HomeMy WebLinkAboutCOUNCIL - AGENDA ITEM - 09/21/2004 - ITEMS RELATING TO THE TIMBERLINE ROAD IMPROVEMENTS ITEM NUMBER: 7 A-B
AGENDA ITEM SUMMARY DATE: September 14, 2004
FORT COLLINS CITY COUNCIL STAFF: Matt Baker
EXECUTIVE SUMMARY
Items Relating to the Timberline Road Improvements Project.
RECOMMENDATION
Staff recommends adoption of the Resolution and of the Ordinance on Second Reading.
EXECUTIVE SUMMARY
A. Second Reading of Ordinance No. 138, 2004, Appropriating Prior Year Reserves in the
General Fund for Transfer to the Capital Projects Fund - Timberline Road Improvements
Project to be Used for the Engineering Design of Timberline Road from Prospect Road to
Drake Road.
This Ordinance, which was unanimously adopted on First Reading on September 7, 2004,
appropriates funding for the final design for the full and complete 4-lane widening project of
Timberline Road between Prospect and Drake in anticipation of potential project construction
funding through the Building on Basics ballot measure. The design would be conducted
concurrently with the Interim 4-lane project design now underway assisted by developer
funding.
B. Resolution 2004-111 Authorizing the Purchasing Agent to Execute a Change Order in
Excess of $100,000 for the Four Lane Engineering Design of Timberline, Drake to
Prospect Project.
This Resolution authorizes the Purchasing Agent to execute a change order to the existing
contract with Interwest Consulting Group to perform the design of the full and complete 4-lane
project concurrently with the Interim Timberline 4-lane design work.
ORDINANCE NO. 138, 2004
OF THE COUNCIL OF THE CITY OF FORT COLLINS
APPROPRIATING PRIOR YEAR RESERVES IN THE GENERAL FUND
FOR TRANSFER TO THE CAPITAL PROJECTS FUND -
TIMBERLINE ROAD IMPROVEMENTS PROJECT TO BE USED FOR THE ENGINEERING
DESIGN OF TIMBERLINE ROAD FROM PROSPECT ROAD TO DRAKE ROAD
WHEREAS,a section of Timberline Road from Prospect Road to Drake Road is well below
the City's level of service requirements,with almost all legs and turn movements failing during the
morning and afternoon peak rush hours; and
WHEREAS,improvements for the aforementioned section of Timberline Road are not a part
of any of the City's current capital improvement programs,and funding for these improvements has
not yet been identified; and
WHEREAS,the developers(the James Company and the Cumberland Group)of two parcels
within a one-mile radius of the Timberline Road and Prospect Road Intersection proposed privately
funding the interim improvements necessary to meet the minimum levels of services at the
Timberline Road and Prospect Intersection; and
WHEREAS,on November 4,2003,City Council accepted a petition on behalf of the James
Company and the Cumberland Group, with regard to the construction of certain interim
improvements along the section of Timberline Road,to create a special improvement district("SID")
as a mechanism for repaying the cost of the interim improvements through assessments levied by
the City against benefitted properties in the SID; and
WHEREAS, the City received a total of $100,000 from the James Company and the
Cumberland Group, which City Council appropriated by adopting Ordinance No. 026, 2004 on
March 2,2004, and such appropriated funds were to be used to prepare plans,estimate of costs, and
maps of the proposed SID in order to complete the engineering design of interim improvements
along Timberline Road; and
WHEREAS, at this same meeting, City Council is considering adoption of Ordinance No.
