HomeMy WebLinkAboutReport - Mail Packet - 7/14/2015 - City Managers Update - July 9, 2015July 9, 2015
ISSUES BEFORE COUNCIL
Water Supply Planning Policy ...................................................................................................2
Natural Areas Land Conservation Review & Potential Transactions ........................................2
Board and Commission Periodic Review ..................................................................................2
Amending the City’s Naming Policy .........................................................................................2
Proposed Pronghorn Antelope Hunting Program at Soapstone .................................................2
Paved Trails Report / Update on English Ranch Community Garden .......................................2
Appeals of the ZBA Decision re: Change of Use for 201 E. Elizabeth .....................................2
Call of Special Election for November 3, 2015 .........................................................................2
Findings of Fact and Conclusions re: Change of Use 201 E. Elizabeth ....................................2
Broadband Strategic Plan ...........................................................................................................2
Northern Integrated Supply Project: Impacts to Fort Collins ....................................................2
Planning Projects in Downtown.................................................................................................3
Railroad Study ...........................................................................................................................3
ECONOMY
Fort Collins Sales and Use Tax ..................................................................................................3
CAPITAL PROJECTS
Engineering Capital Projects ......................................................................................................3
Utilities Capital Projects ..........................................................................................................17
NATURAL AREAS LAND CONSERVATION 2
nd
QUARTER REPORT ...........................45
PUBLIC SAFETY UPDATE
Fort Collins Police Services .....................................................................................................46
Poudre Fire Authority .............................................................................................................47
BUILDING ACTIVITY………………………………………………………………………..51
2
ISSUES BEFORE COUNCIL
July 14 Work Session
Water Supply Planning Policy
o Seek direction from City Council regarding possible changes to the Utilities’
water supply planning policies.
Natural Areas Land Conservation Review and Potential Transactions
o Provide an overview of the Natural Areas Department, in particular its land and
water acquisition strategies and activities, and seek Council guidance
Board and Commission Periodic Review
o Review of the Affordable Housing Board, Community Development Block Grant
Commission, Human Relations Commission, Landmark Preservation
Commission, Senior Advisory Board, Women’s Commission, Zoning Board of
Appeals
July 21 Council Meeting
Amending the City’s Naming Policy
o Review the City’s naming policy for properties and facilities for the purpose of
considering amendments to the Municipal Code.
Proposed Pronghorn Antelope Hunting Program at Soapstone Prairie Natural Area
o Amend the City Code to allow the carry and discharge of firearms for the purpose
of hunting, in particular a pronghorn hunting program proposed for Soapstone
Prairie Natural Area.
Staff Report: Paved Trails Report / Update on English Ranch Community Garden
o Update on new trail construction projects currently planned in the City
Appeals of the Zoning Board of Appeals Decision Regarding the “Change of Use-
Building Permit” for Fraternity Use, 201 E. Elizabeth
Call of Special Election for November 3, 2015
o Calling a Special Municipal Election to be held in conjunction with the November
3, 2015 Larimer County Coordinated Election. This Ordinance does not place a
specific measure on the ballot but preserves the opportunity for Council to place
initiated or referred issues on the November ballot
July 28 Adjourned Meeting
Findings of Fact and Conclusions regarding the Appeals of the Change of Use
Building Permit for Fraternity Use, 201 E. Elizabeth
July 28 Work Session
Broadband Strategic Plan
o Provide a Broadband Strategic Plan update, including feedback from the
Community Engagement to date and draft results from the Benchmark and
Market Analysis research.
Northern Integrated Supply Project (NISP): Impacts to Fort Collins
o Review staff comments on the Supplemental Draft Environmental Impact
Statement for the Northern Integrated Supply Project. Staff will provide an
overview of the potential impacts; whether or not the impacts are adequately
3
described; and, advise Council as the magnitude and implications of the impacts.
Council will be asked to adopt comments by resolution that will be submitted to
the Army Corps of Engineers.
August 4 - Canceled for Neighborhood Night Out
August 11 Work Session
Planning Projects in Downtown
o Provide an update on the progress of three long-range planning projects that are
taking place simultaneously in the city’s historic core. Updates will be provided
for the 1989 Downtown Plan, Old Town Neighborhoods, and the Old Town
Neighborhood Design Guidelines.
Railroad Study
o Discuss and receive Council feedback on the draft report from the 2015 Railroad
Crossing Study for the Riverside Corridor (UP & GWR) which identifies
potential solutions to vehicular traffic congestion due to train switching activities,
and includes information about the railroad improvements in Greeley and
Windsor that may affect switching activities in Fort Collins.
ECONOMY
FORT COLLINS SALES AND USE TAX COLLECTIONS
Sales and Use Tax Collections
May 2015
Sales tax collections increased 5.4%
Use tax collections excluding rebates decreased 1.4%
Sales and use tax collections excluding rebates increased 4.0%
2015 YTD
Sales tax collections increased 7.6%
Use tax collections excluding rebates increased 34.8%
Sales and use tax collections excluding rebates increased 12.5%
CAPITAL PROJECTS
(new information noted in blue text)
1. CITYWIDE PEDESTRIAN ACCESS PROJECT
Funding Source: KFCG/BOB Funds
Estimated Project Budget: $450,000
Status: On Budget, On Schedule
4
The City of Fort Collins Pedestrian Plan addresses citywide pedestrian needs and is a
data-driven approach based on the importance for safe, sustainable walking within City
limits. It however lacks comprehensive condition data for the City’s sidewalk system.
Prior to the beginning of the Pedestrian Needs Assessment project, there was not an
inventory of existing sidewalks or sidewalk deficiencies. This project provides a
complete City sidewalk inventory, identifies sidewalk inadequacies, and identifies
inadequate handicap accessibilities according to Americans with Disabilities Act (ADA)
requirements.
Data collection has been completed with approximately 540 street miles of sidewalk
assessed and inventoried at this time.
37,741 accessible ramps have been identified as acceptable, substandard, or missing in
accordance with the ADA requirements.
Staff has implemented a methodology and analysis program used to prioritize pedestrian
projects. This program takes into account a variety of factors such as, but not limited to,
demand, corridor function, and high priority areas.
o Upcoming project locations: New sidewalk installation along Parker/Remington
and Stuart/Remington. Sidewalk repairs along Meldrum/Oak. New sidewalk
installation along City Park south of Birch.
o Current projects: Contractor repaired approximately 200’ of sidewalk along
Meldrum/Oak. Contractor installed 30’ of new sidewalk to make a
connection along Lemay near Buffalo Run Apts./Walmart. Staff is
continuing to collaborate with CSU staff regarding final layout for the
NRRC connection between Centre Avenue and MAX Spring Creek Station.
Prioritization Model is complete and has been posted to the engineering website:
http://www.fcgov.com/engineering/pedneeds.php. Staff is performing additional public
outreach to reassess the prioritization model. Currently, staff has visited with the
Commissions on Disability and is conducting an online survey. Staff is scheduled to
attend July’s Transportation Commission meeting.
Staff is continuing to collect and update data from projects and developments that
occurred 2013 and 2014.
2. MULBERRY BRIDGE (SH 14) AT THE POUDRE RIVER ENHANCEMENTS
Funding Source: City of Fort Collins
Estimate Project Budget: $750,000
Status: On Budget, On Schedule
5
The Colorado Department of Transportation (CDOT) is replacing the Mulberry Bridge
(State Highway 14) over Poudre River Bridge and the project started in the fall of 2014.
