HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 05/04/2010 - RESOLUTION 2010-023 APPROVING THE NORTH COLLEGE IN DATE: May 4, 2010 AGENDA ITEM SUMMARY STAFF: Clark Mapes FORT COLLINSCOUNCIL Resolution No. 2010-023 Approving the North College Infrastructure Funding Plan. EXECUTIVE SUMMARY The proposed Funding Plan consists of a prioritized list of infrastructure projects needed in the North College Avenue corridor area, along with corresponding potential funding sources to pursue. It contains no new policy decisions, nor any obligations or commitments. Rather, it is an aid to implementation of previously adopted plans. Council approval of the Funding Plan would establish a useful framework to guide work efforts and decision making on funding for infrastructure projects over time. The term"infrastructure projects"generally refers to construction projects thatwould build up a more complete system of streets and utilities in the area. These are basic public facilities needed to support long-term revitalization as envisioned. BACKGROUND / DISCUSSION Initiative for the Funding Plan This Funding Plan was prompted by a joint work session of the Urban Renewal Authority (URA) Board of Commissioners and the North College Citizen Advisory Group (CAG) in July 2008. At the meeting, the Board, the CAG, and staff agreed on the need for this Plan. The need is to help plan for the use of tax increment financing(TIF) revenues under the North College Urban Renewal Plan and identify additional funding mechanisms to complement those currently in place. The Board directed staff to prepare the needed Plan. In March 2009, staff began the process to develop the Funding Plan. In July 2009, at the second annual joint work session, staff presented draft material to the URA Board and received direction and support to complete the Plan and bring it forward for approval. Council Questions About the Funding Plan At the February 2, 2010 City Council meeting, staff presented the Plan for Council approval. Council action was postponed to allow more time to explore and respond to three specific questions from Council, shown below with staff responses. 1. In the Project Summary Table,why aren't developers listed in the"Potential Funding Sources"column for North College Avenue improvement projects that list developers in the "Benefits and Responsibilities" column? Staff Response: The Project Summary Table has been revised in response to the question. Developers have been added into the "Potential Funding Sources"column for these projects. Developers would typically be responsible for the local street portion of street edge improvements needed to bring the street up to standard along their frontage, under City Code. These developer contributions are likely to be minor in the context of the projects listed;but they are a potential funding source and adding them for these projects is an improvement to the document. May 4, 2010 -2- ITEM 23 2. In the Project Summary Table,why isn't Environmental Sustainability listed as one of the"Objectives Met" by projects? Staff Response: This question involves the purpose of the"Objectives Met"column,as well as the overall purpose of the Funding Plan. The purpose of the Plan is to list, organize, and prioritize the projects into a working framework. The purpose of this column was to guide discussion of priorities and logical sequencing among very closely related infrastructure projects, to determine which should be pursued soonest. The primary aspect of sustainability related to this Funding Plan is the cumulative effect that the infrastructure projects will have upon revitalization of the area. In other words, sustainability is a larger objective to be promoted by overall revitalization of the area, but is not a clear objective to identify priorities among the individual projects listed. In this sense, all of the projects affect sustainability in the same way—by contributing a step toward efficient urban infill and redevelopment of a more livable, walkable city. Nevertheless, individual projects will present opportunities for sustainable environmental design including but not limited to material selection, wetland protection, and use of best practices, as they move forward to design and construction. It is premature for this Funding Plan to explore these detailed design aspects of each project; that was not within the purpose and scope of the Plan. 3. In the Project Summary Table,why is Street Oversizing listed as a "Potential Funding Sources" on some arterial and collector street projects, but not on the North College Avenue improvement projects? Staff Response: The Project Summary Table has been revised in response to this question. Street Oversizing is a potential funding mechanism for the North College projects. However,the revision to the document actually removes the reference to Street Oversizing from the"Potential Funding Sources" column entirely, because it is only a mechanism and not a source of funding. This makes the overall document internally consistent,because Street Oversizing is not listed separately as a funding source in Table 2,which summarizes various funding sources on the reverse side of the Project Summary Table. Rather, Street Oversizing falls under the heading of"Developers" as the source. Developers were added to the"Potential Funding Sources" column in response to both this question and question 1 above. Street Oversizing would likely play a very minor role in any instances where it would be involved. It is typically used in conjunction with new developmentto mitigate impacts of growth,and is.restricted from being used to correct existing deficiencies. Purpose of the Funding Plan The purpose of this Funding Plan is to place all of the area's key infrastructure needs into an overall framework to guide work and decisions by the URA, the City, and others with an interest in North College area infrastructure. Previously Adopted Plans The Funding Plan is a tool to help implement the vision, goals, policies, and objectives of previously adopted plans, including: • The 2007 North College Corridor Plan • The 2004 North College Avenue Urban Renewal Plan • The 2000 US2871SH14 Access Management Report All of these plans address infrastructure needs and issues in the North College corridor area. All are consistent with the City's overall Comprehensive Plan known as City Plan. May 4, 2010 -3- ITEM 23 Related to these adopted plans, Fort Collins Utilities and Engineering staff have performed engineering design work on drainage and sewer facilities,and also on the proposed new arterial street known as"Realigned Vine". In addition, a voter-approved capital project to improve North College Avenue between Vine Drive and Conifer Street has been in its design phase during preparation of this Funding Plan. It is known as the Building on Basics, or BOB project. All of this work has contributed to the information in this Funding Plan. Summary of Plan The primary component of the Funding Plan is the Project Summary Table,which lists needed infrastructure projects, designates priorities, and notes potential funding sources. The remainder of the Plan includes additional explanation of the projects and funding sources. Implications of Council Approval If approved,staff will use the Funding Plan to seek funding for projects,and develop recommendations for use of TIF. Also, the Plan will be used for coordination and input on other important capital project lists and budgets used by City departments and the Colorado Department of Transportation. Finally, approval would signify general support for exploring and pursuing special assessment or improvement districts,or other cooperative measures among property owners, developers, and other stakeholders. Approval of the Plan would not create any funding commitments or obligations. Rather, it would support ongoing work and discussion which would lead to funding commitments by appropriate sources over time. Any City capital projects that move forward to build infrastructure would be administered in accordance with the City's Capital Projects Procedures Manual. FINANCIAL IMPACT No direct financial impacts would result from approval of the Funding Plan because the Plan contains no funding commitments. However,as the North College area develops overtime as envisioned,the URA and the City are likely to continue to participate in funding public infrastructure. This Funding Plan would inform those decisions, and thus, it may indirectly have financial implications for the City. Specific financial impacts of projects will be determined on a case-by-case basis as projects proceed to approval of funding, programming, and construction. The question of life cycle costs for operations and maintenance of infrastructure has been a topic of discussion. Such costs are separate and distinct from the capital costs of getting projects designed and built. Cost estimates in the Funding Plan include capital costs only. Funding for operation and maintenance costs for City capital projects must be identified at the time projects are approved, in accordance with the City's Capital Projects Procedures Manual. SUSTAINABILITY: ECONOMIC, ENVIRONMENTAL AND SOCIAL IMPACTS Because this Funding Plan contains no new policy or funding commitments, staff does not find any new impacts on these sustainability considerations--such impacts are addressed in existing adopted plans which this Funding Plan would help to implement: As the North College area develops overtime,economic effects will be complex. Infrastructure projects will be costly; most of them will involve multiple funding sources; and many will require public/private partnership. Costs would be offset by increased values and revenues generated in the area over the long term. The projects in the Funding Plan would be constructed to current standards forwater quality and energy consumption. Any associated development will comply with Land Use Code standards. The projects would buildup a more complete system of public improvements to support the health, safety, and well-being of citizens. May 4, 2010 -4- ITEM 23 In general, the projects listed in the Funding Plan represent investments in efficient infill and redevelopment,with an emphasis on pedestrian facilities and community character, in a close-in location near Downtown. This type of development is envisioned in adopted plans for the area, and is central to sustainability goals. STAFF RECOMMENDATION Staff recommends adoption of the Resolution. BOARD/ COMMISSION RECOMMENDATION On November 19,2009,the Planning and Zoning Board voted 7-0 to recommend approval of the Funding Plan to City Council. The North College Citizen Advisory Group (CAG) on January 7, 2010, voted 6-0 to recommend approval of the Funding Plan to City Council. On January 20, 2010, the Transportation Board unanimously recommended approval of the Funding Plan to City Council. The North Fort Collins Business Association provided a letter in support of City Council approval of the Funding Plan on January 21, 2010. PUBLIC OUTREACH The original idea for the Plan was discussed at the July 2008 joint URA/CAG work session. The planning process to develop the Funding Plan was initiated in March 2009,with draft material developed through a series of five regularly- scheduled monthly CAG meetings, which are open to the public. Progress on the draft material for the Plan was reviewed by the URA Board at a joint work session in July 2009. In September, this information was also presented at a public Open House, and to the North Fort Collins Business Association. The CAG continued to review minor updates at monthly meetings as the Plan document was prepared through the fall of 2009. Various City departments, the Colorado Department of Transportation, and interested members of the public, participated throughout the process. ATTACHMENTS 1. Joint URA/CAG work session summary, July 28, 2009. 2. Planning and Zoning Board minutes, November 19, 2009 3. Transportation Board minutes, January 20, 2010 and November 18, 2009 4. Notes from the North College Citizens Advisory Group, January 7,2010 meeting. 5. Letter from the North Fort Collins Business Association, dated January 21, 2010. 6. PowerPoint presentation ATTACHMENT 1 City of Advance Planning 281 North College Fort Co ins FoortBColl 50 ins,CO 8 522nue 970.221.6376 970.224.6111 -fax fcoov.com/advanceolannino July 30, 2009 Memorandum TO: Urban Renewal Authority Board TH: Darin Atteberry, City Manager Diane Jones, Deputy City Manager Jeff Scheick, Planning, Development & Transportation Director Joe Frank, Advance Planning Director FM: Clark Mapes, City Planner RE: July 28, 2009 Joint Session Summary This memorandum summarizes the Joint Session between the Urban Renewal Authority (URA) Board and the North College Citizen Advisory Group (CAG). Staff presented draft materials on two main topics: a North College Infrastructure Funding Plan, and "green building" aspects of development projects seeking tax increment financing (TIF). URA Board Members Present: Mayor Doug Hutchinson, Mayor Pro-Tem Kelly Ohlson, Aislinn Kottwitz, Ben Manvel, Lisa Poppaw, Wade Troxell, and David Roy. Joint Session Participants: Jeff Scheick, Planning, Development & Transportation Director; Joe Frank, Advance Planning Department Director; Clark Mapes, City Planner; Bob Smith, Water Planning and Development Manager; Kathleen Bracke, Director of Transportation Planning and Special Projects; Greg Woods, Chair of North College Citizen Advisory Group; Dean Hoag, CAG member and President of North Fort Collins Business Association(NFCBA). City of . Wit` Collins Discussion Points and URA Board Direction: North College Infrastructure Funding Plan (NCIFP) • A Board member expressed dislike and disagreement with the Realigned Vine concept and requested clarification of the $24 million cost estimate he has seen in the past. • Tax increment financing is not an automatic entitlement for developers. • The CAG needs to be vigilant about the percentage of tax increment allocated to individual development projects. • The Board relies heavily on.the CAG to scrutinize proposals and make the difficult choices about saving part of the tax increment for capital projects. • Competing needs for funding of development and capital projects are acknowledged and understood by both the Board and CAG. • The Board will expect to see the draft materials developed into a document for adoption. Green Building criteria • Incorporate green building language into TIF application, score card, and agreements. • The purpose and intent is to give attention and provide incentives for projects to go beyond basic Code requirements for energy and resource-conserving features. • 'Considerations should include life cycle analysis (costs, savings, resale value, etc.) • The Board encouraged education on this topic for the CAG, staff and TIF applicants, so that they can then discuss issues and share ideas. The suggestion was made to arrange for presentations by qualified staff working on the Green Building Code, or CSU's Institute for the Built Environment. Other The Union Place project was recently approved for TIF with 75 units. A Board member noticed that the unit count was changed to 89, and requested an explanation of the change to check his assumption that the plan is still as good or better than the plan the Board approved. Adding units to a plan can enhance a plan, or detract from a plan; and plans should be implemented as approved by the Board. Any substantive changes beyond minor amendments should be reviewed with the Board and probably CAG as well. A Board member asked for a description of when the URA will pay for relocation or damages to existing businesses. Next Steps: Staff will prepare a NCIFP document for adoption, with review by the CAG, NFCBA, and the public. Staff will revise the appropriate forms and documents to add green building considerations. Staff will investigate an appropriate green building presentation for the CAG and URA staff. Staff will provide a memo to the Board and CAG explaining changes to the Union Place development plan; compensation to existing businesses; and Realigned Vine costs and reasoning. 