HomeMy WebLinkAboutReport - Mail Packet - 8/19/2014 - City Managers Update - August 14, 2014August 14, 2014
ISSUES BEFORE COUNCIL
Extension of Temporary Parking Requirements in the Transit Oriented Development District .................... 2
Clydesdale Park Annexation .......................................................................................................................... 2
Naming Natural Area at Woodward .............................................................................................................. 2
Timnath IGA Regarding Cooperation on Annexation, Growth Management and Related Issues ................. 2
Disposable Bags ............................................................................................................................................. 2
Skyview General Improvement District (GID) No. 15 Appropriation........................................................... 3
2014 Bicycle Master Plan Update .................................................................................................................. 3
Midtown in Motion: College Avenue Transportation Study.......................................................................... 3
West Central Area Plan .................................................................................................................................. 4
Setting Public Hearing Dates for 2015-2016 Budget Adoption ..................................................................... 4
Resolution in Support of Larimer County Open Space Tax Renewal............................................................ 4
ECONOMY
Fort Collins Sales and Use Tax ...................................................................................................................... 4
CAPITAL PROJECTS
Citywide Pedestrian Access Project ............................................................................................................... 5
Mulberry Bridge (SH 14) at the Poudre River Enhancements ....................................................................... 6
West Mulberry Bridge Replacement .............................................................................................................. 6
West Prospect Bridge Replacement ............................................................................................................... 7
Arthur Ditch at Mountain Avenue and at Myrtle Street ................................................................................. 7
Arthur Ditch Box Section Replacement ......................................................................................................... 8
Shields Street and Drake Road Intersection Improvements ........................................................................... 8
Timberline Improvements – Prospect To Blackbird ...................................................................................... 9
Horsetooth and Timberline Intersection Improvements ............................................................................... 10
Vine and Shields Roundabout ...................................................................................................................... 10
Kechter and Timberline Right Turn Lanes .................................................................................................. 11
Remington Greenway .................................................................................................................................. 12
State Highway 392 and I-25 Interchange Signs ........................................................................................... 12
North College Improvements – Conifer to Willox....................................................................................... 13
Downtown River District Improvements ..................................................................................................... 13
Spring Creek Overpass................................................................................................................................. 14
Lincoln and Lemay Improvements / Woodward Campus ........................................................................... 14
Utilities Capital Projects ......................................................................................................................... 15-22
COMMUNITY EVENTS ................................................................................................................................ 23
PUBLIC SAFETY UPDATE
Fort Collins Police Services .................................................................................................................... 24-26
Poudre Fire Authority ............................................................................................................................. 26-28
BUILDING ACTIVITY .............................................................................................................................. 29-33
2
ISSUES BEFORE COUNCIL
August 19 Regular Meeting
Extension of Temporary Parking Requirements in the Transit Oriented Development District
The Planning and Zoning Board has requested more time to discuss possible parking
requirements for commercial land uses.
Therefore, the recommendations from the TOD Parking Study which are planned to
replace the temporary parking requirements are not ready for the temporary ordinance’s
expiration on September 13, 2014.
New adoption dates:
o Planning and Zoning Board: September 11, 2014
o City Council: October 7, 2014 (1
st
Reading); October 21, 2014 (2
nd
Reading)
Clydesdale Park Annexation
The purpose of this item is to initiate annexation proceedings for the existing Clydesdale
Park subdivision located east of Interstate 25, south of the intersection of East Mulberry
Street and Carriage Parkway. Clydesdale Park includes 217 single-family residential lots
on approximately 75 acres.
Residents of the Clydesdale Park neighborhood have requested this annexation. In
accordance with State law, the purpose of the Initiating Resolution is to accept the
Annexation Petitions and provide a schedule for upcoming Council hearings. Should the
annexation be initiated, two Council hearings will follow on October 7 and October 21.
The approval of the annexation will enable the neighborhood’s streets, including Carriage
Parkway, to be accepted into the City of Fort Collins' Street Maintenance Program.
Residents have expressed concern that their continued maintenance responsibility for
their existing portion of Carriage Parkway is no longer reasonable if the parkway is
extended and used by future development to the south.
Naming Natural Area at Woodward
The purpose of this item is for Council to review names and potentially choose a name
for the new 31-acre natural area conveyed to the City by Woodward Governor. Council
approval of a name may be required because a personal name is under consideration for
the site.
Timnath IGA Regarding Cooperation on Annexation, Growth Management and Related Issues
A 7th Amendment has been prepared for Council consideration to be heard at the August
19 Hearing.
The amendment updates growth management areas for Timnath and Fort Collins, creates
proposed or potential areas of influence that can be used for joint planning, revenue and
cost sharing, and orderly development along the I-25 corridor.
Disposable Bags
The City Council will consider whether to adopt on Second Reading an ordinance
requiring grocers to charge customers at the check-out register 10 cents for single-use
3
disposable shopping bags (both paper and plastic). At the Council’s July 1 hearing,
Ordinance No. 099, 2014 passed on a 5-2 vote.
Second Reading of the ordinance was postponed to August 19 to allow Council to receive
more input from citizens, including questions received at a public informational meeting
held on July 30, which was attended by 50-60 people.
At the August 19 hearing, an alternative ordinance will also be considered. Copies of the
original ordinance from July 1, as well as the new “Option 2” that was recently drafted,
are available on the website at http://www.fcgov.com/recycling/plasticbags.php.
Skyview General Improvement District (GID) No. 15 Appropriation – First Reading
The purpose of this item is to appropriate funds in the Skyview South GID No. 15 funds
to repave Galaxy Way and Galaxy Court (in the Southwest Enclave Annexation).
The Skyview South GID is funded by approximately 148 homeowners in the Skyview
First and Second filings. Through the Skyview GID mill levy, approximately $25,000 is
collected annually. The balance of the GID Reserve, as of 12/31/13, is $115,080.33. The
City’s estimate for repaving is $100,109 and work is to be performed by City crews.
No cost is incurred to the City of Fort Collins. The paving work will be paid for through
the Skyview South GID No. 15 funds.
August 26 Work Session
2014 Bicycle Master Plan Update
Staff initiated the development of the Bicycle Master Plan in October 2013 and, through
extensive public outreach, has developed initial Plan recommendations to achieve the
Plan Vision and Goals.
“The Bicycle Master Plan envisions Fort Collins as a world-class city for bicycling. It is a
city where people of all ages and abilities have access to a comfortable, safe, and
connected network of bicycle facilities, and where bicycling is an integral part of daily
life and the local cultural experience.”
Staff will provide an overview of the 2014 Bicycle Master Plan process, public outreach
and initial Plan recommendations.
Staff will invite feedback and direction on the Plan recommendations, including the
proposed bicycle network approach and recommended bicycle facility
improvements, bicycle programming recommendations, implementation approach, and
next steps in the planning process.
Midtown in Motion: College Avenue Transportation Study
Draft plans for College Avenue in Midtown (from Harmony Road to Prospect Road) will
be presented. After an extensive planning process, with robust stakeholder and public
input, the project team has developed a draft plan for City Council to review.
The draft plans include improvements to the frontage road system, accommodations for
walking and bicycling within Midtown, traffic flow improvements, and connectivity to
MAX.
The project team will be seeking feedback and direction from City Council prior to
completion, with formal adoption this fall.
