Date: July 24, 2023
To: Mayor and City Councilmembers
Through: Kelly DiMartino, City Manager
Tyler Marr, Deputy City Manager
Caryn Champine, Director, Planning, Development and Transportation
From: Kaley Zeisel, Director, Transfort
Subject: July 9, 2024 Work Session Summary: West Elizabeth Enhanced Travel Corridor
BOTTOM LINE
The purpose of this memo is to document the summary of discussions during the July 9, 2024
Work Session. All Councilmembers were present.
DISCUSSION SUMMARY
Transfort and PDT staff provided an update to Council regarding the status of the West
Elizabeth Enhanced Travel Corridor (ETC). Council adopted the initial West Elizabeth ETC plan
in 2016 with recommendations to overhaul the corridor to a multimodal corridor with Bus Rapid
Transit (BRT) service. This project is expected to yield positive outcomes for the Fort Collins
community including: increased safety, improved transit service, ADA compliant pedestrian
facilities and protected cycling facilities. Transfort and Engineering have now completed 60%
design and anticipate completing engineering design by the end of 2025. The current capital
project cost is estimated at approximately $113.7M, annual operating costs are estimated at
approximately $5M per year, a net increase of $2M annually to operate service in this corridor.
Transfort submitted a project rating request to the Federal Transit Administration (FTA) in 2023
for consideration of Federal Fiscal Year (FY) 2025 funding, with a request for CIG funding in the
amount of 65% of the total project cost. In order to be recommended for funding, projects must
receive at least a Medium overall rating from FTA. The West Elizabeth project was rated at
Medium-Low. Transfort has debriefed with FTA regarding ways in which to improve the project
application. Ridership has seen significant increases since the previous submittal, which is
expected to have a positive impact on Transfort’s score. Transfort is also evaluating other
criteria for improvement, such as total federal share requested, and Land Use and Economic
Development factors.
The western terminus of the project will be a new transit station on the corner of West Elizabeth
and Overland Trail, with the current intersection converted to a roundabout for ease of use and
to facilitate the ability for 60FT articulated buses to turn around. This portion of the project has
been awarded funding through FTA’s FY23 Rebuilding America with Sustainability and Equity
(RAISE).
Docusign Envelope ID: 163E327B-6D17-4C63-956A-349E3D6029E4
Transfort plans to resubmit the project to FTA for a project rating in August 2024 to be
considered for FY2026 funding.
NEXT STEPS
Transfort will execute FY23 RAISE funding independent of the CIG Small Starts project to begin
construction on the Foothills Transit Station prior to securing a CIG award to implement the full
West Elizabeth Corridor project.
Transfort will submit the West Elizabeth Enhanced Travel Corridor Project to FTA in August
2024 for consideration of a project rating for CIG Small Starts funding.
FOLLOW-UP ITEMS
1. With the implementation of the West Elizabeth Enhanced Travel Corridor, will there be
greenhouse gas emission reductions?
The following emissions information was calculated by Felsburg Holt & Ullevig (FHU) based on
guidance from the Federal Transit Administration (FTA) for calculating the environmental
benefits for CIG Small Starts projects. Emissions changes are calculated based on projected
changes in automobile and transit vehicle miles traveled (VMT) after the BRT service has been
implemented. FTA utilizes conversion factors of kg/VMT for every combination of vehicle type
and emissions type, and in some cases (like for particulate matter, shown below), the
conversion factor for electric buses is higher than for automobiles. There are expected to be
reductions of greenhouse gas emissions and reductions to emissions of other air quality
pollutants, including Carbon Monoxide (CO) and Volatile Organic Compounds (VOC). These
figures are calculated for the horizon year (Year 20) of the project, these are not aggregate
calculations. Two air pollutants, Mono-Nitrogen Oxides (NOx) and Particulate Matter (PM2)
emissions, are expected to increase based on the formulas provided by FTA, see chart below.
Based on feedback from Sustainability, we believe these numbers are conservative estimates.
FTA’s template and calculations are grounded in national benchmarks and do not take into
consideration local initiatives. For example, Platte River Power Authority’s plan to increase the
mix of renewable energy by 2030 would lead to greater reductions in emissions.
Emission Type Horizon Year Reduction or (Increase)
Carbon Monoxide (CO) 7,136.09 kg
Mono-Nitrogen Oxides (NOx) (377.26) kg
Volatile Organic Compounds (VOCs) 157.63 kg
Particulate Matter (PM2.5) (38.19) kg
Greenhouse Gases (CO2 equivalent) 217.27 tons
Docusign Envelope ID: 163E327B-6D17-4C63-956A-349E3D6029E4
2. Are there currently any planned bike connections along Overland that will connect with
the future Foothills Transit Center?