2 ATTACHMENT 2 Planning&Zoning Board November 19, 2009 Page 13 A. Adding the office and bed and reakfast establishments with six or fewer beds to the existing house and prope y at 1124 West Mulberry Street in the N-C-L zone Is found to comply with the co patibility standards of Section 3.5.1 of the Land Use Code B. Adding the two proposed u es to 1124 West Mulberry Street Is found to comply with the criteria of Section .3.4 of the Land Use Code In that such addition: (1.) Would be a proprlate to the zone district; (2.) Would conf rm to the basic characteristics of the zone; (3.) Would not ave any adverse Impacts on the district; (4.) Would not a detrimental to the public good; (5.) Would not forwarded to City Council for Text Amendment C. Adding the two proposed u es to 1124 West Mulberry Street Is specifically conditioned such that the u s must be contained within the existing structure. And subject to the recommendation that s tes: Staff recommends approval of adding office and bed and breakfast establishment for six or ewer beds as a permitted use for the existing structure at 1124 W. Mulberry Street, subje to the bed and breakfast establishment being reviewed as a PDP by the Planning &Zonin Board as a Type Two review. Member Carpenter seconded the motion. Chair Schmidt noted that when it moves toward th B&B option, they would have to comeback to the Planning &Zoning Board. There would also be nei hborhood meetings at that time so that gives neighbors further opportunity for input. Shepard sal if the motion to approve is carried forward then the next task for the applicant would be for the applicant come down to the zoning department and go through the change of use process. If the Alexander ency moves and say an attorney or an accountant moves in that would not require a change use. If it were to become anything but an office or a B&B, it simply would not be permitted. Member Campana asked if it changes to a B&B would it e a Type 2, requiring Board review. Shepard said yes. Director Dush agreed. Eckman referred the B and to the recommendation on page 9 of the staff report. Member Carpenter made the comment that there are lot of advantages that go with eligible landmark designation and it is something the applicant may w t to look into. The motion passed 7:0. Project: North College Public Infrastructure Funding Plan Project Description: Staff is requesting the Planning and Zoning Board forward a recommendation to City Council to approve the North College Infrastructure Funding Plan by Resolution. Recommendation: Staff recommends approval of the North College Infrastructure Funding Plan. Hearing Testimony Written Comments and Other Evidence . City Planner Pete Wray reported in July 2009 staff received direction and support from the North College Citizens Advisory Board (CAG) and City Council to proceed in finalizing the North College infrastructure Funding Plan (Funding Plan). The purpose of the Funding Plan is to establish a comprehensive list of Planning &Zoning Board 'November 19, 2009 Page 14 capital improvement projects needed within the North College area. This list identifies potential funding sources and suggests partnerships for future implementation. The list will primarily prioritize the projects from Very High to Low, thus establishing a hierarchy of need to guide the City Council and the Urban Renewal Authority(URA) Board in decision making. The Funding Plan also contains a concentration on the highest priority projects and suggests potential funding scenarios to Implement them within a reasonable timeframe. Lastly, this Funding Plan will be monitored and updated annually by staff as progress is made and new information becomes available. Chair Schmidt asked staff to review how this Plan interfaces with some of the other North College related Plans—North College Corridor Plan and City Plan. City Planner Clark Mapes said this Plan directly , implements the North College Corridor Plan and the North College Avenue Urban Renewal Plan by setting up a framework for staff and others to pursue funding for infrastructure needs that are describe in those Plans. Some of the major headings in the North College Corridor Plan are North College Avenue Itself, It speaks to the deficiencies that the Board is well aware of, the need for a more complete street system (parallel streets to College Avenue, connections, and the addition of bike lanes, sidewalks and landscaping, etc.) The North College Plan also describes the need for a drainage system. The area does not have a drainage system. All the projects that are within this plan are projects that cumulatively would build up a more complete street system and a drainage system. Member Smith said he appreciates the presentation—it's a follow-up to their conversations in work session about previously adopted urban planning documents (a corridor plan, a subarea plan, or City Plan itself.) Those are the goals and this is an implementation tool. Public Input: None Member Smith made a motion to recommend to City Council they approve the North College Infrastructure Funding Plan. Member Campana seconded the motion. The motion passed 7:0 Other Business, None Meeting adjourned at 8:05 p.m. St a Dush, Current Planning Director Brigitte 9chmidt, Chair Attachment 3 MEETING MINUTES of the TRANSPORTATION BOARD January 20,2010 6:00 p.m. City of Fort Collins Community Room 215 North Mason Fort Collins, CO 80521 FOR REFERENCE: Chair: Gary Thomas 482.7125 Vice Chair: Ed Robert 224.4864 Staff Liaison: Mark Jackson 416.2029 Administrative Support: Polly Bennett 224.6058 BOARD MEMBERS PRESENT: CITY STAFF PRESENT: Olga Duvall Mark Jackson,Transportation Group Director/Bo iaison,416.2029 Bill Jenkins Polly Bennett,PDT Executive Administrativ ssistant, 221.6763 Kip McCauley Pete Wray, Senior City Planner, 221.675 Shane Miller Clark Mapes, City Planner, 221.6225 Ed Robert Kathleen Bracke,Transportation nning Manager, 221.6140 Garry Steen Marlys Sitter, Transfort Gen Manager, 416.2113 Sid Simonson Kurt Ravenschlag, Trans Assistant General Manager, 221.6386 Gary Thomas Jen Petrik, Transport n Planner,416.2471 Council Member Ben Manvel Helen Migchelbr' , City Engineer, 221.6340 Mike Herzig, ecial Projects Engineer, 221.6583 ABSENT: OTH IN ATTENDANCE Sara Frazier D t Schock, The Baker Group, John Lund ary Keith Floyd, The Baker Group Scott VanTatenhove Jodie Snyder,The Baker Group 1. CALL TO ORDER Chair Thomas called meeting to order at 6:00 p.m. with a quorum present. 2. AGENDA RE 3. PUBLIC CO ENT 4. MINUTES VIEW 5. CO L LIAISON REPORT 6. BI CLE ADVISORY COMMITTEE (BAC)—David "DK" Kemp,Bill Jenkins 7. CUSSION ITEMS ACTION ITEMS A. North College Infrastructure Funding Plan—Pete Wray, Clark Mapes Mapes: We are requesting a recommendation to Council recommending Council approval of the Plan as a framework for ongoing work. As noted before, the Plan emphasizes that it doesn't contain any new policy ideas; it is implementation of previously supported plans. One of the two main issues you raised was operations and maintenance funding. We added 1 i Attachment 3 language to the document on that. The plan includes design and construction costs. O&M costs are distinct and separate. City's capital projects manual specifically states that funding sources for increased O&M costs are to be defined at the time the project is approved. It is a bigger issue than the original initiative of this Plan. It will come up with the CityPlan update. Granted the BOB package includes a 7-year plan for O&M costs. The other main issue you raised was transit. There are no transit projects on the list, as no projects have been identified by Transfort. But words were added to the effect that all the street projects listed are inclusive of transportation facilities and amenities. Thomas: The additions are good. I didn't realize the O&M aspect was in the manual. Jackson: In roadway projects, O&M expenses typically are used to adjust budgets such as the Pavement Management Program. Robert: This is a terrific guide. I'd also like to see this approach put into CityPlan and other procedures plans. Jackson: I think you will see this in more subarea planning. Robert: We discussed being more proactive rather than functioning as "advise and consent." The Redwood project ($750k for 900 feet of street) would open up a good connection. I think it might be worthwhile to find the money to build the connection. Mapes: Those projects are "high" priority instead of"very high" because we see those projects as being triggered by development of the abutting parcels, or the realigned Vine Drive. The "red triangle" projects are important to objectives AND need a proactive intervention by the public sector to get them moving opposed to projects where we see the trigger being a developer. Thomas: If this Board recommends to City Council that they pull these out of the pack, does that mess anything up? Mapes: No, that would be exactly within the intent for this document, to stimulate discussion and ideas. We expect constant change, and we expect that it will be updated as appropriate. Robert: Do you agree that there is little development potential along that small area? Mapes: Yes. Those projects cross peripheral parts of the properties. This is a close call and I think we understand your opinion. It would be a useful connection. Thomas: Let's take that discussion up next month. Jenkins: There is a lot of controversy surrounding the URA and TIFF sources. Where does this sit? Mapes: It is solidly within the original intent of the Urban Renewal Law. The area has deficiencies that would take a very long time before enough development occurred to fund the improvements that are needed. Jenkins: Is there any way to calculate the TIF money going into this for different sources? Mapes: We did that for the County. It wasn't possible to calculate it for the School District with the State's funding formula. We reviewed the amount of tax the County would receive with and without the TIFF. At the end of 25 years, the County gets a big jump in revenue. I believe they did not oppose this TIF area. Jenkins: When you say "development" how is that defined? Mapes: We anticipate a full mix of development with retail, employment, residential and industrial. It will primarily remain a generally service oriented area rather than, say, class A retail that would compete with downtown or other areas south. It is zoned and planned for a full mix of development. Wray: Another example is the industrial area around the old airport. It lacks infrastructure like drainage and utilities. 2 Attachment 3 Robert moved to send a recommendation to Council to approve and adopt this Plan. Steen seconded. Passed unanimously. 9. BOARD MEMBER REPORTS 10. STAFF LIAISON REPORT 11. OTHER BUSINESS 12. ADJOURN Respectfully submitted, Polly Bennett Executive Administrative Assistant Planning, Development, &Transportation 3 Attachment 3 MEETING MINUTES of the TRANSPORTATION BOARD November 18,2009 6:00 p.m. City of Fort Collins Community Room 215 North Mason Fort Collins,CO 80521 FOR REFERENCE: Chair: Gary Thomas 482.7125 Vice Chair: Ed Robert 224.4864 Staff Liaison: Mark Jackson 416.2029 Administrative Support: Polly Bennett 224.6058 BOARD MEMBERS PRESENT: CITY STAFF PRES Olga Duvall Mark Jackson,Tran ortation Group Director/Board Liaison, 416.2029 John Lund Polly Bennett, P Executive Administrative Assistant, 221.6763 Kip McCauley David"DK" mp, City Bicycle Coordinator, 416.2411 Ed Robert Mary Finn aring, Mobility Coordinator NFRMPO,416.2023 Garry Steen Pete W , Senior City Planner, 221.6754 Gary Thomas Clar apes, City Planner, 221.6225 Scott VanTatenhove Bill Jenkins Shane Miller ABSENT: OTHERS IN ATTENDANCE Sid Simonson Anita Basham,Liaison, Senior Advisory Board, 491.9938 Sara Frazier Council Member Ben anvel 3. CALL TO ER 4. AGEND VIEW 3. PUB COMMENT 4. M TES REVIEW 5. UNCIL LIAISON REPORT 6. ICYCLE ADVISORY COMMITTEE . DISCUSSION ITEMS 8. ACTION ITEMS A. North College Infrastructure Funding Plan—Pete Wray, Clark Mapes Thomas: Normally we see projects several times before they go to Council. If we need more time to consider a recommendation, we can postpone that until January. This Plan is set to go to Council on December 15, 2009. We decided to bring this to you tonight to get a recommendation to Council if you are comfortable. t Attachment 3 There is an Urban Renewal Plan for the North College area. which allows use of tax increment financing (TIF). It is governed by the Urban Renewal Authority (URA) Board. The North College Citizens Advisory Group (CAG) advises the URA on use of TIF. This funding plan was prompted by a joint meeting of the URA Board and the CAG, where the need for a plan to guide the use of TIF was discussed and agreed upon. The centerpiece of the funding plan is the list of projects. There are multiple funding sources identified and there are conceptual funding scenarios shown for the highest priority projects. It is a working document which will need frequent updating, at least annually. We are asking Council to approvethis plan, Staff