132,2004 on second reading,which Ordinance would authorize the transfer of appropriations from
the City's Street Oversizing Fund to the Capital Projects Fund - Timberline Road Improvements
project, to be used to complete the street oversizing portion of the design, the geotechnical reports
and environmental studies associated with the Timberline Road Improvements project; and
WHEREAS,City staff is recommending that the contract for design of�terim improvements
associated with the Timberline Road Improvements project be amended to include the full and
complete four-lane widening project of Timberline Road from Prospect Road to Drake Road, in
anticipation of potential project funding through the Building on Basics ("BOB") ballot measure,
scheduled for April 2005; and
WHEREAS, the additional cost of the full and complete 4-lane design of Timberline Road
from Prospect Road to Drake Road is $200,000; and
WHEREAS, staff recommends using General Fund prior year reserves to fund the
aforementioned additional design cost; and
WHEREAS, Article V, Section 9, of the Charter of the City of Fort Collins ("Charter")
permits the City Council to appropriate by ordinance at any time during the fiscal year such funds
for expenditure as may be available from reserves accumulated in prior years,notwithstanding that
such reserves were not previously appropriated; and
WHEREAS,it is the desire of the Council to appropriate the sum of$200,000 from prior year
reserves in the General Fund for transfer to the Capital Project Fund - Timberline Road
Improvements Project to be used with existing appropriations for the full and complete 4-lane
design of Timberline Road from Prospect Road to Drake Road.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF FORT
COLLINS that there is hereby appropriated from prior year reserves in the General Fund, the sum
of TWO HUNDRED THOUSAND DOLLARS($200,000),for transfer to the Capital Projects Fund
- Timberline Road Improvements Project, and appropriated therein, to be used for the full and
complete four-lane design of Timberline Road from Prospect Road to Drake Road.
Introduced and considered favorably on first reading and ordered published this 7th day of
September, A.D. 2004, and to be presented for final passage on the 21st day of September, A.D.
2004.
f�
ATTEST: Mayor
City Clerk
Passed and adopted on final reading this 21st day of September, A.D. 2004.
Mayor
ATTEST:
City Clerk
RESOLUTION 2004-111
OF THE COUNCIL OF THE CITY OF FORT COLLINS
AUTHORIZING AN EXEMPTION TO THE USE OF A COMPETITIVE
PROCESS FOR ADDITIONAL PROFESSIONAL SERVICES IN CONNECTION
WITH THE TIMBERLINE, DRAKE TO PROSPECT PROJECT
WHEREAS, the City previously conducted a competitive request-for-proposals process,
through which Interwest Consulting Group (Interwest) was selected to complete various
professional services related to the engineering design of the Timberline Road, Drake to
Prospect Project (the"Project"); and
WHEREAS, the City entered into a professional services agreement with Interwest for
the completion of the engineering/design for the interim improvements of the Project on July 7,
2004, and work is proceeding satisfactorily pursuant to that agreement; and
WHEREAS, the original scope of work to be completed by Interwest did not include the
completion of the full and complete four lane engineering design(the "Additional Work"); and
WHEREAS, the City has determined since contracting with Interwest that concurrent
engineering design of the interim and four lane projects would save the City both time and
money in advance of the Building on Basics proposed sales tax renewal; and
WHEREAS, the Purchasing Agent has determined that the use of Interwest to complete
the Additional Work through a change order to the existing contract for services would be an
efficient and cost-effective means of accomplishing the same and has submitted the requisite
justification to the City Manager for approval; and
WHEREAS, the Interim City Manager has reviewed and approved the determination of
the Purchasing Agent; and
WHEREAS, the cost associated with the Additional Work totals $200,000, which is
proposed to be appropriated in Ordinance No. 138, 2004; and
WHEREAS, Article IV, Section 8-161(d)(l)j of the Code of the City of Fort Collins
authorizes the Purchasing Agent to contract for services without competition if the services are
to be provided through a change order to an existing professional services contract; and
WHEREAS, Section 8-161(d)(3) requires approval by City Council of exceptions to the
competitive purchasing process for items costing more than One Hundred Thousand Dollars
($100,000)prior to acquisition.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF
FORT COLLINS that the Purchasing Agent is authorized to execute an addendum to the City's
existing contract with Interwest to add the Additional Work to the scope of services to be
completed thereunder, at an additional contract price of $200,000, contingent upon the final
adoption of Ordinance No. 138, 2004, appropriating certain funds therefor.