Construction was delayed due to the September 2013 flood.
Due to the construction, eastbound traffic on Mulberry will be detoured for the duration
of construction.
CDOT has initiated the project. All detours are active. The City continues to work with
CDOT to monitor the detours, making adjustments as needed. The City is also working
with CDOT to ensure appropriate levels of outreach and messaging is provided to the
public.
The City is working with CDOT to add city-funded enhancements to the bridge including
decorative railings, landscaping and urban design features.
CDOT initiated the second phase of the project, focusing on removing and replacing the
remaining south section of the existing bridge. All remaining bridge girders have been
placed, and the concrete bridge deck has been poured. CDOT has shifted focus to
completing surfaces improvements for the south half of the project.
Pedestrian traffic will be prohibited on Mulberry Street between Riverside Avenue and
Lemay Avenue. A signed detour utilizing Lemay Avenue and Riverside Avenue is
provided. Pedestrians and cyclists will continue to have access across Mulberry Street via
the traffic signal at Lemay Avenue throughout Phase 2.
The City has initiated the final design phase for additional urban design elements and
landscaping along Mulberry Street between Riverside Avenue and Lemay Avenue.
Improvements are being coordinated with the various items planned for the bridge and
surrounding developments.
3. WEST MULBERRY BRIDGE REPLACEMENT DESIGN
Funding Source: Colorado Off System Bridge Program (BRO) funds and KFCG 2011
Estimated Project Budget: $1.1M
Status: On Budget, On Schedule
6
The goal of the project is to replace the existing structurally deficient bridge with a new
bridge that meets the current standards.
The posted weight limit on this bridge precludes the passage of emergency vehicles from
the nearby fire station.
In December 2011, the City received a grant for $700,000 in Colorado Off System Bridge
Program (BRO) funds for some of the construction cost.
Construction is planned for winter 2015/spring 2016.
4. ARTHUR DITCH BOX SECTION REPLACEMENT –
OAK/WHITCOMB, CANYON AT MULBERRY POOL
Funding Sources: KFCG / Operation Services, Facilities
Estimated Project Budget: $2M
Status: On Budget, Completed
The intent of this project is to replace two structurally deficient bridge/box sections with
new concrete box culverts.
Value engineering and best practices are being applied to develop the most cost efficient
replacement methods. Both locations lie within local floodplains and will be evaluated
7
prior to final design approval. Coordination efforts also include the Streets Dept.
maintenance schedules to ensure the roadway is reviewed for both short and long term
impacts.
Both projects have reached final completion. Project costs are at, or within, 1% of
budgeted amount. Project close-out and final certifications will be conducted and
during the month of July, retainage is expected to be released during the month of
August, 2015.
This will be the last monthly report for this project as close-out is occurring.
5. ARTHUR DITCH BOX SECTION REPLACEMENT – LOOMIS/OLIVE
Funding Sources: KFCG / Operation Services, Facilities
Estimated Project Budget: $1M
Status: On Budget, On Schedule
The intent of this project is to replace a structurally deficient bridge/box sections with
new concrete box culverts.
Value engineering and best practices are being applied to develop the most cost efficient
replacement methods. This location lies within local floodplains and will be evaluated
prior to final design approval. Coordination efforts also include the Streets Dept.
maintenance schedules to ensure the roadway is reviewed for both short and long term
impacts.
The Olive and Loomis replacement location plan sheets are near complete. This project
will have some front end utility work to coordinate and staff is sorting through those
details for relocation efforts in advance of the box replacement to occur in the
summer/fall of 2015.
Plan finalization will come after the completion of Canyon Street and Oak/Whitcomb.
This is being done to allow any “lessons learned” to be incorporated into the project,
which are expected to add efficiencies and savings to the project.
Floodplain clearances have been approved for construction, and the pertinent flood plain
use permits are being issued.
8
Staff has received the approval of the Arthur Ditch for the necessary ditch crossing
agreement.
Staff will continue to perform outreach to adjacent residents to provide additional
information on the project and its schedule as it becomes available.
6. SHIELDS STREET AND DRAKE ROAD INTERSECTION IMPROVEMENTS
Funding Sources: Federal Hazard Elimination Grant (90%) / Local Match (10%)
Estimated Project Budget: $986,000
Status: On Budget, On Schedule
The main goal of this project is to reduce the accident rate that occurs at this intersection
by installing dedicated right turn lanes in the north and southbound movements. A
reduced movement concept is also being considered to the Raintree Dr./Davidson Rd.
intersection 400 feet south of Shields and Drake.
This project has multiple funding sources - Federal Hazard Elimination Grant: $887,400,
City BOB funding $98,600.
This project has completed the FIR portion of the design and is nearing FOR design
completion as well. As well, the project has received clearance from CDOT right of way
agents to proceed with land acquisition, which is currently on-going.
Project is currently in a “hold pattern” until the offers for additional right of way
acquisitions from the adjacent property owners has been accepted or negotiated.
This process must also be approved by Colorado Department of Transportation,
Right of Way Department, as federal funding requires.
As a result of meeting Federal requirements this project is anticipated to go to
construction in the summer of 2016.
7. TIMBERLINE IMPROVEMENTS – PROSPECT TO BLACKBIRD
Funding Source: Building on Basics (BOB)
Estimated Project Budget: $3,500,000
Status: On Budget, On Schedule
9
The goals of this project are to improve air quality, reduce vehicle wait time and reduce
the accident rate by constructing a free-right turn and acceleration lane from eastbound
Prospect to southbound Timberline; as identified in our Arterial Intersection Prioritization
Study.
The 2005 ballot language stated this project will expand Timberline Road to four (4) lane
arterial standards including:
• Travel lanes, sidewalks, bike lanes and landscaped medians.
• Improvements to the Prospect and Timberline intersection and all its approaches
to add additional turn lanes.
The project will add a sidewalk connection for southbound Timberline from Prospect to
Blackbird.
Additionally, water quality features will be constructed to minimize the flow rates and
volumes as they outlet to the Spring Creek basin.
Construction is expected to begin in the spring of 2016.
A communication plan (public outreach) is being developed and will be implemented
with the final design through construction.
The team is pursuing options for the deconstruction and reuse of two silos which need to
be removed for roadway, bicycle, pedestrian and landscape improvements.
The project website is available through the Engineering homepage at
http://www.fcgov.com/engineering/prospect-timberline.php
8. HORSETOOTH AND TIMBERLINE INTERSECTION IMPROVEMENTS
Funding Source: Building on Basics (BOB) and Federal Grant (CMAQ)
Estimated Project Budget: $3,500,000
Status: On Budget, On Schedule
10
The goal of this project is to relieve traffic congestion and vehicle wait time by
constructing additional intersection turn lanes.
The need for these safety and operational improvements were identified in the
Engineering Department’s recently completed Arterial Intersection Prioritization Study.
Turn lane needs are as follows:
o Right turn lane (southbound Timberline to westbound Horsetooth)
o Right turn lane (eastbound Horsetooth to southbound Timberline)
o Second left turn lane (northbound and southbound Timberline)
The project has moved to the final design phase, streetscape visioning and coordination
with property owners for real estate purchases (right of way and easements).
Additionally, the project will include median and landscape improvements, sidewalk and
bicycle lane improvements and transit infrastructure. Bids for this were opened on May
27 and it is currently going through the award process.