proposes that the Board view the funding plan as a follow- up to previously adopted policy plans, and a guide for staff work and other efforts to implement those plans; rather than a new set of policies, commitments, or obligations. Lund: Are we looking at maintaining things after the project is done? Is there a funding stream for that? Mapes: No, that was not part of the process of identifying the needed capital projects and potential funding. These kinds of capital projects typically do not include O & M costs. Jackson: When we talk about roadway projects, we reconfigure our Pavement Management formula to include the new projects. Lund: We are really bad about providing ongoing funding streams at the front end of a project to take care of it at the back end. Mapes: This plan would be used as information and input to Capital Project lists, and would launch additional staff work pursuing the projects Thomas: Recognizing that operating dollars are different than capital improvement dollars, perhaps it needs to be included. Mapes: On the Building on Basics (BOB)project, we discuss maintenance on every project as part of the design decisions. But in general, these kinds of capital projects don't include the life cycle costs in the capital project cost. That would be a big issue, it could change the Way we look at capital projects. But we did not do that with this list. Miller: In addition to the concern about a dedicated funding stream, the conversation opens a logical way of recognizing that there is funding required over the entire life cycle of a capital project, and measuring it and building it in. It is really important, even absent of being able to correct the dedicated funding issue. Robert: BOB was originally a list of"nice to have"projects. We need to come up with dedicated funding to cover the life cycle of projects. Jenkins: How does the King Soopers project relate to this? Mapes: College from Willox to Highway 1 knocked off that segment from the list. Jenkins: Doesn't the traffic and everything associated with a grocery store of that size figure in to this list? Jackson: The Land Use Plan shows increased traffic demand. Miller: What other funding mechanisms were ruled out? Mapes: A Metro District is one example that comes to mind. Besides TIF, the plan identifies other funding sources that include CDOT/MPO, Developers, SIDS for Stormwater, sales tax initiatives,the Stormwater Capital Improvement Program. Miller: If you couldn't use TIF at all, what kind of funding would be done? Mapes: Development, state and federal grants, voter approved packages. Special Assessment Districts, Capital Expansion Fees, Transportation Fees. 5 i Attachment 3 Robert: Relate to funding, you eliminate a dedicated City sales tax to fund BOB projects. This appears not to consider new sales tax funding. It also doesn't address Bonding. Mapes: Bonding isn't really a source of funding. It is an aspect of SIDS, GIDs, TIF, etc. It is a loan, and you need a source to pay it off. If you have a revenue source, the bond can be issued. ' Wray: We can add some text about considering methods to move it forward more quickly. Miller: The City released information about the Pavement Management shortage showing a rate of return of 10% per year after forfeited interest on the reserves. Council decided that wasn't enough,The rate of return on bonding, less administrative costs and interest paid, would have been paid on doing the project now. Mapes: That isn't the level of this Plan. On any given project, Finance will analyze whether bonding/loans is an attractive option. Bonding was a topic in the CAG meetings. We discussed it in the context of timing. Bonding allows earlier, up-front construction if there is a revenue stream to pay the bonds. Thomas: Would it be good to have Finance come discuss bonding with the Board? Perhaps we can have them come in next spring. ` Mapes: We reserve the right to polish the document even if you make a recommendation tonight, and can add wording to include dedicated sales tax revenue and bonding. Miller: Let's assume we aren't comfortable sending a recommendation. Will that impede your process? Wray: We would be looking at January to come back to you. Jackson: In terms of Staff s intent to get this rolling, it would be a couple of months of delay. Thomas: Your high priority projects, then, are the fiscally constrained Plan. Mapes: Yes. Thomas: The word "transit" doesn't appear in here anywhere. How does this fit our ` objective? Mapes: No transit projects have been identified. There may be some new bus stops, but they aren't Capital Projects. Jackson: You can include rolling stock needed as a Capital Project. Mapes: Any kinds of capital project can be added to the Plan as they come up. Thomas: We've raised the quality of transit stops with Council on two occasions. It seems that this is a good time to bring it up again and drive the stake in the ground. The Plan includes bikes, peds, streetscapes, landscaping, etc. It should include transit supportive facilities and amenities. Mapes: We will add transit supportive facilities and amenities to the Plan. Wray: This is a framework/working tool, which is why we are asking Council to approve.it rather than adopt it. VanTatenhove: Once the shovel is going down, will you come ask us for approval? Mapes: We realized very late that we should have come to the Transportation Board for a recommendation. We learned our lesson and will come to you in the future. VanTatenhove: We want you to have the ability to come back and seek recommendations. Mapes: The Plan is intended to guide and launch actual work. Robert: This is called a Plan but is really a framework. Doesn't Council even want to approve such a thing? Thomas: It isn't saying we're definitely spending a specific amount of money on a project. Miller: In the Transit Update we approved, I got the impression that it would come back to us to review the proposed financing mechanisms. Jackson: Any major City funding initiative should come before this Board (with the exception of grants). 6 Attachment 3 Thomas: The Old Town North Developers were asking Council for money one night. Is that part of this? Mapes: No, that was different. But it was a TIF request, and this is a tool or guide for the URA and Council to help them distribute TIF, so it is indirectly related. This Plan isn't committing or obligating any funding. Robert: Are we recommending approval? Mapes: You are recommending that Council approve the Plan as a guide to pursuing Capital Project Funding for projects in the North College district. Council's approval indicates support for efforts of staff and owners in forming funding partnership situations. It essentially launches more ongoing work. Thomas: Who are we addressing in our recommendation? The URA or the Council? Mapes: The City Council. Thomas: We are only indemnified in our role as an Advisory Board to Council. Steen: Looking at the individual projects, do the Fire Authority/other emergency services review the Plan? Project#15 —Redwood, seems like they should weigh in. Mapes: That particular project is viewed as being developer triggered. However, there has been some discussion that the fairly low price tag might make it feasible for the City to initiate it. Roberts: That project is being held up because of Stormwater drainage (NECCO). Could we consider putting in the Stormwater drains as it is built in advance of NECCO? Mapes: So do you want to move those two Redwood projects up to a"very high" status? This is an example of something we can explore further if Council approves the Plan as a working framework for ideas. . Steen: Project#16 is showing $4.7 million. That doesn't look right. Mapes: The estimates were updated 2 weeks ago...but that project was $200-$300K before the update...it must be a mistake. Miller: Bringing this to us was valuable because it brought forth a bunch of things that need to be considered, but have nothing to do with the framework. Because it did that, I would like to see it again. It is a lot of information to think about and consider. I don't totally understand the implication of endorsing it. I would like to understand it before endorsing it. Lund: I agree with Shane. It probably needs a second look. Robert: This is great work. We should send our thanks. Thomas: If it is just a framework, that is looser and we can write an endorsement reflecting that. I am fine if we want to see it again before writing a recommendation. I'm frustrated that this came to us on such short notice, but am really thrilled to be involved. Board consensus: Requested to bring it back for a second hearing in January. 9. BOARD MEMBER REPORTS Respectfully submitted, 10. STAFF LIAISON 11. OTHER BUSINESS 12 ADJOURN Polly Bennett Executive Administrative Assistant Planning, Development, & Transportation 7 Attachment 4 North College Citizen Advisory Group Meeting Minutes January 7, 2010 CAG member attendance: Don Butler, Bob Brown, Mark Sheeley, Dean Hoag, Jim Eddy, Ben Manvel (Council Liaison), Brigitte Schmidt (PnZ Liaison) Others present: Josh Birks (City Staff), Ken Waido (City Staff), Christina Vincent (City Staff), Clark Mapes (City Staff), Joe Frank (City Staff), Pete Wray (City Staff), Jeff Scheick(City Staff), Jennifer Petrik (City Staff) Call to Order: 7:35am 1. North College Infrastructure Funding Project—Brief Comments by Clark Mapes and Pete Wray Handouts of the plan were received along with two tables: one with funding mechanisms and the other with the list of projects. Staff is seeking a recommendation from the CAG on the plan to the City Council based on nine months of work and conversations at the CAG monthly meetings. The North College CAG recommends the North College Infrastructure Funding Plan to the City Council for adoption. Motion passed 6-0 2. URA Policies and Procedures presentatio:by —presented byCh cent Handouts of the policies were distributed email a meeting. This first look at the policies was to gain comments and knowl om the CAG on the various components that needed improvement or correcti m the document. Many good comments were made'and noted for the documen olicies will be seeking recommendation in February from the CAG to the URA B he URA Board will vote on the item in the Spring. Ad' : 9:OOam ATTACHMENT 5 Eio:r h Fort. CoRirts Bo-,sin " Associati n Positively Impacting Fort Cottins' Northern Gateway 1475 N. College Ave. Ft. Collins, CO 80524 (970) 484-5384 January 21, 2010 Dear Mayor and City Council Members, On behalf of the North College Business Association (NFCBA), this letter reflects support from our members and our Board for adoption. of the North College Infrastructure Funding Plan. City staff has provided several Funding Plan updates to the NFCBA membership and Board over the past year, and we are well aware of the detail that went into its creation. Our members were invited to give comments and suggestions to the plan throughout the process, and our thoughts were well received by City staff. This truly has been a collaborative effort between City staff and the NFCBA membership throughout the creation of this Funding Plan. The Board of the NFCBA believes this plan will serve the needs which it was intended to address: to help guide investment decisions by the Urban Renewal Authority, developers, and any City departments that may be involved in future public infrastructure projects. ' We also believe that this plan. will perhaps assist conversations among citizens in the area regarding cooperation and partnerships which are necessary for some of the infrastructure projects. We are grateful for City staff's work, and look forward to City Council's consideration of the plan on February 2"1 Sincerely, 1 Dean R Hoag ✓✓ President North Ft. Collins Business Association North College Infrastructure Funding Plan 1 February 2 , 2010 Council Meeting : 3 Questions : - " Potential Funding Sources " — Developers - " Potential Funding Sources " — Street Oversizing - " Objectives Met" - Sustainability 2 � uiy Zoos URA Board & Citizen Group : • Need for Funding Plan : - Costs , Priorities & Funding Possibilities - Maximize URA TIF benefits otY of 3 a- for Approval July 2009 Work Session URA Board & Citizen Group : • Draft Material • Direction to Bring Forward for Approval F� o ,- tY or 5 tf� ollin:j Adopted Plans for North College : • 2007 North College Corridor Plan • 2007 Urban Renewal Plan • 2000 US 2871SH14 Access Mgt. Report 6 �tr� Contents of Plan : • Prioritized List of Projects • Potential Funding Sources • Conceptual Funding Scenarios oty o� I:Orcf18 7 1 2009 Citizen Advisory Group Meetings • March Context and Purpose • April Public Funding Sources & Methods • May Project Lists & Priorities • June Scenario Concepts • July Draft Scenarios • July 28 Joint URA Meeting FF City try Fall 2009 - Other Process • North Fort Collins Business Association Presentations • Public Open House • Citizen Advisory Group Updates • Planning & Zoning Board Presentations • Transportation Advisory Board Presentations ctY or �tt 9 If Approved : • Coordinate w/ Capital Improvement Programs • Pursue Funding • Coordinate with developers • Coordinate with affected interests F City of 10 try Recomm A • Citizen Advisory Group • Planning and Zoning Board • Transportation Advisory Board • Letter from NFCBA FotY tor 11 - �f� RESOLUTION 2010-023 OF THE COUNCIL OF THE CITY OF FORT COLLINS APPROVING THE NORTH COLLEGE INFRASTRUCTURE FUNDING PLAN WHEREAS, in July 2008, the Fort Collins Urban Renewal Authority Board of Commissioners (the "URA Board") and the North College Citizen Advisory Group met to discuss the possible establishment of a North College Infrastructure Funding Plan (the "Plan"); and WHEREAS, the URA Board directed staff to prepare the Plan, a draft of which was presented to the URA Board in July, 2009; and WHEREAS,the general purpose of the Plan is to place all of the North College Avenue area key infrastructure needs into an overall framework to guide the work and decisions to be made by the URA Board, the City and others who have an interest in the North College Avenue area infrastructure; and WHEREAS, after substantial public outreach through the meetings of the North College Citizen Advisory Group, staff has prepared and presented the Plan to the City Council; and WHEREAS, the Plan has been recommended for approval by the Planning and Zoning Board, the North College Citizen Advisory Group, the Transportation Board, and the North Fort Collins Business Association; and WHEREAS, the City Council has determined that the approval of the Plan is in the best interests of the City. NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF FORT COLLINS that the North College Infrastructure Funding Plan,dated April 13,2010,attached hereto and incorporated herein by this reference as Exhibit"A", is hereby approved. Passed and adopted at a regular meeting of the Council of the City of Fort Collins this 4th day of May, A.D. 2010. Mayor ATTEST: City Clerk _ _ 1 North College Infrastructure Funding Plan .35 1 1 1 11 •. -�;- _ 35 � - Ilk f � w I � r� {l1.' April Contents Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 1 Background. