2014 Utility Rates and Fees
City Council Work Session
September 24, 2013
2
Agenda
Electric Utility
Wastewater Utility
Water Utility
Stormwater Utility
9/26/2013
2
3
Electric Utility
4
Electric Rate Increase
Two components in 2.0% increase
+ 1.5% retail impact from Platte River Power
Authority’s wholesale rate increase
+ 0.5% for the Fort Collins Solar Program
9/26/2013
3
5
Impacts by Rate Class & Season
6
FULL IMPLEMENTATION IN 2014
Current 2013 Proposed 2014 $ Change % Change
$3,156 $3,366 $210 6.7%
Current 2013 Proposed 2014 $ Change % Change
$30,471 $32,895 $2,424 8.0%
Typical Single Family Lot
8600 square feet, 70 foot of street frontage, 150 amp service, 4/0 secondary service
Model Commercial Development
82,000 sq ft, 190 ft street frontage, 250 ft primary srv, 600 amps, 208Volt, 3-phase, 1-transformer
Option 1: Implement the full increase in 2014
Electric Development Fees
Option 2: Implement 50% of the increase in 2014
and the remainder plus any additional changes
in 2015
9/26/2013
4
7
Wastewater Utility
8
Wastewater Fund
Per 2014 City Budget 3.0% rate increase
Increase necessary for capital improvements
Updated Cost of Service study
Plant Investment Fees for 3” connections specific
to customer like > 3” connections
9/26/2013
5
9
Impacts by Rate Class
Staff recommends gradual rate adjustments
7.5%
-5.6%
4.2%
-3.6%
3.0%
6.1%
-2.5%
2.8%
-1.5%
3.0%
-8.0%
-6.0%
-4.0%
-2.0%
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
Single Family Duplex Multifamily Commercial System-wide
2013 Wastewater Cost of Service Study
Recommendations for 2014 Rates
COS Recommendation
Staff Recommendation
10
Plant Investment Fees
Current Fees Proposed 2014
Volume Volume gpd Proposed Fee
Customer Class 05-'08 data Fees 09-'12 dataChange PIF Change
gpd $ gpd % $ %
PIF $/gpd $ 11.46 $ 12.35 7.8%
Single family Res 300 $ 3,440 250 -17% $ 3,090 -10.2%
Duplex & Multi-fam 210 $ 2,410 200 -5% $ 2,470 2.5%
Nonresidential
Meter Size (inches)
3/4" 600 $ 6,880 530 -12% $ 6,550 -4.8%
1" 1,510 $ 17,300 1,250 -17% $ 15,440 -10.8%
1 1/2" 2,660 $ 30,480 2,420 -9% $ 29,890 -1.9%
2" 4,670 $ 53,520 4,760 2% $ 58,790 9.8%
3" 12,680 $ 145,310 16,930 34% $ 209,090 43.9%
> 3 inches Based on specific customer requirements
9/26/2013
6
11
Water Utility
12
Water Rate Increase
Two components in 4.0% increase
+ 3.0% for increased capital investment in
infrastructure
+ 1.0% for additional costs associated with the
High Park Fire
Updated Cost of Service study
9/26/2013
7
13
Impacts by Rate Class
9.0%
-16.4%
-1.8%
7.7%
3.5% 4.0%
6.6%
-5.0%
0.0%
5.3%
3.5% 4.0%
-20.0%
-15.0%
-10.0%
-5.0%
0.0%
5.0%
10.0%
15.0%
Single Family Multifamily Duplex Commercial High Volume
Industrial
System-wide
2013 Water Cost of Service Study
Recommendations for 2014 Rates
COS Recommendation
Staff Recommendation
Staff recommends gradual rate adjustments
14
Plant Investment Fees
2013 2014
Customer Class / Meter
Size
Peak Day
Usage PIF Fee
Peak Day
Usage Change PIF Fee Change
gpd $ gpd % $ %
PIF $/gpd $ 4.26 $ 4.43 4.0%
Single Family Res
Domestic Use (base) 172 $730 162 -6% $720 -1.4%
Peak Use (per sqft) 785 $0.39 627 -20% $0.32 -17.9%
Multi-family (per unit)
