HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 04/19/2016 - ITEMS RELATING TO THE FOSSIL CREEK TRAIL - COLLEGAgenda Item 7
Item # 7 Page 1
AGENDA ITEM SUMMARY April 19, 2016
City Council
STAFF
Jason Stutzman, Civil Engineer III
SUBJECT
Items Relating to the Fossil Creek Trail - College Avenue to Shields Street Project.
EXECUTIVE SUMMARY
A. Resolution 2016-036 Authorizing the City Manager to Enter Into a Grant Agreement with the State Board
of the Great Outdoors Colorado Trust Fund for the Fossil Creek Trail from College Avenue to Shields
Street.
B. First Reading of Ordinance No. 050, 2016, Appropriating Unanticipated Grant Revenue from Great
Outdoors Colorado (GOCO) in the Capital Projects Fund for the Fossil Creek Trail-College Avenue to
Shields Street Project.
The purpose of this item is to authorize the City Manager to enter into an intergovernmental agreement with
Great Outdoors Colorado (GOCO) for purposes of accepting grant funding and to appropriate the grant funds
for the construction of the Fossil Creek Trail from College Avenue to Shields Street. GOCO has awarded the
City a $1,000,000 trail grant. The proposed project would complete a major connection of the Fossil Creek
Trail from College Avenue to Shields Street. The project involves 1.25 miles of new concrete trail and a major
tunnel underpass structure at the Burlington Northern Santa Fe (BNSF) Railroad. The trail will connect to the
existing Fossil Creek Trail just west of College Avenue and terminate at the existing trail on the east side of
Shields Street. The layout of the trail has been discussed with appropriate City staff and area residents.
Design of the trail tunnel underpass phase of the project has reached the final stage. Construction of the trail
tunnel underpass will begin in 2016. GOCO requires a City resolution authorizing the City to enter into the
grant agreement. Pursuant to the grant agreement the City has until June 2017 to complete the project.
STAFF RECOMMENDATION
Staff recommends adoption of the Resolution and the Ordinance on First Reading.
BACKGROUND / DISCUSSION
In both 1996 and 2008, the City’s Parks and Recreation Policy Plan identified this section of the Fossil Creek
Trail as part of the master plan. The trail segment on Fossil Creek Wetlands Natural Area is shown on the
Fossil Creek Natural Areas Management Plan, which was completed in 2005. The City has been working with
BNSF for several years to get approval of the City’s plans for the underpass, and obtain the necessary
easements from the railroad to complete the work and operate and maintain the underpass on BNSF’s
property.
The GOCO grant agreement requires the City to operate, manage and maintain the project in a reasonable
state of repair for at least 25 years, subject to annual appropriations. The City must also place a sign at the
project site acknowledging GOCO’s assistance.
Agenda Item 7
Item # 7 Page 2
CITY FINANCIAL IMPACTS
Construction of the underpass is expected to cost approximately $2,700,000. Capital funding for the
construction of the underpass was budgeted from the Conservation Trust Fund in years 2015 and 2016.
Obtaining this grant will offset trail funds needed to complete the project. Funds for public art were set aside for
the underpass project from the appropriation of the Conservation Trust Fund money in accordance with the
City Code requirements for Art in Public Places (APP).
The total trail construction project, including the tunnel underpass, is estimated to cost approximately
$4,200,000. Staff will be submitting a budget offer for the remaining funds needed in the 2017-18 budgets.
Additional funding for APP will be included in that budget to bring the total APP funding for the project up to 1%
of the total project budget. Operation and maintenance funding for the project will be about $10,000 per year
and will be budgeted starting in the 2017 Parks budget.
BOARD / COMMISSION RECOMMENDATION
The trail connection was included in the 2013 Paved Recreational Trail Master Plan, which was reviewed by
the multiple boards, including the Parks & Recreation Board and the Land Conservation and Stewardship
Board. Project updates have been reviewed by the Parks and Recreation Board and the Land Conservation
and Stewardship Board as the project has progressed over the last few years.
PUBLIC OUTREACH
The 2008 Parks and Recreation Policy Plan included an opportunity for the community to review a map
showing future trails including the Fossil Creek Trail segment from College Avenue to Shields Street. The 2013
Paved Recreational Trail Master Plan included this proposed trail segment in information presented to the
community for their review.
Citizen responses in the 2013 Paved Recreational Trail Master Plan listed the Fossil Creek Trail from College
Avenue to Shields Street segment as one of the top three needed new trail projects
ATTACHMENTS
1. Location map (PDF)
2. Detailed location map (PDF)
HARMONY ROAD
HORSETOOTH ROAD
TRILBY ROAD
COLLEGE AVENUE
SHIELDS STREET
ATTACHMENT 1
Spring Canyon
Community Park
3.5 miles
Pub ub uublic lic licc cccccc R.RRO RRR.R O .W. W
Proposed Trail Alignment
Tra TTTrail iilll Eas Ea Eaa eme em nt Are Areaa
Proposed
Trail Underpass @
BNSF Railrway
Proposed Trail Alignment
Proposed Neighborhood
Trail Connection
Fossil Creek
Community Park
1.5 miles
EXIST TTING ING
CONNEE EECTI ECTION O
Foss Fossil il Cr rre reek Trail
