Loading...
HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 11/20/2018 - FIRST READING OF ORDINANCE NO. 143, 2018, AUTHORIZAgenda Item 13 Item # 13 Page 1 AGENDA ITEM SUMMARY November 20, 2018 City Council STAFF Eileen Dornfest, Special Projects Manager Carol Webb, Deputy Directory, Utilities Gerry Paul, Director of Purchasing & Risk Management Eric Potyondy, Legal SUBJECT First Reading of Ordinance No. 143, 2018, Authorizing the Purchasing Agent to Enter into Contracts for Services, Professional Services and/or Construction in Excess of Five Years for the Proposed Enlargement of Halligan Reservoir. EXECUTIVE SUMMARY The purpose of this item is to authorize the Purchasing Agent, pursuant to City Code Section 8-186(a), to enter into contracts greater than five years in length for services, professional services and/or construction of the proposed enlargement of Halligan Reservoir, which is the preferred alternative for the Halligan Water Supply Project. The request for a longer contract period is due to the large scope of the project and the uncertainties related to the schedule for design and construction. Any contracts authorized under the proposed ordinance would be no longer than ten years in length. STAFF RECOMMENDATION Staff recommends adoption of the Ordinance on First Reading. BACKGROUND / DISCUSSION The Halligan Water Supply Project (Halligan Project) is currently in the regulatory permitting phase, with federal permitting being led by the United States Army Corps of Engineers (Corps). The schedule for construction of the enlargement of Halligan Reservoir is primarily dictated by the permitting process, and the City has very limited control of the schedule until all permitting is complete. Permitting with the Corps began in 2006 and is anticipated to be complete by 2021, with a Record of Decision issued in 2022. In addition to the federal permitting process led by the Corps, several other permits are needed from other federal, state, and county agencies prior to construction. To expedite transition from permitting to construction, design of the enlargement of Halligan Reservoir will be conducted in parallel with permitting, beginning in 2019. Design for a project the size and complexity of the enlargement of Halligan Reservoir typically takes several years and is conducted in phases. The first phase of design, Preliminary Design, is scheduled for 2019-2020 and will provide critical information needed to verify current Halligan Project assumptions, refine the current construction cost estimate, and provide information needed for several permits required for construction. Following Preliminary Design and cost estimate refinement, the design will be advanced through Final Design at a schedule that will allow construction to begin as soon as all necessary permits are obtained. A Request for Proposals for a design team will be released in 2019. This design team will not only design the enlargement of Halligan Reservoir but will play a critical role during construction to ensure that construction is performed in accordance with the design. If the contract for design is executed in 2019, the current five-year contract limit stated in City Code Section 8-186(a) would terminate the contract in 2024. A best-case project Agenda Item 13 Item # 13 Page 2 schedule is presented in the latest Halligan Project update (Attachment 1), which shows that construction is anticipated to be underway in 2024 and will last approximately two years. This scenario would require a mid- project competitive purchasing process for the Halligan Project design team. Such a mid-project competitive purchasing process would be disruptive to the project and would incur additional cost to the City. If a new team is chosen by a mid-project competitive purchasing process, the change would result in significant costs related to onboarding new team members, as well as uncertainties related to liability for any issues that arise during design or construction. A similar scenario could develop for the construction contractor, who will join the Halligan Project team during design and will be responsible for construction of the multi-year project. Extending the length of contracts for the Halligan Project up to ten years for services, professional services and/or construction will provide the City with the continuity needed for the project team to efficiently deliver this multi-year project. CITY FINANCIAL IMPACTS This is a cost avoidance measure. Cost efficiencies will be realized by the City if the Purchasing Agent can enter into contracts for services, professional services and/or construction in excess of five years for the Halligan Project. ATTACHMENTS 1. Halligan Council Update October 2018 (PDF) HALLIGAN WATER SUPPLY UPDATE PROJECT October 2018 BACKGROUND The Halligan Water Supply Project will enlarge Halligan Reservoir, an existing reservoir on the North Fork of the Poudre River, to help meet future water supply needs. The population for Fort Collins Utilities’ Service Area is projected to increase by 45,000 by 2065, and the current water supply is not enough to support that growth under City policy, especially during a drought. The project would expand the reservoir by about 8,100 acre-feet (AF) by increasing the height of the existing dam by 25 feet. For context, an average single-family home served by Utilities uses almost a third of an AF of water each year. To enlarge Halligan Reservoir, permits are required from the U.S. Army Corps of Engineers (Corps) and other federal and state agencies. Before issuing permits, the Corps will produce an Environmental Impact Statement (EIS), which will be published for public review and comment. The EIS will describe the environmental impacts of the project, along with impacts of other alternatives to enlarging Halligan. HALLIGAN RESERVOIR SURFACE AREA Halligan Dam Existing Surface Area Enlarged Surface Area PROGRESS UPDATE City staff, consultants and the Corps made significant progress during the first three quarters of 2018. Developments include: • All indications are that the federal permitting process for the enlargement of Halligan Reservoir is on track and a Draft EIS is scheduled for mid-2019. • Continued developing mitigation and enhancement measures for the project. The City will issue a Conceptual Mitigation Plan at the same time as the Draft EIS. • Writing Chapters 1 through 4 of the Draft EIS, which will present a summary of the technical work conducted to date, including 1) definition of purpose and need for the project, 2) identification and comparison of alternatives to the Halligan Water Supply Project, 3) a description of