The Active Modes Plan recommends separated bike lanes on Overland Trail as a medium
priority/readiness project. The City will explore this project further through the upcoming NW
Fort Collins Arterial Bikeway Feasibility Study, which we received Safe Streets and Roads for all
funding for. The study area includes Overland Trail from Laporte Ave. to Horsetooth Road.
Aside from this funding for safety studies and conceptual planning, we don’t currently have
funding identified for separated bike lanes on Overland Trail.
3. What is the breakout of the costs related to design and construction management?
Staff received an updated 60% design cost estimate from FHU on July 11, 2024, after the July
9, 2024 work session. The chart below outlines the updated Professional Services Category
with detailed breakdowns of each line item.
Overall, the 60% design estimate increased by approximately $1M, the most notable differences
were an increase in estimated design costs to achieve final design, and an increase in the
amount estimated for Start Up/Commissioning Costs and Art in Public Places. Updated cost
estimates will be completed with each subsequent design milestone (80% and final).
Professional Services
30% Design
Estimate 60% Design Estimate Difference
Final Design to 30% $ 1,500,000 $ 1,500,000 $ -
Final Design to 100% $ 4,010,000 $ 4,713,140 $ 703,140
Construction Administration &
Management $ 3,256,000 $ 3,197,250 $ (58,750)
Legal, Permits, Review fees, etc. $ 939,000 $ 959,175 $ 20,175
Surveys, Testing, Investigation,
Inspection $ 1,371,000 $ 1,400,175 $ 29,175
FTA Required Start Up and
Commissioning & Art in Public
Places $ 1,100,000 $ 1,366,003 $ 266,003
ROW Real Estate Administrative
Services $ 1,920,000 $ 2,000,000 $ 80,000
$ 14,096,000 $ 15,135,743 $ 1,039,743
4. What are the options for remaining estimated $32M in local match?
The City is exploring multiple options for the remaining local match that will be required to meet
the grant requirements. The amount of 2050 Transit Sales Tax that will be needed for capital
and operating will vary depending on how much local match is able to be secured from other
sources.
Docusign Envelope ID: 163E327B-6D17-4C63-956A-349E3D6029E4
Currently, approximately $4 million of the Transit Sales Tax is available annually. Without
additional local funds from other sources, the West Elizabeth ETC project will take
approximately 100% of the remaining Transit Sales Tax Funds over the next 8-9 years for one-
time capital investment. Once operational, the ongoing need is estimated at approximately $2
million annually, or 50% of the remaining 2050 Transit Sales Tax. Actual amounts are
dependent on full design and operational details that are still being assessed, as well as inflation
that is variable depending on construction and service start timeline. This scenario assumes no
additional capital or ongoing items are assigned to the Transit Sales Tax funding source.
The City aims to offset the full local match amount with the following options:
CSU Contribution:
CSU has already contributed approximately $1M in local match toward design for the West
Elizabeth ETC project, Transfort is also aiming to substantially offset the approximately $32
million in capital investment and/or the approximate $2 million in annual operating through a
partnership agreement with CSU.
Without substantial contribution from CSU, the City will need to determine how to proceed, and
whether or not the City wants to consider scaled versions of the project.
Land match:
City staff is exploring the eligibility for other land match opportunities, including land owned by
CSU along the planned BRT route and existing City land including at the Transfort Maintenance
Facility (TMF).
State Opportunities:
Clean Transit Enterprise (CTE) funding: 2024 was the first year of funding for this program,
funds can be used to purchase low or no emission vehicles, chargers, and to purchase and
install electrical infrastructure to facilitate vehicle charging. In the first year of funding there was
approximately $15M available for transit agencies throughout the state, and funds are being
distributed through a discretionary process.
SB24-230: This funding source will be collected from fees of oil and gas producers beginning
July 1, 2025, and will be used to fund transit projects. 70% of available funding will be used to
expand local transit service, most likely using a formula allocation, and 10% of funding will be
used toward a local transit grant program cash fund. The exact method in which these funds will
be distributed to transit agencies has not yet been determined.
Multimodal Options Fund (MMOF):
Funds are typically available at a 50/50 match rate and can be used toward capital or operating.
For fiscal year 2026, there will be $1.3 million for the North Front Range.
Docusign Envelope ID: 163E327B-6D17-4C63-956A-349E3D6029E4
Other Federal Grant Funding Sources:
(Can be used to reduce the request for CIG funding, though still require 20% local match)
o 5339b Bus and Bus Facilities Program
o 5339c Low or No Emissions Program
o Rebuilding America’s Infrastructure with Sustainability and Equity (RAISE)
o Safe Streets for All (SS4A)
o Transportation Alternatives Program (TAP)
o Congestion Mitigation and Air Quality (CMAQ)
Other Opportunities:
City staff is exploring with its federal partners options for low interest rate federal lending
programs.
Docusign Envelope ID: 163E327B-6D17-4C63-956A-349E3D6029E4