Strategic Planning Update
Jackie Sargent, General Manager/CEO
Brad Decker, Strategic Planning Manager
City of Fort Collins - Council Work Session
May 27, 2014
Residential
Small Business
Large Business
Generation Transmission Distribution
Customers
Estes Park
Fort Collins
Longmont
Loveland
Platte River Power Authority
• Sole electricity supplier
• Not for profit
• Local governance
• Joint Ownership
Local Electric System Partnership
Changing Boundaries
2
Platte River Focus – Balance
Reliability
Environmental
Responsibility
Competitive
Price
Safety
Innovation & Sustainability
3
Approved by Board of Directors
December 12, 2013
2014 Strategic Plan
http://www.prpa.org/wp-content/uploads/2014/02/PRPA_SP14_Web.pdf
4
Strategic Initiatives
Improved Collaboration
& Communications
Diversified Energy
Supply Portfolio
Safety
Compliance
Assurance
Operational
Excellence
Financial
Stability
Exceptional
Customer Service
Technological Innovation
& Sustainability
Employee
Goals for Each Engagement
All Departments
All Employees
5
• Woodward Project
• Programs & Services:
– Record performance for Common DSM programs in 2013
– New regional brand for services (“Efficiency Works”)
– System wide Demand Response study
– Fort Collins Solar Program support
– Electric Vehicle stations at Platte River offices
– System wide Solar Garden program study
– FORTZED/CHP subcommittee/Net Zero Cities
– Fiber Leases
• Stakeholder Engagement:
– Boards, Councils, Customers, Community groups
– Strategic Plan development and Resource Planning
– Listening sessions, webinar, meetings/presentations
– Joint customer surveys
Recent Activities
www.efficiencyworks.CO
6
• Solar site evaluation study:
– Initiated by City of Loveland
– Fort Collins/Loveland airport, Rawhide & other sites
– Interconnection feasibility, energy production & system cost
• Medicine Bow Wind Project Life Extension/Upgrade:
– New retrofit technology (first application in U.S.)
– Increased generation output
– Increase plant life from 20 years to 30+ years
• Spring Canyon Wind Project:
– New 32 MW wind project in NE Colorado
– Will roughly double supply of wind energy to Municipalities
– Construction started at wind site
Recent Activities
7
New Wind Resource
Medicine
Bow
Spring
Canyon
Silver
Sage
8
New Wind Resource
9
Strategic Initiatives
Improved Collaboration
& Communications
Diversified Energy
Supply Portfolio
Safety
Compliance
Assurance
Operational
Excellence
Financial
Stability
Exceptional
Customer Service
Technological Innovation
& Sustainability
Employee
Goals for Each Engagement
All Departments
All Employees
10
STRATEGIC PLAN DIRECTIVES/GOALS:
• Investigate options to reduce our carbon footprint:
CO2 emissions – 20% reduction by 2020 as a guideline
• Look at expanded use of renewable resources:
Colorado Standard (qualified sources) – 20% by 2020 as a guideline
• Evaluate natural gas combined cycle generation:
Fuel diversity/reduced emissions/renewable source integration
• Analyze benefits & costs of more distributed resources
Maintain position as lowest cost wholesale supplier in Colorado
Diversify Energy Supply Portfolio
11
Why conduct an IRP?
