HomeMy WebLinkAboutReport - Mail Packet - 5/25/2021 - Fort Collins Connexion Monthly Update - May 2021CONNEXION MONTHLY REPORT MAY 2021 FIBER AREAS UPDATE Monthly info / highlights • Over 42.18 miles of fiber were installed in April, along with 495 vaults and 755 flowerpots (smaller vaults). • Project to date: 489.7miles of fiber have been installed along with 7,602 vaults and over 13,562 flowerpots. • Downtown construction has paused due to a supply issue and will resume by the beginning of June. • Irrigation season has started in Fort Collins and our crews will be utilizing the Spring Checklist to repair irrigation systems and landscape damaged during the winter season. For questions about landscape repairs or to report construction damage, please call our Help Line at 970-674-7800 or email FCResidents@aeg.cc. OVERALL FIBER CONSTRUCTION THROUGH APRIL ‘21 2018 2019 2020 2021 2022 2023 Design Construction Available Atlantic Engineering Group (AEG) work Connexion Service Availableongoing 0 50 100 150 200 250 Y 2019Jan-20Feb-20Ma r-20Apr-20May-20Jun-20Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21Feb-21Ma r-21Apr-21May-21Jun-21Jul-21Aug-21Sep-21Oct-21Nov-21Dec-21#of AreasFiber Areas Complete Actual Forecasted *Includes fibers areas that have construction completed and turned over for QC Total Fiber Areas Complete* 0 Ft 500,000 Ft 1,000,000 Ft 1,500,000 Ft 2,000,000 Ft 2,500,000 Ft 3,000,000 Ft 3,500,000 Ft Y 2019Jan-20Feb-20Ma r-20Apr-20May-20Jun-20Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21Feb-21Ma r-21Apr-21May-21Jun-21Jul-21Aug-21Sep-21Oct-21Nov-21Dec-21Fiiber Pulled in FeetFiber Pulled Actual Forecasted Total Fiber Pulled FINANCES Connexion YTD Budget to Actual as of April ‘21 BUDGET ACTUAL BETTER / (WORSE) Operating Revenues*$2,762,372 $1,242,995 ($1,519,377) Operating Expense**$4,231,346 $1,712,137 $2,519,209 Net Operations ($1,468,974)($469,142)$999,832 Investment Income $190,104 $382,334 $192,230 Net Total ($1,278,870)($86,808)$1,192,062 BUDGET PROJECT TO DATE REMAINING Construction Budget $109,217,775 $83,284,433 $25,933,342 * Excludes investment earnings on bond proceeds ** Excludes Depreciation CONNEXION MONTHLY REPORT Auxiliary aids and services are available for persons with disabilities. V/TDD: 711 MAY 2021 21-23252 In to the third year of Connexion’s rollout, our deployment is on track for construction completion in Q4 2022. • Operating revenues are less than budgeted, as are the operating expenses for April. Resulting in a positive net effect of $1.0 M. • Net total (operating cashflow) was $1.2 M positive compared to budget, driven primarily by lower operating expenses and positive investment income. • We are approximately 76% spent on Construction Budget, reflecting the increase in boring and operating crews in 2021. Completed Bore Length 2,340,157 ft 86.5% Total Bore Length 2,704,557 ft* Completed Fiber Pulled through Conduit 2,585,494 ft 52.2% Total Fiber Pulled through Conduit 4,952,640 ft Total Fiber Area Construction Completed 140 *A Fiber Area on average serves 225 homes 39.2% Total Fiber Area* 357 Spent to Date $83,284,433 76.3% Total Construction Budget $109,217,775 * Bore Length may be updated through the course of the project as design is completed.