4
West Central Area Plan
The update of the 1999 Plan is in full swing with completion of the existing and future
conditions analysis and wrapping up the public outreach associated with crafting a new
vision. The focus now is on developing a refinement of the policy topics and narrowing
down various alternatives.
The segment of Prospect Road between College Avenue and Shields Street is a key
component of the Plan, and range of options are being analyzed on how best to provide
safety for bikes and pedestrians while recognizing that the corridor serves the larger
region.
September 2 Regular Meeting
Setting Public Hearing Dates for 2015-2016 Budget Adoption
City staff members have been working through the Budgeting for Outcomes (BFO)
process to create the 2015-2016 City Manager’s Recommended Budget. For more details
on this process, visit http://www.fcgov.com/bfo.
The August 18 Council Finance Committee meeting and the August 26, 2014 Work
Session will be City Council’s first opportunity to discuss the changes to the BFO process
and the assumptions included in the Recommended Budget.
The City Manager will deliver the Recommended Budget to City Council on August 29.
From there, the Budget evolves from a staff recommendation to Council’s final budget,
making it a reflection of their priorities and those of their constituents. From September
to November, City Council will hear public feedback and make any necessary
adjustments. See the Council Agenda Planning Calendar for specific dates the Budget
will come before Council: http://www.fcgov.com/file-gateway/?id=15&ts=2012-08-
07%2009:57:11.
The final budget will be adopted on October 21 (1st Reading) and November 18 (2nd
Reading).
Resolution in Support of Larimer County Open Space Tax Renewal
The purpose of this item to propose an endorsement of an extension of Larimer County’s
¼ cent sales tax that supports the County’s open space program and that also provides
about ⅓ of the City’s Natural Areas Department revenues.
ECONOMY
FORT COLLINS SALES AND USE TAX COLLECTIONS
June 2014
Sales tax collections increased 7.1%
Use tax collections excluding rebates increased 20.2%
Sales and use tax collections excluding rebates increased 9.5%
2014 YTD
Sales tax collections increased 6.5%
Use tax collections excluding rebates increased 27.2%
Sales and use tax collections excluding rebates increased 9.8%
5
CAPITAL PROJECTS
(new information noted in blue text)
ENGINEERING
CITYWIDE PEDESTRIAN ACCESS PROJECT
Funding Source: KFCG Funds
Estimated Project Budget: $450,000
Status: On Budget, On Schedule
The City of Fort Collins Pedestrian Plan addresses citywide pedestrian needs and is a
data-driven approach based on the importance for safe, sustainable walking within City
limits. It, however, lacks comprehensive condition data for the City’s sidewalk system.
Prior to the beginning of the Pedestrian Needs Assessment project, there was not an
inventory of existing sidewalks or sidewalk deficiencies. This project provides a
complete City sidewalk inventory, identifies sidewalk inadequacies, and identifies
inadequate handicap accessibilities according to Americans with Disabilities Act (ADA)
requirements.
Data collection has been completed with approximately 540 street miles of sidewalk
assessed and inventoried at this time.
37,741 accessible ramps have been identified as acceptable, substandard, or missing in
accordance with the ADA requirements.
Staff has implemented a methodology and analysis program used to prioritize pedestrian
projects. This program takes into account a variety of factors such as, but not limited to,
demand, corridor function, and high priority areas.
o Upcoming project locations scheduled include Jackson, Cherry, Boardwalk,
Lemay.
o Current projects: installation of new ramps at Prospect and Whitcomb as part of
ADA accessibility issue. Sidewalk along Jackson (City Park) is scheduled to
begin the first week in August. Additional projects are currently on hold until
finalization of the new annual concrete maintenance contract.
Staff has identified approximately 21 projects for 2014.
Level of service is being implemented for the sidewalk program and is scheduled for
August 2014.
Prioritization Model is complete and has been posted to the engineering website:
http://www.fcgov.com/engineering/pedneeds.php.
Staff is beginning to collect and update data from projects and developments that
occurred in 2013.
6
MULBERRY BRIDGE (SH 14) AT THE POUDRE RIVER ENHANCEMENTS
Funding Source: City of Fort Collins
Estimate Project Budget: $750,000
Status: On Budget, On Schedule
Colorado Department of Transportation (CDOT)
is replacing the Mulberry Bridge (State Highway
14) over Poudre River Bridge starting in the fall
of 2014. Construction was delayed due to the
September 2013 flood.
Due to the construction, eastbound traffic on
Mulberry will be detoured for the duration of
construction.
The City is working with CDOT to add city-
funded enhancements to the bridge including
decorative railings, landscaping and urban design
features.
WEST MULBERRY BRIDGE REPLACEMENT DESIGN
Funding Source: Colorado Off System Bridge
Program (BRO) Funds and KFCG 2011
Estimated Project Budget: $1.1 million
Status: On Budget, On Schedule
The goal of the project is to replace the existing
structurally deficient bridge with a new bridge
that meets the current standards.
The posted weight limit on this bridge precludes
the passage of emergency vehicles from the
nearby fire station.
In December 2011, the City received a grant for
$700,000 in Colorado Off System Bridge Program
(BRO) funds for some of the construction cost.
Design efforts are underway. Construction is
planned for fall 2014.
7
WEST PROSPECT BRIDGE REPLACEMENT DESIGN
Funding Source: KFCG 2011
Estimated Project Budget: $1.2 million
Status: On Budget, On Schedule
The goal of the project is to replace the existing
structurally deficient bridge with a new bridge
that meets the current standards.
The State of Colorado inspected this bridge in
March 2011 and found significant structural
issues resulting in a temporary plate being
installed and load posting restricted to 15 tons.
City Engineering has awarded the construction
contract to Mountain Constructors.
All sidewalks, bicycle lanes, and driving lanes on
the Prospect/New Mercer bridge were reopened
on May 6, 2014.
The decorative steel railings are being fabricated and will not be available to install until
late July. Decorative rock work will follow the railing installation; the project will be
completed in mid-August 2014.
ARTHUR DITCH AT MOUNTAIN AVENUE AND AT MYRTLE STREET
Funding Source: KFCG Funds
Estimated Project Budget: $975,000
Status: On Budget, On Schedule
The intent of this project is to replace two
structurally deficient bridges with new concrete
box culverts. Both bridges are located on the
Arthur Ditch, within residential areas of the City.
Bridge and roadway construction at both locations
has been completed. Both roadways are open to
the public.
Trolley track reconstruction has also been
completed. All trolley track work was completed
prior to the trolley’s planned summer opening
date.
All work at both sites has been completed.
Additional project information can be found at http://www.fcgov.com/engineering/arthur-
ditch.php.
8
ARTHUR DITCH BOX SECTION REPLACEMENT –
OAK/WHITCOMB, LOOMIS/OLIVE, CANYON AT MULBERRY POOL
Funding Sources: KFCG / Operation Services, Facilities
Estimated Project Budget: $2.5-3 million
Status: On Budget, On Schedule
The intent of this project is to replace three
structurally deficient bridge/box sections with
new concrete box culverts.
Value engineering and best practices are being
applied to develop the most cost efficient
replacement methods. All three locations lie
within local floodplains and will be evaluated
prior to final design approval. Coordination
efforts also include the Streets Department
maintenance schedules to ensure the roadway is
reviewed for both short and long term impacts.
Staff is currently in the process of bringing the
design plans to 95% complete. This is expected to occur in mid-September, followed by
bid advertisement shortly after. Coordination within City departments and outside
companies continues be active.