environmental and cultural resources that could potentially be affected by each alternative, and 4) direct and indirect effects of constructing each alternative. • Staff initiated an evaluation of the feasibility and cost of reintroduction of greenback cutthroat trout, a “threatened” species, to the North Fork of the Cache la Poudre River as a possible enhancement measure to the Halligan project. • Completed additional studies on wetlands and aquatic habitat along the North Fork of the Poudre River, as required by the Corps. To facilitate these studies the water level in Halligan Reservoir was drawn down approximately 6 feet in May. • Investigated land acquisition needed for the project. • Developed plans for completing the design of dam enlargement. An April 6, 2018 memo to City Council provided revised cost estimates for the Halligan Reservoir enlargement. The total estimated cost for the project has increased to $74.1 million, indicating a need for $36.7 million in future appropriations. A breakout of costs is provided in the table to the right. Most of the cost increases are attributable to construction cost escalation, which is compounded by delays in the federal permitting process, and revised estimates of costs required to address project uncertainties. Considering the revised cost of the project, the unit cost of the Halligan Water Supply Project remains significantly lower than that of other water supply options. The Halligan Project will provide firm yield at a cost of $8,800 per AF. For comparison, the market rate for firm yield from the Colorado-Big Thompson, Northern Integrated Supply Project (NISP) and Windy Gap projects is $60,000, $25,000 and $14,000 per AF, respectively. Year-to-date expenditures through September are $550,000. PROJECT SCHEDULE BUDGET Release of the draft EIS is currently anticipated in April 2019. Construction could begin as early as 2023. Other project milestones are shown in the timeline below. EXPENSES ($M)1 To Date2 Future Total Acquisition $3.3 $0.3 $3.6 Permitting & Mitigation $12.7 $8.4 $21.1 Construction - $31.3 $31.3 Debt Service3 $1.9 - $1.9 Risk Mitigation/Contingency - $16.3 $16.3 Total $17.9 $56.1 $74.1 ESTIMATED FINAL UTILITY COST ($M) To Date2 Future Total Project Costs $17.9 $56.1 $74.1 Less Reimbursements4 ($4.6) ($0.1) ($4.7) Total5 $13.3 $56.0 $69.4 APPROPRIATIONS ($M) To Date2 Future Total Past Appropriations $37.4 - $37.4 Required Future Appropriation - $36.7 $36.7 Total $37.4 $36.7 $74.1 1. Expenses include escalation through 2023 in each line item. Line items may not add up to the total due to rounding. 2. Through September 2018. 3. Debt service payments from 2004 to 2014 were allocated as Halligan Project expenses. All future debt service payments will not be counted as a project cost. 4. Reimbursements were received from former project partners (North Poudre Irrigation Co. and the Tri-Districts) between 2005 and 2014; miscellaneous reimbursements have been and will be collected from the City of Greeley and from rents in the future. Reimbursements for project expenses require Council action to be re-appropriated to the project budget. 5. Total Utility cost includes debt service and deducts reimbursements. For more information, visit fcgov.com/halligan Eileen Dornfest, Special Projects Manager • 970-416-4296 • edornfest@fcgov.com Auxiliary aids and services are available for persons with disabilities, V/TDD 711. Esta información puede ser traducida, sin costo para usted, 970-212-2900. Utilities ‘06 ‘07 ‘08 ‘09 ‘10 ‘11 ‘12 ‘13 ‘14 ‘15 ‘16 ‘17 ‘18 ‘19 ‘20 ‘21 ‘22 ‘23 ‘24 ‘25 Federal Permitting - Draft EIS -1- ORDINANCE NO. 143, 2018 OF THE COUNCIL OF THE CITY OF FORT COLLINS AUTHORIZING THE PURCHASING AGENT TO ENTER INTO CONTRACTS FOR SERVICES, PROFESSIONAL SERVICES AND/OR CONSTRUCTION IN EXCESS OF FIVE YEARS FOR THE PROPOSED ENLARGEMENT OF HALLIGAN RESERVOIR WHEREAS, City Code Section 8-186(a) states that no contract for services or professional services, including all renewals, shall be made by the City for a period longer than five years, unless authorized by ordinance, which ordinance shall not be passed as an emergency ordinance; and WHEREAS, City is pursuing the Halligan Water Supply Project (“Project”), which includes the City’s preferred alternative of the enlargement of Halligan Reservoir, an existing reservoir located on the North Fork of the Cache la Poudre River; and WHEREAS, the enlargement of Halligan Reservoir will be a substantial undertaking that will require significant design and construction work, the specifics of which depend on various investigations that are planned to be completed; and WHEREAS, the work associated with the enlargement of Halligan Reservoir, including design and construction work, will likely take more than five years due to various factors, including the scope of the Project and legal and regulatory requirements; and WHEREAS, it is in the best interest of the City and the citizens of Fort Collins, including ratepayers of Fort Collins Utilities, that the City be authorized to enter into contracts for services, professional services, and/or construction in excess of five years for the proposed enlargement of Halligan Reservoir in order to, among other things, receive better proposals for the design and construction work, maintain continuity of the design and construction work throughout the Project, and therefore avoid costs related to transitions of project team members due to contract expiration; ; NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF FORT COLLINS as follows: Section 1. That the City Council hereby makes and adopts the determinations and findings contained in the recitals set forth above. Section 2. That the Purchasing Agent is hereby authorized to enter into contracts for services and professional services in excess of five years, but not to exceed ten (10) years, for the proposed enlargement of Halligan Reservoir. -2- Introduced, considered favorably on first reading, and ordered published this 20th day of November, A.D. 2018, and to be presented for final passage on the 4th day of December, A.D. 2018. __________________________________ Mayor ATTEST: _______________________________ City Clerk Passed and adopted on final reading on the 4th day of December, A.D. 2018. __________________________________ Mayor ATTEST: _______________________________ City Clerk Federal Permitting - Final EIS Federal Permitting - Final Decision Other Federal & State Permitting Preliminary Design Final Design Construction Enlarged Halligan Operations • Provided outreach on the project to environmental groups and federal and state elected officials. N ATTACHMENT 1