HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 08/16/2016 - FIRST READING OF ORDINANCE NO. 100, 2016, APPROPRIAgenda Item 12
Item # 12 Page 1
AGENDA ITEM SUMMARY August 16, 2016
City Council
STAFF
Jon Haukaas, Water Engr Field Operations Mgr
Lance Smith, Strategic Financial Planning Manager
SUBJECT
First Reading of Ordinance No. 100, 2016, Appropriating Prior Year Reserves in the Storm Drainage Fund to
Construct the Fort Collins/Timnath Boxelder Creek Flood Mitigation Projects and Transferring Appropriations to
the Cultural Services and Facilities Fund for the Art in Public Places Program.
EXECUTIVE SUMMARY
The purpose of this item is to appropriate $979,700 from Prior Year Reserves in the Storm Drainage Fund to
cover increased project costs due to a number of additional project scope changes necessary to complete the
Boxelder Creek Outfall project as it crosses Prospect Road.
STAFF RECOMMENDATION
Staff recommends adoption of the Ordinance on First Reading.
BACKGROUND / DISCUSSION
In 2009, the City of Fort Collins and the Town of Timnath entered into an intergovernmental agreement
regarding various issues, including stormwater and floodplain issues (Timnath IGA). The Timnath IGA has
been amended various times. Ordinance No. 047, 2014, approved the sixth amendment to the Timnath IGA
which, among other things, addressed the Boxelder Creek Flood Mitigation Projects and how costs would be
shared. Ordinance No. 090, 2014, appropriated funds to design and construct the Boxelder Creek Flood
Mitigation Projects. The original estimate for the projects was $4,000,000, which Fort Collins and Timnath
have agreed to share equally. The Timnath IGA anticipated that additional funds may be needed due to the
preliminary nature of the design and the timing of the projects to be constructed in a future year. Fort Collins is
the lead and provider of the engineering and project management service for the projects. Fort Collins thus
must appropriate the funds in order to execute the contracts. Timnath will provide reimbursement of shared
costs after completion.
The expenses totaling $979,700 for which additional funding is being requested have been identified since the
inception of this project as described below:
Boxelder Creek Cleanout-$175,000
In order to obtain a Canal Crossing Agreement with the Lake Canal Company for the Boxelder Creek Siphon,
as well as other agreements required for flood control improvements to the north, Lake Canal Company
required Utilities Department to dredge/cleanout Boxelder Creek between Mulberry Street and their diversion
structure on the on Boxelder Creek near I-25.
Agenda Item 12
Item # 12 Page 2
Boxelder Creek Siphon-$104,000
In order to obtain a Canal Crossing Agreement with the Lake Canal Company for the Boxelder Creek Siphon,
the company required several design features that were not anticipated in the original cost estimate. These
features include a debris sump with two manual gates in the upstream inlet structure, and a Parshall Flume
with a manual gate to measure augmentation releases to Boxelder Creek.
Additional Required Prospect Road Improvements-$98,000
The original Prospect Road rehabilitation requirements were to patch Prospect for 115 feet over the new Flood
Overflow Channel box culverts. When the Boxelder Creek Bridge Replacement by Engineering Department
became part of the project there was a complete redesign of Prospect Road between and including both
projects. Additional requirements include additional paving for a total of 370 feet on Prospect Road,
construction of the Glanz property approach, and the construction of a one foot vertical curve over the overflow
channel culverts.
Concrete Toe-Walls, Wing-Walls, Parapet-Walls, and Epoxy Coated Rebar-$53,000
During the design process the tow-walls, wing-walls, and parapet-walls for the box culvert crossing needed to
be increased in size to accommodate the additional loading of the improved Prospect Road design. Three
additional cost increases associated with this work were as follows: The cost of concrete has increased from
when the project was estimated in 2013 from $95/cubic yard to $115/cubic yard. Aggregate costs increased
from $18/ton to $27/ton. The Colorado Department of Transportation required an upgrade to epoxy coated
rebar at a cost of $9,000.
Additional Greeley Waterline Relocation Requirements-$130,000
In order to get approvals from Greeley Water Department to relocate its 27-inch and 30-inch water
transmission mains under the new flood control box culverts and overflow channel, it required additional
relocation pipe lengths, very strict testing and disinfection regiments, additional air valve manholes, and
additional cathodic protection with test stations.
Underdrain to Eliminate State Augmentation Requirements-$44,000
Late in the design process it was discovered that an underdrain was required in the overflow channel to
eliminate evaporation losses from standing groundwater and the requirement to provide augmentation water to
compensate for these losses.
Urban Design Features-$366,000
When Utilities partnered with the Engineering Department to construct both projects under one road closure
the requirement was placed on Utilities to include urban design features on the overflow channel parapet walls
and sidewalks to match the features on the new Boxelder Creek Bridge and the future Prospect Road/I-25
interchange. These urban design features include, but are not limited to, stone facades and stone caps at
columns and walls, railings at parapet walls, structural coating, and sandblasting and staining of stone facades,
caps, and sidewalks.
