HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 05/17/2011 - FIRST READING OF ORDINANCE NO. 062, 2011, APPROPRI DATE: May 17, 2011 Lk AGENDA ITEM SUMMARY
STAFF: Jill Stilwell/Steve Seefeld FORT COLLINSCOUNCIL
First Reading of Ordinance No. 062, 2011, Appropriating Prior Year Reserves in the Capital Projects Fund for the
Building on Basics Lincoln Center Renovation Project.
EXECUTIVE SUMMARY
During the Lincoln Center Addition and Renovation project, an unanticipated structural issue with the 32 year old
Performance Hall walls was discovered. The structural problem is significant and the Performance Hall walls will
require additional structural support. This work must be completed before the facility can be reopened. Previously,
$460,000 was appropriated for these repairs. This ordinance appropriates an additional $135,000 from prior year
reserves in the Capital Project Fund Building Community Choices program to complete the structural work.
BACKGROUND / DISCUSSION
The Building on Basics Lincoln Center Renovation project began in July 2010. The project is renovating 55,000 sq.
ft. and adding approximately 17,000 sq. ft. to the Lincoln Center with a focus on improving the patron experience,
performer amenities, and infusing new life into this community treasure.
During construction, an unanticipated structural issue was uncovered in the 32 year old Performance Hall walls. The
project structural engineer,Martin and Martin,evaluated and tested the walls,and determined that additional structural
support was required(Attachment 1). Ground penetrating radar was used on a representative sample of the wall and
two areas of the wall at the back of the stage were demolished to better understand how the wall was constructed.
Martin and Martin believe the results of its investigation provided a reasonable representative sample-of the existing
` wall construction and that additional invasive testing was unnecessary.
A second structural engineering firm, JVA, was retained by the City to provide a second opinion, and agreed with
Martin and Martin's findings (Attachment 2). Martin and Martin, in consultation with JVA, has developed a series of
structural columns, consisting of steel, concrete, and concrete masonry unit block, that will line the exterior of the
existing performance hall walls at specified intervals that will provide the necessary structural reinforcement.
The original estimate was $460,000 based on a per column basis. This was not a guaranteed maximum price from
the contractor.The repair project with this amountwas brought forward and approved by Council at its regular meeting
on January 18, 2011 (Ordinance No. 006,2011,Attachment 3). The structural work is being completed by the Lincoln
Center renovation general contractor, Bryan Construction, and is running concurrent with the Lincoln Center
renovation, with reopening anticipated in August 2011.
Additional Funding Needed:
The original estimate was based on expected labor and materials required for the repair. The design has changed a
number of times throughout this process in order to make the structure Code compliant, and as a result of the
conditions that were found as work proceeded. An additional $135,000 is needed to complete the repair, with a
guaranteed maximum price of$595,000.The contractor is required to submit all material and labor invoices to the City
in accordance with the contract.
The additional $135,000 will cover the following expenses:
• Insulation Removal: With each of the 21 masonry column locations, it was discovered that the existing
concrete masonry unit block was filled with solidified foam insulation (an atypical construction method).
Since the structural repair calls for steel rebar and concrete to be placed inside the block cells, the
insulation had to be removed and the cells cleaned and repaired by hand. The remaining 11 steel columns
will require the same work. This was not detected by the initial structural investigation through radar or
the test holes and is estimated to be 50% of the additional funds requested.
May 17, 2011 -2- ITEM 11
• Steel plates in Performance Hall West Side-The structural engineer required the steel plates extend down
to the foundation, instead of terminating at the precast concrete. This will require demolition work to go
through the existing precast concrete, masonry repair,and additional steel. It is very labor intensive to cut
through precast concrete and will require two steel crews to complete the work.
• Clarification from structural engineer on miscellaneous details for conditions-The Performance Hall stage
roof needed to be supported while existing wall material was being removed and the new columns
constructed. This was not included in the original estimate, but was determined necessary as the project
progressed.
Funding Options:
Project Contingency: The need to structurally reinforce the Performance Hall walls could not be anticipated and the
cost far exceeds the contingency of the project. The contingency has been needed to cover other unexpected costs
not uncommon with a renovation project.
Lincoln Center Reserves: $350,000 from Lincoln Center Reserves has previously been appropriated toward the
renovation and the wall repair. At the end of 2011, Lincoln Center reserves are estimated to be$175,000, which is
well below a level to fund the additional repair work without putting the Lincoln Center operations budget at risk of
going into the red. Lincoln Center is a $2.9 million operation and faces unique uncertainties because of year long
closure necessitated by the renovation project.