Unde Underp rp ppass @
Coll College ege Aven ve v ue
EXIS EX EXI X TING T NG
CONN ONN ONNNEECTI ECTION ON
Maso Masonnn Trai Traill and
BRT Corr orr orr idor dor dorr
EXIS EXX TING TINGG
CONN CO CCONNECTI ECTI CCCTI TI TION ON
Foss Fossiil oss il Cree Creekkkkkk Tra T iill
Unde ndeeerpas rpas rpasssss
@Shie Shi Shields Stre St et ett ttt
SSSSSSSSSSSSSSkkkkkkkkkkkkkkkyyyyyyyyyyyyyyywwwwwwwwwwwwwwwaaaaaaaaaaaaayyyyyyyyyyyyyyyyyyyyy
NNNNNNNNNNNNNNNeeeeeeeeeeeeeeeeee iiiiiggggggggggggggggghhhhhhhhhhhhhhhhhhbbbbbbbbbbbbbbooooooooooooooooooooorrrrrrrrhhhhhhhhhhhhhhhhhooooooooooooooooooooooooooooooooooddddddddd dddddddddddddddddddddsssssssssssssssss
SSSSSSSSSSSSSSSSSccccccccccccc ccccccccccccceeeeeeeeeeeennniiiiicccccccccccccccccc KKKKKKKKKKKKKKKKKKKKKKnnnnnnnnnnnnnnnooooooooooooollllls sssssssss
NNNNNNNNNNNeeeeeeeeeeeeeeeeeeeeeeeeeiiiiiiiiii iiiiiiiiiiigggggggggggggggggghhhhhhhhhhhhhhhhbbbbbbbbbbbboooooooooooorrrrrrrrrrrrrrrrrhhhhhhhhhhhhhhhhhooooooooooooooooooooooooodddddddddd
dddddddddddsssssssssssssssssssss
Ad AAd AAAAddder er eer Es Essta EEEE ta taaate te tesss
Ne NNe NNNe Neig ig iggghb hb hhb bbbbbbbbbbbbbbbor or orrrhhho ho hooood od
AAAAAAAAAAAAAAAApppppppppppppppppp pppppppppppppppllllleeeeeeeeeeeeeewwwwwwwwwwwwwwwwwoooooooooooooooooooooooooooooodddddddddddddd
NNNNNNNNNNNNNNNNNNNNNeeeeeeeeeeeiiiiiiiiiiiiiiigggggggggggggggg gggggghhhhhhhhhhhhhhhhhhhhhhhhhhhhhbbbbbbbbbbbbbbbbbbbbbbbbooooooorrrrrrrrrhhhhhhhhhhhhhhhhhhhhhhhhhhoooooooooooooooooooooooooooooooodddddddddddddddddddddddddddssssssssssssssssssss
sssssssssssss
CCCCCCCCCCCCCCCCCCCllllllllllaaaaaaaaaaaaaaaaaarrrrrrrrrrrrrreeeeeeeeeeeeeeeeeeeeennnnnnnnndddddddddddddddddddddooooooooooooooooooooooooo oooooooooooonnnnnnnnnnnnnnnnnnnnn HHHHHHHHHHHHHHHHHiiiiiiiiiiiiiiiiilllllllllllllllllllllllllllllllllsssssssssss
NNNNNNNNNNNNNNNNNNNNeeeeeeeeeeeeeeeeeeiiiiiiiiiiiiiiggggggggggggggggggggghhhhhhhhhhhhhhhhhhhhhbbbbbbbbbbbbbbbboooooooooooooooorrrrrrrrrrrrrrrrrr rrrrrrrrrrrrhhhhhhhhhhhhhhhhhhhhhhhooooooooooooooooooooooooooooooooooddddddddddddddddddddsssssssssssssssssss
FUTURE Regional Trail
Connection to Loveland
City of Fort Collins
Project Location Map ATTACHMENT 2
-1-
RESOLUTION 2016-036
OF THE COUNCIL OF THE CITY OF FORT COLLINS
AUTHORIZING THE CITY MANAGER TO ENTER INTO A GRANT AGREEMENT WITH
THE STATE BOARD OF THE GREAT OUTDOORS COLORADO TRUST FUND FOR
THE FOSSIL CREEK TRAIL FROM COLLEGE AVENUE TO SHIELDS STREET
WHEREAS, the State Board of the Great Outdoors Colorado Trust Fund (GOCO) is a
political subdivision of the State of Colorado, which invests a portion of the net proceeds of the
Colorado Lottery in the State’s parks, wildlife, open space and recreational resources; and
WHEREAS, in 1994 GOCO created a statewide grant program through which eligible
entities could apply for grants for local government parks and outdoor recreation projects; and
WHEREAS, in 2014 the City applied to GOCO for a Paths to Parks trail grant to help
fund the connection of the Fossil Creek Trail from College Avenue to Shields Street (the
“Project”); and
WHEREAS, on June 19, 2014, GOCO approved the City’s application and awarded the
City a $1,000,000 grant for the Project; and
WHEREAS, the total cost of the Project, which includes construction of an underpass
under the Burlington Northern Santa Fe Railroad tracks, is approximately $4,200,000; and
WHEREAS, capital funding for construction of the underpass, which is expected to cost
approximately $2,700,000, was appropriated from the Conservation Trust Fund for 2015 and
2016, and the GOCO funds will be used to offset those funds; and
WHEREAS, the GOCO Grant Agreement, a copy of which is attached and incorporated
herein as Exhibit “A” (the “Grant Agreement”), requires a resolution, adopted by the grantee’s
governing body, authorizing the execution of the Grant Agreement and approving its terms and
conditions; and
WHEREAS, the City is authorized to enter into intergovernmental agreements, such as
grant agreements, to provide any function, service or facility, under Article II, Section 16 of the
Charter of the City of Fort Collins and Section 29-1-203 of the Colorado Revised Statutes; and
WHEREAS, the Grant Agreement further requires the City to operate, manage and
maintain the project in a reasonable state of repair for at least 25 years, subject to annual
appropriations, and to place a sign at the Project site acknowledging GOCO’s assistance; and
WHEREAS, City staff recommends that the City Council approve the Grant Agreement
as described herein.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF
FORT COLLINS as follows:
-2-
Section 1. That the City Council hereby makes and adopts the determinations and
findings contained in the recitals set forth above.
Section 2. That the City Manager is hereby authorized to enter into the Grant
Agreement with GOCO, obligating the City to use the $1,000,000 in grant proceeds for
construction of the Fossil Creek Trail connection from College Avenue to Shields Street, in
substantially the form attached as Exhibit A; and that the terms of the Grant Agreement are
approved, together with such other terms and conditions as the City Manager, in consultation
with the City Attorney, determines to be necessary or appropriate to protect the best interests of
the City.
Passed and adopted at a regular meeting of the Council of the City of Fort Collins this
19th day of April, A.D. 2016.