Construction began on May 18, with median removal, lane closures and temporary
pavement/striping for traffic.
Horsetooth Road is currently closed on the west leg from June 1 – July 25 and will
be closed on the east leg from July 13 – Aug 15.
A communication plan (public outreach) has been developed and is being followed.
There have been two press releases as well as updates to the website and email blasts
detailing schedules and what to expect.
The project website is available through the Engineering homepage at
http://www.fcgov.com/engineering/horsetooth-timberline.php
9. VINE AND SHIELDS ROUNDABOUT
Funding Source: Building on Basics (BOB), Federal Grant (STP Metro) and Regional
Road Impact Fees
Estimated Project Budget: $1,700,000
Status: On Budget, On Schedule
11
The main goal of this project is to increase mobility at the intersection via multimodal
transportation improvements. Currently, the east-west lanes on Vine Drive are not
aligned causing additional independent traffic movements which effect the overall
operation of the signal timing.
The City received a federal grant award for $1,054,000 through the North Front Range
Metropolitan Planning Organization in the STP-Metro category.
Other safety concerns which will be corrected at the intersection entail: adding sidewalks
along the northern portion of the project, installing ADA compliant ramps/crosswalks and
adding bike lanes.
The City continues to coordinate our intersection project with Larimer County’s proposed
improvements to Shields Street from 400’ north of Vine Drive to Willox Lane. The
County received three federal grants for this stretch of roadway to accomplish the
following:
o Replace the Shields Street Bridge over the Poudre River
o Improve the Poudre River trailhead parking area and river access
o Reconstruct approximately one mile of Shields Street
A communication plan (public outreach) is being developed and will be implemented
with the final design through construction.
The project website is available through the Engineering homepage at
http://www.fcgov.com/engineering/vsi.php
10. REMINGTON GREENWAY
Funding Source: FC Moves Funding
Estimated Project Budget: $650,000
Status: On Budget, On Schedule
12
The goal of this pilot project is to offer flexibility in street design to calm traffic, support
active modes of transportation and integrate stormwater management strategies.
The design calls for buffered bike lanes, removal of the traffic signals between Prospect
and Mulberry, and the construction of a mini roundabout with curb bulb outs at
Remington and Laurel.
Additional funds were added to the project with approval of the 2015 budget, and funds
from the Pedestrian Needs Assessment, to rebuild sections of sidewalk and curb ramps.
Also, Street Maintenance is using some of its 2015 budget for a surface treatment prior to
restriping the corridor. This will take place in the fall of 2015, after the construction for
this project is complete. Temporary striping will be applied to specific areas along the
Remington Corridor prior to Street Maintenance work.
Construction will start in mid-July.
We are actively coordinating our construction schedule with the US 287 (College
Avenue) CDOT resurfacing project.
A communication plan (public outreach) has been developed and is currently being
implemented.
The project website is available at fcgov.com/advanceplanning/remingtongreenway.php
11. SH 392 AND I-25 INTERCHANGE SIGNS
Estimated Project Budget: $300,000
Status: On Budget, On Schedule
13
The goal of this project is to construct welcoming and aesthetically pleasing signs for
traffic entering the City of Fort Collins and the Town of Windsor along SH 392.
The City has pursued a number of potential sign locations. It was determined that the
medians will be the best location for the signs.
The City is partnering with the Town of Windsor for the design and construction of the
signs.
Contracts are in place between the City and the Contractor (L&M Enterprises), and
Windsor and the Contractor.
Construction of the signs is complete. Solar panel and lighting installation is complete.
Landscaping and irrigation have been installed. The contractor is waiting for CDOT to
repair interchange irrigation so that City staff can inspect and accept median irrigation.
Once irrigation is accepted, project closeout will take place.
12. DOWNTOWN RIVER DISTRICT IMPROVEMENTS
Funding Source: Federal Grants, Local Funds, DDA Funds
Estimate Project Budget: $1.48 million
Status: On Budget, On Schedule
14
The City has contracted with Interwest Consulting to provide engineering services for
various City initiated improvements within the Downtown River District.
The project will also have the capability to provide various engineering services in
preparation of anticipated development.
The City has initiated two projects: 1. Developing an implementation plan for
improvements along Jefferson Street between College Avenue and the Mountain /Lincoln
intersection based on the available budget, and 2. Developing a conceptual design for
improvements along Willow Street between North College Avenue and Linden Street.
Additional projects to follow include the development of engineering plans and
specifications, as well as construction of these improvements along both Jefferson and
Willow based on the results of the above.
The City has adjusted the proposed roadway cross section for Willow Street based on a
thorough review of the original design intent, and the new and emerging land uses in the
area. Focus will now shift to the preliminary engineering phase.
The City has completed final engineering plans along the Feeder Supply
Development’s Willow Street frontage in an effort to coordinate developer and City
planned improvements.
The City continues to work on the Jefferson Street Implementation plan, balancing
planned improvements with available budget and proposed development along the
corridor.
13. LINCOLN (INTERIM) AND LEMAY IMPROVEMENTS / WOODWARD CAMPUS
Funding Sources: City of Fort Collins General Fund, Intersection
Improvement Fund
Estimated Project Budget: $2.1-2.3M
Status: On Budget, On Schedule
This project has several goals. The first is to install three new points of access/turn lanes
to the Woodward Campus, two on Lemay, and one on Lincoln. The project will also
complete the improvements along the west side of Lemay between Lincoln and
Mulberry. This includes completion of the Magnolia intersection to a full movement
location along with curb, gutter and sidewalk for the entire length. An interim sidewalk
15
will also be constructed along the Lincoln front that connects pedestrians to the Poudre
River bridge on Lincoln and into downtown. Lastly, a double left turn configuration will
be installed on southbound Lemay to eastbound Mulberry for as a result of anticipated
traffic volumes for this area.
The City and Mortenson Construction have partnered to identify and employ best
practices regarding communication, safety and general project information to the local
businesses and nearby neighborhoods.
Staff has been working closely with CDOT and contractor personnel to develop final
coordination logistics that will allow for some portions of adjacent Lemay improvements
to occur and tie in with the Mulberry Bridge progress.
Walsh Construction Inc. crews have completed the west side of Lemay Avenue, and all
improvements adjacent to SH-14 relating to the pork chop island.
A major milestone includes paving the west side of Lemay. This will allow the
completion of water and sewer utilities, median modification/new turn lane
reconstruction, and traffic signal infrastructure at Magnolia and Lemay.
Anticipated substantial completion is mid-August 2015. This phase will be
communicated via press releases and social media.
14. NORTH COLLEGE PEDESTRIAN GAP
Funding Sources: CMAQ Grant, URA Contribution, Pedestrian Program Funds
Estimated Project Budget: $900,000
Status: On Budget, On Schedule
The primary goal of this project is to complete a gap in pedestrian infrastructure from
Highway 1 to the south side of the Larimer & Weld Canal.
This project will construct a pedestrian connection crossing the Larimer & Weld Canal
extending north to SH 1 (Terry Lake Rd). The project impacts a federal highway, and is
located outside the City limits but within the Growth Management Area.
The City received a Congestion Mitigation and Air Quality (CMAQ) grant for this
project. Developer contributions through the Urban Renewal Authority (URA) as well as
Pedestrian Program funds make up the local match portion of funding.