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 2 Purpose and Use . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 3 Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 3 List of Infrastructure Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pages 4-7 Potential Funding Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pages 840 Project Location Maps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pages 11 - 14 Funding Scenarios for Very High Priority Projects . . . . . . . . . . . . . . . . Pages 15 -20 Plan Implementation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 21 Appendix A — Map of All Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page A- 1 Appendix B — Project Descriptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pages B- 1 -B-24 North College Infrastructure Funding Plan January 20, 2010 Introduction The North College Infrastructure Funding Plan (Funding Plan) provides a framework to guide efforts by the Urban Renewal Authority (URA), the City, and other stakeholders to assemble funding for public infrastructure projects needed in the North College Avenue corridor area. The Funding Plan essentially consists of a list of projects, with priorities and potential funding sources identified and explained. It does not contain any new goals or policy decisions ; rather, it is an aid to help implement adopted plans . It is part of an ongoing continuum of City efforts to stimulate and support revitalization in collaboration with citizens in the area. seek The term "infrastructure projects" generally refers to construction projects that would build up a more complete system of streets and utilities , including a drainage system to handle runoff from streets and development. These are basic public facilities needed to support long-term revitalization of the area as envisioned in the adopted North College Corridor Plan . The need and initiative for this Funding Plan specifically arose out of administration of the 2004 North College Avenue Urban Renewal Plan, which enables tax increment financing (TIF) to help fund various public improvements . This TIF is administered by the URA, which is governed by City Council members acting as the Board of Commissioners . The URA participates in private development projects to cover financing gaps to make the projects feasible ; and it also expects to initiate or participate in public capital projects to build infrastructure. A North College Citizen Advisory Group (CAG) advises the URA on North College matters, primarily those involving TIF . In July 2008 , the URA held a first annual joint work session with the CAG, and at that meeting, the Board, CAG, and staff all agreed on the need for a prioritized funding plan for infrastructure projects, to help plan for the use of TIF revenues . The Board directed staff to prepare the needed plan. In response, staff initiated a process to develop this Funding Plan. The process centered around a series of five regularly-scheduled monthly CAG meetings that began in March 2009 . Various City departments participated, along with interested members of the public and the Colorado Department of Transportation. North College Infrastructure Funding Plan 1 January 20, 2010 Background Previously Adopted Plans The Funding Plan is a tool to help implement the vision, goals, policies, and objectives of previously adopted plans that address infrastructure needs, including : The 2007 North College Corridor Plan. The 2004 North College Avenue Urban Renewal Plan. The 2000 US287/SH14 Access Management Report. North College Corridor Plan Awareness and understanding of North College area infrastructure issues have grown steadily since the late 1980 ' s. In particular, the original 1994 North College Corridor Plan first articulated infrastructure issues, and led to a number of infrastructure projects . The plan ' s highest priority and largest recommended project was a $ 10 million Dry Creek flood facilities project that removed the Dry Creek floodplain from the area in 2003 . That project set the stage for many subsequent initiatives on infrastructure and revitalization. The North College Corridor Plan was updated in 2007 to reflect new information and changed conditions. Infill Infrastructure Staff Team Assessment In 2004, City staff completed a city-wide assessment of infrastructure needs in areas targeted for infill development and redevelopment activity. The Infill Infrastructure Team Report included a fairly detailed listing of projects needed in the North College area, with general priorities and notes about potential funding sources. That information provided the foundation for the more detailed listing and analysis of projects in this funding plan. North College Avenue Urban Renewal Plan In December 2004, the North College Avenue Urban Renewal Plan was adopted, which further articulated deficiencies and needs in the area, and changed the funding picture by enabling TIF . By 2008 , the URA was beginning to see several significant development projects seeking TIF assistance within the North College area. Engineering Design Work Development activity has been compounded by engineering design work on drainage and sewer facilities , and also on the proposed new arterial street known as "Realigned Vine". This work has also contributed to the information in this Funding Plan. In 2009 , a voter-approved capital project to design and construct North College Avenue roadway improvements was underway, concurrent with this funding plan process. The project is known as the "BOB" project (after the 2005 referendum called the "Building on Basics" capital improvements package) . The BOB project has highlighted issues and yielded more detailed understanding of infrastructure issues related to North College Avenue/US Highway 287 . Tax Increment Policy Questions All of the activity noted above has spotlighted policy questions about allocating TIF revenues to development projects, and reserving TIF revenues for public capital projects. If the TIF revenue stream accrues as projected, the URA could become proactive in initiating capital projects to build infrastructure . 2 North College Infrastructure Funding Plan January 20, 2010 Purpose and Use The main purpose of this Funding Plan is to place all of the area' s key infrastructure needs into an overall framework to guide work efforts and decisions by the URA, the City of Fort Collins, and others with an interest in North College area infrastructure . One key aspect of this Funding Plan' s purpose is to help the URA prioritize and plan for ongoing use of TIF revenues. Also, this Funding Plan is intended to be used for coordination and input into other important capital project programs such as : • The City ' s Stormwater Capital Projects Program • The City ' s Transportation Master Plan • The City ' s Capital Improvement Budget • Colorado Department of Transportation Project Lists • North Front Range Metropolitan Planning Organization Project Lists Finally, another aspect of the purpose is to allow any additional projects or other new information to be incorporated into the plan with updates as needed. During initial preparation of this Funding Plan, the flow of new information and ideas about projects has been constant, and that is anticipated to continue . This Funding Plan does not represent any specific commitment or obligation to fund any given project. Rather, it provides a working framework and guide for those involved in capital project programs . It can be monitored and updated as needed by staff to remain current and useful. Any City or URA capital projects that move forward to construction would be administered in accordance with the City ' s Capital Projects Procedures Manual. Process The planning process to generate this Funding Plan was formally initiated in March 2009 . Draft material was developed in a series of five regularly-scheduled monthly CAG meetings, through spring and summer, 2009 . Draft material was then reviewed by the URA Board at a joint work session with the CAG in July 2009 . In September, this material was also presented at a public Open House and to the North Fort Collins Business Association. As a result of this process, the list of projects was developed along with other pertinent information on the projects . The CAG then periodically reviewed minor updates through fall 2009 as the Funding Plan document was prepared, and finally forwarded a recommendation to City Council regarding plan adoption in early January 2010 . The Planning and Zoning Board and Transportation Board also reviewed the Funding Plan and forwarded recommendations to City Council regarding approval. The final Funding Plan was considered for approval by City Council on February 2, 2010 . 3 North College Infrastructure Funding Plan January 20, 2010 The List of Infrastructure Projects - Project Summary Table The centerpiece of this Funding Plan is the Project Summary Table (Table 1 ), which lists infrastructure projects needed in the area. The table also designates priorities and suggests potential funding sources to pursue, along with other aspects of each project including estimated cost, objectives met, benefits and responsibilities associated with the project, and potential funding sources . Projects Listed in the Summary Table Listed projects are those that have been identified as having a primary, determining role in progress toward the adopted vision and goals for development and redevelopment in the area; and/or having a need for special coordination and partnership among multiple public and private funding sources . Most of the projects were first identified in a 2004 list generated by staff as part of a city-wide assessment of infill and redevelopment issues . That list was reviewed and updated with more detailed attention and discussion during this Funding Plan process. Categories The projects are listed in four categories : • Improvements to Existing Streets • Storm Drainage Facilities • New Streets • Sewer Line It must be noted that projects involving both existing and new streets include a complete set of transportation components such as pedestrian, bicycle, and transit facilities, along with any streetscape enhancements as appropriate . Cost estimates for projects reflect this "complete streets" approach. If any such street components are identified as separate capital projects, it is the intent of this plan to offer the framework to recognize them and aid the pursuit of funding. For example, at this time there are no transit capital projects identified within the area, but capital investments in transit may be needed in the future as part of the Enhanced Travel Corridor designation connecting the Mason Corridor to the future "Realigned Vine Drive" . Priority of Each Project Each project on the list is assigned a relative priority for staff work in pursuing funding. Priorities are assigned from Very High to High, Medium, and Low. Staff and the CAG found no need for numerical scoring or ranking of all projects from top to bottom. The original intent was to identify a few projects to pursue immediately, with a sense of relative priority for all projects . In assigning priorities, staff and the CAG used two main considerations : how projects meet objectives , and the degree to which proactive public funding actions are necessary (as opposed to projects being more a function of private development) . Also, one consideration in assigning Very High priority is the ability to identify a conceptual funding scenario illustrating what it might take to assemble funding for the project. In other words, if no conceptual scenario can be identified for a project, the intent of this plan has 4 North College Infrastructure Funding Plan January 20, 2010 been to either break the project down into more feasible parts, or to reduce the priority until such time as a scenario can be identified and pursued. Lower priority generally indicates projects likely to be implemented further in the future, or not quite as central to the implementation of higher priority projects in the North College area. The list will be a working structure for ongoing efforts over a long term. Priorities are not meant to prevent efforts or actions on any projects . Opportunities may arise that could initiate action at any time on any of the projects, regardless of priority shown. Also, priorities will change as projects are completed and other conditions change in the area. Estimated Cost of Each Project Estimated costs reflect planning-level capital costs of getting the projects designed and built. The estimates were done in 2009 and are time-sensitive . The long-term nature of this funding plan highlights the need to adjust for inflation in later years. Unless more up-to-date inflation information is available, a basic assumption of 3 % per year should be used in future years, and not the 2009 dollar figures shown. Operation and maintenance costs are distinct from capital costs and are not reflected in the estimates . Listed projects would affect these costs to varying degrees, and would affect various operation and maintenance programs and budgets . Funding for operation and maintenance costs for City capital projects must be identified at the time projects are approved, in accordance with the City' s Capital Projects Procedures Manual. Any other specific financial impacts of projects will be determined on a case by case basis as projects proceed to approval of funding, programming, and construction. In the course of creating the Funding Plan, discussions included ideas about bonding or other debt financing to allow up-front construction, if an appropriate revenue source is identified to pay the debt. However, such specific mechanisms are beyond the scope of this Funding Plan, and would be determined later in the funding packages for individual projects. Estimated costs do not include financing costs of any debt financing. Objectives Met by Each Project This column on the Summary Table was used to aid discussion of priorities . The objectives reflect past discussions of Transportation capital projects, the