_________________________________
Mayor
ATTEST:
_____________________________
City Clerk
GRANT AGREEMENT
PROJECT:
Project Title: Fossil Creek Trail - College Avenue to Shields Street
Contract Number: 14364
Completion Date: June 19, 2017
PARTIES TO AGREEMENT:
Board: The State Board of the Great Outdoors Colorado Trust Fund
303 East 17
th
Avenue, Suite 1060
Denver, CO 80203
Grantee: City of Fort Collins
RECITALS
A. The State Board of the Great Outdoors Colorado Trust Fund (referred to herein as
“GOCO” or the “Board”) is a political subdivision of the State of Colorado, created by Article
XXVII of the Colorado Constitution, adopted at the November 1992 General Election, which
article appropriates a portion of the net proceeds of the Colorado Lottery to the Board and directs
the Board to invest those proceeds in the State’s parks, wildlife, open space and recreational
resources.
B. In 1994, the Board created a statewide grant program, pursuant to which eligible
entities could apply for grants for local government parks and outdoor recreation projects to
which Grantee responded with a detailed application (the “Project Application”).
C. Grantee submitted a Project Application to the Board which contemplates the
execution of the project entitled and described above (the “Project”). The Project is briefly
described in the Project Summary attached hereto as Exhibit A. The parties acknowledge that
they have on file a complete copy of the Project Application, which is incorporated herein.
D. The Board approved Grantee’s Project Application on June 19, 2014, subject to
the execution of a detailed grant agreement, and subject to the terms and conditions set forth
herein. The parties intend this agreement to be the detailed final grant agreement required by the
Board (the “Agreement”).
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
EXHIBIT A
2
AGREEMENT
NOW, THEREFORE, in consideration of the parties’ mutual covenants contained herein
and other good and valuable consideration, the receipt and sufficiency of which are hereby
acknowledged, the parties hereto agree as follows:
1. Incorporation of Recitals. The Recitals set forth above are hereby incorporated into
the terms of this Agreement.
2. Representations and Warranties of Grantee.
a. Grantee is a Municipality, duly organized in accordance with the laws of Colorado and
has full and lawful authority to enter into, and comply with the terms of, this Agreement.
b. Grantee’s governing body has authorized entering into this Agreement as evidenced by
the resolution attached hereto as Exhibit B.
c. Grantee does not own the property or properties on which the Project is to be located (the
“Property”). Therefore, the agreement attached hereto as Exhibit E between Grantee and the
Property’s owner continues in effect and unmodified throughout the term of this Agreement..
3. Grant and Project. Subject to the terms and conditions set forth in this Agreement, the
Board hereby awards to Grantee a sum not to exceed $1,000,000.00 (the “Grant”). The Grant
shall be used by Grantee solely to complete the Project, in substantial conformity with the final
plans, specifications, designs and uses approved by the Board.
4. Project Scope. Grantee shall not materially modify the Project or the Project budget
(attached hereto as Exhibit C, the “Budget”) without the prior written approval of the Executive
Director of GOCO (“Executive Director”) or the Executive Director’s designee, such approval
to be in GOCO’s sole discretion. Any material modification to the Project undertaken without
GOCO’s prior written consent may be deemed a breach of this Agreement by GOCO, entitling
GOCO to all remedies available under this Agreement. If Grantee determines with reasonable
probability that the Project will not or cannot be completed as reflected in the Project
Application, Grantee will promptly so advise the Board, and cooperate in good faith to seek a
resolution before any further funds are advanced.
5. Grantee Efforts. Grantee shall complete the Project in a timely fashion, in a good and
workmanlike manner, and consistent with this Agreement and GOCO’s approvals related to the
Project.
6. Completion Date. Grantee shall complete the Project and submit its Final Report no
later than (the “Completion Date”) which is 36 months after the Board’s approval of the
Project. Grantee may request an extension of the Completion Date in compliance with GOCO’s
Overdue Grants Policy, a summary of which is attached as Exhibit D (“Overdue Grants
Policy”). If Grantee determines with reasonable probability that the Project will not or cannot
be completed by the Completion Date or any extended completion date, Grantee will promptly
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
3
so advise the Board, and cooperate in good faith to seek a resolution before any further funds
are advanced.
7. Matching Funds. Grantee shall obtain the matching cash and in-kind contributions for
the Project as reflected in the Budget and as required by GOCO policy, and shall provide such
evidence of the same as GOCO may require in its reasonable discretion.
8. Disbursement of Funds.
a. Progress Payment: Grantee may opt to receive a portion of the Grant funds after starting
but prior to completing work on the Project (a “Progress Payment”). Grantee shall provide
GOCO with a progress report detailing expenditures and progress made to date (“Progress
Report”). The Progress Report must be submitted using GOCO’s Progress Report form
(available at www.goco.org or by contacting GOCO). GOCO may, in its discretion, request
additional documentation to support making a Progress Payment. A Progress Payment shall not
exceed GOCO’s percentage of expected overall costs (as determined by the GOCO-approved
budget) applied to the value of documented eligible expenses or 50% of the Grant, whichever is
less. A Progress Payment shall be considered a loan until the Project is complete and Final
Payment (as defined below) has been made.
b. Final Payment: Once the Project is complete, Grantee shall submit a final report to
GOCO detailing the accomplishments of and expenditures related to the Project (the “Final
Report”). The Project is “complete” when all facilities, trails or other improvements included in
the Project have been built and are ready for their intended use. The Final Report must be
submitted using GOCO’s Final Report form (available at www.goco.org or by contacting
GOCO). GOCO may, in its discretion, request additional documentation before its approval of
the contents of the Final Report. Upon GOCO’s review and approval of the Final Report, GOCO
shall pay the outstanding balance on the Grant (the “Final Payment”), subject to any reductions
contemplated by any provision of this Agreement.
9. Conditions for Disbursement of Funds. Except as provided in Paragraph 10 below,
the Grant is subject to the following requirements and conditions.
a. The Grant and all matching funds shall be used only for the cost of fixed assets, including
construction of new facilities, and enlargement or renovation of existing facilities. The Grant
and all matching funds may not be used to pay for maintenance costs, administrative costs (such
as salaries associated with administering the Grant, office supplies, telephone, or travel
expenses), non-fixed assets (such as athletic or maintenance equipment), or any other costs
deemed to be ineligible by the Board, at the Board’s sole discretion.
b. Disbursement of Grant funds shall be made on the basis of costs actually incurred by
Grantee and supported by written documentation (receipts, bills, etc.). GOCO may, in its
discretion, depending on the nature of the Project, require documentation of mechanics lien
waivers or waivers of claims to public project performance bonds as a precondition to any
disbursement under this Agreement.