16
A signed IGA with CDOT has been executed, and authorization to begin design has been
received.
Interwest Consulting Group has developed a conceptual level plan through a work order
for coordination purposes. City staff has begun coordination efforts with the ditch
company, Larimer County and CDOT.
The City is in the process of consultant selection through a Request for Proposals
(RFP) process. Consultant selection will take place in the month of July 2015, with
full design starting immediately after.
15. NORTH COLLEGE IMPROVEMENTS – CONIFER TO WILLOX
Funding Source: Federal Grants, Local Matching Funds
Estimate Project Budget: $12 million
Status: On Budget, On Schedule
The intent of this project is to design and construct improvements along North College
Avenue from the Conifer/Hickory intersection to Willox Lane, bringing this section of
North College up to four-lane arterial standards as defined by the Larimer County Urban
Area Street Standards. Both medians and sections of the planned rear access roads are
included in the project.
The overall project budget is $12.0 million. This is comprised of roughly 60% federal
funds and 40% local funds.
Pre-project utility relocations began in early June 2014, with an expected completion date
of September 2014.
Construction of a rear access road west of North College was completed in Summer
2014.
Zak Dirt, Inc. was awarded the N. College construction contract and construction for the
improvements along North College Avenue began in October 2014.
The project has completed the west side storm sewer system and waterline modifications.
The project is currently installing concrete pavement along the west side of N. College.
The project is anticipated to be completed in November 2015.
Additional information is available at http://www.fcgov.com/engineering/ncollege.php
Boxelder Creek Ouƞall
June 2015
Major Design Elements—Design Phase Underway/Upcoming Work
Dredging Boxelder Creek Site Map
6 ‐ 12 foot wide x 4 foot high RCBC under East Prospect
200’ long Sidespill Weir on Boxelder Creek
2,700 cfs Flood Channel from Boxelder Creek to Poudre River
New RCBC on Boxelder Creek under East Prospect
New Siphon to replace exisƟng Flume on Lake Canal at Boxelder Creek
Dredging of Boxelder Creek Between Mulberry and I‐25
Dredging of Boxelder Creek between Mulberry and I‐25 Complete
ConstrucƟon of Siphon on Lake Canal
Flood Diversion Channel North and South of East Prospect
Box Culverts Under Prospect
Replacement of Bridge on Boxelder Creek on East Prospect
Dredging Boxelder Creek
Schedule
July 2015 October 2015 January 2016 February 2016 May 2016 October 2016
Dredge Boxelder Creek
Construct New Siphon
UƟlity RelocaƟons at Prospect
Box Culverts and Channel at Prospect
Budget Summary
Budget Expense to Date % Complete
Design $290,000 $125,000 43%
ConstrucƟon $2,291,000 $300,000 13%
Right of Way $100,000 $0 0%
Total $4,060,011 $450,000 11%
Other (City PM) $150,000 $25,000 17%
17
Rigden Water Storage Project
June 2015
Major Milestones/Completed/Underway Upcoming Work
SolarBee mixer assembly Reservoir filled on June 24, 2015
The reservoir was filled on June 24, 2015
AddiƟonal earthwork
Landscaping will be competed in July 2015
The project will be complete in September 2015
Reservoir Reservoir filling begins filling
begins
Schedule
June 2015 July 2015 August 2015 September 2015
Landscaping
AddiƟonal earthwork Project complete
Budget Summary
Budget Expense to Date % Complete
Design $667,547 $649,766 97%
ConstrucƟon $10,940,600 $10,225,760 94%
Right of Way
Total $13,050,164 $12,317,908 94%
Other $1,442,017 $1,442,382 100%
18
June 2015
Major Milestones/Completed/Underway Upcoming Work
Site Map
Contracted with CH2M to provide assistance in developing
Masterplan
Performed ExisƟng FaciliƟes and CondiƟon Assessment
audit and tabulated results
Performed Water Resources and Demand ProducƟon audit
and tabulated results
Electrical System Study
Perform a Regulatory Assessment and Energy Management
Analysis
Develop Recommended Plan and Improvements Program
Schedule
Budget Summary
Budget Expense to Date % Complete
Design $475,743 $87,454 18.4%
ConstrucƟon N/A N/A N/A
Right of Way N/A N/A N/A
Total $560,000 $145,150 25.9%
Other $84,257 $57,696 68.5%
WATER TREATMENT FACILITY 2015 MASTER PLAN
Spring 2015 Summer 2015 Fall/Winter 2015
ExisƟng FaciliƟes/CondiƟon Assess
Electrical System Study
Recommended Plan Submission
Final Masterplan Report Project Complete
19
WATER TREATMENT FACILITY CHLORINE CONTACT BASIN
June 2015
Major Milestones/Completed/Underway Upcoming Work
Site Map
Contracted with CH2M to provide final design services
Performed Geotechnical Study
Performed ComputaƟonal Fluid Dynamic Modeling
Value Engineering Review of DraŌ Documents and
SpecificaƟons
Potholing ExisƟng FaciliƟes
Pre‐purchase Long Lead Items
Schedule
Budget Summary
Budget Expense to Date % Complete
Design $500,000 $286,000 57.2%
ConstrucƟon $9,000,000 0 0%
Right of Way $0 $0 100%
Total $10,700,000 $338,700 3.2%
Other $1,200,000 $50,700 4.2%
Spring 2015 Summer 2015 Fall/Winter 2015
Geotechnical InvesƟgaƟon
CFD Modeling
Potholing / InvesƟgaƟons
Final Plans and SpecificaƟons
Pre‐purchase Long Lead Items Phase I Complete
20
NORTH SHIELDS STREET SANITARY SEWER INTERCEPTOR
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Laying Pipe Site Map
Placed 2750 feet of 21” sewer (To date on north side of
river)
Placed 11 manholes (north side of river)
Placed 12 service stubs
Cross Larimer and Weld Canal through sleeve previously
installed
Place final manhole in the intersecƟon of Willox Lane and
Shields Street
Grout manholes, test, cleanup
Project Closeout
Final Manhole in ROW South of the
Larimer and Weld Canal
Schedule
Budget Summary
Budget Expense to Date % Complete
Design N/A $239,000 100%
ConstrucƟon N/A $1,310,000 79%
Right of Way N/A N/A N/A
Total $2,425,000 $1,811,000 79%
Other N/A $264,000 100%
July 2015
Larimer and Weld Canal/Willox Lane‐21” Sanitary Sewer
Final Manhole in Willox
TesƟng/Clean‐Up/Project CompleƟon (7/17/15)
21
POUDRE RIVER SEWER CROSSING AT SHIELDS STREET
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Manhole Site Map
ConstrucƟon Complete
Re‐submiƩed No Rise CerƟficaƟon
Completed as‐built survey
Complete as‐built drawings
Closeout 404 Permit
Project Closeout
Poudre River at crossing
Schedule
Budget Summary
Budget Expense to Date % Complete
Design N/A $26,400 100%
ConstrucƟon N/A $146,600 90%
Right of Way N/A N/A N/A
Total $210,500 $173,000 90%
Other N/A N/A N/A
July 2015
Project Closeout
22
DWRF Digester 611 Lid Replacement
June 2015
Major Milestones/Completed/Underway Upcoming Work
Digester Lid Assembly Guiderail InstallaƟon Site Map
Digester piping modificaƟons completed
Digester lid delivery completed
Digester assembly underway
Digester weld tesƟng underway
Complete welding and tesƟng
Start coaƟng installaƟon
Schedule
Budget Summary
Budget Expense to Date % Complete
Design $32,570 $20,905 64%
ConstrucƟon $1,085,872 $769,746 71%
Right of Way
Total $1,128,442 $790,651 70%
Other $10,000 $0 0%
June 2015 July 2015 August 2015 September 2015
Digester Lid FabricaƟon
Lid Assembly and CoaƟng
InstallaƟon and TesƟng
23
DWRF South Process Train BNR & Replacement Project
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
DWRF South Process Train
LocaƟon Map
New Nueros Blowers in SPT
Blower Building
Basin wall placement completed
Basin Leak/HydrostaƟc test completed in both E & W Basins
Blower delivery and installaƟon completed
AeraƟon piping installaƟon underway
Electrical infrastructure underway
Basin backfill underway
UƟlity chase and walkway installaƟons
RAS/PEF pipeline installaƟon
Basin sample line installaƟon
Electrical transformer installaƟon at DWRF substaƟon
Lamson blower installaƟon
Electrical duct bank compleƟon to uƟlity chase
DWRF SPT Basin Wall ConstrucƟon
Schedule
Budget Summary
Budget Expense to Date % Complete
Design $913,076 $907,585 100%
ConstrucƟon $8,632,633 $5,044,497 58%
Right of Way .