Floodplain clearances have been approved for construction, and the pertinent floodplain
use permits are being issued.
Staff has sent the current plan sheets to the legal staff of the Arthur Ditch for review and
impending ditch crossing agreement.
Staff continues to perform outreach to adjacent residents to provide additional
information on the project and its schedule as it becomes available.
SHIELDS STREET AND DRAKE ROAD INTERSECTION IMPROVEMENTS
Funding Sources: Federal Hazard Elimination Grant (90%) / Local Match (10%)
Estimated Project Budget: $986,000
Status: On Budget, On Schedule
The main goal of this project is to reduce the
accident rate that occurs at this intersection by
installing dedicated right turn lanes in the north
and southbound movements. A reduced
movement concept is also being considered to the
Raintree Drive/Davidson Road intersection 400
feet south of Shields and Drake.
This project has multiple funding sources:
Federal Hazard Elimination Grant - $887,400
City BOB funding - $98,600
Staff has selected Interwest Consulting Group for
the design of these improvements.
The intersection location has several environmental clearances to complete prior to
moving towards the design stage. However, a draft concept has been developed for
9
illustration purposes and serves as a model while the state and federal hurdles are
completed.
Proposed alignments are currently being reviewed for impacts and cost. Outreach will
begin shortly with adjacent neighbors and property owners.
Other safety components that will be corrected at the intersection include providing
higher visibility for bicyclists by removing right turn movement conflict and installing
ADA compliant ramps.
The City anticipates construction of the intersection to occur in summer 2015.
TIMBERLINE IMPROVEMENTS – PROSPECT TO BLACKBIRD
Funding Source: Building on Basics (BOB)
Estimated Project Budget: $3.5 million
Status: On Budget, On Schedule
The goals of this project are to improve air
quality, reduce vehicle wait time and reduce the
accident rate by constructing a free-right turn and
acceleration lane from eastbound Prospect to
southbound Timberline, as identified in our
Arterial Intersection Prioritization Study.
The 2005 ballot language stated this project will
expand Timberline Road to four (4) lane arterial
standards including:
o travel lanes, sidewalks, bike lanes and
landscaped medians; and
o improvements to the Prospect and Timberline intersection and all its approaches
to add additional turn lanes.
The project will add a sidewalk connection for southbound Timberline from Prospect to
Blackbird.
Additionally, water quality features will be constructed to minimize the flow rates and
volumes as they outlet to the Spring Creek basin.
Construction is expected to begin in the spring of 2016.
A communication plan (public outreach) is being developed and will be implemented
with the final design through construction.
A Historical Report is being finalized for the silos and Johnson family farm house.
The project website is available through the Engineering homepage at
http://www.fcgov.com/engineering/prospect-timberline.php.
10
HORSETOOTH AND TIMBERLINE INTERSECTION IMPROVEMENTS
Funding Source: Building on Basics (BOB) and Federal Grant (CMAQ)
Estimated Project Budget: $3.5 million
Status: On Budget, On Schedule
The goal of this project is to relieve traffic
congestion and vehicle wait time by constructing
additional intersection turn lanes.
The need for these safety and operational
improvements were identified in the Engineering
Department’s recently completed Arterial
Intersection Prioritization Study. Turn lane needs
are as follows:
o right turn lane (southbound Timberline
to westbound Horsetooth);
o right turn lane (eastbound Horsetooth
to southbound Timberline); and
o second left turn lane (northbound and southbound Timberline).
City Staff appropriated the CMAQ funds through Council in February 2013. These funds
were applied for based upon the need for a dedicated, southbound right turn lane.
The project has moved to the final design phase, streetscape visioning and coordination
with property owners for real estate purchases (right-of-way and easements).
Additionally, the project will include median and landscape improvements, sidewalk and
bicycle lane improvements and pavement improvements.
Construction is expected to begin in the spring of 2015.
A communication plan (public outreach) is being developed and will be implemented
with the final design through construction. The project website is available through the
Engineering homepage at http://www.fcgov.com/engineering/horsetooth-timberline.php.
VINE AND SHIELDS ROUNDABOUT
Funding Source: Building on Basics (BOB), Federal Grant (STP Metro) and Regional
Road Impact Fees
Estimated Project Budget: $1.7 million
Status: On Budget, On Schedule
The main goal of this project is to increase
mobility at the intersection via multimodal
transportation improvements. Currently, the east-
west lanes on Vine Drive are not aligned causing
additional independent traffic movements which
effect the overall operation of the signal timing.
The City received a federal grant award for
$1,054,000 through the North Front Range
Metropolitan Planning Organization in the STP-
Metro category.
Other safety concerns which will be corrected at
11
the intersection entail adding sidewalks along the northern portion of the project,
installing ADA compliant ramps/crosswalks and adding bike lanes.
The City continues to coordinate our intersection project with Larimer County’s proposed
improvements to Shields Street from 400’ north of Vine Drive to Willox Lane. The
County received three federal grants for this stretch of roadway to accomplish the
following:
o replace the Shields Street Bridge over the Poudre River;
o improve the Poudre River trailhead parking area and river access; and
o reconstruct approximately one mile of Shields Street.
Construction is expected to begin in the spring of 2015.
A communication plan (public outreach) is being developed and will be implemented
with the final design through construction.
The project website is available through the Engineering homepage at
http://www.fcgov.com/engineering/vsi.php.
KECHTER AND TIMBERLINE RIGHT TURN LANES
Funding Source: Building on Basics (BOB)
Estimated Project Budget: $725,000
Status: On Budget, On Schedule
The goal of this project is to relieve traffic
congestion and vehicle wait time by constructing
two dedicated right turn lanes along southbound
and northbound Timberline Road.
The need for the northbound turn lane
improvement was identified in the Engineering
Department’s recently completed Arterial
Intersection Prioritization Study. The need for the
southbound turn lane improvement was triggered
by the proposed traffic impacts for the Crowne on
Timberline development. The developer funds
were appropriated into the Capital Project so the two turn lanes could be designed and
built as one package.
The proposed improvements will reduce the peak hour delay by 15%.
The project will include an interim, detached sidewalk along Timberline Road, with
accessible curb ramps being installed on the northeast and southeast corners.
The City will purchase the ultimate right-of-way from the southeast corner property
owner to accommodate the future four-lane Timberline section.
Construction began in July and is expected to be complete in early September.
A communication plan (public outreach) is being developed and will be implemented
with the final design through construction,
The project website is available through the Engineering homepage at
http://www.fcgov.com/engineering/kechter-timberline.php.
12
REMINGTON GREENWAY
Funding Source: FC Moves Funding
Estimated Project Budget: $450,000
Status: On Budget, On Schedule
The goal of this pilot project is to offer flexibility
in street design to calm traffic, support active
modes of transportation and integrate stormwater
management strategies.
The conceptual design calls for buffered bike
lanes, removal of the traffic signals between
Prospect and Mulberry, and the construction of a
mini-roundabout with curb bulb outs at
Remington and Laurel.
Future phases would add more bulb outs at
strategic locations to shorten the pedestrian
crosswalk lengths.
Construction is expected to begin in the spring of
2015.
A communication plan (public outreach) is being developed and will be implemented
with the final design through construction.
The project website is available at
http://www.fcgov.com/advanceplanning/remingtongreenway.php.
SH 392 AND I-25 INTERCHANGE SIGNS
Estimated Project Budget: $300,000
Status: On Budget, On Schedule
The goal of this project is to construct welcoming
and aesthetically pleasing signs for traffic entering
the City of Fort Collins and the Town of Windsor
along SH 392.
