HomeMy WebLinkAboutReport - Mail Packet - 8/22/2023 - Connexion June 2023 Report (3)JUNE MONTHLY REPORT
PUBLISHED: JULY 2023
Overall Fiber Construction through June 2023
Total Fiber Areas Complete*
Total Fiber Area Construction Completed
353
*A Fiber Area on average serves 225 homes
99%
Total Fiber Area*
357
Take Rate*
* As of June 1, 2023. Take Rate of residential
neighborhoods released for a minimum of 90 days.
34%
*Includes fiber areas that have construction completed and turned over for QC
Monthly info / highlights
• The Connexion team has been active in the community the past few
months at various outdoor festivals and events. Our residential sales
representative has been able to sign folks up in person and in real time
while working events and out in the community and this has helped our
boost our installation numbers as well overall brand awareness.
• Follow us on Social Media! @FoCoConnexion
23-25528 | Auxiliary aids and services are available for persons with disabilities.
Finances
Connexion YTD Budget to Actual as of June 2023
• We are approximately 98.8% spent on the currently appropriated
project budget which includes an additional $20M approved by
City Council on April 5th, 2022 to allow for completion of the
network buildout and installation of Connexion customers. This
addition is reflected in the budget of $142.2M.
• In addition to a slower rate of installs to begin the year, revenue
is off due to irregular intergovernmental revenues not yet billed.
Expenses were significantly below budget as a result of the lower
cost of goods sold (internet/video content) from lower sales
volumes and continued favorable operating costs from lower
staffing levels than budgeted.
• Resulting net total margin was favorable to budget by
approximately $155K.
BUDGET 1 ACTUAL
BETTER/
(WORSE)
Operating Revenues 2 $8,975,085 $7,268,067 $(1,707,018)
Operating Expenses 3 $9,312,342 $7,450,231 $1,862,111
Net Operations $(337,257) $(182,164) $155,093
Investment Income (Expense) $- $- $-
Net Total $(337,257) $(182,164) $155,093
APPROPRIATED
BUDGET
PROJECT TO DATE REMAINING
Construction Budget $142,208,249 $139,835,268 $2,372,981
Notes: Results are preliminary and unaudited
1 Adjusted operating budget reflects impacts of increased capital budget of $142.2 M.
2 Excludes investment earnings on bond proceeds
3 Excludes Depreciation and Interest Expense
0
50
100
150
200
250
300
350
400
Y 2019Feb-20Apr-20Jun-20Aug-20Oct-20Dec-20Feb-21Apr-21Jun-21Aug-21Oct-21Dec-21Feb-22Apr-22Jun-22Aug-22Oct-22Dec-22Feb-23Apr-23Jun-23#of AreasActual Forecasted