Domestic Use (base) 120 $510 121 1% $540 5.9%
Peak Use (per sqft) 217 $0.27 192 -12% $0.25 -7.4%
Nonresidential
Meter Size
inches
3/4 1,850 $7,880 1,580 -15% $7,000 -11.2%
1 5,340 $22,750 4,300 -19% $19,050 -16.3%
1 1/2 11,130 $47,410 9,390 -16% $41,600 -12.3%
2 16,970 $72,290 14,540 -14% $64,410 -10.9%
3 38,800 $165,290 32,730 -16% $144,990 -12.3%
> 3 inches Based on specific customer requirements
9/26/2013
8
15
Water Right Utilization Fee
In addition to Raw Water Requirement
Necessary to fully utilize accepted water rights
Specific to the irrigation company
16
Stormwater Utility
9/26/2013
9
17
Permit Fees
Per 2014 City Budget no rate increase
Proposed adjustments to Floodplain Permit fees
No changes to these fees since adoption
New rates based on actual cost of reviews
Stormwater Permit Fees Current $ Proposed $
Floodplain Use Permit $25 $50
Floodplain Model Analysis Review $300 $500
Floodplain Variance $300 $1,000
18
Plant Investment Fees
Stormwater Plant Investment Fee
2013
Current
Fee
2014
Proposed
Fee
% Change
$6,390 $7,817 22%
9/26/2013
10
19
Typical Residential Utility Bill
20
Typical Residential Summer Utility Bill
SUMMER Current 2013 Estimated 2014 $ Increase % Increase
Electric
700 kWh / mo
Wastewater
4,800 gal / mo
WQA
Stormwater
8,600 sq. ft. lot,
light runoff
Water
15,000 gal / mo
Total Estimated
Average
Monthly Utility
Bill
$ 30.87 $ 32.76
$ 14.26 $ 14.26 $ -
Typical Residential Customer - Monthly Utility Bill
4.0%
6.6%
$ 6.75
$ 3.52
$ 174.71
$ 56.89
$ 167.96
$ 53.37
0.0%
$ 69.46 $ 70.80 $ 1.34 1.9%
$ 1.88 6.1%
9/26/2013
11
21
Typical Residential Winter Utility Bill
WINTER Current 2013 Estimated 2014 $ Increase % Increase
Electric
700 kWh / mo
Wastewater
4,800 gal / mo
WQA
Stormwater
8,600 sq. ft. lot,
light runoff
Water
15,000 gal / mo
Total Estimated
Average
Monthly Utility
Bill
$ 26.59 $ 28.35 $ 1.76 6.6%
$ 133.96 $ 138.57 $ 4.61 3.4%
6.1%
$ 14.26 $ 14.26 $ - 0.0%
$ 30.87 $ 32.76 $ 1.88
$ 62.24 $ 63.21 $ 0.97 1.6%
Typical Residential Customer - Monthly Utility Bill
22
Typical Residential Development
Fees
9/26/2013
12
23
Typical Residential Development
Current 2013 Proposed 2014 Change
Electric
Electric Development Fee $3,156 $3,366 $210 6.7%
Water
Raw Water Requirement $5,203 $5,203 $0 0.0%
Water Right Utilization Fee $3,202 $3,202
Plant Investment Fee $4,084 $3,472 -$612 -15.0%
Wastewater
Plant Investment Fee $3,440 $3,090 -$350 -10.2%
Stormwater
Plant Investment Fee $1,082 $1,324 $242 22.4%
Total $16,965 $19,657 $2,692 15.9%
Assumptions:
8,600 sq. ft. lot
70 foot frontage
6,156 sq. ft. common area and right-of-way
150 amp service
24
Typical Residential Development
$13,809
$16,291
$20,546
$26,401
$29,582
$31,371
$-
$5,000
$10,000
$15,000
$20,000
$25,000
$30,000
$35,000
Fort Collins
(Current 2013)
Fort Collins
(Proposed 2014)
Longmont Greeley FCLWD / South
FC Sanitation
ELCO / Boxelder
Sanitation
Water, Wastewater, and Stormwater Plant Investment Fees
Stormwater
Wastewater
Water
9/26/2013
13
25
In Summary
2014 Proposed Rate Increases:
Electric 2.0%
Wastewater 3.0%
Water 4.0%
Stormwater 0.0%
Plant Investment and Development Fees updated
New Water Utilization Fee proposed