HomeMy WebLinkAboutReport - Mail Packet - 4/27/2021 - Fort Collins Connexion Monthly Report - April 2021CONNEXION MONTHLY REPORT APRIL 2021 FIBER AREAS UPDATE Monthly info / highlights • Over 29.4 miles of fiber were installed in March, along with 322 vaults and 606 flowerpots (smaller vaults). • Project to date: 447.5 miles of fiber have been installed along with 7,107 vaults and over 12,807 flowerpots. • Extreme cold temperatures in early 2021 resulted in limited Connexion underground construction and an increase in temporary drop installations to homes. As weather conditions are improving, our crews are returning to permanently bury these lines. • All construction work occurs in the public right-of-way (ROW) or existing utility easements. Our crews do their best to minimize damage to landscaping and irrigation systems. When damage does occur, please call our Help Line at 970-674-7800 for assistance. OVERALL FIBER CONSTRUCTION THROUGH MARCH ‘21 2018 2019 2020 2021 2022 2023 Design Construction Available Atlantic Engineering Group (AEG) work Connexion Service Availableongoing 0 Ft 500,000 Ft 1,000,000 Ft 1,500,000 Ft 2,000,000 Ft 2,500,000 Ft 3,000,000 Ft 3,500,000 Ft Y 2019Jan-20Feb-20Ma r-20Apr-20May-20Jun-20Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21Feb-21Ma r-21Apr-21May-21Jun-21Jul-21Aug-21Sep-21Oct-21Nov-21Dec-21Fiiber Pulled in FeetFiber Pulled Actual Forecasted 0 50 100 150 200 250 Y 2019Jan-20Feb-20Ma r-20Apr-20May-20Jun-20Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21Feb-21Ma r-21Apr-21May-21Jun-21Jul-21Aug-21Sep-21Oct-21Nov-21Dec-21#of AreasFiber Areas Complete Actual Forecasted *Includes fibers areas that have construction completed and turned over for QC Total Fiber Areas Complete* Total Fiber Pulled FINANCES Connexion YTD Budget to Actual as of March ‘21 BUDGET ACTUAL BETTER / (WORSE) Operating Revenues* $1,978,739 $889,229 $(1,089,510) Operating Expense** $3,196,374 $1,268,733 $1,927,642 Net Operations $(1,217,635) $(379,504) $838,131 Investment Income $142,578 $385,677 $243,099 Net Total $(1,075,057) $6,173 $1,081,231 BUDGET PROJECT TO DATE REMAINING Construction Budget $109,217,775 $80,032,246 $29,185,529 * Excludes investment earnings on bond proceeds ** Excludes Depreciation CONNEXION MONTHLY REPORT Auxiliary aids and services are available for persons with disabilities. V/TDD: 711 APRIL 2021 21-23092 As we enter in to the third year of Connexion’s rollout, our deployment is on track for construction completion in Q4 2022. • Operating revenues are less than budgeted, as are the operating expenses for March. Resulting in a positive net effect of $838 K. • Net total (operating cashflow) was $1.08 M positive compared to budget, driven primarily by lower operating expenses and positive investment income. • We are approximately 73% spent on Construction Budget, reflecting the increase in boring and operating crews in 2021. Completed Bore Length 2,193,389ft 86.5% Total Bore Length 2,536,272 ft Completed Fiber Pulled through Conduit 2,362,802ft 47.7% Total Fiber Pulled through Conduit 4,952,640 ft Total Fiber Area Construction Completed 129 *A Fiber Area on average serves 225 homes 36.1% Total Fiber Area* 357 Spent to Date $80,032,246 73.2% Total Construction Budget $109,217,775