vision and goals of the North College Corridor Plan, and discussions among staff and the CAG. The objectives are as follows : IDN Distinct Identity or Sense of Place — Improve Public Perception APF Adequate Public Facilities — Fix Obstacles to Development ECN Support Economic Development LEV Leverage — Opportunities for Cost Sharing or Public/Private Partnership Opportunities SFT Safety — Reducing Hazards for All Transportation Modes LOS Level of Service for All Transportation Modes PED Pedestrian and Bike Activity FIN Financing Feasibility, Political and Ownership Realities FIX Fixes a Problem in Existing Public Infrastructure 5 North College Infrastructure Funding Plan January 20, 2010 Benefits and Responsibilities Associated with Each Project This column on the Summary Table was used to aid discussion of potential funding sources. Some of the projects on the list offer general, area-wide benefits, suggesting a broader responsibility for funding; while others would offer more specific benefits for certain properties, suggesting different types of potential funding sources. Potential Funding Sources for Each Project Given the nature and magnitude of needs in the area, partnerships among many different public and private sources are likely to be required. This column on the table contains suggestions for funding sources that appear appropriate to the project, and worth pursuing with further staff work. Other Infrastructure Not Listed The Project Summary Table is not a comprehensive list of every infrastructure facility that may be needed over time. Additional supporting infrastructure will be needed as a function of development and redevelopment projects. For example, water, sewer, stormwater, electric, gas, communications, and other utilities are generally not identified and listed unless they present special opportunities or challenges . Also, local street improvements or other public access facilities may be needed. It is presumed that these facilities will be programmed into development projects or larger capital projects, in conjunction with abutting developers and property owners . Many of the utilities noted above would be built in association with street projects, but they are not reflected in any the assumptions about listed projects. If any additional projects, or parts of projects, are identified in the future, they can be added to this Funding Plan. In fact, that is part of the intent of this Funding Plan, to be a useful framework for ongoing work. 6 North College Infrastructure Funding Plan January 20, 2010 Table 1 - Project Summary Table North College Infrastructure Funding Plan Very High Priority G13I2010 (a) Priority is based on need for public funding and City objectives. Advance Planning Department, 221L376 da Benefits and Responsibildes are in order from direct to indimd. ESTIMATED PROJECTS PRIORITY (a) COST, 2009 OBJECTIVES MET BENEFITS & RESPONSIBILITIES b POTENTIAL FUNDING SOURCES IMPROVEMENTS TO EXISTING STREETS ► 1 N College Av - 750' from Hemlock to Conifer, street edges VH $2,700,000 ON, SFT, PED, LOS Area, City, State, Developers TIF, 2015 Citywide CIP, Developers (remainder post-BOB project) 2 N College Av - 1/2 mile from Vine to Conifer, Medians, East Side Circulators and Overlay M $1 ,600,000 IDN, SFT Area, City, State, Developers Developers, CDOT Programs, TIF, Federal Grants, Mil Levy (remainder post-BOB project) 3 N College Av - 300' Conifer to Hickory (remainder post-HIES Project) VH $1,550,000 LOS, APF, ECN, ON, PED State, City, Developers, Area TIF, 2015 Citywide CIP, Developers 4 N College Av - Conifer/Hickory intersection realignment of Conifer to meet Hickory L $6,700,000 FIX, APF City, State, Area Future City CIP 5 N College Av - 1/2 mile from Hickory to Willox, interim asphalt path H $840,000 SFT, LOS, FIN, PED Area, City, State 2015 Citywide CIP, Federal Grants, COOT Programs, Mil Levy, TIF 6 N College Av - 1/2 mile Hickory to Willox, permanent sidewalk only VH $2,100,000 SFT, LOS, PED Area, City, State 2015 City CIP, TIF, Federal Grants, COOT Programs, Mil Levy, Developers jlli 7 N College Av - 1/2 mile Hickory to Willox, street edges minus sidewalk VH $10,850,000 ON, SFT, LOS Area, City, State, Developers 2015 City CIP, TIF, Federal Grants, Mil Levy, Developers 8 N College Av - 1/2 mile from Hickory to Willox, medians and overlay M $1 ,360,000 IDN, SFT, LOS Area, City, State, Developers Future City CIP 9 N College Av - 1/4 mile from Eaton Ditch to Hwy 1 L $3,700,000 IDN, SFT, PED, LOS Area, State, City CDOT Programs, State & Federal Grants, Developers 10 Vine Dr - 1/2 mile from College to Linden M $2,800,000 LOS, IDN Area, City, Developers Developers, TIF (URA & DDA) 11 Willox Ln - 1/2 mile from Union Pacific Railroad to College L $2,760,000 LOS Area, City, Developers Developers (remainder post-Union Place development) 12 Alley upgrade - parallel east 1/4 mile from Conifer to Bristlecone L $308,000 LOS, FIN Developers, Area, City, State Developers, TIF NEW STREETS 13 Realigned Vine Or - 118 mile from College to Jerome, M $244,000 ECN, LOS, IDN Developers, Area, City Developers, TIF interim street connection for abutting development 14 Realigned Vine Or - 1/8 mile from College to Jerome, full Arterial M $3,850,000 ECN, LOS, ON Developers, Area, City Developers, TIF 15 Realigned Vine Or - new concrete intersection at North College Av L $3,816,000 City, State Future City CIP 16 Realigned Vine Or - 3/8 mile from Jerome to Redwood L $7,600,000 APF, ECN Developers, Area, City Developers 17 Redwood St - missing southern segment 600' Cajetan to "Realigned Vine" H $471 ,000 APF, LOS, FIN, ECN Developers, Area, City Developers, TIF 18 Redwood St - missing northern segment 400"'Realigned Vine" to current terminus H $314,000 LOS, APF, FIN, ECN Developers, Area, City Developers, TIF 19 Mason St - parallel west circulator 3/8 mile from Alpine to Hickory L $1 ,380,000 LOS Area, City, State Future City CIP, Developers 20 Mason St - parallel West 112 mile from Hickory to Willox M $2,100,000 ECN, IDN, LEV, LOS Developers, Area, City Developers, TIF, SID STORM DRAINAGE Part ITIE 21 NECCO - primary "backbone" section from Pond E to Vine Drive VH $6,000,000 APF, ECN Developers SID, Utilities CIP 22 NECCO - redevelopment system (upstream of Pond E) L $4,000,000 APF, ECN Developers SID, Utilities CIP 23 NCDID - west side drainage system L $6,000,000 APF, ECN Developers, Owners SID, Utilities CIP SEWER LINE 24 Sewer westside - City sewer from Alpine to Poudre Valley Plaza H $1 ,200,000 FIX, APF, LEV Owners Utilifies Maintenance Program TOTAL COST, 2009 DOLLARS NINE $74,243, Key to Acronyms LEV - Leverage, Cost Sharing, or PubliWPrivate Partnership opportunities APF - Adequate Public Facilities — Solve Obstacles to Development by Meeting Standards LOS - Level Of Service for All Transportation Modes CIP - Capital Improvements Program, e.g., the current "Building on Basics" (BOB) voter-approved sales tax referendum and City Utilities programs NCDID - Drainage Improvements Design DDA - Downtown Development Authority NECCO - Northeast College Corridor Outfall ECN - Support Economic Development PED - Pedestrian & Bike Activity FIN - Financing Feasibility, Political & Ownership Realities SFT - Safety/Hazard Elimination for All Transportation Modes FIX - Fixes A Problem in Existing Public Infrastructure SID - Special Improvement District -- Builds infrastructure funded by special assessments on property based on special benefit to the property IDN - Distinct Identity or Sense of Place, Change Public Perception TIF - Tax Increment Financing URA - Urban Renewal Authority Table 2 - Potential Funding Sources North College Infrastructure Funding Plan 12/30/2009 POTENTIAL FUNDING SOURCE FOR INITIATING FUNCTION FOR NORTH COLLEGE AREA ACTION NORTH COLLEGE AREA REVENUE ADMINISTRATION COMMENTS &elope Developer Improvements Development Project Build all infrastructure needed by the Developer City Engineering Primary source of all city infrastructure. development project. Investment Street Oversizing Program Development Project Fund oversized portion of Collector and Arterial Development City Engineering New developments city-wide pay impact fees for street costs related to growth, since they all Streets. Keep up with city-wide growth in Impact Fees contribute to city growth. Funds pay costs of building Collector and Arterial Streets, above Local traffic. Street costs. Developer Repays Development Project Allocate costs fairly, mitigate costs for the "first Developer City Engineering Requires a developer to pay for their share of typical street or utility improvements if another one in" who triggers development requirements, Investment developer or the City have previously built the improvements and filed for repayment. (First one to and gain participation by developers who develop builds needed facilities, then is eligible to be repaid the fair share from others who develop benefit. later but also benefit from the facilities.) Property Tax Increment Urban Renewal Authority (URA) Tax Increment Development Project or Assist development projects, and initiate capital Portion of URA Board (City Council No new or additional tax — captures portion of property tax resulting from increases in property Financing (TIF) URA Capital Project projects. Focus is on construction of public property taxes acting ex offcio) values. URA can facilitate, coordinate, stimulate, and leverage multiple efforts. improvements that meet objectives. collected State and Federal Transportation Gran Various grants from the Metropolitan Planning Application by City staff North College Avenue/US 287 Improvements. Various state and City Transportation Planning, City staff already collaborates actively and continuously to pursue appropriate grant funding under Organization, Colorado Department of Transportation, federal programs City Council these programs. Colorado Department of Local Affairs, Others City Sales Tax Ballot Issues e.g., current Building on Basics (BOB) Capital City Capital Public improvements that need a 'trigger" other Dedicated Sales City Council, City Manager Typical package is 1/4 cent sales tax, (25 cent sales tax per $100 sale). Yields about $40M, divided Improvements Package (city-wide) Improvements Process than development. Tax among many projects. `Dperty Tax Mil Levy General Improvement District (GID) Petition of Owners -- Enhancements and amenities, local identity, Additional GID Board (City Council acting Appropriate for projects with general, area-wide benefits. Downtown is an excellent example of use 30% or 200 of those in local matching funds for grants, demonstration Property Tax Mil ex officio) of a GID to fund beautification, pedestrian, and parking improvements. A ten-mil levy in the North district of local commitment to revitalization. Levy College area would yield about $250,000 per year, similar to downtown. This has supported funding of streetscape projects in the $1 million range. Ten mils on a $1 million property would add $2,900 tc a $25,000 tax bill. Special Assessment on Benefitting Properties Special Improvement District (SID) Petition of Owners -- Coordinate multiple owners and funding Assessment on City Council, City Engineering Assessment for improvements tailored to benefit. Can be per acre, per cubic foot of stormwater 50 0 of those in district sources to build facilities that enable later benefifting runoff, per linear foot of street or pipe, etc, as appropriate. development. properties Utilities Monthly Rates Stormwater Capital Improvement Program (CIP) City Utilities CIP Process Build "regional" facilities that serve large areas Monthly utility City Council, City Utilities Competing city-wide demands are high. Programming projects typically takes years. beyond the scope of individual developments. rates Utilities Maintenance Programs City Utilities Maintenance Maintain and replace outdated utility lines. Monthly utility City Utilities, City Council Only known project being considered at this time is sewer line serving west side of North College Program rates Avenue. Property Owners Voluntary Dedication Property Owners Allows infrastructure funding dollars to Owners equity City Real Estate Services, City West Elizabeth in Campus West is an excellent example where property owners voluntarily maximize construction of improvements that Engineering dedicated strips of land for improvements, to maximize those improvements. benefit property owners. Potential Funding Sources Table Table 2 provides additional information on potential funding sources listed on the Project Summary Table. The staff team, with input from the North College Advisory Committee, and the URA Board, identified these potential funding sources as most appropriate to the identified projects, and worthwhile to pursue . Developers (development improvements, street oversizing program, repays) The first source, development contributions, provides the primary source of all city infrastructures . For vacant properties in the North College area targeted for new development, this source has the greatest potential . Potential funding from existing development and redevelopment is more difficult to achieve . Deficiencies with existing infrastructure, which was not constructed to urban standards, may require other funding tools, along with development contributions . Urban Renewal Authority (URA) Tax Increment Financing (TIF) With the URA TIF tool in place, this revenue stream is a good tool to fund a variety of projects in the North College area. However, the North College Urban Renewal Plan area is not projected to generate tax increment revenues adequate to solely cover costs of larger capital improvement projects in the area. While this revenue source is a good funding tool, other funding partnerships and sources need to be considered in combination, in order to feasibly finance larger, high cost projects . State and Federal Transportation Grants This funding source represents various grants from the Metropolitan Planning Organization, Colorado Department of Transportation, Colorado Department of Local Affairs, and others. City Transportation staff already collaborates actively and continuously to pursue appropriate grant funding under these programs . Projects from across the state compete for these sources of funding. Capital Improvement Program — Dedicated City Sales Tax The current 2005 Capital Improvement Program, Building on Basics (BOB), provides revenue from a 1/4 cent renewal on sales tax for projects throughout the city. Included in this round of BOB , was the North College Avenue streetscape edge infrastructure improvements from Vine Drive