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
4
c. Except as otherwise agreed to in advance by GOCO in accordance with the terms of this
Agreement, no material modifications may be made to the Project. Material modifications to the
Project to which GOCO has not agreed may result in a reduction in the Grant. “Material
modifications” may include, but are not necessarily limited to, a reduction in the total cost of the
Project, a reduction in the size or number of recreational development components to be
constructed, changes to the nature of the recreational development components to be constructed,
or any other variance from the Project as presented in the Project Application. It is the sole
responsibility of Grantee to inform GOCO of any such modifications to the Project. GOCO
strongly encourages Grantee to contact GOCO in writing when it becomes aware of or wishes to
make any such modifications, however seemingly minor, to the Project.
10. Waiver. The Executive Director or the Executive Director’s designee may in such
person’s discretion, waive or agree to modify one or more of the obligations in sections 8, 9,
and 16 of the Agreement, or may permit performance of one or more of such obligations
subsequent to disbursement.
11. Payment of Grant Subject to Sufficient Net Lottery Proceeds. Payment of the Grant
is subject to GOCO’s determination in its sole discretion that it has received and has available
sufficient net lottery proceeds to fund the Grant. In determining the sufficiency of net lottery
proceeds, GOCO may consider all facts and circumstances as it deems necessary or desirable in
its discretion, including, but not limited to, adequate reserves, funding requirements and/or
commitments for other past, current and future grants, and past, current and future GOCO
operating expenses and budgetary needs.
12. Project Operation and Maintenance.
a. Subject to annual appropriations, Grantee shall operate, manage, and maintain the Project
in a reasonable state of repair for the purposes specified and for the useful life of the Project in
the Project Application, in accordance with product warranties and/or the generally accepted
standards in the parks/recreation community, and provide and maintain access to the Project and
to the Property, regardless of the Property’s ownership. The Grantee has estimated a useful life
of 25 years in the project application.
b. Failure to comply with the provisions of Paragraph 12.a. may be deemed a breach by
Grantee under Paragraph 21, below.
c. GOCO shall not be liable for any cost of maintenance, management or operation of the
Project.
d. Within 60 days of a reasonable request by the Board, Grantee will provide the Board with
adequate records reflecting the operating and maintenance costs of the Project and provide the
Board with such other information concerning the use of the Project by the public and the impact
of the Project.
e. The Grantee’s administrative staff shall present to the Grantee during the Grantee’s
annual budget process a request for an appropriation sufficient to meet the financial obligations
of the Grantee presented by this Agreement. The Grantee will use its best efforts to fully
consider such appropriation and the Parties understand that Board is relying upon fair and full
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
5
consideration of annual appropriation in its decision to extend its resources and the grant
hereunder, and enter into this Agreement. In the event that the Grantee fails to appropriate
sufficient funds to meet the obligations of this Agreement, the Grantee shall provide notice to the
Board of the specific reason(s) for any decision not to appropriate funding. Grantee’s
administrative staff shall notify the Board of any recommendation not to fund or to partially fund
the annual appropriation necessary to fulfill Grantee’s obligations hereunder.
13. Public Access. Grantee agrees, for itself and its successors in interest, to allow
reasonable public access to the Project for the term specified in Section 12. Grantee may
temporarily close such public access for construction, maintenance, emergency situations, or
other reasonable purposes.
14. Compliance with Regulatory Requirements and Federal and State Mandates.
Grantee hereby assumes responsibility for compliance with all regulatory requirements in all
applicable areas, including but not limited to nondiscrimination, worker safety, local labor
preferences, preferred vendor programs, equal employment opportunity, use of competitive
bidding, permits, approvals, and other similar requirements. To the extent permitted by law,
Grantee will indemnify and hold the Board harmless from any liability for any failure to comply
with any such applicable requirements.
15. Nondiscrimination. During the performance of this Agreement, Grantee and its
contractors, subcontractors and agents shall not unlawfully discriminate against any employee
or applicant for employment because of race, religion, color, national origin, ancestry, physical
handicap, medical condition, marital status, age or sex, or any other basis prohibited by local,
state or federal law. Grantee and its contractors shall ensure that the evaluation and treatment of
their employees and applicants for employment are free of such discrimination. Further, during
the performance of this Agreement, Grantee and anyone acting on behalf of Grantee shall not
engage in any unlawful discrimination in permitting access and use of the Project.
16. Publicity and Project Information.
a. Grantee shall erect and maintain a sign at a prominent location on the Project site
acknowledging the assistance of Great Outdoors Colorado and the Colorado Lottery. GOCO
will provide such signs at no cost to Grantee. Alternatively, GOCO will provide reproducible
samples of its logo to Grantee for custom signs.
i. GOCO shall approve in advance the design of any permanent sign materially
varying from the signs provided by GOCO. To obtain such approval, Grantee shall submit to
GOCO plans describing the number, design, placement, and wording of signs and placards. Plans
shall be submitted to the Board for review and approval prior to completion of the Project.
ii. The Board may withhold Final Payment pending evidence of placement of
permanent signage.
b. Grantee shall acknowledge Board funding in all publicity issued by it concerning the
Project.
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
6
c. Grantee shall cooperate with the Board or the Board’s designee in advance in preparing
public information pieces related to the Project.
d. Grantee shall give the Board the right and opportunity to use information gained from the
Project.
e. Grantee shall give the Board a minimum 30 days’ notice of Project grand openings,
dedications, or other events.
f. Grantee shall give timely notice of the Project, its inauguration, significance, and
completion to the local members of the Colorado General Assembly, members of the board of
county commissioners of the county or counties in which the Project is located, as well as to
other appropriate public officials.
g. Grantee shall provide quality digital photographs or printed photographs, if unable to
provide digital photographs (collectively, “Photographs”) of the completed Project with the Final
Report. For the avoidance of doubt, all Photographs taken by Grantee of the Project constitutes a
“work made for hire” pursuant to the U.S. copyright law (17 U.S.C. Section 201(b)) Grantee
agrees that all copyrights and other property rights, in the Photographs developed by Grantee in
conjunction with the Project are further owned by GOCO and Grantee hereby forever and
irrevocably assigns to GOCO, without further consideration, all right, title and interest in such
copyrights and other proprietary rights. Grantee agrees that GOCO, its successors and assigns,
shall have the exclusive right to file copyright applications in the United States and throughout
the world to the Photographs, or any portion thereof, in the name of GOCO. Grantee hereby
agrees that GOCO, its successors and assigns may act as attorney-in-fact to execute any
documents that GOCO deems necessary to record this grant with the United States Copyright
Office or elsewhere. Grantee agrees to execute any and all documents reasonably requested by
GOCO to enforce its rights under this provision.
h. At no time shall Grantee represent in any manner to the public or to any party that it is
affiliated with GOCO or acting on behalf of GOCO.
