HomeMy WebLinkAboutReport - Mail Packet - 11/23/2021 - Fort Collins Connexion Monthly Report - November 20210
50
100
150
200
250
300
350
400
Y 2019Feb-20Apr-20Jun-20Aug-20Oct-20Dec-20Feb-21Apr-21Jun-21Aug-21Oct-21Dec-21Feb-22Apr-22Jun-22Aug-22Oct-22Dec-22#of AreasActual Forecasted
0.0
1.0
2.0
3.0
4.0
5.0
6.0
Y 2019Feb-20Apr-20Jun-20Aug-20Oct-20Dec-20Feb-21Apr-21Jun-21Aug-21Oct-21Dec-21Feb-22Apr-22Jun-22Aug-22Oct-22Dec-22Fiber Pulled in FeetMillionsActual Forecasted
CONNEXION MONTHLY REPORT
NOVEMBER 2021
Overall Fiber Construction through October ‘21
2018 2019 2020 2021 2022 2023
Design
Construction
Available
Atlantic Engineering Group (AEG) work Connexion Service Available
ongoing
81.1%
Completed Bore Length
2,936,497 ft
90.2%
Total Bore Length
3,254,371 ft*
Completed Fiber Pulled through Conduit
4,018,753 ft
Total Fiber Pulled through Conduit
4,952,640 ft
Total Fiber Area Construction Completed
227
*A Fiber Area on average serves 225 homes*Adjusted for Interest Payments
63.6%
Total Fiber Area*
357
Spent to Date
$ 109,347,168
94%
Total Construction Budget
$ 116,808,249
* Bore Length may be updated through the
course of the project as design is completed.
31%
Take Rate*
* As of 11/01/2021. Take Rate of residential neighborhoods
released for a minimum of 90 days.
*Includes fibers areas that have construction completed and turned over for QC
Total Fiber Areas Complete*Total Fiber Pulled
CONNEXION MONTHLY REPORT
Auxiliary aids and services are available for persons with disabilities. V/TDD: 711
NOVEMBER 2021
21-23742
Fiber Areas Update
Monthly info / highlights
• Over 54.6 miles of fiber were installed in October along with 290
vaults and 252 flowerpots (smaller vaults).
• Project to date: 761.13 miles of fiber have been installed along with
9,543 vaults and over 17,186 flowerpots.
• Fort Collins residents can input their address and see whether their
residence is In Design, In Construction, or has Service Available!
Our address look-up tool can be found on the Connexion website at
fcconnexion.com.
• It is that time of year again to turn off and blow out your sprinkler
systems! Connexion crews and contractors do their best to not
disturb your yard when installing conduit and fiber. But during the
winter, it can be difficult to see if a sprinkler head or perennial was
damaged. If you notice anything was disturbed, we will come back
in the spring to get everything back to its original condition! If you
have questions or concerns now, or in a few months, just call our
construction hotline 970-674-7800 or email FCResidents@aeg.cc
Finances
Connexion YTD Budget to Actual as of October ‘21
• Connexion deployment remains on track for
construction completion in Q4 2022.
• Construction Budget reflects an additional appropriation
of $8.2 Million from existing reserves authorized by City
Council on September 7, 2021. We are approximately
94% spent on the appropriated construction Budget.
• Net Total continues to be favorable to budget by approximately
$1.1 million, a result of operating expense containment more
than compensating for the shortfall in revenues YTD.
BUDGET ACTUAL BETTER / (WORSE)
Operating Revenues*$ 9,293,620 $ 4,454,647 ( $ 4,838,973 )
Operating Expense**$ 10,927,162 $ 4,904,952 $ 6,022,210
Net Operations ( $ 1,633,542 )( $ 450,305 )$ 1,183,237
Investment Income (Expense)( $ 2,438,634 )( $ 2,525,936 )( $ 87,302 )
Net Total ( $ 4,072,176 )( $ 2,976,241 )$ 1,095,935
APPROPRIATED
BUDGET
PROJECT TO DATE REMAINING
Construction $ 116,808,249 $ 109,347,168 $ 7,461,081
* Excludes investment earnings on bond proceeds
** Excludes Depreciation and Interest Expense