HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 11/29/2011 - XCEL ENERGY WEST MAIN REPLACEMENT PROJECTDATE: November 29, 2011
STAFF: Helen Migchelbrink, Larry
Schneider, Mark Sears
Megan Trujillo, Xcel Energy
Pre-taped staff presentation: available
at fcgov.com/clerk/agendas.php
WORK SESSION ITEM
FORT COLLINS CITY COUNCIL
SUBJECT FOR DISCUSSION
Xcel Energy West Main Replacement Project.
EXECUTIVE SUMMARY
Xcel Energy is developing plans for an 80 mile long high pressure natural gas pipeline replacement
project that begins at the Wyoming border and ends in Broomfield. The existing pipeline, an 8- inch
diameter pipe installed in 1929, will be replaced with a 16-inch diameter pipeline that will be rated
to a pressure of 1020 pounds per square inch gage (psig.) Xcel’s goal is to install the pipeline within
public roadways wherever possible for safety reasons. Xcel is working with City staff to continue
refining the pipeline routing. This project will impact City streets and natural areas.
GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED
The purpose of this work session is to inform Council of Xcel Energy’s plans to replace the existing
gas pipeline through the City with a new larger gas line, and to identify the impacts to the street
system and the natural areas. Staff is seeking Council input on the pipe line alignment early in the
design process.
BACKGROUND / DISCUSSION
Project Description
The West Main Pipeline was installed in 1929 as a high pressure natural gas pipeline that served the
communities on the western Front Range. The pipeline begins near the Wyoming border and ends
near Broomfield. Beginning in 2009, Xcel Energy started assessing the integrity of the pipeline as
mandated by several federal codes and from the Public Utilities Commission (PUC). These
assessments are done by filling the pipeline with water and increasing the pressure inside the
pipeline by a multiplier of the maximum pressure allowed on the pipeline, and also by inserting In
Line Inspection (ILI) tools into the pipeline. ILI tools look for corrosion, cracks, dents, and loss of
the wall thickness of the pipeline.
Currently, Xcel Energy is still assessing the integrity of the pipeline to ensure it is safe to operate
until replacement, but the results from the testing have shown that the existing pipeline needs to be
November 29, 2011 Page 2
replaced. Xcel Energy evaluated the size required for not only for current demand, but also for at
least 30 years into the future. It was determined that the new pipeline should be a 16-inch diameter
pipeline, and the pressure that the pipeline will be rated to is 1020 psig.
The existing 8-inch pipeline currently lies within Timberline Road, Horsetooth Road, and Shields
Street. Xcel Energy is proposing to relocate the new high pressure gas line outside of the roadways
wherever possible for safety reasons. The pipeline will have a much higher potential of being
damaged if it is in the roadway. Some portions of the pipeline in the roadway will have to be
replaced due the existing distribution system for Fort Collins customers. Xcel Energy is working
with City staff to determine the best locations for the City and Xcel Energy. The pipeline routing
has already been modified based on input from the City staff.
The replacement of this gas line will have impacts to the City’s street system as well as the Natural
Areas.
Street System Impact
Three major streets will be potentially impacted by the replacement of the gas line: Timberline
Road, Horsetooth Road, and Shields Street. Horsetooth Road, and Shields Street were paved in
2011 as part of the Streets Department Maintenance Program (SMP).
Prior to any SMP work being performed, a utility notification is sent to other City departments and
private utility companies. Xcel responded and stated they did not have any concerns or projects
impacting the 2011 SMP. Xcel did not know, at the time, that it would be replacing the gas line.
The City moved ahead with scheduled maintenance treatments. Xcel will be required to repave all
of the impacted streets to bring them back to equal or better conditions.
City Engineering will inspect all work performed by Xcel within the City public right-of-way. An
excavation permit will be issued to Xcel, and it will be required to pay applicable “street cut” fees.
The fees are tripled for streets overlaid within the last five years.
The good news is that this project potentially will provide an opportunity for the Street Maintenance
Program to coordinate with Xcel on any remaining street maintenance needs within the project
limits.