to Conifer Street. A few of the proposed future projects identified in this Plan suggest potential future revenue funding from the next round of BOB in 2015 . Property Tax Mil Levy (General Improvement District) A General Improvement District (GID) establishes an additional property tax mil levy on properties within a designated district boundary. The GID would require a petition of owners, a minimum of thirty percent of those owners in the District, resulting in about 200 owners. This type of funding is appropriate for projects with general, area-wide benefits . Downtown is an excellent example of use of a GID to fund beautification, pedestrian, and parking improvements . A 10-mil levy for the North College area, similar to the Downtown GID, would yield about $250,000 per year as an example. A 10-mil levy on a $ 1 million property would add $2,900 to a $25 ,000 property tax bill. 9 North College Infrastructure Funding Plan January 20, 2010 Special Assessment of Benefiting Properties (SID) A Special Assessment District (SID) represents an assessment for improvements tailored to a specific benefit for the affected properties . The property assessment can be a per acre, square footage of existing building business space, per cubic foot of storm water runoff, and/or per linear foot of street or utility pipe, as appropriate. This revenue tool allows for coordination of multiple owners and funding sources to build facilities that enable later development. The SID requires a petition of a minimum of 50% of the affected owners in the District. It enhances the City ' s ability to provide public improvements by assessing all or part of the cost of the improvements against the properties that specifically benefit from them. Utility Rates This Funding Plan includes references to the City' s Stormwater Capital Improvements Program, and the Water Utilities Maintenance Program. These are funded through monthly rates paid by users city-wide. Property Owner Dedications This form of "funding" is actually a mechanism to eliminate costs of purchasing right-of-way for infrastructure, with affected property owners voluntarily contributing street right-of-way or utility and access easements to a given package of funding for needed improvements . This would allow infrastructure funding dollars to maximize construction of improvements that benefit the property owners . Project Location Maps The following pages contain project location maps showing groups of projects by category from the Project Summary Table. 10 North College Infrastructure Funding Plan January 20, 2010 North College Infrastructure Funding Plan IMPROVEMENTS TO EXISTING STREETS MAP r +` • F �+ J �].1�[ .4n n 1 F ,. Imo' r ' E VviMox Lrti 5 Y 5- • 1 w 14/ onifef t r ' ti Mill • ,` • f5 r. 4 V ne Dr ,z F1 .• 1 I , J� k y � _. _ III I •- 4 . y �. - - - �� Projects Other College Ave College Ave - inbBrim Patin College Ave (750 ft Hemlock - Conirerl (11`2 mi Hickory - Willox) (1M mi Eaton Ditch - Hwy 11 0 Water College Ave College Ave - Sidewalk Vine Dr Railroad (112 mi Vine - Conifer) 1112 mi Hickaryr - Willoxl %(112 mi College - Linden) College?HickarylCon ife r College Ave - Street Edges Mllox Ln Intersection (1J2 mi Hickory - WYllox) 10 (ill mi Union Pacific RR - College) CollegerHickarylCon ifer College Ave - Madlaaa0wadaY East Alley F-Zh�'{� Ai intersection (112 mi Hickory - Wi Iloxl (114 m i Conifer - Bristleconel 0ins 11 North College Infrastructure Funding Plan January 20, 2010 North College Infrastructure Funding Plan NEW STREETS MAP ( Tr IT , i ' # 5„ 5 , 5 d r Fyn., �. Te-5cs.rrT i a _ o . +� u 76MIT . 01 . :ate r- kDry St Conifer: t --�- i -4 . qr } Irw m Mi4 : . ... : r fAL Projects Other Realigned Vine - Interim Redwood St so (I1& mi CoIle-ge - Jerome) (600 ft Cajetan - Realigned Vine) ❑ Water Realigned Vine - Full Arterial iikRedwood St Railroad (IM Fri College - Jerome) (400 ft Realigned Vine - Redwood ) so Realigned Vine - Intersection Mason St (118 mi College - Jerome) (318 mi Alpine - Hickory) Realigned Vine Mason St Fort` D[Uns 318 mi Jerome - Redwood ( IQ mi Hickory - Willox) 12 North College Infrastructure Funding Plan January 20, 2010 North College Infrastructure Funding Plan STORM DRAINAGE IMPROVEMENTS MAR NO — vic vxL E 1fillox Ln f. . .,O 0 ; . _ .. NOP 11 F ON k NO imp data - k ,� 1 1 <" r JNO •tea.. wl r R '�`' NJ NO YO • lm,. . NO IN INN Y } _ J tJv ' N NO F NO ON NO rt rth }•," ��� • L k y._ yf F. k�.. ONION F - _ 0 lit T � 4 ON ' TTAk Nom 1F IN I L }} +rr r ILNONr NNNNiN _ NO NO .e, . NO v ONO onlf {`•• „ ._ P fit " iL _ NO NO NO NO NO — NO r s COO ita . r ► p) {1h ' e E vi ' Dr ON Projects Other Northeast College Corridor Outfall (NECCQ) (Main Drainage Outfall ) f Detention Pond NECCO (Redevelopment System Upstream) o Water it YL' West Side [)rain age Systern Railroad 14r► 13 North College Infrastructure Funding Plan January 20, 2010 North College Infrastructure Funding Plan SEWER LINE MAP 1 r 4 .. __ . w — — y • 'r �y r r r iell ' _ r 4 w Wiilox Ln • ' lye {• . . , UL � y � { •I l � yl . _ F. - JJ��rrRR { 'yl 1 = � Ri m r � - y Y IN x I ! r IV �L . 01 WNW r I ! r Li 4Ulrll 1� Y Projects Other City Sewer (Alpine - Poudre Vly Plaza) 0 Water Utilitiy {„ '� Connection Railroad toAlns 14 North College Infrastructure Funding Plan January 20, 2010 Funding Scenarios for the Very High Priority Projects A few of the listed projects are shown as Very High priority. Discussion and analysis has focused on these top projects, and preliminary work has already begun on seeking funding for them. One aspect of assigning the Very High priority designation is the ability to identify a conceptual funding scenario for the project. These scenarios are to illustrate the types and magnitude of funding that could possibly accomplish the projects, to guide efforts and actions in pursuit of funding. Each funding source in the scenarios below appears potentially feasible; but none are certain at the time of this writing. Every one will require significant follow-up effort and actions by the City, URA, private citizen leadership, and property owners working cooperatively. Timing, agreements, and community support are major issues associated with each scenario . As projects become further defined, the dollar figures will change . Funding Scenario for Project 1 on Project Summary Table : North College Avenue Street Edge Improvements, Hemlock Street to Conifer Street Estimated Cost: $2 . 7 million Tax Increment Financing $2 , 7001000 TOTAL MW $2 , 700 , 000 This project will complete the North College Avenue improvements begun with the 2005 Building on Basics (BOB) voter-approved capital improvements package. This project will focus on bike lanes, curb, gutter, parkway landscaping, sidewalks, and streetscape enhancements . This scenario is simple — tax increment projections indicate that TIF is expected to become available and be appropriate to fund this project because of its priority. Also, developer contributions are another potential source of minor funding for this project and others involving North College Avenue. However, they are not listed in the scenario because the amount would be minor in the context of the project, and timing would be completely unpredictable. Developer responsibility would only involve the local street portion of missing street edge improvements , and would only become available if any properties complete the development process for redevelopment or change of use projects . 15 North College Infrastructure Funding Plan January 20, 2010 Funding Scenario for Project 3 on Project Summary Table : North College Avenue Complete Street Edge Improvements, Conifer Street to Hickory Street Estimated Cost: $ 1 ,260 ,000 MMM Tax Increment Financing $ 1 ,0005000 2015 Citywide Capital Improvements $5501000 Package TOTAL $ 11550 ,000 This project will complete the improvements begun by a CDOT Hazard Elimination and Safety Grant in 2011 , and will extend the North College Avenue improvements begun with the 2005 Building on Basics (BOB) voter-approved capital improvements package . It includes bike lanes, new or relocated signals, sidewalks, landscaping, driveway access, a median, paving overlay, and striping. TIF projections indicate that funding may become available and be appropriate for this project. TIF may prove adequate to fully fund the improvements ; however, the scenario includes a "placeholder" designation for possible inclusion in the next package of capital improvements which would be expected to be referred to voters in 2015 . The adequacy of TIF and possible cost sharing with a City Capital Project should be explored further, with possible adjustment of the amounts as shown. For the same reasons that the 2005 BOB package included North College Avenue improvements, extending those improvements may be justifiable in the next package, especially if the funds are leveraged by TIF . Developer contributions are another potential source of minor funding for this project and others involving North College Avenue. However, they are not listed in the scenario because the amount would be minor in the context of the project, and timing would be completely unpredictable . 16 North College Infrastructure Funding Plan January 20, 2010 Funding Scenario for Project 6 on Project Summary Table , North College Avenue Sidewalks, Hickory Street to Willox Lane Estimated Cost: $2 , 100 ,000 2015 Citywide Capital Improvements $ 900 , 000 Package Federal Grants $ 300 , 000 CDOT Programs $ 1001000 Property Tax Mil Levy $2001000 (General Improvement District) Tax Increment Financing $6001000 TOTAL , 100,000 This project is a six-foot wide concrete sidewalk to connect gaps in the sidewalk system in the 1/2-mile stretch of North College Avenue between Hickory Street and Willox Lane . It is broken out separately from the remainder of street edge improvements which constitute the next scenario below, as a less costly, interim alternative in the event that funding for full completion can not be found. This scenario represents partial continuation of the improvements begun with the BCC and BOB voter- approved capital projects . It would be appropriate as a possible use of TIF and a new mil levy funding district, given its priority. The safety aspect of the project is a reason to seek CDOT and federal grant dollars. Developer contributions are another potential source of minor funding for this project and others involving North College Avenue. However, they are not listed in the scenario because the amount would be minor in the context of the project, and timing would be completely unpredictable . 17 North College Infrastructure Funding Plan January 20, 2010 Funding Scenario Project 7 on Project Summary Table : North College Avenue Complete Street Edge Improvements, Hickory Street to Willox Lane Estimated Cost: $ 10, 850,000 Tax Increment Financing $5 ,000,000 2015 Citywide Capital Improvements Package $5 ,000,000 Property Tax Mil Levy $625 ,000 (General Improvement District) Federal Grants $2251000 TOTAL This project includes the remainder of street edge improvements needed for this stretch of North College Avenue, in the event the sidewalk project in the previous scenario is done separately in advance of this project. That sidewalk project corresponds to the same stretch of the street and ideally, the two projects would be done as one . This project includes bike lanes, curb and gutter, parkway landscaping, and streetscape enhancements . This scenario may represent a stretch of the funding sources to their limits, but it would complete the last remaining stretch of North College Avenue improvements to transform the image of the street. Developer contributions are another potential source of minor funding for this project and others involving North College Avenue. However, they are not listed in the scenario because the amount would be minor in the context of the project, and timing would be completely unpredictable . 18 North College Infrastructure Funding Plan January 20, 2010 Funding Scenario for Project 21 on Project Summary Table , Drainage System East Side of North College Avenue Estimated Cost: $ 6,000 ,000 Special Assessment on Benefitting TBD Properties Stormwater Capital Improvement TBD program TOTAL $ 6 , 0001000 This project is the primary "backbone" portion of a drainage system called the Northeast College Corridor Outfall (NECCO) . While the funding allocations shown in all of the conceptual funding scenarios are merely illustrative to give a sense of magnitude, TBD indicates that conceptual numbers are to be determined. City staff has begun analysis to give a better understanding of appropriate allocations based on technical calculation of benefits and responsibilities using runoff calculations from each property that would benefit. Very High Priority Projects Location Map The following map shows only the projects assigned Very High Priority, for which the funding scenarios above have been developed. 19 North College Infrastructure Funding Plan January 20, 2010 North College Infrastructure Funding Plan PR ORITY PROJECTS MAP - W Willox � n ; , �-SIn . Elwimox LrrnQIIL. i 7�17r� 1 1F ri• �; �.�{ ;c Mr;L 4 i-;S• ► ` a J In nnie { J 5 �— �F .Inn Inn.- nnn_ � jn '_ ; In - Inn ,; Innn in nnn HicA or St nnapq I _ Pik 3 _ _ J M1 'F ' 5 .. + iLIn ■ � . nninnnnin , I ' ` 1 In Yj fpk ¢ R isIn — 'f L I'_ — 1£ ;' Street Improvements Stoun Drainage rnprovements Other College Ave Northeast College CorrUOFCutfalI NECCO) Detention (760 Ft Hemlock - Conifer) (plain Drainage DuffalQ Pond CollegerHirkoryJConifer ❑ Water Intersection College Ave - Sidewalk Railroad h-f (V2 mi Hickory - Wiliam) College Ave - Street Edges Fort` oAins f1 !2 mi Hickory - Wilknc) 20 North College Infrastructure Funding Plan January 20, 2010 Funding Plan Implementation This Funding Plan will guide discussions and efforts over many years . New information and changes have been constant, and that is expected to continue . The project information in this Funding Plan, including estimated costs, timing and potential funding sources, will evolve and change as new progress is made and new information is available . Yet, this Funding Plan is important in determining a basis for identifying priority projects and potential funding for them. Below, staff has developed a general timeframe for initiating project coordination and funding scenarios for each project. For the projects listed in the one- to four-year timeframe, staff has already started certain aspects of coordination to identify conceptual design and funding components . Other projects are not as ready, or depend on development initiatives rather than staff initiatives, and are listed in longer timeframe categories. Project Funding Efforts Timeframe 1 -4 4-8 Years 8-20 Years Years Projects : Projects : Projects : 193 ,6 , 7,21 295 , 8 ,9, 10 , 13 , 14 , 17, 18 ,20,24 2,4, 8 , 10, 11 , 12 , 13 , 14, 15 , 16, 19920,22923 Follow Up Actions Coordination With Other Plans The Transportation Master Plan is in the process of being updated, along with City Plan, beginning in the fall of 2009 and projected to be completed in early 2011 . The recommendations of this Funding Plan will need to be coordinated with the update to the Transportation Capital Improvements Program. Staff will also need to coordinate with other City Capital Improvement Program efforts . Monitor Funding Plan Information As new information is available, staff will need to review and monitor updates to the Funding Plan project status and funding recommendations. Coordination with Affected Interests City and URA staff should continue to initiate and coordinate efforts among various stakeholders to identify, establish, and allocate funding. 