The City has pursued a number of potential sign
locations. It was determined that the medians will
be the best location for the signs.
The City is partnering with the Town of Windsor
for the design and construction of the signs.
Design is currently underway, with construction
expected to take place in fall 2014/spring 2015.
13
NORTH COLLEGE IMPROVEMENTS – CONIFER TO WILLOX
Funding Source: Federal Grants, Local Matching Funds
Estimate Project Budget: $12 million
Status: On Budget, On Schedule
The intent of this project is to design and
construct improvements along North College
Avenue from the Conifer/Hickory intersection to
Willox Lane, bringing this section of North
College up to four-lane arterial standards as
defined by the Larimer County Urban Area Street
Standards. Both medians and sections of the
planned rear access roads are included in the
project.
The overall project budget is $12 million. This is
comprised of roughly 60% federal funds and 40%
local funds.
Pre-project utility relocations began in early June 2014, with an expected completion date
of September 2014.
Construction of a rear access road west of North College began in late-July 2014. The
expected completion date of this project is late-September 2014.
The planned improvements for North College Avenue are currently out to bid. Bids will
be opened in late-August 2014. Construction is anticipated to begin shortly thereafter.
Additional project information is available at
http://www.fcgov.com/engineering/ncollege.php.
DOWNTOWN RIVER DISTRICT IMPROVEMENTS
Funding Source: Federal Grants, Local Funds, DDA Funds
Estimate Project Budget: $1.48 million
Status: On Budget, On Schedule
The goal of this project is to develop a consulting
contract capable of providing engineering services
and subsequent construction projects for various
improvements within the Downtown River
District.
The project will also have the capability to
provide various engineering services in
preparation of anticipated development.
The first two projects to be addressed are
developing an implementation plan for
improvements along Jefferson Street between
College Avenue and the Mountain/Lincoln
intersection based on the available budget, and to develop a conceptual design for
improvements along Willow Street.
14
Additional projects to follow include the development of engineering plans and
specifications, as well as construction of these improvements along both Jefferson and
Willow based on the results of the above.
An intergovernmental agreement between the City and the Downtown Development
Authority was finalized allowing design work to begin on the Willow Street
Improvements Project.
Design work on the Jefferson Street and Willow Street projects has begun.
SPRING CREEK (NRRC) OVERPASS
Funding Source: Federal Congestion Mitigation and
Air Quality (CMAQ) Grant and Building on Basics
(BOB) Funds
Estimated Project Budget: $2.75 million
Status: On Budget, On Schedule
The goal of the project is to construct a new
pedestrian/bike overpass that will link the Mason
Bike Trail and the federal campus on the west side
of the railroad tracks to the Mason Corridor Bus
Rapid Transit MAX station on the east side of the
tracks.
An additional phase of construction will add stairs
to the structure.
LINCOLN AND LEMAY IMROVEMENTS / WOODWARD CAMPUS
Funding Sources: City of Fort Collins General Fund, Intersection
Improvement Fund
Estimated Project Budget: $2.1-2.3 million
Status: On Budget, On Schedule
This project has several goals. The first is to install three new points of access/turn lanes
to the Woodward Campus, two on Lemay, and one on Lincoln. The project will also
complete the improvements along the west side of Lemay between Lincoln and
Mulberry. This includes completion of the Magnolia intersection to a full movement
location along with curb, gutter and sidewalk for the entire length. An interim sidewalk
will also be constructed along the Lincoln front that connects pedestrians to the Poudre
River bridge on Lincoln and into downtown. Lastly, a double left turn configuration will
be installed on southbound Lemay to eastbound Mulberry for as a result of anticipated
traffic volumes for this area.
The City and Mortenson Construction have partnered to identify and employ best
practices regarding communication, safety and general project information to the local
businesses and nearby neighborhoods.
Utility work for the site has commenced.
The roadway improvement slated for Lincoln and Lemay will be open for bid mid-
August.
15
UTILITIES
COLLEGE AVENUE WATER LINE REPLACEMENT
Project Description: In anticipation of CDOT paving
in 2015, this project will replace the existing 4” cast
iron waterline in College Avenue from Mulberry to
Buckeye.
Project Status: Construction phase and public
outreach continues.
Anticipated Completion Date: This project is
planned to start May 5 and be completed by mid-
August.
Ahead/Behind/or on Schedule: On Schedule
Total Project Budget: $2.5 million
Budget Status: Project is within budget.
Highlights:
All work is complete between Mulberry and
Laurel and College Avenue is open to traffic in
this section.
The new 8 inch PVC line is in service from Mulberry to Locust.
Replacement of the sewer and waterlines in Laurel across College are nearly complete.
Barricades in College south of Laurel have been placed as the next section of waterline
replacement in College south to Elizabeth begins.
Public outreach continues on multiple fronts.
WEST VINE BASIN OUTFALL CHANNEL
Project Description: This is a joint project between
the City and Larimer County to design and construct a
stormwater outfall channel for the West Vine Basin to
the Poudre River. The project is being coordinated
with Larimer County’s widening of Shields Street
from the Arthur Ditch to Willox.
Project Status: Construction is underway.
Excavation and hauling is approximately 100%
complete. Drop Structures have been installed. Final
grading and landscaping to be complete by
September.
Anticipated Completion Date: Fall 2014
Ahead/Behind/or on Schedule: On Schedule
Total Project Budget: Alternatives Analysis Phase: $104,000; Final Design: $243,000;
Total Project Cost: $2.8 million
Budget Status: Project is within budget.
Highlights:
Poudre River Trail is open.
Final grading and landscaping ongoing.
16
GRANDVIEW AVENUE VALVES REPLACEMENT PROJECT
Project Description: Decommissioning of Utilities’ 20 inch water transmission main between
Tarragon Lane and Grandview Avenue, and the removal of the existing valve vault in LaPorte
Avenue at Grandview Avenue. The project involves removing services and distribution lines
from the 20 inch steel line and tapping them into
other nearby mains. There will also be a 12 inch
HDPE sliplining at Lilac Apartments. The valve
vault in LaPorte Avenue at Grandview will be taken
out of service. This will remove four 90-year-old
inoperative valves from the distribution system.
Three new 20 inch butterfly valves and new valve
vaults will replace the old obsolete valve system.
The 20 inch cast iron main will then be cut, drained
and flash-filled. Work scheduled to precede
repaving of LaPorte Avenue by Streets from Shields
Street to LaPorte Avenue in August 2014.
Project Status: Sliplining at Lilac Apartments
complete. Taft Hill Road portion of the work is
complete. New valves at Grandview installed. Old
valve vault at Grandview demolished. New pipe at Grandview. Manholes under construction.
Anticipated Completion Date: Work to be completed by August 2014.
Ahead/Behind/or on Schedule: Construction started May 27, 2014 (on schedule).
Total Project Budget: Design and Valve Procurement: $750,000
Budget Status: Project is within budget.
Highlights:
90-year-old valve vault containing 4 inoperative 20 inch valves to be abandoned.
3 new 20 inch butterfly valves and valve vaults to be installed.
BOXELDER CREEK OUTFALL IMPROVEMENTS
Project Description: Large regional flood control
project to be designed and constructed under
Intergovernmental Agreements with Timnath
Development Authority and Boxelder Basin
Stormwater Authority. Project involves channel
grading and road crossing improvements from I-25 to
the Poudre River along the Boxelder Creek Corridor.
