FORT COLLINS CITY COUNCIL DATE: January 16, 2001
STAFF: Matt Baker
SUBJECT:
First Reading of Ordinance No. 8, 2001, Appropriating Prior Year Reserves in the Street
Oversizing Fund and Authorizing the Transfer of Appropriations from the Street Oversizing
Fund to the Capital Projects Fund for the Timberline and Drake Roadway Improvements.
RECOMMENDATION:
Staff recommends adoption of the Ordinance on First Reading.
FINANCIAL IMPACT:
This Ordinance transfers $3,223,712 from the Street Oversizing Fund into the Capital Projects
Fund to construct arterial roadway improvements for the Timberline and Drake Roadway
Improvements. This project will go to bid as soon as funds are available. All of the funds will be
appropriated from the Street Oversizing Program.
EXECUTIVE SUMMARY:
Arterial street improvements are planned for approximately one mile of Timberline Road, from
Vermont Drive to approximately 2000 feet north of the intersection with Drake Road. Drake
Road will be improved from the Union Pacific Railroad tracks on the west end of the project to
approximately 1000 feet east of the intersection with Timberline Road. The project will
construct full intersection improvements including auxiliary turn lanes.
BACKGROUND:
Over the past two years staff has completed the design of the Timberline and Drake Roadway
Improvements Project. This project is being constructed in conjunction with the Rigden Farm
development and is fully funded by development through the Street Oversizing Program. The
improvements will span on Timberline Road from Vermont Drive to 2000 feet north of the
intersection and on Drake Road from the Union Pacific Railroad tracks east of the intersection
1000 feet. The project is planned to begin construction in the spring of 2001, with final
completion and landscaping to be completed in the fall of 2001.
The improvements to Timberline Road include widening Timberline Road to a four-lane arterial
with landscaped medians. This widening will accommodate turn lanes at Custer Drive and
DATE: January 16, 2001 2 ITEM NUMBER: 13
Sagebrush Drive, as well as entrances to future development on Timberline and to Sagebrush
Drive on Drake Road. There will be double left turn lanes constructed with this project on all
approaches to the intersection of Timberline and Drake. The improvements will include curb
and gutter, 8 foot sidewalks, 8 foot bike lanes, colored concrete handicap access ramps, full
length medians with plantings and hardscaping, asphalt and concrete paving with decorative
crosswalks, and storm sewer and waterline installation. An important feature of this project is
the effort to preserve the existing ash trees in the landscaped medians.
The Pavement Management Program will take advantage of this construction project to complete
some repair and maintenance work adjacent to the project. These improvements will be
completed as part of the same construction contract; however, funding of these repairs is already
budgeted and appropriated.
In order to take this project to bid and to start construction in the spring, funding for the project
must be appropriated into the Capital Project Fund.
ORDINANCE NO. 8, 2001
OF THE COUNCIL OF THE CITY OF FORT COLLINS
APPROPRIATING PRIOR YEAR RESERVES IN THE STREET OVERSIZING FUND AND
AUTHORIZING THE TRANSFER OF APPROPRIATIONS FROM THE STREET
OVERSIZING FUND TO THE CAPITAL PROJECTS FUND FOR THE TIMBERLINE AND
DRAKE ROADWAY IMPROVEMENTS
WHEREAS, City staff has been working on the design plans for a section of Timberline
Road from Vermont Drive north to the intersection of Timberline and Drake Roads(the"Project')
including the widening of Timberline to a four-lane arterial with landscaped medians; construction
of double left turn lanes on all approaches to the intersection of Timberline and Drake;curb,gutter,
eight-foot sidewalks and bikelanes;ADA compliant access ramps;full length medians with plantings
and hardscaping; asphalt and concrete paving with decorative crosswalks; and storm sewer and
waterline installation; and
WHEREAS, the Project will be constructed in conjunction with the Rigden Farm
development; and
WHEREAS, the estimated cost of the Project is $3,223,712, and funds are available in the
form of prior year reserves in the Street Oversizing Fund; and
WHEREAS,upon completion of the bid process,the Project will begin in the spring of 2001,
with final completion and landscaping to be completed in the fall of 2001; and
WHEREAS, Article V, Section 9, of the Charter of the City of Fort Collins (the "Charter")
permits the City Council to appropriate at any time during the fiscal year such funds for expenditure
as may be available from reserves accumulated in prior years, notwithstanding that such reserves
were not previously appropriated; and
WHEREAS,Article V,Section 10,of the Charter authorizes the City Council to transfer by
ordinance any unexpended and unencumbered amount or portion thereof from one fund or capital
project to another fund or capital project,provided that the purpose for which the transferred funds
are to be expended remains unchanged; and
WHEREAS,it is the desire of the City Council to appropriate funds totaling$3,223,712 from
prior year reserves in the Street Oversizing Fund, and authorize the transfer of said appropriations
to the Capital Projects Fund, to be used to construct improvements along Timberline Road from
Vermont Drive north to the intersection of Drake Road and including the intersection of Timberline
and Drake Roads.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF FORT
COLLINS that the sum of THREE MILLION TWO HUNDRED TWENTY-THREE THOUSAND
SEVEN HUNDRED TWELVE DOLLARS ($3,223,712), is hereby appropriated for expenditure
from prior year reserves in the Street Oversizing Fund,authorized for transfer to the Capital Projects
Fund,Timberline and Drake Road capital project,and appropriated therein,to be used to construct
improvements along Timberline Road from Vermont Drive north to the intersection of Drake Road
and including the intersection of Timberline and Drake Roads.
Introduced and considered favorably on first reading and ordered published this 16th day of
January, A.D. 2001, and to be presented for final passage on the 6th day of February, A.D. 2001.
Mayor
ATTEST:
City Clerk
Passed and adopted on final reading this 6th day of February, A.D. 2001.