition costs are primarily for the purchase of the Halligan Reservoir property from the North Poudre Irrigation Company (NPIC). The permitting costs include consulting services, legal, project management and other related project costs. Given the evolving scope of federal permitting and fluctuations in construction cost indices, and in order to ensure consistent information, cost projections will be updated annually and provided to City Council. Cost projections for the project were last updated in a February 23, 2016 memorandum to City Council. Expenses ($M) Previous Period Cost1 Cost Through March 2016 Acquisition $3.3 $3.3 Permitting $9.8 $10.2 Debt Service2 $1.9 $1.9 Total $15.0 $15.4 Estimated Final Ratepayers Cost ($M) To Date1 Total Project Costs $15.0 $15.4 Less Reimbursements3 ($4.5) ($4.5) Total4 $10.5 $10.9 1) Costs through March 2016. 2) Debt service payments from 2004 to 2014 were allocated as Halligan project expenses. All future debt service payments will not be accounted as a project cost. 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Federal Permitting ‐ Draft EIS Federal Permitting ‐ Final EIS Federal Permitting ‐ Permit Decision Preliminary and Final Design Construction Enlarged Halligan Operations DocuSign Envelope ID: BAC4E11A-8262-4561-B647-88F4A82F40A0 4 3) Reimbursements were received from former project partners (NPIC and the Tri-Districts) between 2005 and 2014. 4) Net project cost includes debt service and deducts reimbursements. CC: Water Board DocuSign Envelope ID: BAC4E11A-8262-4561-B647-88F4A82F40A0