HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 07/21/2015 - SECOND READING OF ORDINANCE NO. 074, 2015, AUTHORAgenda Item 3
Item # 3 Page 1
AGENDA ITEM SUMMARY July 21, 2015
City Council
STAFF
Jon Haukaas, Water Engr Field Operations Mgr
Phil Ladd, Utilities Customer Accounts Supervisor
SUBJECT
Second Reading of Ordinance No. 074, 2015, Authorizing the Transfer of Previously Appropriated Funds in
the Storm Drainage Fund From Individual Stormwater Basin Capital Projects into the Stormwater Basin
Improvement Capital Project.
EXECUTIVE SUMMARY
This Ordinance, unanimously adopted on First Reading on July 7, 2015, transfers and consolidates previously
appropriated funds from the nine individual stormwater basin capital projects and the Drainage System
Replacement Project into the citywide Stormwater Basin Improvement Capital Project. All appropriations will
continue to be used for stormwater basin management improvement projects, while improving transparency
and flexibility to fund and construct the highest priority stormwater improvements that are required citywide.
STAFF RECOMMENDATION
Staff recommends adoption of the Ordinance on Second Reading.
ATTACHMENTS
1. First Reading Agenda Item Summary, July 7, 2015 (w/o attachments) (PDF)
2. Staff memo, July 10, 2015 (PDF)
3. Ordinance No. 074, 2015 (PDF)
Agenda Item 9
Item # 9 Page 1
AGENDA ITEM SUMMARY July 7, 2015
City Council
STAFF
Jon Haukaas, Water Engr Field Operations Mgr
Phil Ladd, Utilities Customer Accounts Supervisor
SUBJECT
First Reading of Ordinance No. 074, 2015, Authorizing the Transfer of Previously Appropriated Funds in the
Storm Drainage Fund From Individual Stormwater Basin Capital Projects into the Stormwater Basin
Improvement Capital Project.
EXECUTIVE SUMMARY
The purpose of this item is to transfer and consolidate previously appropriated funds from the nine individual
stormwater basin capital projects and the Drainage System Replacement Project into the citywide Stormwater
Basin Improvement Capital Project. All appropriations will continue to be used for stormwater basin
management improvement projects, while improving transparency and flexibility to fund and construct the
highest priority stormwater improvements that are required citywide.
STAFF RECOMMENDATION
Staff recommends adoption of the Ordinance on First Reading.
BACKGROUND / DISCUSSION
Prior to 1998, monthly stormwater capital improvement fees were collected individually by each separate
drainage basin and could only be used for the basin in which the fees were collected. Ordinance No. 168,
1998 changed the collection and use of monthly stormwater fees from the individual basins to a consolidated
uniform and citywide basis. Since 2006 (Ordinance No. 136, 2005) stormwater plant investment fees have also
been collected on a citywide basis. With the change in funding, prioritization of stormwater capital
improvements is done on a citywide basis for the safety and well-being of all citizens.
Each basin’s capital improvement project retains some unspent funding previously appropriated to that specific
basin. Basin specific projects continued to be funded with these remaining appropriations. Since the adoption
of the 2013-2014 Budget new appropriations are made to the citywide Stormwater Basin Improvements Project
and not to individual basins.
At this time, there are appropriations remaining in each basin project at a level that is either (A) insufficient to
pay for any particular project or (B) the monies remain in basins that do not have immediate capital project
needs. The consolidation of all these appropriations into the citywide Stormwater Basin Improvement Project
will allow staff to fund larger capital projects benefiting the City as a whole, as well as the specific basin for
which the funds were created.
The individual Stormwater Fund Basin accounts to be consolidated are shown in the following table:
Old Town Basin Improvements $11,184
Dry Creek Basin Improvements $1,043,059
ATTACHMENT 1
Agenda Item 9
Item # 9 Page 2
W. Vine Basin Improvements $763,585
Foothills Basin Improvements $4,778
Canal Importation Basin Improvements $602,946
Cooper Slough Boxelder Basin Improvements $353,956
Fossil Creek Basin Improvements $224,548
Cache La Poudre Drainageway Basin Improvements $167,780
Drainage System Replacements $174,020
Total Transfer to Stormwater Basin Improvements Capital Project $3,345,855
If the Ordinance is adopted, these project account balances will be moved under the citywide Stormwater
Basin Improvement Capital Project account and all open projects within the specific basins will also be under
the citywide project for accounting purposes.
