HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 12/02/2008 - RESOLUTION 2008-117 APPROVING THE EXEMPTION TO THE ITEM NUMBER: 23
AGENDA ITEM SUMMARY DATE: December2, 2008
FORT COLLINS CITY COUNCIL STAFF: Jim O'Neill
Bob Hover
SUBJECT
Resolution 2008-117 Approving the Exemption to the Use of Competitive Process for the Purchase
of a 15KV Electrical Switchgear Power Control Center.
RECOMMENDATION
Staff recommends adoption of the Resolution.
FINANCIAL IMPACT
To meet the electric needs of current and future customers,the Fort Collins Light and Power Utility
is building a new distribution substation at Portner Road(west of the Transfort facility). Funds for
the Portner Substation were budgeted in 2008.
EXECUTIVE SUMMARY
Fort Collins Utilities will be purchasing one new 15KV electrical power control center for
installation at the new Portner Substation, located on Trilby, between South College and South
Lemay Avenue. The Portner Substation will supply power to southeast Fort Collins and allow for
load transfer from the Harmony Substation. It is scheduled to be energized Fall 2009. The
switchgear will be purchased directly from the manufacturer, Powell Electrical Manufacturing
Company for a total price of$2,129,015.
BACKGROUND
Power control centers serve as the primary distribution point for main feeders which carry electrical
power to specific areas of the City. It is analogous to the breaker panel in a house, but on a much
larger scale. The power control centers also incorporate protective relaying for substation
transformers and feeders, Supervisory Control and Data Acquisition(SCADA)systems,and related
control systems. All existing power control centers in the Fort Collins system have been
manufactured by Powell Electrical Manufacturing of Houston, Texas. Powell is the only
manufacturer that can meet the City's longstanding quality electrical equipment and assembly
specifications.
December 2, 2008 -2- Item No. 23
Interchangeability of equipment throughout the electrical system benefits the City in reduced
engineering, construction and start up costs,training and long term maintenance costs, uniformity
in operations, safety,and reduced spare parts inventory. In addition,the delivery time is shortened
and manufacturing errors are minimized,due to the fact the manufacturer has already produced the
Utilities standard design and performed the required engineering and testing.
The quality of the Powell equipment has proven itself since 1986, when the first power control
center was purchased. There has never been a failure of a major equipment component in any of
the power control centers purchased. Failures in this kind of equipment are usually catastrophic in
nature and very expensive to repair. The disruption to customers and loss of revenue would be quite
substantial.
Fort Collins Utilities currently has six other Powell power control centers at substations in the Fort
Collins electric distribution system, and Powell electrical switchgear at the Drake Water
Reclamation Facility. Once power control centers are installed,the expectation is that they have an
in service lifetime in excess of 40 years. All power control centers are sized for double the existing
transformer capacity to allow for upgrading substation power transformers in the future without
changing out the power control centers.
Powell has agreed to a purchase price for the Portner power control center of$2,129,015. This is
a competitive price in the current market The purchase is an exact copy of the ones purchased in
the past,with the exception of using the latest relays and a different SCADA Remote Terminal Unit
(RTU). The last power control center was purchased on November,29,2000 for$1,244,445. There
has been a huge increase in commodity prices for steel and copper over the last 8 years.
Article IV, Section 8-161(d)(1)a. and c. of the City Code authorizes the Director of Purchasing and
Risk Management to contract for material without competition if there exists only one (1)
responsible source or a particular material or service is required to maintain interchangeability or
compatibility as a part of an existing integrated system.
The Director of Purchasing and Risk Management has determined that only one responsible source
exists for the 15KV electrical switch gear power control center manufactured by Powell, which is
the particular equipment required to maintain interchangeable and compatible breakers and relays
throughout the City's electrical system. The City Manager has approved this purchase. Council
approval is also required for exception over $200,000 by Section 8-161(d)(3) in an open meeting
for final approval.
ATTACHMENTS
1. Power Control Centers at the Harmony Substation.
i
ATTACHMENT 1
Figure I is a picture of power control centers at Harmony substation.
�.
41Power Control
R
RESOLUTION 2008-117
OF THE COUNCIL OF THE CITY OF FORT COLLINS
APPROVING AN EXEMPTION TO THE USE OF A COMPETITIVE
PROCESS FOR THE PURCHASE OF A
15KV ELECTRICAL SWITCHGEAR POWER CONTROL CENTER
WHEREAS, the City's Light and Power Utility is in need of a 15KV electrical
switchgear power control center for the Portner Substation site; and
WHEREAS, Powell Electrical Manufacturing Company ("Powell") is the only
manufacturer that produces equipment in accordance with City specifications and that is
interchangeable with existing infrastructure; and
WHEREAS, funds for the purchase of such equipment have been budgeted and approved
in the Light and Power Utility budget for 2008; and
WHEREAS, the interchangeability of equipment throughout the electrical system
benefits the City in reduced engineering, construction and start-up costs, maintenance and
inventory costs, and safety; and
WHEREAS, Article IV, Section 8-161(d)(1)a. of the City Code authorizes the Purchasing
Agent to contract for material without competition if there exists only one (1) responsible
source; and
WHEREAS, Article IV, Section 8-161(d)(1)c. of the City Code authorizes the Purchasing
Agent to contract for material without competition if a particular material or service is required
to maintain interchangeability or compatibility as a part of an existing integrated system; and
WHEREAS, the Purchasing Agent has determined that Powell is the only responsible
source for the 15KV electrical switch gear power control center, which equipment is required to
maintain interchangeable and compatible breakers and relays throughout the City's electrical
system; and
WHEREAS, the Purchasing Agent has submitted the requisite justification for this
determination to the City Manager for approval; and
WHEREAS, the City Manager has reviewed and approved this acquisition; and
WHEREAS, Section 8-161(d)(3) requires the City Manager submit all procurements over
Two Hundred Thousand Dollars ($200,000) to the City Council in an open meeting for final
approval.
NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF FORT
COLLINS that the Purchasing Agent is hereby authorized to contract with Powell Electrical
Manufacturing Company to purchase a 15 KV electrical switchgear power control center in an
amount not to exceed $2,129,015.
Passed and adopted at a regular meeting of the Council of the City of Fort Collins this
2nd day of December A.D. 2008.
Mayor
ATTEST:
City Clerk