17. Liability.
a. Grantee shall be responsible for, and to the extent permitted by law (including any
constitutional or statutory limitations on the ability of a governmental entity to provide
indemnification), indemnify, defend and hold harmless the Board, its officers, agents and
employees from any and all liabilities, claims, demands, damages or costs (including reasonable
legal fees) resulting from, growing out of, or in any way connected with or incident to Grantee’s
performance of this Agreement. Grantee hereby waives any and all rights to any type of express
or implied indemnity or right of contribution from the State of Colorado, the Board, its members,
officers, agents or employees, for any liability resulting from, growing out of, or in any way
connected with or incident to this Agreement. Grantee acknowledges that Grantee is the owner
of the Project and the Property upon which it is located, or has control of the Project and the
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
7
Property, and that GOCO neither possesses nor controls the Project, the Property, nor the
operations of the Project.
b. Anything else in this Agreement to the contrary notwithstanding, no term or condition of
this Agreement shall be construed or interpreted as a waiver, either express or implied, of any of
the immunities, rights, benefits or protection provided to the Board under the Colorado
Governmental Immunity Act (“CGIA”) as amended or as may be amended in the future
(including, without limitation, any amendments to such statute, or under any similar statute
which is subsequently enacted). This provision may apply to Grantee if Grantee qualifies for
protection under the Colorado Governmental Immunity Act, C.R.S. §24-10-101 et seq. The
Board and Grantee understand and agree that liability for claims for injuries to persons or
property arising out of the negligence of the Board, its members, officials, agents and employees
may be controlled and/or limited by the provisions of the CGIA. The parties agree that no
provision of this Agreement shall be construed in such a manner as to reduce the extent to which
the CGIA limits the liability of the Board, its members, officers, agents and employees.
18. Audits and Accounting. Grantee shall maintain standard financial accounts,
documents, and records relating to the use, management, and operation of the Project. The
accounts, documents, and records related to the Project shall be retained by Grantee for not less
than five (5) years following the date of disbursement of funds under this Agreement. The
Board, or its designated agent, shall have the right, upon reasonable notice to Grantee, to audit
the books and records of Grantee which pertain to the Project and to the use and disposition of
the Grant. While Grantee is not required to use GAAP (Generally Accepted Accounting
Principles), Grantee shall use reasonable and appropriate accounting systems in maintaining the
required records hereunder.
19. Inspection. Throughout the term of this Agreement, GOCO shall have the right to
inspect the Project to ascertain compliance with this Agreement.
20. Withdrawal of Board Funding; Termination of Agreement. Anything else in this
Agreement or otherwise to the contrary notwithstanding, the Board may withdraw, in whole or
in part, the Grant and/or terminate this Agreement, and/or seek a refund of payments already
made if the Board determines in its discretion that:
a. facts have arisen or situations have occurred that fundamentally alter the expectations of
the parties or make the purposes for the Grant as contemplated infeasible or impractical;
b. any material modifications in the scope or nature of the Project have occurred from that
which was presented in the Project Application and such material modifications have not
received the prior written approval of GOCO;
c. any statement or representation made by Grantee in the Project Application, this
Agreement, the Progress Report, the Final Report, or otherwise is untrue, inaccurate or
incomplete in any material respect;
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
8
d. the results of GOCO’s review of the Progress Report, or the Final Report are not
acceptable to GOCO;
e. the Project will not or cannot be completed by the Completion Date or any extensions
granted thereto or delays in the implementation of the Project have occurred which, in the
Board’s judgment, make the Project impracticable;
f. the Project will not or cannot be completed within the Budget or any approved
modifications, or the total Project cost and/or Grantee’s matching funding are reduced;
g. title to or encumbrances against the Property are or become such that Grantee is unable to
complete the Project, or the Project and/or the Property are or become unavailable for public use.
21. Breach.
a. In the event that Grantee breaches any of the terms, covenants, representations, or
conditions of this Agreement, the Board may elect to enforce any and all remedies available at
law or in equity, including without limitation, any of the following:
i. Prior to payment of Grant:
A. Withdraw the Grant and terminate this Agreement; and,
B. Deny Grantee eligibility for participation in future Board grants, loans or
projects.
ii. After payment (partial or full) of Grant:
A. Deny Grantee eligibility for participation in future Board grants, loans or
projects;
B. Seek specific performance of Grantee’s obligations under this Agreement;
C. Receive reimbursement in full of disbursement made under the Grant.
b. The foregoing remedies are cumulative and may be exercised independently or in
combination and are not exclusive to one another or to any other remedies available at law or in
equity. In the event GOCO must pursue any remedy hereunder and is the substantially
prevailing party, GOCO shall be awarded its costs and reasonable legal fees, including costs of
collection.
22. Good Faith. There is an obligation of good faith on the part of both parties, including
the obligation to make timely communication of information which may reasonably be believed
to be material to the other party.
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
9
23. Assignment. Grantee may not assign its rights under this Agreement without the
consent of the Board, which consent shall be in the discretion of the Board. Any assignment
shall require that, at a minimum, the assignee is eligible to receive grants from the Board and
assumes Grantee’s ongoing obligations under this Agreement.
24. Applicable Law. This Agreement shall be governed by the laws of the State of
Colorado and venue for any dispute hereunder shall lie exclusively in the State Courts of the
City and County of Denver.
25. No Joint Venture. Nothing in this Agreement shall be construed to create a joint
venture, partnership, employer/employee or other relationship between the parties hereto other
than independent contracting parties. Except as permitted under the remedies provisions
hereunder, neither party shall have the express or implied right to act for, on behalf of, or in the
name of the other party.