Natural Areas Impacts
Xcel has stated that it is willing to work with staff to avoid, minimize and mitigate impacts to natural
areas. Excel is willing to time the construction to minimize impacts to wildlife and vegetation; bore
the pipe line under wetlands and sensitive vegetation and habitat; and to time restoration to
maximize success. As with all construction there will be short term impacts to vegetation and
wildlife that cannot be avoided or mitigated. The trenching operation would impact vegetation for
a width of approximately 75’. Xcel is required to place above ground markers within eye sight of
one another which will have an impact to the view shed. There will also be impacts in the future due
to routine maintenance, repairs and ultimate replacement of the gas line. The site specific impacts
identified at this time are as follows:
November 29, 2011 Page 3
• Coyote Ridge Natural Area
Xcel wants to place the gas line along the west side of Shields Street just outside of the
future right of way to avoid future conflicts. The installation of the pipe line would have
temporary impacts to a 1.25--mile stretch of what is currently wheat field and significant
impacts to a 0.25-mile stretch of primarily native prairie vegetation. The wheat field will be
restored to native grasses in the future. The installation would have minimal long term
impacts on wildlife.
• Hazaleus Natural Area
Xcel wants to place the gas line along the east side of Shields Street outside of the future
right-of-way to avoid future conflicts. The installation of the pipe line would impact mostly
non-native grasses and have minimal long term impact on wildlife. Xcel proposes to bore
under the wetlands to avoid impacts to the wetlands. The area impacted by the proposed gas
line installation will be impacted in the future to construct a regional recreation trail.
• Cathy Fromme Prairie Natural Area
Xcel wants to place the gas line along the west side of Shields Street just outside of the
future right-of-way to avoid future conflicts. Xcel is proposing to bore under much of site
to avoid impacts. In the areas where Xcel will not be able to bore there would be minimal
long term impacts to wildlife, and potentially significant impacts to native prairie vegetation,
the trailhead parking lot, and the Fossil Creek trail.
• Kingfisher Point Natural Area
Xcel’s 8” gas line crosses Kingfisher in an existing easement. Xcel is planning to use the
existing easement to install the new gas line across Kingfisher and the Poudre River. Xcel
is proposing to bore under the river, the Poudre River trail, and much of Kingfisher to avoid
impacts. In the areas where Xcel will not be able to bore there will be long term impacts to
recently restored native grasses and minimal long term impacts to wildlife.
Summary
City staff will continue to work with Xcel Energy through the project design to determine a detailed
location of the pipeline to limit the project impacts. Easements from the City through its Natural
Areas may be required by Xcel to accommodate its preferred alignment. Any impacts to City streets
will be fully mitigated, and the roadways will be restored to their current condition.
ATTACHMENTS
1. Map
2. Powerpoint presentation
2
Xcel Loveland/Fort Collins Replacement Line
VINE
MULBERRY
PROSPECT
DRAKE
TI MBERLI NE
HARMONY
TRILBY
57 ST
HORSETOOTH
LEMAY
COLLEGE
SHI ELDS
PSCo Major Gas
Delivery Points
Existing 8”
Line and 16”
Replacement
Natural Areas
Coyote Ridge
Hazaleus
Cathy Fromme
Kingfisher
N
ATTACHMENT 1
1
West West Main Main Replacement Replacement Project Project
November 2011
ATTACHMENT 2
2
Loveland/Fort Collins Replacement Line
VINE
MULBERRY
PROSPECT
DRAKE
TIMBERLINE
HARMONY
TRILBY
57 ST
HORSETOOTH
LEMAY
COLLEGE
SHIELDS
PSCo Major Gas
Delivery Points
Existing 8”
Line and 16”
Replacement
Natural Areas
Coyote Ridge
Hazaleus
Cathy Fromme
Kingfisher
N
ATTACHMENT 2
3
West Main Background
• High pressure natural gas pipeline installed 1925-
1931
• Extends from Wyoming border south into
Broomfield (approximately 80 miles of pipeline)
• Backbone of the natural gas system in the Front
Range and is critical to maintaining reliable
natural gas service serving several communities
including:
– Fort Collins, LaPorte, Loveland, Greeley
Longmont, Lafayette, Louisville, Boulder,
Broomfield, Westminster, Denver, etc.