General Fund Reserves: $310,000 from General Fund Reserves has previously been appropriated toward the
renovation and the wall repair. Other planned and anticipated uses of General Fund reserves are expected to lower
unassigned fund balance to below the 60 day level prescribed by the Fund Balance Policy.
Building Community Choices Remainder Funds:The Capital projects Fund, Building Community Choices reserve,has
a balance of$6.8 million, derived primarily from interest earnings, which is available for other capital projects. This
ordinance appropriates money from Capital Projects Fund reserves in the Building Community Choices program.
FINANCIAL/ ECONOMIC IMPACTS
This Ordinance will appropriate additional funding for the Lincoln Center Renovation to complete the additional
structural support as follows:
Prior Year Reserves (Capital Projects Fund): $135,000
This funding source is part of the residual reserves from the Building Community Choices—Community Enhancements
program..
ENVIRONMENTAL IMPACTS
The Lincoln Center renovation and this additional structural work will meet LEED Gold standards.
STAFF RECOMMENDATION
Staff recommends adoption of the Ordinance on First Reading.
ATTACHMENTS
1. Martin and Martin Memo, September 28, 2010
2. JVA Memo, December 9, 2010
3. Ordinance No. 006, 2011
ATTACHMENT 1
MARTIN /MARTIN MEMORANDUM
1111 I TINE Y,Nli1N P.rR6
Pago 1 of 2
To: Chris Freeland I Dave Lingle Date: September 28,2010
Aller Lingle Massey Architects From: Garth Scholl P.E.
712 Whalers Way,SuiteB-100 Project No.: 21763.&02
Fort Collins,Colorado Project Title: Lincoln Center Wnll Investigation
Copy To: Steve Seefeld
City of Fort Collins
RE: Existing wall investigation results and recommendations
At this point in time we have investigated the existing stage walls by using Ground Penetrating Radar(GPR)to
scan the following locations:
-back interior stage wall at approximately 4'-0"
-back exterior stage wall at approximately 4'-0"
-stage exterior side walls at approximately 4'-0"
-back interior stage wall at approximately mid-height,limited by access to approximately 12'in length.
Additionally,two areas of the brick wytbc portion of the wall at the back of the stage were selectively demolished
to observe the vertical reinforcing and grout at the in-wall columns. We observed this selective demolition to
better understand how the wall was constructed. At this point we believe.that the results of our investigation
provide a reasonable representative sample of the existingwall construction. We do not believe additional GPR
scans or additional selective demolition will uncover conditions which differ significantly than those which have
been found. We believe the investigative portion of the work to be essentially complete.
During our investigation we found large voids in a significant percentage(approximately 33%)of the reinforced in-
wall columns. The voids observed are potentially detrimental to the strength and performance of the wall. The
grout surrounding the reinforcing within the brick portion of the wall was poorly consolidated for the full extent
that was demolished;the grout appeared to unconsolidated mortar which appeared to have been placed with a
trowel. Based on these observations we believe that the construction would not have met inspection requirements
at the time the building was constructed and the construction would definitely not meet the special inspection
requirements of the current code. Also while at the site we observed a comer of the existing building which had
been damaged with the recent construction,some of the brick face shells bud been broken off. Based on the
existing structural drawings a column should be located at this damaged comer,the column was not in place at the
exposed portion of wall. With the above information taken into account along with the height of these exterior
walls we have significant concerns related to the structural intcyqity and load capacity of the walls.
Based on a review of the 1973 UBC the wall height to thickness ratio exceeds the typical recommended value and
the design would have required special consideration. Additionally the design which appears on the existing
structural drawings is not entirely consistent with the wall construction observed. The location of the reinforcing
and the cell arrangement within the brick do not match the existing structural drawings. Under the 20061BC the
height to thickness ratio of the existing wall would only be pennitted with special inspection. Additionally,we
believe that the multi-wythe construction would not meet the requirements of the 20061BC for the existing wall
height to thickness ratio.
RaviudOM/rala
12499 West Colfax • Lakewood,Colorado 80215 • Telephone:303-431-6100 • www.martinmartin.com
Civil Department Fax 303-431-1028 • Structural Department Fax:303-431-6866 • Marketing Department Pax:303,156-9923
i
MEMORANDUM
Page 2
Bnscd on the results of the investigation,design calculations and discussions with the general contractor who
observed reinforcing in tmgrouted cells during the demolition of some of the 1977 edition walls we recommend that
the remaining walls of similar construction be reinforced. We believe the deficiencies noted above are throughout
the 1977 edition and recommend that all of the remaining 1977 edition welts be reinforced.