26. Severability. If any provision of this Agreement, or the application thereof, is found to
be invalid, the remainder of the provisions of this Agreement, or the application of such
provision, other than those as to which it is found to be invalid, shall remain in full force and
effect.
27. Time is of the Essence. Time is of the essence in this Agreement.
28. Survival. The terms and provisions of this Agreement and the parties’ covenants
hereunder shall survive the funding of the Grant and the completion of the Project.
29. Fax and Counterparts. This Agreement may be executed in one or more counterparts,
each of which shall be an original, but all of which when taken together shall constitute one
Agreement. In addition, the parties agree to recognize signatures of this Agreement transmitted
by telecopy or e-mail as if they were original signatures.
30. Third Party Beneficiary. The Board and Grantee hereby acknowledge and agree that
this Agreement is intended only to cover the relative rights and obligations between the Board
and Grantee, and that no third party beneficiaries are intended.
31. Construction. Each party hereto has reviewed and revised (or requested revisions of)
this Agreement, and therefore, any usual rules of construction requiring that ambiguities are to
be resolved against a particular party shall not be applicable in the construction and
interpretation of this Agreement.
32. Waiver. The failure of either party to enforce a term hereof shall not be deemed a
waiver of such term or right of enforcement as to that breach or any subsequent breach of the
same, similar or different nature. No waiver shall be enforceable hereunder unless signed by the
party against whom the waiver is sought to be enforced.
33. Entire Agreement. Except as expressly provided herein, this Agreement constitutes
the entire agreement of the parties. No oral understanding or agreement not incorporated in this
Agreement shall be binding upon the parties. No changes to this Agreement shall be valid
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
10
unless made as an amendment to this contract, approved by the Board, and signed by the
parties.
IN WITNESS WHEREOF, the parties by signature below of their authorized representatives
execute this Agreement effective as of [[SertifiDate_2]].
STATE BOARD OF THE GREAT GRANTEE:
OUTDOORS COLORADO TRUST FUND City of Fort Collins
By: [[SertifiSStamp_2]] By: [[SertifiSStamp_1]]
Lise Aangeenbrug Title: [[SertifiTitle_1]]
Executive Director
*NOTE* Signee should be same individual
authorized to sign grant agreement in
attached resolution (EXHIBIT B)
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
EXHIBIT A
Project Summary
Applicant: City of Fort Collins County: Larimer Log Number: 14364
Project Title: Fossil Creek Trail - College Avenue to Shields Street
Funding Summary: Applicant Funding
Partner(s) Funding
GOCO Grant Amount $1,000,000.00
Total Project Cost $2,657,035.00
Project Description:
The City of Fort Collins is request GOCO funds to construct 1.25 miles of concrete trail. Project
components include a 70-foot long railroad underpass and three 10-foot wide steel pedestrian bridges to
cross Fossil Creek. A soft surface trail will run adjacent to the paved trail.
Staff and Peer Reviewer Comments:
This trail segment will complete the Fossil Creek Trail from its start at Spring Canyon Community Park
to Fossil Creek Community Park spanning a distance of nearly 6.5 miles. This new trail segment will
provide connection to two, 100 acre community parks, three large natural areas, three area schools, one
environmental education center, and connection to the City• s trail system where users can enjoy access
to an additional 17 city natural areas and eight city parks. This trail will also connect to the regional
Poudre River Trail.
Completion of the Fossil Creek trail is the #1 ranked priority out of 20 priorities identified by the
community in the City• s Paved Recreation Trail Master Plan. Additionally, as part of the City• s Parks
and Recreation Policy Plan, residents ranked paved recreational trails as the top most important outdoor
facility to be added, expanded or improved.
It is good to see successful collaboration between the City and the Burlington Northern Santa Fe
Railroad (BNSF). The City has been working with BNSF for nearly one and a half years to get this
Score Summary
Rank: 3
Overall Score: .00
GOCO Staff Score:
Reviewer Average:
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
12
project completed. BNSF has formally authorized the City to proceed with construction of the pedestrian
and bicycle underpass. The trail underpass has reached the 60% design phase with BNSF• s crossing
process. Final plans will be submitted as the fourth step and should be approved in June 2014 by the
railroad.
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
EXHIBIT B
RESOLUTION (REQUIRED)
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
EXHIBIT C
BUDGET
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
Source of Funds Date Secured GOCO Grant Applicant Match Partner Match Amount of CTF Total Funding($)
CASH
Great Outdoors Colorado 6/1/2014 $1,000,000.00 $1,000,000.00
City of Fort Collins Jan-14 $3,223,306.47 $3,223,306.47
[List Partner] $0.00
[List Partner] $0.00
[List Partner] $0.00
$1,000,000.00 $3,223,306.47 $0.00 $0.00 $4,223,306.47
IN-KIND
[List Source] $0.00
[List Source] $0.00
[List Source] $0.00
TOTAL SOURCE OF FUNDS $1,000,000.00 $3,223,306.47 $0.00 $0.00 $4,223,306.47
Number of
Units Cost Per Unit Total Funding ($)
GENERAL CONDITIONS $738,750.00
Mobilization/Demobilization 1.00 $ 369,000.00 $369,000.00
Construction Surveying 1.00 $ 25,000.00 $25,000.00
SWMP Plan/Inspection & Maintenance 1.00 $ 9,300.00 $9,300.00
Tracking pads, silt fence, wattles, 1.00 $ 7,550.00 $7,550.00
Concrete wash-out 1.00 $ 6,400.00 $6,400.00
Construction Activity Vibration Monitoring 1.00 $ 11,600.00 $11,600.00
Railroad Track Monitoring 1.00 $ 26,700.00 $26,700.00
Railroad BNSF Track Flagging 1.00 $ 250,000.00 $250,000.00
Railroad Training 1.00 $ 7,500.00 $7,500.00
Railroad Insurance/Bonds/Permits 1.00 $ 25,700.00 $25,700.00
SITE WORK $262,100.00
Access Road - East side 1,950.00 $ 18.40 $35,888.00