CITY FINANCIAL IMPACTS
The Ordinance does not appropriate any new funding. The Ordinance provides for the consolidation of
existing appropriations to improve transparency and flexibility of using the existing stormwater basin
improvement appropriations to fund the highest priority projects. This Ordinance is also consistent with the
objectives stated by City Council in Ordinance No. 168, 1998, for uniform and citywide operation, maintenance,
and improvements to the stormwater system.
Stormwater funds will continue to be spent in alignment with the Stormwater Enterprise requirements and
approved Stormwater Master Plans.
BOARD / COMMISSION RECOMMENDATION
Funding of Stormwater Master Plan projects has been discussed with the Water Board many times over the
past several years. At its June 18, 2015 meeting, the Board recommended consolidation of the remaining
stormwater basin budgets as presented by staff on a vote of 7-1. (Attachment 2)
ATTACHMENTS
1. Ordinance No. 168, 1998 (PDF)
2. Water Board minutes (draft), June 18, 2015 (PDF)
ATTACHMENT 2
- 1 -
ORDINANCE NO. 074, 2015
OF THE COUNCIL OF THE CITY OF FORT COLLINS
AUTHORIZING THE TRANSFER OF PREVIOUSLY APPROPRIATED FUNDS IN THE
STORM DRAINAGE FUND FROM INDIVIDUAL STORMWATER BASIN CAPITAL
PROJECTS INTO THE STORMWATER BASIN IMPROVEMENT CAPITAL PROJECT
WHEREAS, this Ordinance provides for the consolidation of existing appropriations to
improve transparency and flexibility of using the existing stormwater basin improvement
appropriations to fund the highest priority projects, consistent with the objectives stated by City
Council in Ordinance No. 168, 1998, for uniform and city-wide operation, maintenance, and
improvements to the Stormwater system; and
WHEREAS, at this time, there are appropriations remaining in each basin project either
(A) at a level that is insufficient to pay for any particular project or (B) not needed because the
basin project does not have immediate capital project needs; and
WHEREAS, the consolidation of all these appropriations into the citywide Stormwater
Basin Improvement Project will allow staff to fund larger capital projects benefiting the City as a
whole, as well as the specific basin for which the funds were created; and
WHEREAS, the specifics of this re-appropriation were reviewed at the June 18, 2015,
Water Board meeting and the Board recommended consolidation of the remaining stormwater
basin budgets as presented by staff; and
WHEREAS, this Ordinance does not appropriate any new funding; and
WHEREAS, Article V, Section 10, of the City Charter authorizes the City Council to
transfer by ordinance any unexpended and unencumbered appropriated amount or portion thereof
from one fund (project) to another fund (project), provided that the purpose for which the
transferred funds are to be expended remains unchanged.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF
FORT COLLINS that the following funds are hereby authorized for transfer and appropriated for
expenditure for the purposes stated below.
Appropriation FROM these projects in the Storm Drainage Fund:
Old Town Basin Improvements $11,184
Dry Creek Basin Improvements $1,043,059
W. Vine Basin Improvements $763,585
Foothills Basin Improvements $4,778
Canal Importation Basin Improvements $602,946
Cooper Slough Boxelder Basin Improvements $353,956
Fossil Creek Basin Improvements $224,548
Cache La Poudre Drainageway Basin Improvements $167,780
Drainage System Replacements $174,020
- 2 -
TOTAL $3,345,855
Appropriation TO this project in the Storm Drainage Fund:
Stormwater Basin Improvements Capital Project $3,345,855
Introduced, considered favorably on first reading, and ordered published this 7th day of
July, A.D. 2015, and to be presented for final passage on the 21st day of July, A.D. 2015.
__________________________________
Mayor
ATTEST:
_______________________________
City Clerk
Passed and adopted on final reading on this 21st day of July, A.D. 2015.
__________________________________
Mayor
ATTEST:
_____________________________
City Clerk