HomeMy WebLinkAboutReport - Mail Packet - 1/25/2022 - Fort Collins Connexion Monthly Report - January 2022CONNEXION MONTHLY REPORT JANUARY 2022 Overall Fiber Construction through December 2021 92% Completed Bore Length 3,005,598 ft Total Bore Length 3,070,670 ft* Completed Fiber Pulled through Conduit 4,310,079 ft Total Fiber Pulled through Conduit 4,701,973 ft Total Fiber Area Construction Completed 248 *A Fiber Area on average serves 225 homes 69% Total Fiber Area* 357 Spent to Date $113,614,085 97% Total Construction Budget $ 116,808,249 * Bore Length may be updated through the course of the project as design is completed. *Includes fibers areas that have construction completed and turned over for QC Total Fiber Areas Complete*Total Fiber Pulled 2018 2019 2020 2021 2022 2023 Design Construction Available Atlantic Engineering Group (AEG) work Connexion Service Available ongoing Take Rate* * As of 1/1/22. Take Rate of residential neighborhoods released for a minimum of 90 days. 31% 97.9% CONNEXION MONTHLY REPORT Auxiliary aids and services are available for persons with disabilities. V/TDD: 711 JANUARY 2022 22-23867 Fiber Areas Update Monthly info / highlights • Over 27.5 miles of fiber were installed in November along with 60 vaults and 42 flowerpots (smaller vaults). • Project to date: 816 miles of fiber have been installed along with 9,664 vaults and over 17,283 flowerpots. • Fort Collins residents can input their address and see whether their residence is In Design, In Construction, or has Service Available! Our address look-up tool can be found on the Connexion website at fcconnexion.com. • Fort Collins Connexion’s new billing system and customer portal are live and we want to help get you set up quickly and easily so you can access all the new features. When you set up your account, you can review your billing history, sign up for paperless billing, pay your bill and manage your account all from the Self-Service Portal. • Follow us on Social Media! @FoCoConnexion Finances Connexion YTD Budget to Actual as of December 2021 • Connexion deployment remains on track for construction completion by mid-2022 with service availability to all premises by the end of 2022. • Construction Budget reflects an additional appropriation of $8.2 million from existing reserves authorized by City Council on September 7, 2021. We are approximately 97% spent on the appropriated construction Budget. (Including the $6M of re-deployed operating budget, we are 93% spent against available budget.) • Net Total margin continues to be favorable to budget by approximately $1M, a result of operating expense containment more than compensating for the shortfall in revenues YTD. BUDGET ACTUAL BETTER / (WORSE) Operating Revenues1 $12,240,121 $5,849,688 $(6,390,433) Operating Expense2 $13,870,023 $6,243,113 $7,626,910 Net Operations $(1,629,902) $(393,425) $1,236,477 Investment Income (Expense) $(5,257,475) $(5,438,977) $(181,502) Net Total $(6,887,377) $(5,832,402) $1,054,975 APPROPRIATED BUDGET3 PROJECT TO DATE REMAINING Construction $116,808,249 $113,614,085 $3,194,164 1 Excludes investment earnings on bond proceeds 2 Excludes Depreciation and Interest Expense 3 Excludes $6M of available re-deployed operating budget