HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 04/06/2010 - FIRST READING OF ORDINANCE NO. 036, 2010, AMENDING DATE: April 6, 2010 .
STAFF: Brian Janonis _
Patty Bigner
First Reading of Ordinance No.036,2010,Amending Section 26-283 of the City Code to Authorize the Utilities General
Manager to Establish Temporary Arrangements for Use of City Wastewater System Capacity.
EXECUTIVE SUMMARY
This change to Chapter 26 of the City Code provides authorization for temporary wastewater service arrangements.
Generally, Utilities customers establish parameters for wastewater discharge flows and pay associated plant
investment fees prior to service delivery. In some instances, usually with an expansion of service, parameters for
wastewater service cannot be determined until the expansion is complete. This Code change provides general
guidelines for this specific type of service agreement.
BACKGROUND / DISCUSSION
Chapter 26, Sections 26-283 and 26-284 describe the basis and establish charges for sewer plant investment fees.
At times, a customer may be unable to accurately calculate wastewater flows due to changes or expansion of a
manufacturing or business process. Since blocks of wastewater capacity are generally available, this type of
arrangement allows the Wastewater Utility to use excess capacity to generate revenue, and allows the customer to
meet temporary business needs.
FINANCIAL IMPACT
This City Code amendment does not have long term financial impacts. In the short term, the Wastewater Utility
benefits from the revenue generated from excess capacity.
SUSTAINABILITY: ECONOMIC, ENVIRONMENTAL AND SOCIAL IMPACTS
The type of Code amendment described in this Ordinance provides more financial flexibility to the City's Wastewater
Utility customers,supporting business expansion or changes without requiring overpayment of sewer plant investment
fees while service needs are being established. Once service needs are established, sewer plant investment can be
identified more accurately, along with the determination of capital needs, if any. The Utility benefits from the use of
excess capacity on a temporary basis. Proper sizing of facilities reduces the environmental impact of both the
business and the Utility. This change is temporary in nature and does not have a long or short term impact on the
public health of the community, and does not have a significant impact on service levels.
STAFF RECOMMENDATION
Staff recommends adoption of the Ordinance on First Reading.
BOARD/COMMISSION RECOMMENDATION
At its March 25, 2010 meeting, the Water Board voted unanimously to recommend Council approve the proposed
Code revision for temporary wastewater service.
ATTACHMENTS
1. Draft minutes from the Water Board meeting of March 25, 2010
ATTACHMENT
Excerpt from Unapproved Water Board Minutes, March 25, 2010
Wastewater Flows Determination
Customer and Employee Relations Patty Bigner introduced a proposed change to Section
26-283 of City Code to authorize the Utilities Executive Director to establish temporary
arrangements for use of City wastewater system capacity. An example of the application
of this change would be a brewery with its own wastewater system which cannot be used
during an expansion, thereby creating a need to lease some wastewater capacity. The
City can treat their effluent for them during this type of transition.
What is the difference and financial impact to the City? Utilities has seen this type of
occurrence very infrequently in the past, so there hasn't been an established manner for
dealing with it. These arrangements allow Utilities to generate revenue from excess
capacity when it does occur. In the past, we've approached by estimating the Special
Plant Investment Fees (SPIFs) and then settled the account when the actual data became
available.
Was there a specific occurrence that prompted this change? Yes, several breweries are
expanding.
What is the impact to customers? It provides them flexibility and time if their
construction doesn't move along as quickly as anticipated. It reduces the amount of
money they have to commit to their construction.
Have the breweries made a statement of their issue or concern? No. However, staff
would like to be able to execute agreements with them.
Motion: Board Member Dornfest moved that the Water Board recommend that
City Council approve the proposed Code revision for temporary wastewater
service, consistent with staffs recommendation. Board Member Eccleston
seconded the motion.