Access Road - West side 1,000.00 $ 27.61 $27,606.16
Construction Fencing & Widen Gate @ College Avenue 2,500.00 $ 15.34 $38,341.88
Staging Area (150'x150') - Clear & Grub / Excavation/Base 1.00 $ 57,359.46 $57,359.46
Topsoil Stockpile & Replace (east & west) 1.00 $ 6,032.46 $6,032.46
Temp culvert access - 30" RCP w/ Rip Rap 1.00 $ 9,611.03 $9,611.03
Excavation for Trail 1,025.00 $ 12.27 $12,576.14
Embankment for Trail 1,365.00 $ 12.27 $16,747.73
Final Site Shape & Grade 30,000.00 $ 1.12 $33,740.86
Trail Subgrade Prep Outside Tunnel/Load & Haul-off Excess 1.00 $ 24,196.28 $24,196.28
EAST ARCHED HEADWALL $255,240.00
Install Sheet Piling 1995.00 $ 43.11 $85,994.67
Excavate Face of Headwall 450.00 $ 51.52 $23,182.13
Install Caissons 2.00 $ 7,149.14 $14,298.28
Wall Rebar, Mesh & Installation 9.60 $ 2,523.23 $24,222.96
Shotcrete Headwall Facing 1490.00 $ 69.39 $103,389.15
Railing 79.00 $ 52.57 $4,152.81
WEST ARCHED HEADWALL $273,872.00
Install Sheet Piling 2250.00 $ 40.91 $92,049.01
Excavate Face of Headwall 450.00 $ 48.89 $22,001.96
Install Caissons 2.00 $ 6,785.18 $13,570.37
Wall Rebar, Mesh & Installation 11.30 $ 2,394.77 $27,060.91
Shotcrete Headwall Facing 1750.00 $ 65.86 $115,248.36
Railing 79.00 $ 49.89 $3,941.39
RETAINING WALLS $35,000.00
East Retaining Wall - 110.00 $ - $0.00
West - 100 Year Flood Protection Wal 100.00 $ 350.00 $35,000.00
THRUST PLATFORM & BLOCK $55,000.00
Excavate for Jacking Frame/Work Platform 1.00 $ 5,569.62 $5,569.62
Thrust Block with Mud Slab Floor 1.00 $ 12,009.49 $12,009.49
Thrust Block Helical Piles 8.00 $ 4,351.27 $34,810.13
Demo Thrust Block for Trail 1.00 $ 2,610.76 $2,610.76
14 FEET DIAMETER TUNNEL $761,094.04
Proposed Budget - REVISED
PATHS TO PARKS TRAIL INITIATIVE - City of Fort Collins
UTILITY RELOCATIONS $100,000.00
F/A Utility Relocation 1.00 $ 100,000.00 1.00 $ 100,000.00 $100,000.00
CONSTRUCTION ADMINISTRATION $371,100.00
DESIGN SERVICES - UNDERPASS ONLY $479,365.24
DESIGN SERVICES - TRAIL (COLLEGE TO SHIELDS) ONLY $100,000.00
EASEMENTS / R.O.W. $30,000.00
$4,223,306.47
No. of Units /
Hours Cost Per Unit / Hour Total Funding ($)
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$4,223,306.47
Explanation Requirement Actual Meets Req? GOCO's % of TC
25%/Total Costs $1,055,827 $3,223,306 Yes
10%/Total Costs $422,331 $3,223,306 Yes
GOCO % of Total Costs 23.68%
USE OF FUNDS - CASH SUBTOTAL
IN-KIND Use of Funds
Professional Services
vendor/service provider
vendor/service provider
Materials
vendor/service provider
vendor/service provider
vendor/service provider
Equipment
Minimum Total Match
Minimum Cash Match
USE OF FUNDS - IN-KIND SUBTOTAL
TOTAL PROJECT COST
CALCULATION OF MATCH REQUIREMENTS
Item
vendor/service provider
Paths to Parks Trail Initiative Grant
March 2014 2 of 2 City of Fort Collins
EXHIBIT D
OVERDUE GRANTS POLICY
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
GREAT OUTDOORS COLORADO
POLICIES & PROCEDURES
MANUAL
Policy: Overdue
Grants
Approval Date: June 11, 2013
I) PURPOSE
Great Outdoors Colorado (GOCO) understands that there are unforeseen circumstances
that may interfere with a grantee’s ability to complete a project by the project completion
date set forth in the Grant Agreement. The Overdue Grants Policy outlines the options
available to grantees to extend a grant deadline and the procedures associated with
submitting grant extension requests.
II) POLICY STATEMENT
A grantee has two options to extend the project completion date in the Grant Agreement: a
staff extension or a Board extension. Staff can grant an extension for at least 90 days and up
to the date of the next scheduled GOCO Board meeting beyond that 90 days. If the grantee
needs more time than that, the grantee must request a Board extension. GOCO expects the
grantee to request the appropriate amount of time needed to complete the project. A
grantee can request a second Board extension if needed, although this is not a favorable
action.
Failure to complete a project by the original due date, or by any extended due dates
authorized by staff or Board, may result in the de-authorization of the grant by the Board
and a suspension from applying in future grant cycles.
III) PROCEDURES
A) Staff Extensions
x The grantee must submit a request for a staff extension prior to the original project
completion date via email or postal mail to GOCO staff.
x Requests must include the following: a) grantee name b) project title c) contract
number from the grant agreement d) original project completion date e) percent of
project completion to date or due diligence items completed to date for land
acquisitions f) reason for delay g) estimated date of project completion or closing g)
estimated date of final report submission to GOCO, if applicable.
x A grantee may only request one staff extension.
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
x If the grantee needs an extension for longer than the time provided by a staff
extension, the grantee can forgo the staff extension and request a Board extension.
x Staff will notify the grantee via email of the decision to grant or deny the request for
a staff extension.
B) Board Extensions
x The grantee must submit a request for a Board extension prior to the original or staff
extended project completion date via email or postal mail. Requests must be
addressed to the GOCO Board.
x Requests must include the following: a) grantee name b) project title c) contract
number from the grant agreement d) original project completion date and if
applicable, staff extended project completion date e) percent of project completion
to date or due diligence items completed to date for land acquisitions f) reason for
delay g) estimated date of project completion or closing g) estimated date of final
report submission to GOCO, if applicable.
x The Board will consider the request for Board extension at its next scheduled
meeting. Staff will notify the grantee via email of the Board’s decision to grant or
deny the request for a Board extension.
x A grantee can request a second Board extension if additional time is needed beyond
that provided by the first Board extension. Requests for a second Board extension
will follow all of the procedures listed above.