We would offer the following preliminary concepts to strengthen the existing wall. The first concept would be to
add a structural steel column spanning between the foundation and roof to the existing wall,the columns would
most likely be spaced at eight foot on center between the existing in-wall columns. The steel columns could be cut
into the existing wall and surrounded by grout or added to the outside of the wet]without cutting into die existing
wall. If the column is added to the outside of the wall it portion of the well would have to be grouted in order to
provide a connection between the wall and the new column. A second aitemate would be to remove strips of the
existing wall back to the interior CMU face shell and add a flush wall 24"wide by 12"deep CM colwnn at eight
feet on center spaced between the existing in-wall columns. Both of these options could be constructed from the
exterior portion of the building.
We would recommend the owner and design team discuss these two concepts with the contractor. The contractor
review would be both for general constructability and to see if any additional reinforcing ideas are presented by the
contractor. After taking into account uny comments from the contractor we will be able to provide a better
construction cost estimate.
I
aAPrtotscrs 176r 0rwrvrao9-rd•la.dm a�urdO212R
12499 Wet Colfax • P.O.liox 151500 Lakewood,Colorndn 80215 Telephone:303-431-6100 • www,tnur inrnartio.com
Civil Department Fax:303-431-4028 Structural Department Fax:303-431-6866 Marketing Department Fax.303456-9923
ATTACHMENT 2
JVA,
111�/ / L 25o Torpoquar
25 Otd Town S uaro
�J dJ`5111 suite Zoe
Fort Collins,CO 80524
Ph: 970.225.9099
December 9, 2010 Fax:970.225.6923
Toll Free:877,444.1951
Chris Freeland, AIA, LEED AP web site:
Alter-Lingle-Massey Architects w Jvajva.com
712 Whalers Way EK all:
Building B,Suite 100 Into@Jvajva.com
Tort Collins, CO 80525
RE: Lincoln Center Wall Investigation
JVA Project No. 14455
Dcar Chris:
This letter is to summarize JVA's preliminary findings regarding die Lincoln Center masonry
wall investigation, subsequent strengthening recommendations, and proposed construction costs
for repairs.
JVA was asked to review the documents provided to us to determine whether the repairs
recommended by Martin/Martin were appropriate and whether the associated costs were
appropriate. JVA has reviewed the original building drawings,the contractor's cost summary
dated 11/23/10, two memos by Martin/Martin dated 9/28/10 and 10/15/10,and the wall
strengthening drawings prepared by Martin/Martin and dated 11/24/10. Additionally, we visited
the site on 12/2/10 and 12/9/10 and spoke directly with Garth Scholl at Martin/Martin on
12/9/10. Alter considering all of these items, we conclude the following:
1) We concur that the exterior walls in question are deficient.
I Based on our own site observations,there are significant defects in the construction of the
masonry walls. These include ungrouted portions of reinforcing bars w thin masonry cavities,
poorly consolidated grout,and inadequate cover of reinforcing bars. M onry walls of this
height require significant reinforcing that is properly grouted into the monry cavity to ensure
that the reinforcing and masonry act as one unit. At the locations we observed, this was not
achieved and we do not believe the walls function as intended nor meet building code
requirements.
The question has been appropriately raised as to why the walls have not exhibited any signs of
distress in more than 30 years since the building was constructed. We believe there are a few
factors that might explain finis. The highest winds generally come from the west and the north,
and the building is largely shielded from westerly winds by the Mulberry Pool and northwest
portion of the Lincoln Center. Tt is possible that the walls in question have not experienced the
design wind pressure over much of their life due to being partly shielded by these buildings.
Additionally, while many reinforcing locations have been noted to lack jn-0ut or have poorly
consolidated grout,there are likely portions of the walls where some bond(albeit weak)between
reinforcing and masonry was achieved, and this in combination with being shielded by
surrounding buildings may have meant that the wall had enough capacity to remain stable for
BOULDER I FORT COLLINS WINTER PARK
Lincoln Center Wall Investigation
l`I'I'O`..RR, .`7`L1\ Chris Freeland 1219110
Page lof3
i
the loads actually experienced until now. The loads actually experienced,however, arc likely
much less than those required by code.
We must stress that any existing structural capacity that has prevented these walls from
structural failure until now cannot be quantified nor relied upon to prevent structural failure in
the future. For this reason,Abe recommend that repairs be made.
i
2) We believe the repair recommendations made by Martin/Martin arc reasonable and
appropriate for the deficiencies observed.
Having reviewed the repair drawings provided by Martin/Martin,performed preliminary
calculations,and spoken with Garth Scholl about their design methods and intent, we believe the
repairs they've recommended arc reasonable and would provide structural integrity to the wall..
