October 6, 2015
Ginny Sawyer, Policy and Project Manager
Darin Atteberry, City Manager
WORK SESSION ITEM
City Council
SUBJECT FOR DISCUSSION
Timing of Community Improvement Program Projects (Dedicated ¼-cent).
EXECUTIVE SUMMARY
The purpose of this item is to discuss and confirm project timing for projects approved in April 2015 as part of the
¼-cent Community Improvement Program. The Program includes 17 funds and projects to be implemented
between 2016 and 2025.
GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED
1. Which of the one-time capital projects does Council support completing between 2016 and 2019?
2. Of the timing scenarios provided, which is Council’s preference?
BACKGROUND / DISCUSSION
After an 18-month community conversation and ballot referral by Council, in April 2015, voters approved a 10-
year, ¼-cent sales tax for specific community improvements. All projects/funds are very specifically identified in
the ballot language and in the associated ordinance. However, the timing of the projects is not defined.
Staff has worked on numerous timing scenarios, taking into account community needs and desires, project
readiness, leveraging opportunities, and program effectiveness. This work and associated discussions have led
to the creation of multiple possible timing scenarios.
Following the August 25 work session, staff was asked to develop additional timing scenarios. Six scenarios were
developed and provided in a memo to Council. For this work session, staff has reduced the options to three that
appear to be most viable.
Considerations:
All scenarios reflect grant matches needed in select funds.
Capital Projects:
Carnegie Building- $1.7M
City Park Train- $350K
Club Tico- $250K
Poudre River/Whitewater Park- $4M
Gardens Visitor’s Center- $2M
Lincoln Bridge- $5.3M
Linden Street- $3M
SE Community Center- $14M
Willow Street- $3.5M
Funds:
Affordable Housing- $4M
Arterial Intersections- $6M
Bike Infrastructure- $5M
Bike/Ped Crossings- $6M
Bus Stops-$1M
Nature in the City- $3M
Sidewalks- $14M
Bus Replacement- $2M
October 6, 2015 Page 2
All funds need and desire predictable and relatively even funding to manage programs, workloads, and to
accomplish identified goals.
The Lincoln Bridge, Poudre River Enhancements, and the SE Community Center are the three major projects
that drive the timing options.
Public Outreach
Following the previous work session on August 25, staff posted an online questionnaire regarding timing and
hosted an open house. While the open house had minimal attendance, the conversation was good and focused
on understanding the complexities and give and take of a pay-as-you-go program and a desire to provide
amenities for the entire community.
The online questionnaire saw a large number residents in the southeast quadrant of the City participate and
reflected a strong desire to complete the Southeast Community Center as early in the process as possible.
Detailed questionnaire results are provided in the Council memo.
ATTACHMENTS
1. Timing Scenarios (PDF)
2. Description of Capital Projects and Funds (PDF)
3. August 25 Work Session Summary (PDF)
4. Powerpoint presentation (PDF)
SCENARIO A SCENARIO B SCENARIO C*
Capital Projects by Year:
City Park Train- 2016
Club Tico- 2016
Lincoln Bridge- 2016/17
Visitor’s Center- 2017
Poudre River- 2018
Willow Street- 2018/19
Linden Street- 2019/20
Carnegie- 2020
SE Community Center- 2023/24
Capital Projects by Year:
City Park Train- 2016
Club Tico- 2016
Lincoln Bridge- 2016/17
Visitor’s Center- 2017
Poudre River- 2018
Willow Street- 2018/19
Linden Street- 2019/20
SE Community Center- 2022/23
Carnegie- 2024
Capital Projects by Year:
City Park Train- 2016
Club Tico- 2016
Lincoln Bridge- 2016/17
Poudre River- 2017
Visitor’s Center- 2018
Willow Street- 2018/19
Linden Street- 2019/20
SE Community Center- 2022/23
Carnegie- 2024
Fund totals 2016-2019 only:
Affordable Housing- $1.1M
Arterial Intersections- $1.7M
Bike Infrastructure- $1.2M
Bike/Ped Crossings- $3M
Bus Stops-$400K
Nature in the City- $800K
Sidewalks- $4.2M
TransFort Bus Replacement- $500K
Fund totals 2016-2019 only:
Affordable Housing- $1.1M
Arterial Intersections- $1.5M
Bike Infrastructure- $1.35M
Bike/Ped Crossings- $3.5M
Bus Stops- $400K
Nature in the City- $800K
Sidewalks- - $4.2M
TransFort Bus Replacement- $500K
Fund totals 2016-2019 only:
Affordable Housing- $1.1M
Arterial Intersections- $1.5M
Bike Infrastructure- $1.35M
Bike/Ped Crossings- $3.5M
Bus Stops- $400K
Nature in the City- $800K
Sidewalks- - $4.2M
TransFort Bus Replacement- $500K
*Scenario C has a $1.25M deficit in 2017 that needs to be resolved.
*Resolution could be an advance from Building Community Choices (to be paid back in 2018).