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
EXHIBIT E
INTERGOVERNMENTAL (or other) AGREEMENT
(If applicable)
DocuSign Envelope ID: A9837BC3-01F9-454C-8F53-71D400D28AAD
-1-
ORDINANCE NO. 050, 2016
OF THE COUNCIL OF THE CITY OF FORT COLLINS
APPROPRIATING UNANTICIPATED GRANT REVENUE FROM GREAT
OUTDOORS COLORADO (GOCO) IN THE CAPITAL PROJECTS FUND FOR
THE FOSSIL CREEK TRAIL-COLLEGE AVENUE TO SHIELDS STREET PROJECT
WHEREAS, the State Board of the Great Outdoors Colorado Trust Fund (GOCO) has
awarded the City of Fort Collins a $1,000,000 trail grant for the construction of the Fossil Creek
Trail from College Avenue to Shields Street (the “Project”); and
WHEREAS, the purpose of this item is to appropriate grant funds to the Project; and
WHEREAS, the Project would complete a major connection of the Fossil Creek Trail
from College Avenue to Shields Street and involves 1.25 miles of new concrete trail and a major
tunnel underpass structure at the Burlington Northern Santa Fe (BNSF) Railroad; and
WHEREAS, the trail will connect to the existing Fossil Creek Trail just west of College
Avenue and terminate at the existing trail on the east side of Shields Street; and
WHEREAS, the City has been working with BNSF for several years to get approval of
the City’s plans for the underpass, and obtain the necessary easements from the railroad to
complete the work and operate and maintain the underpass on BNSF’s property; and
WHEREAS, construction of the underpass is expected to cost approximately $2,700,000
in total; and
WHEREAS, capital funding for the construction of the underpass was appropriated from
the Conservation Trust Fund in years 2015 and 2016 and obtaining this grant will offset trail
funds needed to complete the project; and
WHEREAS, funding for public art for the underpass portion of the Project was
previously appropriated from the Conservation Trust Fund in accordance with the Art in Public
Places (APP) provisions of the City Code; and
WHEREAS, the total Project including the tunnel underpass and trail construction is
estimated to cost approximately $4,200,000; and
WHEREAS, staff will be submitting a budget offer for the remaining funds needed in the
2017-18 budgets, including additional funding for APP, with operation and maintenance funding
for the Project of about $10,000 per year budgeted starting in the 2017 Parks budget; and
WHEREAS, Article V, Section 9, of the City Charter permits the City Council to make
supplemental appropriations by ordinance at any time during the fiscal year, provided that the
total amount of such supplemental appropriations, in combination with all previous
-2-
appropriations for that fiscal year, does not exceed the current estimate of actual and anticipated
revenues to be received during the fiscal year; and
WHEREAS, City staff has determined that the appropriation of the revenue as described
herein will not cause the total amount appropriated in the Capital Projects Fund to exceed the
current estimate of actual and anticipated revenues to be received in that fund during any fiscal
year.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF
FORT COLLINS as follows:
Section 1. That the City Council hereby makes and adopts the determinations and
findings contained in the recitals set forth above.
Section 2. That there is hereby appropriated for expenditure from unanticipated grant
revenue in the Capital Projects Fund the sum ONE MILLION DOLLARS ($1,000,000) for the
Fossil Creek Trail-College Avenue to Shields Street Project.
Introduced, considered favorably on first reading, and ordered published this 19th day of
April, A.D. 2016, and to be presented for final passage on the 3rd day of May, A.D. 2016.
__________________________________
Mayor
ATTEST:
_______________________________
City Clerk
Passed and adopted on final reading on the 3rd day of May, A.D. 2016.
__________________________________
Mayor
ATTEST:
_______________________________
City Clerk
47-50 Installation of Guide Rails-GBM pilot tube/auger bore 1.00 $ 68,000.00 $68,000.00
Tunnel Shield/Jacking Frame Fabrication 1.00 $ 90,269.79 $90,269.79
Tunnel Set-up 1.00 $ 28,383.80 $28,383.80
14-feet Diameter Casing Pipe - material 70.00 $ 3,430.48 $240,133.94
Tunnel Casing - installation/jacking/welding/lubrication 70.00 $ 3,012.87 $210,900.95
Tunnel Spoils/Grouting & Settlement Allowance 1.00 $ 47,257.87 $47,257.87
67 Tunnel Lining 1.00 $ 45,367.55 $45,367.55
58-62 Concrete Trail inside tunnel - Flowfill/Concret 70.00 $ 439.72 $30,780.14
BRIDGES $217,500.00
65 Foot Steel Pedestrian Prefabricated Bridge 1.00 $ 71,500.00 $71,500.00
50 Steel Foot Pedestrian Prefabricated Bridge 2.00 $ 55,000.00 $110,000.00
Pedestrian Bridge Abutment w/ Helix Pier System 6.00 $ 6,000.00 $36,000.00
CONCRETE PAVING $484,920.00
Colored Concrete Paving - (5 inch thick) 61,260.00 $ 7.00 $428,820.00
C&G along Fossil Creek Parkway 2,700.00 $ 18.00 $48,600.00
ADA Ramp 3.00 $ 2,500.00 $7,500.00
LANDSCAPE AND RESTORATION $47,200.00
Soil Retention Matting 1,000.00 $ 4.00 $4,000.00
Seeding, Mulching &Site Restoration 6.00 $ 4,200.00 $25,200.00
Gravel Path - Larimer County Youth Corp 1.00 $ 15,000.00 $15,000.00
Trail Signage 3.00 $ 1,000.00 $3,000.00
LIGHTING $125,000.00
Electric - Lights, Conduit 1.00 $ 25,000.00 $25,000.00
Transformer & Service 1.00 $ 100,000.00 $100,000.00
Proposed Budget - REVISED
TOTAL CASH CONTRIBUTIONS
CASH Use of Funds
PATHS TO PARKS TRAIL INITIATIVE - City of Fort Collins
Paths to Parks Trail Initiative Grant
March 2014 1 of 2 City of Fort Collins