HomeMy WebLinkAboutReport - Mail Packet - 6/22/2021 - Fort Collins Connexion Monthly Report - June 2021CONNEXION MONTHLY REPORT JUNE 2021 FIBER AREAS UPDATE Monthly info / highlights • Over 40.7 miles of fiber were installed in May, along with 166 vaults and 861 flowerpots (smaller vaults). • Project to date: 530.4 miles of fiber have been installed along with 7,768 vaults and over 14,423 flowerpots. • Fort Collins residents can now input their address and see whether their residence is In Design, In Construction, or has Service Available! Our address look-up tool can be found on the Connexion website at fcconnexion.com. • Irrigation season has started in Fort Collins and our crews are utilizing the Spring Checklist to repair irrigation systems and landscape damaged during the winter season. For questions about landscape repairs or to report construction damage, please call our Help Line at 970-674-7800 or email FCResidents@aeg.cc. OVERALL FIBER CONSTRUCTION THROUGH MAY ‘21 2018 2019 2020 2021 2022 2023 Design Construction Available Atlantic Engineering Group (AEG) work Connexion Service Availableongoing 0 Ft 1,000,000 Ft 2,000,000 Ft 3,000,000 Ft 4,000,000 Ft 5,000,000 Ft 6,000,000 Ft Y 2019Feb-20Apr-20Jun-20Aug-20Oct-20Dec-20Feb-21Apr-21Jun-21Aug-21Oct-21Dec-21Feb-22Apr-22Jun-22Aug-22Oct-22Dec-22Fiiber Pulled in FeetFiber Pulled Actual Forecasted *Includes fibers areas that have construction completed and turned over for QC 0 50 100 150 200 250 300 350 400 Y 2019Feb-20Apr-20Jun-20Aug-20Oct-20Dec-20Feb-21Apr-21Jun-21Aug-21Oct-21Dec-21Feb-22Apr-22Jun-22Aug-22Oct-22Dec-22#of AreasFiber Areas Complete Actual Forecasted Total Fiber Areas Complete* Total Fiber Pulled 56.5% FINANCES Connexion YTD Budget to Actual as of May ‘21 BUDGET ACTUAL BETTER / (WORSE) Operating Revenues*$3,620,159 $1,637,642 ($1,982,517) Operating Expense** $5,318,750 $2,179,550 $3,139,200 Net Operations ($ 1,698,591)($541,908)$1,156,683 Investment Income $237,630 $769,213 $531,583 Net Total ($1,460,961)($227,305)$1,688,266 BUDGET PROJECT TO DATE REMAINING Construction Budget $109,217,775 $87,848,910 $21,368,865 * Excludes investment earnings on bond proceeds ** Excludes Depreciation CONNEXION MONTHLY REPORT Auxiliary aids and services are available for persons with disabilities. V/TDD: 711 JUNE 2021 21-23322 In to the third year of Connexion’s rollout, our deployment is on track for construction completion in Q4 2022. • Operating revenues are less than budgeted, as are the operating expenses for May. Resulting in a positive net effect of $1.1 M. • Net total (operating cashflow) was $1.6 M positive compared to budget, driven primarily by lower operating expenses and positive investment income. • We are approximately 80% spent on Construction Budget, reflecting the increase in boring and operating crews in 2021. Completed Bore Length 2,458,917 ft 90.9% Total Bore Length 2,704,557 ft* Completed Fiber Pulled through Conduit 2,800,299 ft Total Fiber Pulled through Conduit 4,952,640 ft Total Fiber Area Construction Completed 151 *A Fiber Area on average serves 225 homes 42.3% Total Fiber Area* 357 Spent to Date $87,848,910 80.4% Total Construction Budget $109,217,775 * Bore Length may be updated through the course of the project as design is completed.