21 North College Infrastructure Funding Plan January 20, 2010 Appendixes A . Overall Project List Map Be Individual Project Summaries loll II; III ■ • • f a f * ■ $ �.L_. . k t y + F y 1 Mgt y � r 4 ] iY1° : p r gt• r ill . . } 1. on t }. ,r 7 ' . f l in �' � "! *• ail ' f � i r_ er. . �23 InIsm I € . ' .'�5 ��' Ye LPL �i. •Ii - 4 r ' .• On nI Y _ iLA 1i a 3 t ��[[}•Y�}� I`� 1fi ]k • .". f . x. • �;p� .1 4c Imo` In . �r •.q4•. y ' 6 , r. ,,� nnIL { . . In. On v Ll t. _�=:•'`.'_'� F. f fit ' 02 .`r `— • 49 Ell � � n:la ' {tip �y i 'kmi - , , .I . . ; , �` ,,. i4. Lti mIn In il * ` - . f. 61 � L� '— `, •, �,• ;•r nin +` �' + , ''- - : Y • A�f�' 0 . 1 1�7 y•. V J . nn t - ll {f J%..;mp f a ' ., ' { 1 :1 y . Improvementsamm Street Drainage 7HAUN OF?:11Ed j& n i tGGegGoinnclDrOufflell *;main iDrairbegen T y iL Dantmtlon J on Dineliniage Syatern } Pond WWnPWZmlJdFcrnt . Redwood) y1ffbersm4lork .2 mi Coll - Lindmi al III Danigan - RoallUrLed Who) Sewer Line t : 11 # DDininclaflon 3 12 T Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project I on Project Summary Table : North College Avenue Street Edge Improvements, Hemlock Street to Conifer Street This project is an approximately 750-foot long stretch of North College Avenue improvements begun with the 2005 Building on Basics (BOB) voter-approved capital improvements package. It focuses on bike lanes, curb, gutter, parkway landscaping, sidewalks, and streetscape enhancements . This scenario is simple — tax increment projections indicate that TIF is expected to become available and be appropriate to fund this project because of its priority. Summary Table Information Benefit/ i Wi pi Very High $2 ,7009000 North College Area, City, TIF, 2015 City CIP State, Developers Criteria and Objectives ■ Distinct identity/sense of place Pedestrian and bicycle activity ■ Safety Level of service Project Location Map 5 t . .� . . j Lni — 14 �— �— He•mlxa�kr-- _ College Ave CD (750 ft Hem lock - Conifer) o W o F � Iin , . d•ef,, �r pep® e North College ltittasttuctut-e Funding Plan 1 inch- _ '; FAO fret HLPROVEAENT .S TO EXISTING STREETS A?AP Page B- 1 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 2 on Project Summary Table : North College Avenue Access Management Improvements, Vine Drive to Conifer Street This project involves a 1 /2-mile stretch of North College Avenue, together with a new parallel circulation route through properties on the east side of the roadway. It focuses on access management improvements called for in the 2000 US287/SH14 Access Management Report. Landscaped medians define left-turning movements at specified locations that offer access to a parallel street and/or drive system. The system provides new alternative access to properties that currently have uncontrolled, full-movement access which would be eliminated. Finally, the project would complete any needed overlay. Summary Table Information Sources[ riority Estimated Cost Benefit/ Funding Responsibilities Medium $ 1 ,700,000 North College Area, City, Developers, CDOT Programs, TIF , State, Developers Federal Grants, Mil Levy Criteria and Objectives ■ Distinct identity/sense of place Safety Project Location ,nif —M. ,m io.d. . _ .t a College Ave (1 /2 mi Vine - Conifer) E-Vine •Dr __ i IT e North College lrlfrastructut-e Funding Plan 1 inch = 1 $ 124 feet lAFROVEAENTS TO EXISTING STREETS AMP Page B-2 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 3 on Project Summary Table : North College Avenue Street Edge Improvements, Conifer Street to Hickory Street This project involves an approximately 300-foot stretch of North College Avenue from Conifer Street to Hickory Street. It completes the improvements begun by a CDOT Hazard Elimination and Safety Grant project done in conjunction with the 2005 Building on Basics (BOB) voter-approved capital project, and extends the street edge improvements begun with the BOB project. It focuses on bike lanes, curb and gutter, new or relocated signals, sidewalks, landscaping, driveway access, paving overlay, and striping. Project Information Benefit/ Funding Sources &rMFEstimated i Responsibi BBBBBBBBBB Very High $ 1 ,5509000 State, City, Developers , TIF, 2015 City CIP North College Area Criteria and Objectives ■ Distinct identity/sense of place Pedestrian and bike activity ■ Support economic development Level of service ■ Adequate public facilities Project Location H) Wen ' 3 N0 Bonis= a- - i•G" =fit oD '= mIL �r=Ct Humx Co lleg elHickorylConifer o = Intersection 14 W 0 e North College ltittastructut-e Funding Plan 1 inch 81510 fret lAPROVEAENT .S TO EXISTING STREETS AMP Page B-3 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 4 on Project Summary Table . Realignment of Conifer Street to Create New Intersection with Hickory Street This project is a long-term solution to eliminate the offset intersections of Conifer and Hickory Streets with North College Avenue. It consists of realigning Conifer Street to create a new, single intersection of Hickory, Conifer, and North College Avenue; and abandoning the current intersection at Conifer and North College Avenue. This new alignment would run through the location of the existing Palomino Motel, and also through a platted vacant parcel east of the motel. This project is most feasible if it can be combined with a redevelopment project involving the properties affected by the realignment, in order to create new property value and economic activity associated with the new street corners that would be created. The project includes a complete new stretch of arterial street, approximately 500 feet in length, and associated changes at the new intersection and the intersection to be abandoned including all street components such as curb, gutter, sidewalk, bike lanes, medians, roadway paving, striping, signals, landscaping, drainage, other utilities, and driveway access. Project Information rPriM Wstimateld Cost Responsibilities Funding Sources Low $ 6,700 ,000 City, State, North College Future City CIP Area Criteria and Objectives ■ Fixes a problem in existing public Adequate Public Facilities infrastructure Project Location Hrbdp - N is f — 4 - is Mgt m HemIdj k-St CollegelHickory /Conifer MG Intersection — 14 - - u e North College Infrastructure Funding Plan 1 inch = 850 feet IAPROVEMENTSTOEXISTING STREETS MAP Page B-4 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 5 on Project Summary Table : North College Avenue Interim Asphalt Path Connections, Hickory Street to Willox Lane This project would provide pedestrian connections across gaps in the sidewalk system in this 1 /2-mile stretch of North College Avenue. It is an alternative option to Project 6 . It involves a reduced right-of- way requirement for purchase, and fewer impacts to existing development and drainage, than permanent standard improvements . Thus is less costly, making it more feasible in the short term. Project Information I ' Mar— Funding Sources High $ 84000 North College Area, City, 2015 City CIP , Federal Grants, CDOT and State Programs, Mil Levy, TIF Criteria and Objectives ■ Fixes a problem in existing public Level of service, financial feasibility infrastructure Pedestrian and bike activity ■ Safety Project Location —J LIRre4l] Uniiiii OD _ u Co liegeAve - Interim Path ( 112 mi Hickory - Willox ) b 'Liao -I .sin L l r 1 ql m North College 1rlft-astrYrcture Funding Plan 1 inch = 731 feet APROVEA-BENTS TOEXISTING STREETS IWAP Page B - 5 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 6 on Project Summary Table : North College Avenue Sidewalks, Hickory Street to Willox Lane This project would provide permanent, standard concrete sidewalks across gaps in the sidewalk system in this 1 /2-mile stretch of North College Avenue . It would be placed in an ultimate location per the City ' s current standard for a four-lane arterial roadway. It could be fitted into existing conditions without triggering drainage facilities or other street improvements, which could be added later. It is an alternative option to Project 5 , Project Information Funding Sourcei Very High $2 , 100,000 North College Area, City, 2015 City CIP , TIF , Federal Grants , and State CDOT Programs, Mil Levy Criteria and Objectives ■Safety Pedestrian and bike activity ■ ■ Level of service Project Location d - J} :L ,1 J2 —0— LLl College Ave - Sidewalks ( V2 mi Hickory - Willox ) b lJil,T �1 -I .sin L l r FE RP North College 1rlft-astnicture Funding Plan 1 inch = 731 feet APROVEA-BENTS TO EX/STING STREETS IWAP Page B -6 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 7 on Project Summary Table : North College Avenue Street Edge Improvements, Hickory Street to Willox Lane This project focuses on street edge improvements including bike lanes, curb and gutter, parkway landscaping, and any enhanced streetscape elements consistent with goals for the area. Sidewalks are listed separately as Project 6 . Project Information Funding®rioriMppEstimated Cost Benefit/ Sources Responsibilities Very High $ 101850,000 North College Area, City, 2015 City CIP, TIF, Federal Grants, State, and Developers Mil Lev Criteria and Objectives ■ Distinct identity/sense of place ■ Safety and hazard elimination for all transportation modes ■ Pedestrian and bike activity ■ Level of service Project Location -I C --1 �� L of 1 �U 14 College Ave - Street Edges ( 1 /2 mi Hickory - Willo ;: ) i Wall o�6 eel p dl odair North College lnffastnictcrre Funding Plan 1 inch = 731 feet MPROVE/LoU-NT .S TOEXISTING STREETS IWAP Page B -7 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 8 on Project Summary Table : North College Avenue Access Management Improvements, Hickory Street to Willox Lane This project involves a 1 /2-mile stretch of North College Avenue. It focuses on access management improvements called for in the 2000 US287/SH14 Access Management Report. The project focuses on landscaped medians to define left-turning movements at specified locations. A parallel system of streets and/or drives would provide new alternative access to properties that currently have uncontrolled, full-movement access which would be eliminated. For this stretch, the parallel system consists of Project 12 on the east side, and Project 20 on the west side. These three projects are all interrelated and would need to be coordinated together. This project would include an overlay to complete the improvement of the roadway. Project Information Benefit/ Sourcesriority Estimated Cost *let* Funding Responsibi i ies 1 in Medium $ 1 ,3601000 City, North College Area, Future City CIP, CDOT Programs, State Developers, TIF Criteria and Objectives ■ Distinct identity/sense of place Level of service ■ Safety and hazard elimination for all transportation modes Project Location 119 to a CD m' R mar- i U ° 14 1610 -�' T T - �n sonCollege Ave - MedianslOverlay 410 ( 1 /2 mi Hickory - Willox ) !� IN North College Infrastructure Funding Plan 1 it F[-i = r d l fret I&PROVFANNENTS TO EXISTING STREETS 10 P Page B - 8 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 9 on Project Summary Table : North College Avenue Street Improvements, Larimer Weld Canal to State Highway 1 This project extends slightly less than 1 /2 mile along a stretch of North College Avenue which is not within the city limits in 2009, nor does annexation appear imminent. This project would improve North College Avenue to a City standard as a complete street, with street edge improvements, medians, and paving overlay. Also, it includes architecturally enhanced pedestrian bridges over the canal on both sides of the existing roadway bridge . Project Information Priority = ed Cost Benefit/ Funding Sources — 77 Responsibilities High $3 ,70000 North College Area, City, CDOT Programs, State and Federal and State Grants, Developers Criteria and Objectives ■ Safety and hazard elimination for all ■ Pedestrian and bicycle activity transportation modes ■ Level of service ■ Distinct identity/sense of place Project Location L Terry Lau i OUntl ]I'CIUbeRd College Ave ( 114 mi Eaton Ditch - Hwy 1 ) 14MM 03 U P W -in -�� f } ,y , het m - 'r IN Nillox-Lnill ox'Ln ti e North College Infrastructure Funding Plan 1 inch- = 11042 fret /NPROVEA-BENTS TOEXISTING STREETS 11,44P Page B-9 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 10 on Project Summary Table : East Vine Drive Street Improvements, North College Avenue to Linden Street This project extends 1 /2 mile along Vine Drive from North College Avenue to Linden Street. It focuses on street improvements including street edge improvements and paving overlay. Improvements would bring to street to a City standard as a complete street, with unique adaptations to reflect goals for the area and floodway restrictions which would apply to a portion of the project. Project Information 6I ' _ Responsibilities Medium $21800 , 000 North College Area, City, Developers, Street Oversizing, TIF and State Criteria and Objectives ■ Distinct identity/sense of place Level of service Project Location Ip ill n� st 9'' oo°®° LD I,lk l y E Vine =Dr� �' F Vino Dr I ' r (112 mi College - Linden) Iq J 1 n + f f e North College Infrastructure Funding Plan 1 inch = 746 feet APROVEA�ENTS TO EXISTING STREETS IWAP Page B- 10 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 11 on Project Summary Table : Willox Lane Improvements from North College Avenue to the Union Pacific Railroad Tracks This project extends approximately 1 /2 mile west along Willox Lane from North College Avenue. The western half of this stretch is outside City Limits in 2009 . Approximately 1 /4 mile along the south side of this stretch will be improved by development. This