Project Status: Preliminary design complete.
Environmental assessment has been filed with
Colorado Division of Wildlife. CLOMR submittal in
preparation.
Final Design and Permitting Requirements: May
2014 – April 2015
Anticipated Completion Date: December 30, 2016
On Schedule: On Schedule
Total Project Budget: $4.1 million
17
Budget Status: IGA with Timnath completed.
Highlights:
Preliminary design complete.
Design of Siphon at Lake Canal underway.
Project under final design.
Project construction schedule subject to delay due to delay in the construction of the
Mulberry Bridge Replacement Project by CDOT and the proposed detour route for trucks
on East Prospect.
CATHODIC PROTECTION OF WATER TREATMENT FACILITY AND
TRANSMISSION AND DISTRIBUTION SYSTEM WATER LINES
Project Description: Investigation of existing systems in place used to protect waterlines from
corrosion, design of rehabilitation of existing and new
systems to prevent corrosion, and construction of
modified and new systems.
Project Status: On Schedule
Anticipated Completion Date: This is an ongoing
project.
Ahead/Behind/or on Schedule: On Schedule
Total Project Budget: $304,000 (2014)
Budget Status: Within Budget
Highlights:
Working with consultant and contractor on
testing current cathodic protection levels and
locations, and installing modified and new
systems where needed.
Reviewing projects and work status for 2014
with consultant and contractor to create schedule and work orders.
Working at the Water Treatment Facility (WTF) on the new yard piping project to
include and update cathodic protection of the new piping, then connect into rectifiers.
Working with Cathodic Protection consultant to study integrity and continuity of 60”
PCCP transmission main from WTF to intersection of Overland Trail and Lake Street.
Working with contractor on recommendations for repairs and modifications to cathodic
protection on the 60” PCCP transmission main and at the WTF.
Working with contractor to install new test station on the 60” PCCP transmission main
this fall 2014.
18
STREAM REHABILITATION AND ENHANCEMENT PROGRAM
Project Description: Stream rehabilitation and habitat enhancement across City including
stabilizing stream channel morphology,
rehabilitating/creating new native in-stream and
riparian habitat to attract and support native fish and
wildlife populations, and promote BMPs to improve
water quality. First watershed in program is Fossil
and Mail Creek.
Project Status: Working with consultant on design
and environmental permitting.
Anticipated Completion Date: Construction of first
project, Fossil Creek reach upstream of Lemay, to
begin fall of 2014.
Ahead/Behind/or on Schedule: On schedule
Total Project Budget: $1.2 million
Budget Status: Within Budget
Highlights:
Centennial Archaeology conducted a Limited Results Cultural Resource Survey which
was requested by the Corps of Engineers.
Received nationwide permit from Corps of Engineers.
Reviewing requirements for groundwater permit with CDPHE.
Received groundwater permit from CDPHE.
Working with team on costs and schedule for construction.
Working with PR on website.
On track for Fossil Creek segment construction to begin this fall.
Independent Cost Estimate reconciliation complete.
Preparing contractor work order contract documents as well as consulting engineer
resident engineering contract.
RIGDEN MUNICIPAL STORAGE POND
Project Description: The project will consist of the construction of a gravel pit water storage
reservoir to include a pump station and associated
piping. The project is located northeast of the Ziegler
Road and Horsetooth Road intersection. Purpose of
the storage is to retime flows to meet water rights
return flow obligations and meet augmentation
requirements. Project is a cooperative effort with
Natural Areas and Parks.
Project Status: Under Construction
Anticipated Completion Date: Design complete in
2013; construction in 2014.
Ahead/Behind/or on Schedule: On Schedule
Total Project Design Budget: $457,782
Total Project Construction Budget: $10.6 million
Budget Status: Within Budget
19
Highlights:
The earthwork contractor has removed 1,000,000 cubic yards of material or
approximately half of what will be removed.
Installation of the pump station electrical components continues.
The piping contractor has completed the installation of the inlet and outlet piping except
for the tie-in to the diversion structures.
Pressure testing of the pipelines is scheduled for July 31.
WATER TREATMENT FACILITY YARD PIPING MODIFICATIONS
Project Description: Design and construction of a new 48 inch diameter steel raw water
pipeline to replace the aged 30 and 36 inch Horsetooth raw water pipelines, and a new 36 inch
diameter steel backwash pump station influent line to
replace the existing cast iron pipeline. Both of these
pipelines have shown damage due to electrolysis.
The existing finished water backwash influent line is
also located under an existing sludge drying pond,
increasing the possibility of cross contamination, so it
will be abandoned.
Project Status: Kicked off design May 2013.
Construction began in October 2013.
Anticipated Completion Date: Planned for fall
2014.
Ahead/Behind/or on Schedule: On schedule.
Project suspended until October when water demand
goes down to complete Horsetooth Raw Water lines.
Total Project Budget: $2.3 million
Budget Status: On Budget
Highlights:
Placed asphalt base course on roadway where pipe is installed.
Rotated valve operators on 36” and 42” Butterfly valves.
Finished air valve construction at new 24” / 27” connection.
Performed final grading at the new Meter Vault and air valve.
Final graded backfill at 36” Backwash Pump Station feed.
Finished cleanup and final punch list items for work completed.
Removed existing Valve Vault #1 and hauled away debris.
Plugged existing 20”, 36”, 27” and 24” pipelines @ Valve Vault #1 with concrete.
Finished 60” pipeline blowoff structure.
Worked on Punch List items.
20
PLUM STREET SANITARY SEWER IMPROVEMENTS
Project Description: Design and construction of a replacement sanitary sewer system that
currently lies in Shields Street, Plum Street between Shields and City Park Avenue and City Park
Avenue. This sewer is in very poor condition and will
soon be undersized as new development occurs in the
immediate vicinity.
Project Status: Project complete except closeout.
Anticipated Completion Date: Project complete
except closeout.
Ahead/Behind/or on Schedule: Project complete
except closeout.
Total Project Budget: $1 million
Budget Status: On Budget
Highlights:
Asphalt patched Plum Street and City Park
Avenue with base course.
Completed Punch List items.
All pipelaying and restoration complete.
WATER TREATMENT FACILITY – 2014 MASTERPLAN UPDATE
Project Description: Fort Collins Utilities currently has two planning documents: the 2007
Water Treatment Facility Electrical Master Plan
(EMP) and the 2010 Water Treatment Facilities
Master Plan. This document will update the Water
Treatment Facilities Master Plan and incorporate the
EMP.
Project Status: Issued Request for Proposal in
December 2013.
Anticipated Completion Date: Master Plan to be
completed by December 2014.
Ahead/Behind/or on Schedule: On Schedule
Total Project Budget: $350,000
Budget Status: On Budget
Highlights:
Due to the resignation of current Water
Production Manager, work on Water
Treatment Facility – 2014 Master Plan Update has been suspended until new Water
Production Manager is hired.
21
WATER TREATMENT FACILITY STORMWATER CONTAINMENT BERMS
Project Description: Design and construction of a
system of swales and berms around the existing
solids drying beds to protect them from spilling in a
100-year rain event.
Project Status: City Stormwater Division portion of
design kicked off March 2013. Ayres Associates
portion of design started March 2014, complete June
2014. Construction began in July 2014.
Anticipated Completion Date: Substantial
completion scheduled for October 2014.