1
Capital Projects
City Park Train
$350K
This project brings back the much loved City Park train in a new, expanded location east of the
playground.
Club Tico Renovation
$250K
This project completes the renovation of Club Tico at City Park by renovating the kitchen and
restrooms and adding a second story deck on the south side of the facility.
Downtown Poudre River Enhancements and Whitewater Park
$4M for initial construction / $50K for annual operations and maintenance
The Coy diversion project (near the Power Plant building) involves modifying or removing the Coy
diversion structure, creating a whitewater park with viewing/picnic areas, improving access to the
river, enhancing the river’s habitat and beauty, and adding a pedestrian bridge over the river east of
College. The project also lowers the river channel to improve flood mitigation and prevent flooding
of College Avenue.
Additional Considerations:
Citizens are raising $1.5 Million as part of the project
Gardens on Spring Creek Visitor’s Center
$2M for initial construction/ $40K for annual operations and maintenance
This project completes the Visitor’s Center at the Gardens on Spring Creek. The Visitor’s Center
currently contains a production greenhouse, Evelyn Clark Classroom, a lobby and offices. The
envisioned building contains a conservatory, large meeting room, observation tower, new entryway
with gift shop, a small café, and additional office space. These additions will double the square
footage of the facility.
Additional Considerations:
Citizens are raising $1 Million as part of the project
Lincoln Avenue Bridge
$5.3M for initial construction/ $36K for annual operations and maintenance
This project will fund design, right-of-way acquisition, and construction of improvements to the west
segment of Lincoln Avenue located between the Union Pacific Railroad Tracks just north of
Jefferson Street to 1st Street, including the Poudre River Bridge.
Linden Street Renovations
$3M for initial construction / $12K for annual operations and maintenance
This project will fund the final design and construction of the preferred options for the renovation of
an important downtown block of Linden Street. This block is one of the city’s most programmed
streets, hosting festivals, events and concerts throughout the year. This project concept would
reconstruct the entire block into a brick street that could be closed off for special events but still allow
vehicle parking in non-event days.
ATTACHMENT 2
2
Renovation of the Historic Carnegie Building
$1.7M for initial construction; $10K for annual operations and maintenance
This project renovates the historic 1904 Carnegie library building in Library Park to enhance its use
as a community asset. The project specifically focuses on stabilizing and protecting this historic
structure, addressing infrastructure issues, adding needed amenities, such as a staircase and
restrooms, and other general improvements to allow it to serve as a community center in the heart of
downtown.
Southeast Community Center and Outdoor Pool
$14M for initial construction/ $230K for annual operations and maintenance
This project envisions a unique Community Center focused on innovation, technology, art, recreation
and the creative process. The Center will be a place for the community to try-out new technologies
like 3-D printers, laser cutters, robotics and emerging software. It will be a true makerspace. It will
include a multi-functional performance space and a social area. The Center will focus on wellness
with fitness rooms for classes from Aikido to Zumba and by connecting to the beautiful surrounding
park environment. The Center will also have a large outdoor leisure pool with water slides, sprays
and jets, decks, a lazy river and open swimming area.
Willow Street Improvements
$3.5M for initial construction/ $11K for annual operations and maintenance
This project would fund final design and construction of improvements to Willow Street as identified in
the River District Infrastructure Plan. This project is envisioned to extend vibrant, pedestrian-
oriented activities to the River District. Wide sidewalks, on-street parking, urban design, landscaping
and potentially a linear water feature are planned.
Additional Considerations:
Downtown Development Authority is willing to contribute ~400K to this project
Funds
Affordable Housing Fund
$4M over 10 years
This fund would provide a revenue source for the capital costs of development or rehabilitation of
one or more housing projects designated specifically for low income individuals and families. The
$4M contribution may be combined with or leverage other sources of income directly related to
housing affordability including funds from the Housing Bank, licensing fees, Affordable Housing fund,
grants, etc.
Additional Considerations:
Local commitment of funding in the first years of the BOB time period is critical for being
awarded Low Income Housing Tax Credits and other leveraging opportunities.
Arterial Intersection Improvements Fund
$6M over 10 years
This project provides funding for improvements to arterial intersections prioritized by congestion and
safety improvements for all travel modes. Previous funding for these projects was highly successful
as matching funds for grants and the dollars were doubled over the life of the tax. The fund is a
3
direct and effective way to address citizen concerns regarding worsening traffic, congestion and
roadway safety.
Additional Considerations:
Having continuous funding provides the most flexibility to match dollars for short lead time
grant and leveraging opportunities.
Need sufficient match in 2017 and 2018 (total of ~$500,000) for a federal grant.
Bicycle/Pedestrian Grade-Separated Crossings Fund
$6M for construction/ $20K for operations and maintenance
This project establishes an annual fund that would construct top priority grade-separated bicycle and
pedestrian crossings across arterial roadways. Potential locations include the Power Trail crossing at
Harmony Road, crossing Shields Street west of the CSU Main Campus, crossing Prospect Road
near Center Avenue, and major arterial crossings by the Mason Trail.