project focuses on street edge and roadway improvements to bring the street to a City standard for Minor Arterial streets . Project Information Sources ii Am 11P n lifies Low $2 ,7601000 North College Area, City, Developers, Street Oversizing and Developers Criteria and Objectives ■ Level of service Project Location LP etid �Casa}= = rap — 14 i I 1c Ln _ E:WillOz•Gn J > ti — ua IWillo ;•, Ln U ( 112 mi Union Pacific RR - College) z Bristle•aone- r�� e Notth College lntt-astnicture Funding Plar1 1 inch = 834 feet APRCPVEAIENTS TO EX/STIN6 STREETS IWAP Page B - 11 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 12 on Project Summary Table : Alley Upgrade, East Side of North College Avenue, Conifer Street to Bristlecone Street This project is located parallel to and approximately 200 feet east of North College Avenue . It would improve a gravel alley to a paved street to provide rear access to properties fronting on North College Avenue . It would be most feasible if done in cooperation with owners and developers interested in redevelopment of those properties. It would provide a crucial component of access management improvements to North College Avenue which constitute Project 8 . Project Information 7I ' i , • i iAWL I IIIIII Low $ 308 , 000 North College Area, Developers, TIF, Street Oversizing Developers, City, State Criteria and Objectives ■ Level of service ■ Financial feasibility, political and ownership realities Project Location 9 G2}� irlox-L=n B .ist e_ Qr -er@w& 2 r Hib.d • t Q r_Ei 1111 � EastAlleY �� ' • b's �k1a -- (114 mi Conifer - Bristlecone) + Ti 14 - em . t� � • .i - r e North College lrlfrastructure Funding Plan 1 inch 1 , 0114 fret dPROVEAENTS TOEXISTING STREETS A1AP Page B- 12 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 13 on Project Summary Table : Interim "Realigned Vine Drive" Connection from North College Avenue to Jerome Street This project is an interim local street connection that would be incorporated into any later project to complete the new "Realigned Vine Drive" as a full arterial street. It would help facilitate development on abutting properties, and would likely be triggered by such development. It would include travel lanes and street edge improvements as appropriate to function for abutting development in the interim while allowing for incorporation into a later arterial street project. It extends 660 feet from North College Avenue to Jerome Street. Project Information Benefit/ �Mz r1 1 1 1Sources li 1 Medium $2441000 Developers, North College Developers, TIF, Street Oversizing Area, City Criteria and Objectives ■ Distinct identity/sense of place ■ Support economic development ■ Level of service Project Location as Hoesmilse k—&t 01 ` 1 P r� U IZ Pinoen } 1` - CD 14 - ,r4, d e Notth College Intrastnictut-e Funcang Plati 1 inch = 543 fret NBId' S TREE Tti ATAP Page B - 13 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 14 on Project Summary Table : "Realigned Vine Drive" Connection from North College Avenue to Jerome Street, Full Arterial Street This project would construct a new arterial street for 660 feet from North College Avenue to Jerome Street. It is a crucial connection to provide access for significant new development envisioned on vacant land in the immediate area, and also a useful connection to the Old Town North development, which has begun development of the area as envisioned with significant infrastructure investments . This project is likely to be triggered by development. Project Information Benefit/ I ' 1 1 1 1Sources pi Medium $3 , 850,000 Developers, North College Developers, TIF, Street Oversizing Area, City Criteria and Objectives ■ Level of service ■ Support economic development ■ Distinct identity/sense of place Project Location as d m He•m•le k-Fq1 01 1 P r!j U IZ Pino•n } P _ 14 co 11 IL e North College lnfrastnicture Funckng Plan 1 inch = 543 feet NEW STREETS MAP Page B- 14 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 15 on Project Summary Table : "Realigned Vine Drive," New Concrete Intersection at North College Avenue The project consists of constructing a new concrete intersection at North College Avenue/Realigned Vine Drive, to bring the intersection to City standards . This project would need to be done as a City capital project. The benefits would involve life cycle cost effectiveness for the City and State, which are responsible for long-term maintenance of this arterial and highway intersection. Project Information 11 1 Low $3 , 8161000 City and State Developers, TIF, Street Oversizin Criteria and Objectives None of the objectives used in this Funding Plan were found to be achieved to a particular degree by this project, as compared to an asphalt intersection. The objectives for this Funding Plan are based on the vision and goals for the area; while the objectives behind concrete intersection standards are city- wide objectives for long-term cost effectiveness . Project Location H� ml� k—fit as 1 p rla— U Z Pinoen } 14 fTl e North College Infrastructure Funding Plan 1 inch = :543 feet NE141 STREETS IWAP Page B- 15 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 16 on Project Summary Table : "Realigned Vine Drive," Jerome Street to Redwood Street This project is a new arterial street extending 3/8 mile from Jerome Street to Redwood Street. It would facilitate development of abutting land, and be triggered by such development. Project Information F— Benefit/ riority Estimated Cost 6P �L Funding Sources Responsibilities Low $ 7 , 600 , 000 Developers, North College Developers, Street Oversizing Area, City Criteria and Objectives ■ Adequate public facilities ■ Support economic development Project Location a) Y _ }10 L7 t .a) r —� o00 Heem•Ib , x=m V i n e Dr =-= , 0 �v mi Jerome - Redwoa � flis o � o �z el ® O Rinom-�� prise- 000��� 14 s e North College IrlfrastnrcWt-e Fcrrlding Plan 1 inch = 604 feet NEW STREETS IWAP Page B- 16 Appendix B North College Infrastructure Funding Plan Is Individual Project Description Summary Project 17 on Project Summary Table : Redwood Street, South Segment from Cajetan Street to "Realigned Vine Drive" This project would add a segment of Redwood Street approximately 600 feet in length, as part of connecting across a gap between completed portions of Redwood Street. The project would provide a new Collector street to extend the street in a manner consistent with the previously built portions . Together with Project 18 , and in coordination with Project 16, this project would provide an important and broadly beneficial link between the North College corridor area and Downtown. Project Information ated Cost Benefit/ Funding Sources IN ompi Responsibilities High $4711000 Developers, North College Developers, Street Oversizing, TIF Area, City Criteria and Objectives ■ Adequate public facilities Level of service ■ Support economic development Financial feasibility Project Location Ne-w _V.ine. Dr oe ® o®' , d } In _ d m r 40J d -cyL `T Z 14 U' - I E=Vine ;Dr + U L rZ � - - - r-1 e North College infrastnicture Ftinding Plar1 1 inch = 741 feet NEYY STREETS REAP Page B- 17 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 18 on Project Summary Table : Redwood Street, North Segment from "Realigned Vine Drive" to Current Terminus This project would add a 400-foot segment of Redwood Street, as part of connecting across a gap between completed portions of Redwood Street. The project would provide a new Collector street to extend the street in a manner consistent with the previously built portions . Together with Project 17, and in coordination with Project 16, this project would provide an important and broadly beneficial link between the North College corridor area and Downtown. Project Information Fr Wstilmated C . � Funding High $314,000 Developers, North College Developers, Street Oversizing„ TIF Area, City Criteria and Objectives ■ Adequate public facilities Level of service ■ Support economic development Financial feasibility Project Location 0 0 31: 6� 14 - - - - ewVine Dr m 1 � J 1P one St z C e North College lnfrastnicWt-e Ftrrlding Plan 1 inch = 751I fret NEA' S FREE FSMAP Page B - 18 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 19 on Project Summary Table : Improve and Extend Mason Street from Alpine Street to Hickory Street This project is a parallel circulator street on the west side of North College Avenue . About half of this project would improve an existing unpaved street between Alpine and Hemlock Streets . The remaining portion would need to be established in new right of way acquired from existing subdivided and developed properties to connect from Hemlock to Hickory Street. Project Information Bene Wrii i Ji R WDResponsibilities Low $482 ,000 North College Area, Future Cit CIP, Developers Criteria and Objectives ■ Safety Project Location 2 W r 14 c ; N •Eol geAve a c c G S' 0000 ci a� _ o - == 1 +� North College lrtfrastnictme Futiditig Plan 1 nd-i _ 571 fpPt NE141STREETS104P Page B- 19 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 20 on Project Summary Table : Extend Mason Street from Hickory Street to Willox Lane This project is a new parallel street on the west side of North College Avenue. It provides rear access to properties fronting on North College Avenue, thus facilitating access control improvements described in Project 8 , and introduces new access and a utility corridor into rear portions of deep parcels that extend 1 /8 mile back from North College Avenue, opening up opportunities for development. A very high level of initiative and cooperation among multiple property owners would be required. Project Information Prior* timated Cost Benefit/ Funding Sources Responsibilities Medium $2 , 100 ,000 North College Area, City, Developers, TIF, SID and developers Criteria and Objectives ■ Leverage ■ Support economic development Level of service ■ Identity/sense of place Project Location \ �04 t5;gym � I' �y +, 14 �I �Eoll geAVe Wpm lei North College Infrastructure Funding Plan 1 irich = 62 [I feet NBI' .S TREE TS RRAP Page B-20 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 21 on Project Summary Table : Storm Drainage Facilities — North East College Corridor Outfall — "Primary Backbone" This project is a proposed drainage outfall system south of Conifer Street, east of North College Avenue extending to a crossing of Vine Drive about 1 /3 mile east of Lemay Avenue . This project is being called the "primary backbone" portion of a larger Northeast College Corridor Outfall (NECCO) system which would cover the entire east side of North College Avenue, including areas north of Conifer Street. The project includes a detention pond on the west side of Redwood Street draining into pipes within the proposed "Realigned Vine" alignment. Large pipes would cross under Lemay Avenue and then turn south to cross under Vine Drive. This project would help facilitate development of about 370 acres of undeveloped land, much of which was removed from the Dry Creek floodway in 2004 . Such development would include the "Realigned Vine" arterial street, which is crucial to development in western portions of the Mountain Vista area, in addition to the North College area. Project Information Priority Estimated Benefit/ Funding Sources Cost Responsibilities Very High $ 6 , 0005000 Developers SID, Utilities CIP Criteria and Objectives ■ Adequate public facilities Support economic development Project Location u, Na ko m i itk Sst t n: 'ifCD H ml • ck�St U c E Z CD J Pin In St z in co skbon E Vine Dr 14 l_ Tr Ijill- 41 e Mrtl>I College lrlfr-astructure Funding Plan 1 inch = 114F; 7 fe et STORM DRAINAGE IM^ROVENENTS MAP Page B-21 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 22 on Project Summary Table : Storm Drainage Facilities — North East College Corridor Outfall - Upstream Redevelopment System This project is a portion of the NECCO overall project and is located north of the proposed "backbone" segment in Project 21 . This project includes a system of pipes that collect runoff and transport it to the regional stormwater quality and detention pond located in Project 21 and to the "backbone" downstream of the regional pond. This system would allow for the development of vacant lots and parcels and the redevelopment of existing developed parcels and would provide an outlet for existing developed areas . Project Information F Benefit/ I ' r or Estimated iori ist it* Funding Sources Responsibil Low $4,000,000 Developers SID, Utilities CIP Criteria and Objectives ■ Adequate public facilities Support economic development Project Location 1t C7rO'tl.S r NECCO (Redevelopment System Upstream ) - - =' cn S a 'St, LT �' i Nokomis Ct ii C�-j nifer1St = < JH. Jrn16ck�St L c1 V I � c ID n. r .-- it rm infn r1 ��_ .` ' L . Maim� S o t •\ , F30 e North College Infrastructure Funding Plan 1 inch = 1 ,467 feet STORMDRAINAGE IRPROVE&ENTS IWAP Page B-22 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 23 on Project Summary Table : Storm Drainage Facilities — West Side Drainage System This project is major new system that would support full build-out of the west side of North College Avenue . Project Information riority Estimated Cost Benefit/ Funding Sources Responsibilities Low $ 6 , 000 000 Developers and Property SID Utilities CIP ' Owners ' Criteria and Objectives ■ Adequate public facilities Support economic development Project Location J � I Met, t - = 0 � t c —a . - " lil vi C7 } W�`j N •Coll eg a Av.e 14 (se, speAM ao NCDID (West Side Drainage System) L I North College Infrast►ucture Fcrrlding Plar1 1 inch = 1 , 034feet STORMDRA1NAGEI&MOVENENTSNIAP Page B-23 Appendix B North College Infrastructure Funding Plan Individual Project Description Summary Project 24 on Project Summary Table : Storm Drainage Facilities — West Side Sewer Line This project replaces an aging, deficient sewer line extending along almost the entire west side of North College Avenue, from Alpine Street to Poudre Valley Plaza Mobile Home Park. It includes construction of a new utility sewer line across both undeveloped land and existing development. Project Information Priority Estimated Cost Benefit/ Funding Sources MIIIII Responsibilities High $ 1 ,200 , 000 Property Owners , Utilities Maintenance Program Developers Criteria and Objectives ■ Fixes a problem in existing public Adequate public facilities infrastructure Level of service Project Location tau;dy C0 C. L;8-4 e - -i _ c a ui t� a N •Coll eg a ALU v.e Ilk r'f = -- et a. s pt n c :J City Sewer p ❑ (Alpine - Poudre Vly Plaza } 7�„ 7 JU ra 711 111 T North College Infrastnrctcrre Funding Plan 1 inch- = 1 , 0 ;=14 fret NEWER LJNE MP Page B -24