Changing landscape of the energy
generation and delivery business
-2.9%
5.0%
0.0% 0.0%
13.2%
-5.0%
-3.0%
-1.0%
1.0%
3.0%
5.0%
7.0%
9.0%
11.0%
13.0%
15.0%
Coal &
Petroleum
Natural
Gas
Nuclear Hydro Renewables
Change in U.S. Generating
Capacity over the Past
Decade
Source: Energy Information Administration
Future
resource and financial
responsibility
→ Satisfy owner and community
needs
→ Strategic Plan objectives
→ Board directives
12
Preparing for future needs
Phases of Planning at Platte River
1970’s-1980s 1980’s-1990’s Early 2000’s Current Phase
Building:
• Craig
• Rawhide
• Transmission
Operations:
• Craig
• Rawhide
• Transmission
• Municipal sales
• PSCo sale
• Debt reduction
Summer Peak:
• Five new gas CTs
• Transmission
• End of PSCo sale
• Hydro (drought)
• Craig & Rawhide
operations
• Rate increases
Flexibility:
• Renewables
• Demand response
• Distributed generation
• New technologies
• Diverse member needs
• Balancing multiple
uncertainties &
managing risks
13
• Platte River’s coal capacity is
relatively high
• Share of hydro and wind
resources is higher than
industry average
• Platte River has a significant
share of gas peaking capacity
Current capacity resource mix
Intermediate resources can improve Platte River’s asset mix,
and provide flexibility to accommodate more renewables
Coal Gas Peaking Hydro Wind
14
Supply Opportunities
• Platte River is at the
headwaters of U.S.
fuel supply
• Platte River has a
favorable geographic
location to access
renewable resources
15
Geothermal
Solar
Wind
Conventional
Gas
Coal
Platte River is well-situated to access a diverse mix of energy resources
The 2014 IRP focus
• Based on the results of Platte River’s 2014 Strategic Plan
• Pursue and deploy resource and market options that limit business and environmental
risk through:
Diversified resource mix
Innovation
Collaboration
Carbon emissions
Maintain position as low-cost
provider
…while maintaining
safety and reliability
16
Platte River’s IRP analysis
Platte River’s analytical process can be summarized by the “3 Ms”
Models
Methods
Metrics
The software and systems necessary to conduct an
analysis to complete an Integrated Resource Plan
The modeling assumptions, routines, and
approaches used to evaluate a system of energy
resources
The mathematical relationships that convey the
performance and behavior of a portfolio of resources
under varying assumptions
17
Models
Platte River’s IRP modeling effort will draw upon a diverse set of industry
experts for software and advisory services.
All Energy
Software Integration EEC
Enchantment Energy
Market Resource
Options
Economic and
Market Analysis
Plant Engineering
Services
Conservation,
Distributed Generation,
and Renewables
18
Methods
• Modeling will be performed at the
system level, with all municipal
loads, surplus sales and resources
combined.
• 40-year planning horizon
• 20-year decision horizon
• Resources—mature vs. evolving
• Modified coal
operations/retirements
• Demand-side resources
• Distributed resources
• GHG reduction guidelines
AURORAxmp will use a 20-
year modeling horizon
Normal retirements are
between 2040 and 2050
Existing technologies will be
the primary focus
PR—20%/2020; 80%/2050
FC—80%/2030; 100%/2050
• DSM will act as an adjustment to load
• DG will act as a dispatchable resource
19
Metrics
Evaluation of scenarios will be based on two primary factors: cost and risk
Low Capital
High Fuel
High Capital
Low Fuel
Least-cost planning alone is not ideal for
optimizing Platte River’s long-term portfolio
Risk
Cost
Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7 Case 8
20
Schedule
Staffing &
Support
Software and
Systems
Modeling/
Analysis
Communication
Jan-Mar Apr-Jun Jul-Sep Oct-Dec
New Staff Additions
Software Acquisition and
Deployment
Listening
Sessions
Modeling Plan
Development
Consulting Selections
Data Collection
Decision Analysis
Stakeholder
Communications/
Draft Report
Consultant Reports
Final Report
Survey
Reporting
Customer Surveys
Drafting IRP
Fort Collins
Climate Action Plan
Jan-Mar ‘15
21
Analysis for the City of Fort Collins
• Council approved Resolution 2014-028 on April 1, 2014
• Platte River is partnering with Fort Collins Utilities to develop a set
of electricity resource planning scenarios to support Fort Collins’
Climate Action Plan
• An Intergovernmental Agreement is being developed
– Will be proposed to City Council on June 3, 2014
22
The Value of Partnership
Estes Park
Fort Collins
Longmont
Loveland