Total $9,595,709 $5,972,750 62%
Other $50,000 $20,668 41%
June 2015 July 2015 August 2015 September 2015 October 2015 November 2015
Structural Concrete InstallaƟon
RAS/PEF/Chem Duct Bank
A‐Basin Mechanical InstallaƟon
Electrical Equipment Install
24
Mountain Avenue Waterline Replacement
June 2015
Major Elements Upcoming Work
Service Pit ExcavaƟon Site Map
Water Main Replacement from Grant to Shields
Replacement of 80 year old cast iron water mains with new PVC
InstallaƟon of new copper services to curb stop
InstallaƟon of new fire hydrants
ConstrucƟon is complete on South Side.
Westbound lane of Mountain will be closed ,
starƟng July 6th.
Pipe BursƟng on Mountain Avenue
Schedule
June 2015 July 2015 August 2015
South Side ConstrucƟon
North Side ConstrucƟon
Budget Expense to Date % Complete
Design $200,000 $117,000 58%
ConstrucƟon $993,000 $85,000 8%
Right of Way NA NA NA
Total $1,353,0000 $255,000 19%
Other $160,000 $53,000 33%
Budget Summary
25
Old Town Water and Wastewater Master Plan
June 2015
Major Elements Upcoming Work
Wastewater Flow Data Site Map
Comprehensive assessment of water and wastewater system in Old Town
Develop a prioriƟzed list or replacement projects
Develop Cost EsƟmates for replacement projects
Plan for infrastructure upgrades for downtown redevelopment
Water and Wastewater Model Updates
PrioriƟzaƟon Model
Downtown Redevelopment Review
DefiniƟon of Improvements
ExisƟng Cast Iron Pipe
Schedule
June 2015 July 2015 August 2015 September 2015 October 2015
System Assessment & Problem IdenƟficaƟon
Project PrioriƟzaƟon
DefiniƟon of Improvements
Cost EsƟmaƟng
Final Report
City Council AdopƟon
Budget Expense to Date % Complete
Design $250,000 $100,000 40%
ConstrucƟon NA NA NA
Right of Way NA NA NA
Total $250,000 $100,000 40%
Other NA NA NA
Budget Summary
26
Cathodic ProtecƟon
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Annual Test Site Readings Taken At WTF Site Map
Conducted annual CP test site readings at WTF
Reviewed and read Contractor installed new test sites at WTF
Preparing for conƟnuity correcƟons along AB line
Contractor Installed New Test Sites At
WTF
Schedule
June 2015 July 2015 August 2015 September 2015
Annual WTF CP Readings
Tested New WTF CP Test Sites
Budget Summary
Budget Expense to Date % Complete
Design $0 $0 0%
ConstrucƟon $93,000 $15,123 16%
Right of Way $0 $0 0%
Total $101,325 $23,448 23%
Other $8,325 $8,325 100%
27
Fossil Creek Stream RehabilitaƟon Project
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
PlanƟngs of naƟve trees and bushes Site Map
Repairs due to heavy rainfall and irrigaƟon ditch flushing
flows
PlanƟngs of naƟve trees and bushes
PlanƟngs to conƟnue through June with final plants sched-
uled for September
Site closed with fencing and signage for the next 3-5 years
to allow for naƟve vegetaƟon restoraƟon
Contractor invoices sƟll coming in
Repairs Due to Heavy Rainfall and Ditch
Flushing Flows
Schedule
June 2015 July 2015 August 2015 September 2015
Contractor Repairs
Further PlanƟngs
Budget Summary
Budget Expense to Date % Complete
Design $341,727 $317,472 93%
ConstrucƟon $979,505 $691,073 71%
Right of Way $1,243 $1,243 100%
Total $1,432,139 $1,119,452 78%
Other $109,664 $109,664 100%
28
Northeast College Corridor Ouƞall Phase 3 (NECCO3)
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Hydroseeded and mulched, bore Site Map
construcƟon complete
Hydroseeded and mulched, bore construcƟon complete
Working on purchase of pond and backbone, as well as FE‐
MA CLOMR and COE permit
Working on purchase of pond and backbone, as well as FE‐
MA CLOMR and COE permit
Hydroseeded and mulched, bore
construcƟon complete
Schedule
June 2015 July 2015 August 2015 September 2015
Hydroseeded and Mulched
Pond Purchase and Modeling
Budget Summary
Budget Expense to Date % Complete
Design $198,207 $115,447 58%
ConstrucƟon $846,213 $447,650 53%
Right of Way $2,186 $2,186 100%
Total $1,046,606 $573,283 55%
Other $8,000 $8,000 100%
29
Mall Project
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Conduit Installation for New CB Pots
Transformer
East Lawn Transformer Installed
Completed vault replacement at Standford
and Monroe
Work conƟnues on seƫng transformers
RelocaƟon of vault at Monroe and College in
progress
85% of all the conduit installaƟon is complete
Cable pulling to exisƟng pad sites conƟnues
Transformer for the New Ross building has
been set and energized
Pull cable to exisƟng pad sites as contractor
progress is made.—Ongoing
WaiƟng direcƟon to move feeders from PDT
Determine final circuit needs and installaƟon
Ɵming.
Dependency: Project compleƟon in Septem-
ber is dependent on the compleƟon of the
contractor’s work being complete on Ɵme
351 E. Foothills Parkway—Concrete
Transform Pad Pouring
Schedule
April 2015 May 2015 June 2015 July 2015 Aug 2015 Sept 2015
Electrical ExcavaƟon
Transformer InstallaƟon
Vault RelocaƟon Project Complete
ConstrucƟon Budget—PM Abrams
ConstrucƟon Cost EsƟmate: $1,300,000
Work Complete $ 910,00.00
Project 70% Complete
30
Woodward Governor Project
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Metering Cabinets Woodward Governor Site
750 cable assembly complete
Hydro Engineering vault structural miƟgaƟon
complete
InstallaƟon of control switches underway
Circuits energized and de-energized for Dyna
Electric to complete their terminaƟons
WaiƟng for Dyna Electric work compleƟon on
the customers side to complete energizing
ReinstallaƟon streetlights on Lincoln Avenue
Installation of Metering Cabinet
Schedule
April 2015 May 2015 June 2015
Ground ExcavaƟon
Cable Assembly
Cable InstallaƟon
Hydro Engineering Structural Vault CompleƟon Energize June 30
ConstrucƟon Budget
ConstrucƟon Cost EsƟmate $ 2,000,000.