Ahead/Behind/or on Schedule: On Schedule
Total Project Budget: $300,000
Budget Status: On Budget
Highlights:
City Stormwater engineering completed
design criteria.
Ayres Associates contracted to perform civil design.
Hydro Construction contracted to construct improvements.
Construction begins in July 2014 with completion scheduled for early October 2014.
South swale excavation started, with concrete crossing pan constructed.
DRAKE WATER RECLAMATION FACILITY SOUTH PROCESS TRAIN
IMPROVEMENTS
Project Description: The project will consist of the demolition of a portion of the existing
process train, construction of new tanks for the new
biological nutrient removal process, upgrading the
south aeration system, and replacement of old
mechanical and electrical systems.
Project Status: Design in progress.
Site Application submitted to the State.
Anticipated Completion Date: December 2015
Ahead/Behind/or on Schedule: On Schedule
Total Project Design Budget: $1.2 million
Total Project Construction Budget: $7.7 million
Budget Status: Within Budget
Highlights:
Process Design Report submitted to CDPHE.
Value Engineering in progress.
22
DRAKE WATER RECLAMATION DIGESTER LID DEMOLITION
Project Description: The project consists of the demolition of failed anaerobic digester lid 611
in preparation for replacement of the lid.
Project Status: Construction is 95% complete.
Anticipated Completion Date: June 2014
Ahead/Behind/or on Schedule: 30 days behind due to weather issues.
Total Project Design Budget: $25,000
Total Project Construction Budget: $210,000
Budget Status: Within Budget
Highlights:
Digester Lid completely removed. Site cleanup in progress.
NORTHEAST COLLEGE CORRIDOR OUTFALL PROJECT (NECCO) PHASE 3
Project Description: Analysis, feasibility, design, and construction of storm drainage outfall for
the Lower Dry Creek Basin east of North College and south of the Larimer and Weld Canal,
particularly a regional detention pond just north of
East Vine Drive and culverts to convey flows and
provide an outfall under East Vine Drive and the
BNSF along Dry Creek to create connectivity for flow
conveyance and drainage for Dry Creek.
Project Status: Currently in design and feasibility.
Anticipated Completion Date: December 2015.
Ahead/Behind/or on Schedule: On Schedule
Total Project Budget: $1 million (2014)
Budget Status: Within Budget
Highlights:
Working with consultant on design and
alternatives, as well as scheduling CLOMR
preparation and permitting with BNSF and
Corps of Engineers.
Working with ROW to begin discussions on purchasing land for regional pond and
easements for conveyance pipes and channels.
Met with BNSF Roadmaster to discuss permit submittal to bore stormwater pipes under
BNSF tracks.
Met with Corps of Engineers to discuss criteria for obtaining a nationwide permit for the
project.
23
COMMUNITY EVENTS
Red Rock Tour
Location: Edora Pool Ice Center
Date/Time: Tuesday, August 19, 2014 9:30 AM
Details: Red Rocks Amphitheater is a geological phenomenon - the only naturally occurring,
acoustically perfect amphitheater in the world. This tour will feature interactive
educational displays featuring the geologic and music history of Red Rocks. We'll also
learn about the geology, wildlife, and history of the surrounding park.
$45/Member Price $40.
Note: Fee includes transportation, lunch, tour, and escort. Lunch at the beautiful Ship
Rock Grille inside Red Rocks.
Contact Information: Recreation
Phone: (970) 221-6655; Email address: recreation@fcgov.com
She Groovez in the Backyard
Location: Senior Center, 1200 Raintree Drive
Date/Time: Sunday, August 31, 2014 7:00 PM
Details: She Groovez is a female Rhythm and Blues band that rocks the music of the 70’s. They
are so much fun when they are belting out "Funky Music, Fire and Good Times" that the
whole audience feels like they stepped into a time machine. Who Grooves? You will at
this concert. $20 at the door/$15 pre-sale.
Note: This is an outdoor concert. Popcorn and a cash bar will be available.
Contact Information: Recreation
Phone: (970) 221-6655; Email address: recreation@fcgov.com
Pooch Plunge
Location: City Park Pool
Date/Time: Monday, September 1, 2014 4:00 PM
Details: It’s canine time at City Park Pool! Each pooch can bring two human friends (no
swimming with your four-legged friends, please). Bid on the Silent Auction items while
you are there, Fido deserves it!
Tickets go on sale beginning August 1. $5
Contact Information: Recreation
Phone: (970) 221-6655; E-mail address: recreation@fcgov.com
To view the full calendar of events, visit http://www.fcgov.com/events/
24
PUBLIC SAFETY UPDATE
FORT COLLINS POLICE SERVICES
Coffee with the Chief
The Coffee with Chief Hutto monthly community outreach activity was held July 24 at Everyday
Joe’s Coffee House, 144 S. Mason Street. The next event will be held on August 28 from
9–10 a.m. at Café Ole, 646 S. College Avenue.
Community Awareness Program (CAP) Training
Nine people attended the free Community Awareness Training offered on July 24 by Fort Collins
Police. The CAP was created by the Counterterrorism Education Learning Lab (CELL), a non-
profit, nonpartisan institution, which is dedicated to the prevention of terrorism through
education, empowerment and engagement. The CAP is an award-winning interactive course
taught by members of the local public safety community. It provides citizens with the basic tools
needed to recognize and help prevent criminal activity and terrorism in the United States while
preserving civil liberties protected by the U.S. Constitution.
Murder-Suicide
Fort Collins police responded to a double shooting on July 24 in the 6300 block of Thompson
Drive. The Larimer County Coroner identified the shooting victims and the manner of death as
Gene Kapperman, age 73, suicide, and Brandon Kapperman, age 26, homicide. Both men
resided in Fort Collins, Colorado.
Police Explorers Earn Awards
Members of the Fort Collins Police Explorer Post recently attended the Regional Law
Enforcement Explorer Conference in Gunnison, Colorado and earned the following awards:
Troy VanDress - 1st place in Death Investigations
Christina Bartlett - 5th place in Death Investigations
Allison Weber - 5th place in Passive Resistance DT
RJ Tuttle - 5th place in Traffic Stops
Fort Collins Explorers, ages 16–21, volunteer their time to learn about the field of law
enforcement. For many, this is an opportunity to acquaint themselves with the field of law
enforcement as a future career choice. Explorers receive a variety of training and often assist
police personnel with traffic control and other non-enforcement functions.
Missing Endangered Adult Located
Fort Collins police and the community searched for 64-year-old George Gosden who suffered
from dementia and wandered away from his home on July 5. After 10 days of extensive
searches, the Larimer County Sheriff’s Office received a report of a deceased male found by a
citizen in a field in the 6100 block of Zeigler Road in unincorporated Larimer County. The
County Coroner identified the decedent as George Gosden and ruled his death accidental. This
was a sad outcome to a tragic event.
25
Fatal Motor Vehicle Collision
Police responded to a fatal traffic crash July 23 at the intersection of N. Timberline Road and
Mountain Vista Drive involving a pickup truck and an Infiniti sedan. The driver of the Infiniti
turned westbound onto Mountain Vista Drive in front of an approaching pickup and the vehicles
collided. The 70-year-old driver of the Infiniti sedan was transported to the hospital where she
later died.