Additional Considerations:
Need sufficient dollars with in a two year period ($1.5 to $2m) to fund one crossing.
Bicycle Infrastructure Improvements - Safe Routes to Everywhere
$5M over 10 years
This package provides funding to be used toward stand-alone bicycle infrastructure projects as well
as add-on elements to other projects that complete or enhance the City’s bicycle network. Projects
will enhance safety, provide wayfinding, and improve comfort for bicyclists.
Additional Considerations:
In 2014 City Council adopted a new Bicycle Master Plan that establishes a “low stress”
bicycle network with a proposed completion date of 2020. Delayed or inconsistent funding
would result in the networks not being completed according to the plan timeframe.
Bus Stop Improvements -Safe Routes to Everywhere
$1M over 10 years
Currently there are more than 200 bus stops within the Transfort system that do not meet Americans
with Disabilities Act (ADA) access requirements. This funding would allow Transfort to upgrade 10
bus stops per year to be ADA accessible and improve mobility options for disabled residents of Fort
Collins.
Additional Considerations:
Consistent annual funding would allow for more efficient planning and scheduling of work.
Implementing Nature in the City
$3M for specific projects/ $100K for operations and maintenance
The City is transitioning from a large, suburban town to a small, urban city with a projected 250,000
residents. As this happens, it is critical that we protect access to nature and the key open spaces
that define our community. Natural spaces within our urban setting are valuable not only as habitats
and for aesthetics, but they are also key to preserving quality of life, and the sense of place that
makes Fort Collins unique. To achieve the vision set forth in the Nature in the City strategic plan,
this project will: (1) fill in gaps either to achieve a 10-minute walk or to enhance species connectivity,
and (2) enhance existing sites to provide greater habitat variety and natural experiences.
4
Additional Considerations:
It is expected that these funds will leverage internal funds and perhaps external funds as
well. Consistent annual funding will inspire the confidence of our potential partners.
Pedestrian Sidewalk and ADA Compliance Program - Safe Routes to Everywhere
$14M over 10 years
The Pedestrian Sidewalk and ADA Compliance Program is based on the 2013 assessment and the
program cost has been quantified into a 52-year program. The City is not in compliance with the
Americans with Disabilities Act. With the $134 million Sidewalk and ADA Compliance Program
needs, a sustainable and predictable revenue source is needed to implement the overall cost of
construction of a 52-year compliance program.
Additional Considerations:
Critical to have consistent funding which will allow an annual program that can leverage
projects with Street Maintenance, Capital Projects, Safe Routes to School program and the
Bus Stop program.
Transfort Bus Fleet Replacement
$2M over 10 years
The funding of this project would provide the 20% local match needed to replace 20 heavy duty
buses over the next 10 years. This 20% or, $2 million, would be leveraged to receive $8 million of
federal and state grant funding. Over the next ten years three-quarters of Transfort’s fleet will be
beyond its useful life. The replacement of buses beyond their useful life will reduce maintenance
expenses and ensure reliable service to the Transfort customer.
Additional Considerations:
Funding should match grant cycles.
ATTACHMENT 3
1
Council Work Session
October 6, 2015
Timing of Community Improvement
Program Projects
ATTACHMENT 4
Questions/Direction Sought
2
§ Which of the one-time capital projects does Council support
completing between 2016-2019?
§ Of the timing scenarios provided, which is Council’s preference?
Background
3
§ Dedicated tax (pay as you go) is method Fort Collins has historically
used to fund capital
§ Estimate ¼ -cent revenue at $83M
§ Target project dollar amount: $75.1 M
§ 5 years of O&M for select projects: $2.6M
§ 3% inflation on non-fund projects: $5.3 M
Community Improvement-Funds
4
Funds
§ Affordable Housing Fund- $4M
§ Arterial Intersection Improvements Fund - $6M
§ Bicycle Infrastructure Improvements - $5M
§ Bike/Ped Grade-Separated Crossings Fund - $6M
§ Bus Stop Improvements - $1M
§ Nature in the City - $3M
§ Pedestrian Sidewalk/ ADA Compliance - $14M
§ Transfort Bus Fleet Replacement - $2M
Community Improvement-Projects
5
Capital Projects
§ Carnegie Building Renovation - $1.7M
§ City Park Train - $350K
§ Club Tico Renovation - $250K
§ Downtown Poudre River Enhancements- $4M
§ Gardens on Spring Creek Visitor’s Center - $2M
§ Lincoln Ave Bridge Improvements - $5.3M
§ Linden Street Renovations - $3M
§ Southeast Community Center/Outdoor Pool - $14M
§ Willow Street Improvements – $3.5 M
Timing Rationale
6
§ Provide citizens tangible projects as early as possible
§ Leverage available funds and opportunities
§ Provide even and predictable funding for Funds throughout the
10-year term
§ Work with known grant cycles
7
8
9
Questions/Direction Sought
10
§ Which of the one-time capital projects does Council support
completing between 2016-2019?
§ Of the timing scenarios provided, which is Council’s preference?