If further material savings measures are to be explored, we would suggest that the following
design assumptions be verified. Note that we do not wish to imply that these items were not
accounted for,but only suggest verification.
a. Verify wind criteria used is 100 mph velocity(3 second gust), Exposure 13, Occupancy
I Category III, with adjustment for altitude.
b. Verify that a tributary area of wall height by 8' width was used for calculating wind
pressure coefficients. 'I'lie code also permits even less stringent criteria.of wall height by
a width of•l/3 the wall height if so desired.
c. For purpose of wall deflection,verify that 70%of the component and cladding wind
pressure is used as allowed by code.
3) We suggest the following alternatives be explored or revisited to determine whether
cost savings may be found.
a. Consider the use of structural steel in place of concrete and masonry pilasters. We
understand from to l"ll;with Garth Scholl that this option was considered. However,
after reviewing the repair drawings and costs,we believe this option should be explored
once more in conjunction with items 3b and 3c below. A single piece of steel could be
brought onsite and erected in less time than forming the partial height concrete pilaster,
then placing masonry.
b. In conjunction with item 3a, consider erecting steel wind-colutruis from the inside of the
building wherever possible, so that exterior finishes would not be required around
pilasters.
c. Consider options that do not involve demolition of brick veneer,but involve bolting
through the brick and masonry wall. fltis might eliminate most of the.880,000 cost
associated with saw-cutting the brick,
d. Consider spacing pilasters or wind columns at greater spacing,such as 10 feet or 12 feet,
to decrease the number of pilasters required.
e. Consider using fewer attachnnents to existing structure. The details require grouting
existing walls every 16"to 24"and installing dowels or ties. Increasing this spacing to
32"or 48"may decrease the amount of time and labor required to place grout and
dowels.
BOULDER I FORT COLLINS I WINTER PARK
i
Lincoln Center Wall Investigation����
Chris Freeland, 1219110
LM S:V1 it Page 3of3
4) We suggest the following items from the contractur's cost summary be reviewed:
a. The cost of structural work(Divisions 2 through 5) accounts for$377,000 of the
$608,963 total cost, or roughly 62%of the total cost. Based on the fact that this work is
primarily exterior and structural in nature, and that work is already in progress on site,
we'd expect the overall cost to be lower.
b. The general conditions cost(Division 1)appears high based on the fact that many items
are already onsite. It would appear that roughly 10 weeks is required to perform the
additional repair work specified. Is the overall schedule being extended by 10 weeks to
warrant 10 weeks of additional costs for items such as water/icc/cups, telephone,fencing,
toilets,etc that are already on site'
c. The general conditions costs include roughly$52,000 for 5 additional personnel(project
manager,superintendent,project engineer,layout helper, and project administrator), is
Us personnel in addition to the staff already on site, and would they be devoted solely to
the repair work? Would additional time be spent onsite compared to the overall schedule,
or would this time be shared with existing activities?
d. We suggest that more detailed information be provided about the extent of weather
protection required. The cost for this item was listed.as$28,000.
e. The combined cost of$67,606 for finishes, mechanical, and electrical (Divisions 9, 15,
and 16)appears high for work that is primarily exterior. If not previously clarified, we
suggest that additional information be provided to the City as to the extent of work
required under these items to justify their cost.
In summary it is our opinion that strengthening of the walls in question is required. While we
understand that a mmriber of options were explored and that value-engineering was done as part
of the design process for these repairs,we believe that some cost savings might be possible as
described in items 2 through 4.
Please do not hesitate to contact us if you have any questions or if we can be of further
assistance.
Sincerely,
JVA, rNCORPORATP..D
Prepared By:
R nald Manske, P.E.
Project Manager
Reviewed By:
Michael cDonald,P.E.