Unfounded Bomb Calls
Several 7-11 stores in Fort Collins and others along the Front Range received unfounded bomb
reports on July 28. This is part of a nationwide scam where an unidentified caller reports a bomb
in the store, threatens to detonate it unless the clerk loads money on reloadable, prepaid cards,
and provides the card number to the caller. The calls were all unfounded. The FBI is
investigating.
Another Phone Scam
The Sheriff reports a new phone scam is circulating in Larimer County designed to extort and
defraud residents by claiming they owe money for back taxes or unpaid service bills. The callers
identify themselves as government officials, often from the IRS or a public utility, and demand
payment of back taxes or unpaid service bills. They aggressively argue that if payment is not
made immediately, the police will be dispatched to arrest or physically harm them. Additional
information and guidance on what to do if you receive a call can be found at
larimer.org/news/newsDetail.cfm?id=2553.
Crime Trends
There is a disturbing upward trend occurring with suicide calls. The past 14 months have seen
frequent monthly spikes with no real downward trends. Whether mental health related, substance
abuse related, or any combination of matters, suicide calls have a lasting effect on friends and
family.
26
Crime Prevention
During July, the Crime Prevention Specialist handled 19 telephone calls on a variety of topics.
There were presentations to 378 people which included an informational booth at the Emergency
Preparedness Expo at JAX with members of the police dispatch team, as well as several safety
classes at the Children’s Workshop.
A breakdown of the month’s Crime Prevention activities follows:
• Crystal Lakes Volunteer Fire Department Annual Parade and Safety Fair - 200 attended
• RESTORE - 50 attended
• Restorative Justice Session - 13 attended
• Emergency Preparedness Expo - 50 attended
• Children’s Workshop Safety - 60 attended
Crime Prevention Tip
It’s that time of year again when children are getting ready for school. Please take the time to
show your children the safe route to school and home again. Whether walking, riding a bicycle
or the bus, teach them all of the safety rules. Visit the Safe Kids of Larimer County website for
information: safekidslcc.org.
POUDRE FIRE AUTHORITY
Fire Sprinklers Save Apartment Building
Poudre Fire Authority responded to the report of a kitchen fire the evening of July 14.
Fortunately, when firefighters arrived the fire had already been extinguished by fire sprinklers.
All four occupants were able to escape without harm. The sprinkler system saved not only the
one unit, but the whole building and possibly lives. Fire and smoke damage was very minor and
contained to the kitchen area. Damage estimates are $2,000; over $1 million saved.
Fire investigators determined this was a flash-type fire from cooking with oil on the stovetop.
The heat generated was hot enough to activate the kitchen sprinkler head and one in the living
room.
Assisting agencies: Fort Collins Police Services, Fort Collins 911, and PVH/UC Health
Emergency Services.
27
Large Animal Rescue Program
After months of planning, PFA was able to bring the Large Animal Rescue Program online
July 2, 2014. To our knowledge, PFA is only the second fire department in Colorado to offer
this service. Equipment was procured and training of Fire Station 12 and support company
personnel (ladder trucks) was completed. Prior to official training and equipment purchases
crews still responded a couple times per year for these types of incidents. PFA would like to
thank our partners in this endeavor: City of Fort Collins Light & Power, Colorado State
University and Loveland Fire Rescue Authority.
Jax Safety Fair
PFA helped to plan and organize the annual safety fair hosted by Jax Outdoor Gear on North
College Avenue. Participating agencies included City of Fort Collins Office of Emergency
Management Community Emergency Response Team, Larimer County Sheriff’s Office, Larimer
County Telephone Authority (LETA 9-1-1), Poudre Valley Hospital EMS, Red Cross Northern
Colorado and United States Coast Guard Auxiliary. The purpose of the fair was to help prepare
our customers before an emergency or disaster occurs. Prepared customers place less of a strain
on first responders during incidents.
Incident Statistics (by category)
Report Period: July 2014 Total Loss
Fires 38 $39,645
Overpressure/rupture, explosion-no fire 1
Rescue / EMS 1,112
Hazardous Condition - no fire 30
Service Call 51
Good Intent Call 153
False Alarms / False Calls 115
Severe Weather & Natural Disaster 1
Special Incident Type 7
Total = 1,508
YEAR-TO-DATE 2014 Total Loss
Fires 210 $1,541,757
Overpressure/rupture, explosion-no fire 6
Rescue / EMS 7,447
Hazardous Condition - no fire 189
Service Call 432
Good Intent Call 783
False Alarms / False Calls 689
Severe Weather & Natural Disaster 1
Special Incident Type 25
Total = 9,782
28
Comparison: July 2013 Total Loss
Fires 39 $537,380
Overpressure/rupture, explosion-no fire 2
Rescue / EMS 1,106
Hazardous Condition - no fire 27
Service Call 56
Good Intent Call 104
False Alarms / False Calls 109
Severe Weather & Natural Disaster 1
Special Incident Type 2
Total = 1,446
Comparison: YEAR-TO-DATE 2013 Total Loss
Fires 236 $2,222,681
Overpressure/rupture, explosion-no fire 8
Rescue / EMS 7,114
Hazardous Condition - no fire 212
Service Call 433
Good Intent Call 720
False Alarms / False Calls 703
Severe Weather & Natural Disaster 1
Special Incident Type 17
Total = 9,444
*Information subject to change due to updated data.
29
BUILDING & PLANNING ACTIVITY
COMMUNITY DEVELOPMENT & NEIGHBORHOOD SERVICES
2013 YTD 2014 YTD % Change
Development Project Submittals Received 348 328 -6%
Conceptual/Staff Reviews Performed 166 138 -17%
Building Permits Issued 3,842 4,533 +18%
Building Permit Valuations ($M) $197 $345 +75%
Building Inspections Performed 18,349 20,211 +10%
Plan Reviews Performed 1,313 1,549 +18%
Development Review revenues are approximately $954K over projections for 2014 as of July 31.
Development Projects of Note
Capstone Cottages Project Development Plan - A proposed new student housing project
located on the northeast corner of Lincoln/Lemay, includes approximately 185 dwelling
units on 26 acres. The staff review for the initial round is complete and a second
neighborhood meeting was held on July 24, 2014.
City-initiated Annexation of existing Clydesdale Park Neighborhood - Located at the
intersection of East Mulberry Street (Hwy 14) and Carriage Parkway, the annexation is
proceeding forward with the following key dates scheduled:
o August 19 - City Council Initiating Resolution;
o September 11 - Planning and Zoning Board;
o October 7 - City Council 1st Reading;
o October 21 - City Council 2nd Reading.
Foothills Mall Redevelopment – The Foothills Mall Redevelopment Phase One and
Phase Two Final Plan and development agreement have been recorded and site work has
commenced. Phase Three is anticipated to be finalized and recorded in early August.
Two Minor Amendments have been submitted. Weekly construction coordination
meetings are being held with City staff and the developer. A second master demolition
permit has been created listing American Demolition. The first demo permit listed Alpine
Demolition who is no longer involved. Permits under review:
o Cinemark Movie Theater, 335 E Foothills - Major revisions submitted; large set
of plans to re-review.
o New parking structure, 315 E Foothills - Plan review complete.
o New core and shell, 3120 S. College - Plan review complete.
Rigden Farm Sixth Filing – New residential multifamily development proposing 33
dwelling units.