Work Complete $1,900,000.
Project 95% Complete
31
North College Improvement Project
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Overhead Power Lines Underground
Conversion/Conduit Installation
Street Lighting Installation
Completed West side excavaƟng, trenching and
installaƟon of electric faciliƟes
Removing streetlights as needed on the
Eastside
One half of 3 phase primary has been energized
(Hickory North to Hibdon)
Half of street lighƟng is ready (waiƟng approval
from CFC Engineering)
InstallaƟon of the main line on the East
side of college
Upgrade street lighƟng
Removal of overhead will begin in July
Excavation
Schedule
April 2015 May 2015 September 2015
Removed Street Lights
Overhead power lines undergrounded
Conduit InstallaƟon Rain Delay
Upgraded Street LighƟng Project Complete
June 2015
ConstrucƟon Budget—PM Mark Smith
Total Contract Values $570,000
Work Complete $199,500
Project 35% Complete
32
East Harmony Duct Bank—Timberline to I‐25
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Area that will be affected Harmony Substation
Northern Engineering survey complete
Northern Engineering completed the first
draŌ of horizontal map
IdenƟfy potenƟal routes from Northern Engi-
neering horizontal map
Pothole for exisƟng infrastructure and use lo-
cates to determine route, depth, and locaƟon
of the new duct bank
Project Risk: Funding
Infrastructure in place that will require
pot holing
Schedule
May 2015 June 2015 July 2015 August 2015 September
2015
December 2016
Project Survey/Design
Define Route
Duct Bank InstallaƟon Project Complete
ConstrucƟon Budget
Total Project Value $ 3,000,000.
Work Complete $150,000.
Project 5% Complete
33
Carpenter Duct Bank
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Easement required with Natural Carpenter Road West Bound
Resources
Design of 2.6 miles duct bank underway Easements
Alignment agreement with Natural Re-
sources
Risk: Easement Agreement with Natural
Resources
Location of the 2.6 mile Carpenter
Duct Bank
Schedule
May 2015 June 2015 September 2016
Design
Easements
ExcavaƟon/ConstrucƟon
Duct Bank InstallaƟon Project Complete
July 2015
ConstrucƟon Budget
Total Contract Values $2,000,000.
Work Complete $60,000
Project 3% Complete
34
Drake SubstaƟon to Lake Street Duct Bank
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Possible Heavy Pedestrian/Bike Traffic
that will be affected by construction
Areas that will be affected by
installation
Route coordinaƟon with CSU is underway. Easements
Finalizing RFP for Engineering Consultant
Route CompleƟon
Risk: Easement Ɵmeline and budget con-
cern.
1.2 Miles of Duct Bank from Drake
Substation
Schedule
May 2015 June 2015 July 2016
Design
Easements
ExcavaƟon/ConstrucƟon
Duct Bank InstallaƟon Project Complete
July 2015
ConstrucƟon Budget
Total Contract Values $370,000.
Work Complete $11,100.
Project 3% Complete
35
Howes/Mulberry to Laurel Street Duct Bank
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Construction wouldn’t start until CSU
dismissal 2016
CSU Involvement is Crucial
Design of 1/2miles of duct bank
CoordinaƟon with CSU is underway
Project full funded by CSU
Easements
Finalizing RFP for Engineering Consultant
Locates and Route CompleƟon
Map of the 1/4 mile Duct Bank
Schedule
May 2015 June 2015 October 2016
Design
Easements
ExcavaƟon/ConstrucƟon Starts May 2016
Duct Bank InstallaƟon Project Complete
July 2015
Complete in De-
cember 2015
ConstrucƟon Budget
Total Contract Values $500,000.
Work Complete $5,000.
Project 1% Complete
36
Avery Park Neighborhood Conversion
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Map of Avery Park Neighborhood—
Total Project 354 Lots
Avery Park
Design complete
Second implementaƟon and coordinaƟon
Complete
Project compleƟon is dependent upon
project prioriƟes
Locates and route compleƟon
Upgrade street lighƟng
ParƟal Phase 1: Move electric from rear lot
to front lot—34 conversions
Boring and City coordinaƟon with owners
Area Affected Before Conversion
Total Phase 1 = 110 Lots
Schedule
May 2015 June 2015 November 2015 March 2016
Design
ConstrucƟon
Street LighƟng InstallaƟon Project Complete
ConstrucƟon Budget
Total Contract Values $190,000.
Work Complete $5,700.
Project 3% Complete
37
SW AnnexaƟon: Trilby/Shields to TaŌ
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Trilby Road West Bound Trilby and Taft Hill Road
Design Phase Complete
Duct bank standards update complete
Locates compleƟon
Last phase of annexaƟon excavaƟon/construcƟon
1 mile of duct bank installaƟon
Overhead conversion installaƟon
Project CompleƟon Dependent on Project Priori-
Ɵes
Map of SW Annexation
Schedule
May 2015 June 2015 TBD
Design
Duct Bank Standards Update
Duct Bank InstallaƟon
Electric Conversion InstallaƟon Project Complete
July 2015
ConstrucƟon Budget
Total Contract Values $1,100,000.
Work Complete $165,000.
Project 15% Complete
38
Scenic Knolls—Shields/South Fossil Creek Parkway
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
40 Estate Lots: Overhead Line
Conversion
Area Affected: Scenic Knolls
Subdivision
Design Phase Complete
Locates complete
SAGE ContracƟng boring underway
Overhead power line conversion
Project compleƟon is dependent upon
project prioriƟes
Location of Overhead Conversion
Schedule
June 2015 July 2015 August 2015 December 2015
Design
Contract Boring
Electric Conversion InstallaƟon Project Complete
ConstrucƟon Budget
Total Contract Values $310,000.
Work Complete $62,000.
Project 20% Complete
39
Applewood Rebuild—Shields/North Fossil Creek
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
REA Pedestal that will be replaced New Pedestals replacing old pedestals
Design complete Undergrounded infrastructure replace-
ment/maintenance—65lots
SAGE boring coordinaƟon
Install new conduit and cable
Location of Applewood Rebuild
Schedule
June 2015 July 2015 August 2015 December 2015
Design
Electric conduit and cable installaƟon Project Complete
SAGE boring
ConstrucƟon Budget
Total Contract Values $310,000.
Work Complete $62,000.
Project 20% Complete
40
East Vine Duct Bank—Phase I
June 2015
Major Milestones/Completed/Underway Upcoming Work
Installation of pump station
foundation piers.mp
Boring under I‐25 Colorado Boring: Boring Spacers
Design complete
1 of 2 borings under I-25 complete
1/2 mile of new duct bank—under I-25
Colorado Boring to complete second bor-
ings under I-25
Trenching along I-25 to Ɵe in exisƟng
vaults
Affected Area: East Vine West Bound
Schedule
June 2015 July 2015 August 2015 November 2015
Design
Tie into exisƟng vaults Project Complete
Colorado Boring
I-25 Trenching
ConstrucƟon Budget
Total Contract Values $315,000.