Regional Manager
BOULDER I FORT COLLINS I WINTER PARK
ATTACHMENT 3
L
ORDINANCE NO. 006, 2011
OF THE COUNCIL OF THE CITY OF FORT COLLINS
APPROPRIATING PRIOR YEAR RESERVES IN THE CULTURAL SERVICES FUND
AND PRIOR YEAR RESERVES IN THE GENERAL FUND FOR TRANSFER TO THE
CAPITAL PROJECTS FUND AND APPROPRIATING UNANTICIPATED
REVENUE IN THE CAPITAL PROJECTS FUND FOR THE BUILDING ON
BASICS LINCOLN CENTER RENOVATION PROJECT
WHEREAS, on November 1, 2005, Fort Collins voters passed Ordinance No. 092, 2005
approving the"Building on Basics" ("BOB") tax for certain capital projects including the Lincoln
Center Renovation Project; and
WHEREAS, the total cost of the renovation project was estimated to be $7.3 million,to be
paid for with $5.5 million of BOB funding,$621,855 in funding from the Downtown Development
Authority, and the remaining amount from other sources; and
WHEREAS, during construction of the Lincoln Center Renovation project, which began in
July 2010, an unanticipated structural issue was uncovered in the performance hall walls and it has
been determined that additional improvements in the form of structural reinforcement will be
necessary; and
WHEREAS,these improvements will be completed by the general contractor on the project
at an estimated cost of$460,000; and
WHEREAS, in order to fund the additional improvements, staff has recommended that
$150,000 be appropriated from prior year reserves in the Cultural Services Fund and$310,000 from
prior year reserves in the General Fund for transfer to the Lincoln Center Renovation Capital
Project; and
WHEREAS,Article V, Section 9 of the City Charter permits the City Council to appropriate
by ordinance at any time during the fiscal year such funds for expenditure as may be available from
reserves accumulated in prior years, notwithstanding that such reserves were not previously
appropriated; and
WHEREAS, City staff has determined that the appropriation of the revenue as described
herein will not cause the total amount appropriated in the Capital Projects Fund to exceed the current
estimate of actual and anticipated revenues to be received in that fund during any fiscal year.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF FORT
COLLINS as follows:
Section 1. That there is hereby appropriated for expenditure from prior year reserves in
the Cultural Services Fund the sum of ONE HUNDRED FIFTY THOUSAND DOLLARS
($150,000) to be transferred to the Capital Projects Fund and appropriated therein for the Building
on Basics - Fort Collins Lincoln Center Renovation Project,
C 0 Py .
Section 2. That there is hereby appropriated for expenditure from prior year reserves in
the General Fund the sum of THREE HUNDRED TEN THOUSAND DOLLARS ($310,000)to be
transferred to the Capital Projects Fund and appropriated therein for the Building on Basics - Fort
Collins Lincoln Center Renovation Project.
Introduced, considered favorably on first reading, and ordered published this 18th day of
January, A.D. 2011, and to be presented for final passage on the t day of February, A.D. 2
Mayor
ATTEST:
City Clerk
Passed and adopted on final reading on the 1 st day of F ru A.D. 2011.
May r ,
ATTEST:_
City•Clerk
C(a ply
ORDINANCE NO. 062, 2011
OF THE COUNCIL OF THE CITY OF FORT COLLINS
APPROPRIATING PRIOR YEAR RESERVES IN THE CAPITAL PROJECTS FUND
FOR THE BUILDING ON BASICS LINCOLN CENTER RENOVATION PROJECT
WHEREAS,on November 1,2005,Fort Collins voters passed a ballot measure establishing
a one-quarter cent sales tax to fund the capital projects in the "Building on Basics" ("BOB")
program, which program includes the Lincoln Center Renovation Project (the "Project"); and
WHEREAS,the total cost of the Project was estimated to be $7.3 million and construction
began in July 2010; and
WHEREAS, during construction of the Project, an unanticipated structural issue was
uncovered in the performance hall walls and it was determined that structural reinforcement would
be necessary; and
WHEREAS,the original estimate for the additional structural improvements was$460,000
and the City Council previously appropriated that amount; and
WHEREAS,as the work progressed,some additional issues were discovered in the walls and
it has been determined that an additional $135,000 is needed to complete the structural
improvements; and
WHEREAS, City staff recommends that the City Council appropriate $135,000 from
reserves in the Capital Projects Fund,Building Community Choices residual balance for the Project;
and
WHEREAS,Article V, Section 9 of the City Charter permits the City Council to appropriate
by ordinance at any time during the fiscal year such funds for expenditure as may be available from
reserves accumulated in prior years, notwithstanding that such reserves were not previously
appropriated; and
WHEREAS, City staff has determined that the appropriation of the revenue as described
herein will not cause the total amount appropriated in the Capital Projects Fund to exceed the current
estimate of actual and anticipated revenues to be received in that fund during any fiscal year.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF FORT
COLLINS that there is hereby appropriated for expenditure from prior year reserves in the Capital
Projects Fund Building Community Choices reserve the sum of ONE HUNDRED THIRTY-FIVE
THOUSAND DOLLARS ($135,000) for the Project.
Introduced, considered favorably on first reading, and ordered published this 17th day of
May, A.D. 2011, and to be presented for final passage on the 7th day of June, A.D. 2011.
Mayor
ATTEST:
City Clerk
Passed and adopted on final reading on the 7th day of June, A.D. 2011.
Mayor
ATTEST:
City Clerk