30
Woodward – Final plans for Phase One are complete and site work for the main campus
building has commenced. A minor amendment was also submitted on July 18, 2014 to
change the approved Final Plans for Phase One. The changes remove the Production
Support Building (PSB), located along East Lincoln Avenue, from the Phase One plans
and expand the main building to include a portion of the PSB functions. The changes
also integrate additional landscaping into the East Lincoln frontage to further buffer
views toward the main building. The Final Plans reserve the option to include the PSB
and/or other buildings along East Lincoln with subsequent phases. A Footing and
Foundation (F&F) permit has been issued for the core and shell, which allows installation
of all structural foundations and underground utilities. Underground inspections have
begun with no issues at this time. Tenant finish plans were submitted this week for
review with plan review expected in 3-4 weeks.
Summit Parking Garage – Upon appeal, Council remanded the Summit Parking Garage
development project back to the Hearing Officer for further consideration. The remand
hearing is scheduled for September 4, 2014.
Bucking Horse Third Filing Major Amendment - Submitted on June 18 with mylar
submittal anticipated in early August.
Projects that submitted Final Plans in July
Timbervine PDP submitted on July 30, 2014.
Construction Projects of Note for July
Commercial addition of 10,828 square feet for The Square shopping center to house
Trader Joe’s and Sierra Trading Post.
New 71,165 square foot Morningstar long-term care facility at East Horsetooth Road and
Lochwood Street.
Other Items of Note
Nature in the City – The Nature in the City strategic plan was funded through the Annual
Appropriation Ordinance and launched in January 2014. This strategic plan will develop
a vision for incorporating nature into the urban environment and include design
guidelines, policies, and actions for achieving this vision.
o We are currently conducting the inventory and assessment (using existing data,
e.g., GIS, Natural Areas bird data, etc., and field data to be collected this summer
at 165 sites throughout the City) using a triple bottom line approach and have
already engaged almost 350 citizens and met with four City Boards. The
assessment will be complete in September.
o The project was also awarded $25,000 from the City’s Sustainability Innovation
Fund to build the first green wall in our community. We are collaborating with the
Institute for the Built Environment and the Urban Lab (urbanlab.colostate.edu) to
31
design and install the wall this year at the Fort Collins Museum of Discovery. A
task force comprised of CSU, City staff, and private sector representatives has
been formed to oversee this effort.
o A staff report is planned for the July 15, 2014 Council Meeting.
For more information about the project, please see our website at
fcgov.com/natureinthecity.
Oil & Gas – A moratorium is now in place for all hydraulic fracturing within the City of
Fort Collins. The moratorium will remain in place for up to five years and stops the
current operator from using hydraulic fracturing to enhance existing wells or drill new
ones. Staff has ceased working on Land Use Code revisions until further direction is
received from Council. Two firms have been retained to make recommendations on
methods of compliance related to property values and health impacts of hydraulic
fracturing. Staff members have met with both firms and reviewed a draft document on
property values.
Old Town Fort Collins Historic District Design Standards - The purpose of this item is to
adopt an ordinance updating the Old Town Fort Collins Historic District Design
Standards. The update to the design standards defines and illustrates characteristics for
compatible future development within the Old Town District and in the adjacent area, and
a means for incorporating modern sustainable building practices into historic preservation
projects.
o The Landmark Preservation Commission, at its May 14, 2014 hearing,
unanimously recommended Council’s adoption of this item. The Planning and
Zoning Board unanimously recommended Council’s adoption of this item at their
June 12, 2014 hearing.
o Council unanimously voted to adopt the Design Standards on First Reading – July
1, 2014. Second Reading is scheduled for July 15, 2014.
o Council unanimously voted to adopt the Design Standards on Second Reading on
July 15.
Smoking Ordinance Expansion Options – City Council passed two additions to
the Smoking Ordinance on Second Reading on July 15:
1. Electronic Smoking Devices – prohibits the use of electronic smoking devices in all
places where conventional smoking is prohibited. This becomes effective July 26.
2. 100% Hotel/Motel Rooms –100% of hotel/motel rooms required to be smoke free.
This becomes effective January 1, 2015.
Items to consider later (October 7):
1. Parks, Trails, and Natural Areas – Council also directed staff to bring an ordinance
for consideration that would prohibit smoking in all parks, trails, and natural areas.
Golf courses would be exempt from this requirement (this direction was not
unanimous). Additional information about enforcement will be provided. Additional
32
communication with Fossil Ridge High School Student Council members will occur
to ensure staff understands the issues occurring at the park next to the school.
2. Public Events – Council directed staff to bring an ordinance for consideration that
would require public events to be smoke free. Council did not request the allowance
of designated smoking areas. Because many public events for 2014 have already
begun the permitting process, as well as their marketing process, Council agreed that
this requirement should be considered with implementation beginning for the 2015
public event season. Staff will visit with event planners and patrons during the 2014
event season to gain additional feedback.
3. Old Town/Downtown – Council directed staff to bring an ordinance for consideration
that would require certain areas within the Old Town/Downtown area to be smoke
free. Different options about the boundaries for this area were discussed. Staff will
provide options for consideration including Old Town Square, as well as an expanded
area that could possibly be phased in over time. Staff will meet with business owners
within these areas to discuss their thoughts, concerns, questions, and suggestions.
Staff will also meet with Boulder staff to get a better understanding of
implementation and potential unintended consequences of the smoke-free regulations
of the Pearl Street Mall. Additionally, staff will provide detailed enforcement
information and potential costs for Council consideration.
Transit-Oriented Development (TOD) Parking Study – Kimley-Horn and Associates have
been hired to assist with the study. The Planning and Zoning Board has requested more
time to discuss possible commercial parking requirements, thus staff is requesting
Council extend the temporary ordinance at the August 19 meeting. The Study
recommendations and Land Use Code ordinance are scheduled for adoption by City
Council on October 7 (First Reading) and October 21 (Second Reading).
Urban Agriculture
o A 6-month update on urban agriculture was provided to Council in July. This
update highlighted the urban agriculture licenses issued to date and staff’s
continued collaboration with the Northern Colorado Local Food Cluster.
o A budget offer has been prepared for the 2015-2016 BFO cycle to align internal
staff efforts in the development of the local food and wellness strategic plan; this
offer is entitled “Sustainability Policy and Project Manager.”
o A new FAQ document has been developed to answer basic questions about what
the City allows and where. This document can be viewed at
fcgov.com/urbanagriculture.
West Central Area Plan / Prospect Corridor Design – Updated vision and priorities for the
West Central area of the City (generally south and west of the CSU main campus). This
effort is updating the 1999 West Central Neighborhoods Plan based on emerging issues
and trends. Areas of focus include neighborhood character, transportation needs, the
33
natural environment, and a new design for Prospect Road from Shields to College. To
date, the project has concentrated on evaluating existing and future conditions and
developing a vision for the plan, and the team is scheduled to present at the August 26
City Council Work Session. More information on the project can be found at
fcgov.com/westcentral.
Outreach to date:
o Four public outreach listening sessions – March/April, 175 attendees
o 20 neighborhood walking tours – April/May, 80+ attendees
o Online “Wiki Map” – being used to collect input and ideas from those interested in the
planning effort, including those unable to attend other public events, 90+ users
o Visioning events: 5/21 (Drake Centre), 4/29 (Senior Center) – 74 attendees
o Outreach at the Drake Road Farmers’ Market and CSU Lagoon Concert Series
o Presentations to Boards and Commissions: Parking Advisory Board, Transportation
Board, UniverCity Connections Transportation and Mobility Task Force
o Online Visioning Survey – 337 respondents
Development Projects under Appeal
No projects currently under appeal.