Work Complete $78,750.
Project 25% Complete
41
HARMONY SUBSTATION SECURITY WALL
June 2015
April
2015
May
2015
June
2015
July
2015
August
2015
September
2015
Design
Permiƫng
ConstrucƟon
Major Design Elements Upcoming Work
Installation of pump station
foundation piers.mp
Dixon Creek Substation completed Site Map
security wall
Increased measure of physical security
Enhanced aestheƟcs of substaƟon property
12 foot high x 1471.9 linear feet block fence
Two 20’ gates constructed of steel and one 4’
man gate
AutomaƟc gate opener installed on main gate
with keypad for secure entrance and exit.
Complete construcƟon contracts
Complete construcƟon schedule
Complete planning process
Install silt fence (BMP)
Install temporary fence
Drill Piers for wall
Set and grout columns
Harmony Substation Site
Schedule
ConstrucƟon Budget
Total Contract Values: $720,819
Expenditures thru June 24: $18,399
Project: 3% Complete
42
TIMBERLINE SUBSTATION SECURITY BEAMS AND CAMERAS
June 2015
Jan 2015 Feb 2015 Mar 2015 April 2015
2015
May June 2015 July 2015
Design
ConstrucƟon
Major Design Elements Upcoming Work
Installation of pump station
foundation piers.mp
Camera InstallaƟons Site Map
Increased measure of substaƟon security
Infrared beam foundaƟon layout
InstallaƟon of 2nd PTZ camera
Complete wiring and control diagrams
Perimeter beams are in operaƟon
Mount camera and pull fiber
Check out camera controls
Timberline SubstaƟon Site
Schedule
Design/ConstrucƟon Budget
Approx. Total Contract Values $25,000
Expenditures thru May 28 $18,000
Project 85 % Complete
43
Legend:
On Track to be completed on or before targeted completion date.
Caution in completing the project on time.
Warning/Off Track in completing the project on time.
COMPLETE: Project or task is complete.
44
NATURAL AREAS LAND CONSERVATION
2015 - 2nd Quarter Report
Land Conservation Update - June 2015 Acreage Cost
Land Conserved - Jan - Mar 22.57 $ 416,474
Land Conserved - Apr - Jun - $ -
Land Conserved - Jul - Sept - $ -
Land Conserved - Oct - Dec - $ -
Total Land Conserved - Year to Date 22.57 $ 416,474
Land Conservation Summary - To Date Acreage Cost
Acres of Land Purchased 35,026
Acres of Land Leased 893
Acres of Land Placed in Conservation Easements 5,816
Total Conserved - To Date 41,736 $ 81,260,437
Land Conservation Funds Budgeted for 2015* $ 8,855,120
* Includes prior year reserves and unanticipated revenues.
Acquisitions To Date - 2015 Acreage Cost
Kingfisher NA - Schneider Property in partner with Streets, Utilities and Forestry - 24 Total
Acres 8.31 $ 146,330
Magpie Meander NA - Jensen Property 6.76 $ 270,144
Redwing Marsh - North Marketplace donation 7.50 $ -
Total Conserved - Year to Date 22.57 $ 416,474
Property Under Contract Acreage Cost
Springer - Fisher 7.82 $ 510,441
Total Under Contract 7.82 $ 510,441
Net Land Conservation Funds Remaining for 2015 $ 7,928,205
45
PUBLIC SAFETY UPDATE
FORT COLLINS POLICE SERVICES
Police investigate a stabbing
Police Services investigated a stabbing of a transient male in Library Park located at 400
Peterson. The victim was able to identify a suspect by street name only and is another transient
who was in the area. The victim survived the attack and the investigation continues.
DUI Checkpoint enforcement
On June 6, 2015, Police Services in conjunction with the Larimer County DUI Task Force
conducted a DUI sobriety checkpoint. The effort was part of the “Drive Sober or Get Pulled
Over” campaign statewide. The checkpoint had 822 vehicles pass through and resulted in 9
arrests.
Police raise awareness about stolen vehicles and items stolen from vehicles
Fort Collins has seen an increase in stolen motor vehicles as well as items stolen from inside
those vehicles. This includes firearms that were left unsecured inside a vehicle. Many of the
vehicles stolen were unlocked. Police Services sent out awareness information and urged citizens
to lock up there vehicles and to not leave valuables unsecured and out in the open. This invites
thieves to steal these items.
Police Officer FTO Graduation.
Fort Collins police welcomed three new officers to the ranks. These officers completed a 15
week intensive field training program and began their careers as Fort Collins Police Officers.
First Female Fort Collins Police Motor Officer
Sergeant Sara Lynd became the first female Fort Collins Officer to be certified as a motorcycle
officer. Sgt. Lynd will be taking over supervision of the Traffic Enforcement Unit in November
and part of her duties is to supervise the motor unit. The motorcycle qualification course is not
for the faint of heart and is a huge accomplishment.
Police Services Awards Ceremony
June is when Fort Collins Police pauses acknowledge and present awards and medals to several
individuals and teams for outstanding achievements over the past year. Among those awards
Police Services presented a medal to Dispatcher Tracy Staruck who is the first civilian employee
in the history of Fort Collins Police to be awarded a medal.
Crime Prevention
This month, the Crime Prevention Specialist had 26 telephone calls that ranged from information
on Crime Free Multi-housing for property managers to working with a senior who feels that she
has been scammed by a contractor. Presentations were done for the children at the United Way
Day care on children’s safety as well as a safety class for the realtors at the Keller-Williams Fort
Collins office.
Here’s the breakdown on activities in June:
46
United Way Day Care, Child Safety, 75 attend
CSU University Village Safety Fair, 175 attend
Keller-Williams, Realtor Safety, 50 attend
Cherry Hills Condos, Neighborhood Watch, 5 attend
Crime Prevention Tip
As you may have read in the news, there have been numerous vehicle trespasses. Many of the
vehicles have been unlocked, and many have valuables such as laptops and firearms in them.
Please don’t offer the opportunities to crooks and take the time to remove valuables from your
vehicles and lock them. Don’t become a victim of crime.
POUDRE FIRE AUTHORITY
Notable Incidents/Items/Events:
PFA Receives Recommendation for Accredited Status - A peer review team representing
the Center for Public Safety Excellence (CPSE) has recently completed a site visit as part of
the Authority’s application for accredited status from the Commission on Fire Accreditation
International (CFAI). The peer team assessed the Authority’s processes including risk-
assessment, strategic planning, response strategies, and adherence to 253 performance
indicators that cover the full-range of fire service operations.
The team notified the Poudre Fire Authority on June 11th, 2015 that they are making a
recommendation for accredited status for the Poudre Fire Authority. The Poudre Fire
Authority will now appear before the Commission on Fire Accreditation International
(CFAI) on August 27th, 2015 in Atlanta, GA as the final step in granting accredited status to
the Authority.
Fire Chief Tom DeMint stated that the agency’s achievement of this milestone, on its way to
Accredited Agency status, “demonstrates the PFA’s drive for continuous organizational
improvement and accountability to the citizens we serve.”
47
More information regarding the Center for Public Safety Excellence, Inc., and the
Commission of Fire Accreditation International, Inc. can be found at
http://www.publicsafetyexcellence.org.