ATTACHMENT 2
4
Why Replacement?
Results from Federal DOT code inspections
Anomalies found during integrity assessments prompting
immediate repairs
Pipeline corrosion more prevalent than expected (loss of
pipe thickness)
Pipeline exit strategy initiated December 2010
Will continue integrity assessments, repairs and safe
operation of pipeline until retired
Began talking with Fort Collins late spring 2011
ATTACHMENT 2
5
Pipeline Routing
Preferred route resulted from talks with the City staff
and included:
• Proximity to existing facilities.These points of
service are critical for continued safe and reliable
natural gas to the citizens and businesses within
the City of Fort Collins.
• Safety of the new pipeline
– Installation outside congested roadways
whenever possible
• Sensitivity to the environment and natural areas
• Reduce impact to customers/residents as much
as possible
ATTACHMENT 2
6
Fort Collins Impacts
• Pipeline route includes replacing the line in the
pavement and in some natural areas
– Pavement impacts: Timberline Rd, Horsetooth Rd, and
Shields St
– Natural Areas: Cathy Fromme Prairie, Hazaleus, Coyote
Ridge, and Kingfisher Point
• City assisting with route refinement to lessen the
impact to residents
– Identify project coordinating opportunities with City
projects (i.e., water replacements, sewer work, etc.)
ATTACHMENT 2
7
Natural Areas Impacts
• Xcel will work with City Staff to avoid, minimize
and mitigate impacts
– Construct pipeline in winter to minimize
impacts to wildlife and vegetation
– Bore pipeline under wetlands and sensitive
vegetation and habitat
– Restoration prior to spring to maximize
success
ATTACHMENT 2
8
Natural Areas Impacts
• Coyote Ridge
– Temporary impacts to wheat field
– Minimal impacts to wildlife and view shed
– Above ground markers
• Hazaleus
– Impacts to mostly non-native grasses which
will be restored to native grasses
– Minimal impacts to wildlife and viewshed
– Impacted area will be a regional trail in future
– Above ground markers
ATTACHMENT 2
9
Natural Areas Impacts
• Cathy Fromme
– Potential significant impacts to native prairie
vegetation
– Minimal impacts to wildlife
– Above ground markers
•Kingfisher
– Potential significant impacts to recently
restored native grass
– Minimal impacts to wildlife
– Above ground markers
ATTACHMENT 2
10
Pavement Impacts
• Street Maintenance Program (SMP) Utility
Notifications
– Sent prior to any SMP work being performed
to other City departments and private utility
companies
– Minimize the impact of utility cuts on the
pavement and to coordinate work with others
– Two coordination notices sent to Xcel prior to
performing our 2011 Street Maintenance
Program.
ATTACHMENT 2
11
Pavement Impacts
• Xcel responded and stated that they did not have
any concerns or projects impacting the 2011
streets.
• Three streets that were overlaid in 2011 will be
impacted.
1) Shields St. – from Horsetooth Rd. to Harmony
Rd.
2) Horsetooth Rd. – from College Ave. to
Timberline Rd.
ATTACHMENT 2
12
Pavement Impacts
• Additionally, two more streets will be impacted
that have received recent overlays:
1) Shields St. – from Harmony Rd. to Bon
Homme Richard Dr. (2009)
2) Timberline Rd. – from Vermont Dr. to
Horsetooth Rd. (2008)
ATTACHMENT 2
13
Project Summary
• Replacement of the 8” West Main Pipeline with a
new 16” pipeline
– 2013 – 2014 replacement in Fort Collins,
Loveland, and Larimer County
• $136 million project estimate
• 3 - 4 year replacement schedule remaining
ATTACHMENT 2
14
NEXT STEPS
• Action by Council Regarding Easements Within
the Natural Areas
• Excavation Permitting Through the Engineering
Department
ATTACHMENT 2
15
ATTACHMENT 2