Vote on the motion: It passed unanimously.
f
ORDINANCE NO . 036, 2010
OF THE COUNCIL OF THE CITY OF FORT COLLINS
AMENDING SECTION 26-283 OF THE CODE OF THE CITY OF FORT COLLINS
TO AUTHORIZE THE UTILITIES GENERAL MANAGER
TO ESTABLISH TEMPORARY ARRANGEMENTS FOR USE OF
CITY WASTEWATER SYSTEM CAPACITY
WHEREAS , on occasion, City wastewater customers require temporary wastewater service
for interim conditions or uses, and the City Code does not include express provisions governing the
manner in which such temporary service would be provided; and
WHEREAS , the City Council desires to authorize the Utilities General Manager to have and
exercise the authority to establish temporary arrangements for the provision of City wastewater
services, including the authority to impose a temporary wastewater plant capacity charge, in
accordance with the standards and requirements set forth herein.
NOW THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF FORT
COLLINS as follows :
Section 1 . That Section 26-283 (a) of the Code of the City of Fort Collins is hereby
amended to read as follows :
Sec. 26-283. Sewer plant investment fees (SPIF) ; basis.
(a) An applicant desiring to connect to the wastewater utility shall pay the utility
a sewer plant investment fee (SPIF) as prescribed in § 26-284 of this Article in
addition to any other connection fee or charge imposed by this Article. Except to the
extent that the deferral of all or any portion of such payment has been approved by
the City Council by resolution or except as provided in either Subsection (e) or
Subsection (g) of this Section, this fee shall be paid in full at the time the sewer
connection permit is issued. In the case of an increase in SPIF rates between the time
of application for the permit and the applicant's actual payment of sewer connection
charges, the rates in effect on the date of payment shall apply.
Section 2 . That Section 26-283 of the Code of the City of Fort Collins is hereby
amended by the addition of a new subsection (g), to read as follows :
(g) If the General Manager determines that sufficient excess wastewater system
capacity is available, and if a customer requires temporary service for a temporary
use or condition not exceeding three (3 ) years in duration, the General Manager may
arrange for the provision of temporary wastewater service through a special services
agreement in the manner prescribed in § 26-290 of this Article.
( 1 ) If the full SPIF due in connection with any such service is not paid prior to
connection or deferred as provided in Subsection (a), above, the associated
special services agreement shall require the customer to pay a temporary
wastewater plant capacity charge each month, which charge shall be one-
twelfth ( 1 / 12) of eight (8) percent of the calculated SPIF charge, based on
BOD, TSS and monthly discharge volume in gallons . These payments will
not be credited against any SPIF amount due in connection with service to
the customer for any subsequent temporary or permanent use or condition,
regardless of whether the permanent use or condition is the same as, or
comparable to, the temporary use or condition.
(2) The customer shall also be required to pay any and all other service and
connection fees or charges associated with the temporary wastewater service
as generally imposed by this Article, including but not limited to monthly
service charges for discharged wastewater. If charges for temporary
wastewater service are based upon estimates of the quantity or characteristics
of the wastewater discharged and the actual quantity or characteristics are
subsequently measured and found to have exceeded the discharge limits for
which any fees or charges have been paid, the customer shall be required to
pay such additional temporary wastewater plant capacity charges, monthly
charges, or other charges required in light of the underestimate of discharged
flows .
(3 ) Except as set forth herein, all requirements for wastewater discharges in this
Article, including but not limited to industrial pretreatment and other
regulatory requirements, shall apply to temporary wastewater service .
Section 3 . That all action not inconsistent with the provisions of this Ordinance
heretofore taken by the City or its officers and otherwise directed toward the authorization of
temporary wastewater services hereby ratified, approved and confirmed.
Section 4 . That, if any section, subsection, paragraph, clause or other provisions of this
Ordinance shall for any reason be held to be invalid or unenforceable, the invalidity or
unenforceability thereof shall not affect any of the remaining sections, subsections, paragraphs,
clauses or provisions of this Ordinance .
Introduced, considered favorably on first reading, and ordered published this 6th day of
April, A.D . 2010, and to be presented for final passage on the 20th day of April, A.D . 2010 .
Mayor
ATTEST :
City Clerk
-2-
Passed and adopted on final reading on the 20th day of April, A.D . 2010 .
Mayor
ATTEST :
City Clerk
-3 -