Contribution to Art in Public Places-$9,700
These additional costs require an additional 1% contribution to the Art in Public Places Fund. The stormwater
utility has not yet reached the cap on its annual Art in Public Places contributions for 2016 (each utility’s
contributions are capped at .5% of its annual budgeted operating revenues).
Agenda Item 12
Item # 12 Page 3
CITY FINANCIAL IMPACTS
The Storm Drainage Fund Reserve currently has a balance of approximately $4.1 million. Approximately $2
million is proposed to be used in the 2017-2018 BFO process. Additionally, as of July operating revenues in
the Storm Drainage Fund are 7.4% over budget, or $628K. At the current rate it is estimated operating
revenues will be $1-$1.5 million over budget for the year.
BOARD / COMMISSION RECOMMENDATION
This project has been presented to the Water Board many times over the past several years. Initially in the
Master Planning phases and more recently in the final design and construction update phases. The Water
Board continues to support the project.
-1-
ORDINANCE NO. 100, 2016
OF THE COUNCIL OF THE CITY OF FORT COLLINS
APPROPRIATING PRIOR YEAR RESERVES IN THE STORM DRAINAGE
FUND TO CONSTRUCT THE FORT COLLINS/TIMNATH BOXELDER
CREEK FLOOD MITIGATION PROJECTS AND TRANSFERRING
APPROPRIATIONS TO THE CULTURAL SERVICES AND FACILITIES
FUND FOR THE ART IN PUBLIC PLACES PROGRAM
WHEREAS, in 2009 the City and the Town of Timnath (“Timnath”) entered into an
intergovernmental agreement (“IGA”) regarding certain stormwater and floodplain issues; and
WHEREAS, the IGA has been amended various times, including by a sixth amendment,
approved by Ordinance No. 047, 2014 (“Sixth Amendment”); and
WHEREAS, the Sixth Amendment identifies the scope and locations of the Boxelder
Creek Flood Mitigation Projects (“Projects”); and
WHEREAS, at that time of the Sixth Amendment, the cost of the Projects was estimated
to be $4,000,000, which amount Fort Collins and Timnath have agreed to share equally in order
to complete the Projects; and
WHEREAS, the Sixth Amendment anticipated that additional funds may be needed due
to the preliminary nature of the design and the timing of the Projects to be constructed in future
years; and
WHEREAS, the actual costs of the Projects has been greater than originally estimated
dues to a number of causes; and
WHEREAS, Fort Collins, as lead and provider of the engineering and project
management service for the Projects, must appropriate the funds in order to execute the contracts
for the Projects; and
WHEREAS, Timnath will provide reimbursement of shared costs after completion of the
Projects pursuant to the Sixth Amendment; and
WHEREAS, Fort Collins Utilities is requesting an appropriation of $979,700 from the
Storm Drainage Fund Reserves to cover increased costs of the Projects; and
WHEREAS, of the total $979,700 requested appropriation, $9,700 represents the amount
to be appropriated in the Art in Public Place (“APP”) project for the Storm Drainage Fund, and
of that $9,700 amount, $2,134 (22%) will be transferred to the Cultural Services and Facilities
Fund for the maintenance of the artwork and operations of the APP program; and
WHEREAS, Article V, Section 9 of the City Charter permits the City Council to
appropriate by ordinance at any time during the fiscal year such funds for expenditure as may be
-2-
available from reserves accumulated in prior years, notwithstanding that such reserves were not
previously appropriated; and
WHEREAS, Article V, Section 10, of the City Charter authorizes the City Council to
transfer by ordinance any unexpended and unencumbered appropriated amount or portion thereof
from one fund (project) to another fund (project), provided that the purpose for which the
transferred funds are to be expended remains unchanged.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF
FORT COLLINS as follows:
Section 1. That the City Council hereby makes and adopts the determinations and
findings contained in the recitals set forth above.
Section 2. That there is hereby appropriated for expenditure from prior year reserves
in the Storm Drainage Fund the sum of NINE HUNDRED SEVENTY-NINE THOUSAND
SEVEN HUNDRED DOLLARS ($979,700) as follows:
Boxelder Creek Crossing of Prospect Road Project $970,000
Art in Public Places Project 9,700
TOTAL $979,700
Section 3. That the unexpended appropriated amount of TWO THOUSAND ONE
HUNDRED THIRTY-FOUR DOLLARS ($2,134) is authorized for transfer to the Art in Public
Places Projects from the Storm Drainage Fund to the Cultural Services and Facilities Fund and
appropriated therein for the Art in Public Places Program Maintenance and Operations.
Introduced, considered favorably on first reading, and ordered published this 16th day of
August, A.D. 2016, and to be presented for final passage on the 6th day of September, A.D.
2016.
__________________________________
Mayor
ATTEST:
_______________________________
City Clerk
-3-
Passed and adopted on final reading on the 6th day of September, A.D. 2016.
__________________________________
Mayor
ATTEST:
_______________________________
City Clerk