Poudre River Assist- Firefighters were training on swift water rescue the afternoon of June
4
th
when a 911 call reported two men had fallen off inner-tubes they were riding and were in
the Cache la Poudre River at Picnic Rock. As firefighters rushed to the scene they were
informed the men had made it safely to the opposite side and were out of the river. Once
crews arrived on scene they confirmed there were three men in the party; one made it safely
to the parking lot; however the two others were unhurt and still on the opposite side of the
river.
Crews were able to set up a rescue boat and rope system along with deploying seven rescue
swimmers to the opposite shore. They made contact with the men then assisted them with
donning personal floatation devices and helmets for the return trip. The men were placed
into the boat and safely ferried back across the river.
Poudre Fire Authority would like to remind citizens to please take the utmost caution when
recreating on our local waterways.
Assisting Agencies: City of Fort Collins-911; Poudre Valley Hospital Emergency Services
and Special Operations Response Team.
Fire Camp- PFA hosted the third Fire Camp for high school students over three days in
June. The students, selected by members of the Recruitment Committee were able to get
a first-hand look at what it takes to be a firefighter. Physical fitness, hose work, self-
contained breathing apparatus drills, rappelling and more were experienced. The young
48
men and women were very excited to participate and even had a short graduation
ceremony.
Whole Foods Market Community Pancake Breakfast Fundraiser- PFA was honored
to participate with Whole Foods Market for this fun event. Proceeds go to the PFA Fire
Safety Education Fund, administered by the Community Foundation of Northern
Colorado. This money is used to purchase smoke alarms and carbon monoxide alarms
for customers in our district who cannot afford them; plus educational materials and child
car seat supplies.
Fire Academy Graduates- Five new PFA firefighters graduated from the Front Range
Fire Academy on June 6
th
after sixteen weeks of training. The graduates went onto two
additional weeks of in-house training prior to being placed on shift. We welcome our
new firefighters.
Fireworks Campaign- As part of the city fireworks campaign committee, PFA has also
been trying to get the message out that ALL fireworks are illegal. Most front-line
apparatus and staff cars have been outfitted with a mix of decals to encourage citizens not
to use fireworks. Information has also been disseminated through many channels
including social media. Additionally patrols with PFA and FCPS teams have been
scheduled in order to handle complaints received during peak usage times.
Incident Statistics (by category)
Report Period: June 2015 Total Property Loss
Fires 25 $ 16,575
Overpressure/rupture, explosion-no fire 4
Rescue / EMS 1,184
Hazardous Condition - no fire 59
Service Call 79
Good Intent Call 166
False Alarms / False Calls 113
Severe Weather & Natural Disaster 2
Special Incident Type 2
Total = 1,634
49
YEAR-TO-DATE 2015 Total Property Loss
Fires 173 $ 2,301,797
Overpressure/rupture, explosion-no fire 9
Rescue / EMS 6,884
Hazardous Condition - no fire 214
Service Call 375
Good Intent Call 925
False Alarms / False Calls 607
Severe Weather & Natural Disaster 2
Special Incident Type 13
Total = 9,202
Comparison: June 2014 Total Property Loss
Fires 32 $ 415,050
Overpressure/rupture, explosion-no fire 1
Rescue / EMS 1,143
Hazardous Condition - no fire 25
Service Call 97
Good Intent Call 121
False Alarms / False Calls 88
Severe Weather & Natural Disaster 0
Special Incident Type 1
Total = 1,508
Comparison: YEAR-TO-DATE 2014 Total Property Loss
Fires 172 $ 1,527,112
Overpressure/rupture, explosion-no fire 5
Rescue / EMS 6,332
Hazardous Condition - no fire 159
Service Call 378
Good Intent Call 636
False Alarms / False Calls 574
Severe Weather & Natural Disaster 0
Special Incident Type 18
Total = 8,274
*Information subject to change due to updated data.
50
BUILDING & PLANNING ACTIVITY
June 2015
2014 YTD 2015 YTD % Change
Development Project Submittals Received 189 179 -5 %
Conceptual/Staff Reviews Performed 120 101 -16 %
Building Permits Issued 3,154 4,758 +51 %
Building Permit Valuations ($M) $282.4 $262.6 -7 %
Building Inspections Performed 16,944 16,386 -3 %
Plan Reviews Performed 1,272 1,221 -4 %
Overall development review revenues are $407,052 over projection for 2015 as of June 30th. General Fund revenues are
$376,990 over projection; however, Engineering Development Review revenues are under projection $30,063.
Development Projects of Note Status/Updates
CSU Parking Lot at Research
Boulevard
Approved and under construction.
CSU Medical Center Will be reviewed as a Site Plan Advisory Review and a
formal submittal is anticipated for August.
Downtown Plan First phase (issues identification) is complete. Walking
tours scheduled for July 9
th
and 10
th
, followed by a
visioning event on July 13
th
at the Lincoln Center from
6-8pm.
Downtown Hotel Proposal underway for a 164-room hotel and 2 parking
lot options. The Project Development Plan was
submitted on June 23
rd
; any revision will be reviewed
by July 21
st
; the Planning and Zoning Board will
review this project on September 10
th
.
Foothills Mall Redevelopment Under construction; construction meetings continue
weekly with City Staff and developer.
Landmark Residences on
Mountain Avenue
Approved and awaiting final plans from developer
(anticipated soon).
Lincoln Corridor Plan 10 recommended infrastructure projects; total cost
estimated to be $19.3M; proposals for final design due
July 14
th
; construction to begin mid-July.
51
Mountain Vista Subarea Analysis Follow-up information was requested by City Council
and staff is coordinating this effort.
Nature in the City Design guidelines nearing completion; progress
continues for both 10-minute walk and wildlife
connectivity analyses (tentative September
completion); citizen science bird and butterfly data
collection occurring this summer in partnership with
CSU; NIC is working on collaboration for several
strategic plans and grant initiatives.
Neighborhood Districts Hired new Staff Administrator; amended project
charter; still identifying Neighborhood Advisory
Group; scope of engagement study developing (RFP
for release in July/August); continuing work with
CSU’s Center for Public Deliberation.
Old Town Neighborhood Plan and
Design Guidelines
Phase I of the planning process complete; Phase II is in
progress; public workshop scheduled for July 8
th
.
Design guidelines progressing similarly; first draft
being reviewed by staff and Landmark Preservation
Commission and will go out for public comment later
this summer.
633/639 S. College Ave @ Laurel Construction continuing on schedule.
Smoking Ordinance Expansion
Options
Working with Employee Committee and City
Attorney’s office; developing transition program for
employee; first phase of education and outreach
campaigns continuing.
Social Host Public engagement strategy being developed;
Technical Advisory Committee being identified (1
st
meeting in July); public engagement with community
from August – October; public engagement with
CSU/FRCC September – October; going to City
Council work session in November.
Woodward Campus Construction is moving along smoothly; final
inspections are also continuing as planned.
Young People’s Learning Center Submitted final plans in June.
52
Development Projects Currently Under Appeal:
201 East Elizabeth Street:
The Zoning Board of Appeals decision to uphold the CDNS Director’s decision to approve the 201
East Elizabeth Street building permit application to change the use to a fraternity has received 3
appeals. These appeals are to City Council. The City Clerk’s office has scheduled the appeals to be
heard on July 21, 2015. A site visit also has been scheduled on July 20, 2015. The deadline for City
Council to hear the appeal is August 10, 2015.
53