Passed and adopted at a regular meeting of the City Council held this 21st day of
September, A.D. 2004.
Mayor
ATTEST:
City Clerk
ITEM NUMBER: 15
AGENDA ITEM SUMMARY DATE: September 7, 2004
FORT COLLINS CITY COUNCIL
STAFF: Matt Baker
EXECUTIVE SUMMARY
First Reading of Ordinance No. 138, 2004, Appropriating Prior Year Reserves in the General
Fund for Transfer to the Capital Projects Fund - Timberline Road Improvements Project to be
Used for the Engineering Des Road to Drake Road.
RECOMMENDATION i mb R s
Staff recommends adoption of the Ordinance on First Reading.
FINANCIAL IMPACT
The additional $200,000 cost of the full and com lete 4-lane design would be funded by
advancing General Fund Res es i cip n f ro the $1,000,000 General Fund
Transportation Capital rese budg d fo Thi a good use of the budgeted
transportation capital reserve tha i as tential t the
significant savings, and
accelerates a BOB project so tha a resi s wi see near erm improvement as a result of the
election.
EXECUTIVE SUMMARY
This Ordinance appropriates funding for the final design for the full and complete 4-lane
widening project of Timberline Road between Prospect and Drake in anticipation of potential
project construction funding t u h ui P
i al t measure. The design would
be conducted concurrently h the I rimect sign now underway assisted by
developer funding.
The additional $200,000 cost of the full and complete 4-lane design would be funded by
advancing General Fund Reserves in anticipation of funds from the $1,000,000 General Fund
Transportation Capital reserve budgeted for 2005.
It is requested that Council authorization be granted to amend the existing contract with
Interwest Consulting Group to perform the design of the full and complete 4-lane project
concurrently with the Interim Timberline 4-lane design work.
September 7, 2004 -2- Item No. 15
BACKGROUND
The engineering process for the Interim Timberline Road (Prospect to Drake) widening is
proceeding at this time. Interwest Consulting Group has been retained as the lead design
engineering firm. The design timeline allows roadway construction to begin in the fall of 2005
and to be completed in 2006.
The interim design is of necessity a compromise. For the portion of the project that does not
front the two properties under oadw
a do Prospect, the project cannot
be built to full standards wita fun l O y right-of-way may be acquired
and improvements made to and th iently provide four lanes and remove
the APF restrictions at the int improve nts to meet full standards would
largely be the responsibility of the City as they will address existing deficiencies. If the interim
improvements are built as envisioned, once the incremental funding is available to complete the
project, it would require a follow up project in the same location with the accompanying
additional disruption.
Additional funding of $3.1 million for the full and complete 4-lane improvement, including
constructing the Prospect intersection to full standards, is included as a candidate for funding in
the proposed sales tax renewal (Building on Basics - BOB). If the measure is successful in April
2005 and includes this project y ve gr ed for the full and complete
improvements before constru on of nteri p 'e egi
If the BOB measure passes, i a cond a construction of the full and
complete 4-lane improvements, rather than allow the interim widening to be built, then following
it with another construction project on the same stretch of road. Besides the savings from
efficiencies, it's a far better public relations approach. The proposal is to conduct the design of
the full and complete 4-lane widening of Timberline concurrent with the interim design work. To
wait to initiate the ultimate design until after the election would delay the entire project nine to
twelve months. If the design is already complete when the BOB vote occurs, the original
schedule can be retained. Conservatively estimating construction cost escalation rates, not
delaying the full project design c ul Op
ut $350,000 over a year. If the BOB measure
passes, the General Fund Tr port i1 se 1 l�reimbursed for the $200,000
amount.
This is a good use of the budge a tran capital reserve in that it has the potential to
leverage significant savings, and accelerates a BOB project so that the residents will see near
term improvement as a result of the election. Since the 4-lane standard arterial roadway will be
needed at some point in the future, this design effort will not be wasted.