HomeMy WebLinkAboutElectric Board - Minutes - 10/06/2011Electric Board Meeting Minutes
October 6, 2011
1
Fort Collins Utilities Electric Board Minutes
Thursday, October 6, 2011
Electric Board Chairperson City Council Liaison
Steve Wolley, 288-0317 Lisa Poppaw, 223-4136
Electric Board Vice Chairperson Staff Liaison
Edward DeCourcey, 206-9996 Brian Janonis, 221-6702
Roll Call
Board Present Chairperson Steve Wolley, Vice Chairperson Ed DeCourcey, Board Members John
Graham, John Harris, and Steve Yurash
Board Absent Board Member Peggy Plate
Staff Present Patty Bigner, Steve Catanach, Ellen Switzer, Bill Switzer, John Phelan, Jenny Lopez-
Filkins, Robin Pierce, and Harriet Davis
Guests Rick Coen and Peter O’Neill
Meeting Convened
Chairperson Wolley called the meeting to order at 5:31 p.m.
Public Comment
None
Approval of September 7, 2011, Minutes
Vice Chairperson DeCourcey questioned how an item from the September meeting (Energy Policy
Goals Recommendation) would be presented to the future Energy Board as per the Electric Board’s
suggestion. Vice Chairperson DeCourcey suggested the item be an action item for the new board’s
review.
Board Member Harris moved to approve the minutes of the September 7, 2011, meeting. Board
Member Yurash seconded the motion, and it passed unanimously.
Update on Electric Rate Options from September 13 Work Session
(Presentation available upon request)
Customer and Employee Relations Manager Patty Bigner introduced this topic. Utilities presented
information on Electric Rate Options to City Council at the September 13 Work Session. Council
requested more information on how price elasticity is calculated as well as what system benefits
were derived from tiered rates. They were interested in the results of their decision regarding tiered
rates. City Council also wanted to know how goals are going to be accomplished and what is the
impact going to be on customers. In response to their feedback, Utilities has prepared a new
presentation for the October 11, 2011 Work Session. Ms. Bigner stated Utilities is using an industry
standard to calculate elasticity. They picked the moderate level as a result of this. (A copy of the
Work Session Summaries from September 13 and October 11 are attached).
Electric Board Meeting Minutes
October 6, 2011
2
Board discussion:
Is this consistent with the water rates? Ms. Bigner stated most of the water savings relate to outdoor
water use. Light and Power Operations Manager Steve Catanach stated it is much easier to reduce
your water usage than electricity usage.
Ms. Bigner stated the October 11 presentation will include four options. The presentation was
expanded to include more explanation of concepts and definitions. A briefing on energy
conservation, including water programs, is also included in the presentation. It is available on
www.fcgov.com.
Is the Communication Plan also included in the presentation? The Communication Plan for drafting
the ordinance is included; however, it needs to be finalized. The Fort Collins Sustainability Group is
writing a letter of support. This group emphasized customer assistance, and would like to see
provisions for individuals that require medical equipment.
Do you have any information on the Home Audit Promotions that were mentioned at the September
meeting? Ms. Bigner stated Utilities is currently promoting the home energy efficiency programs
and audits with Lowes, Home Depot, and Ace Hardware Stores. Ms. Bigner stated the audit
program is doing well this year.
A board member questioned when the peak cost is going down and the electric rate going up for the
General Services (GS) group? Mr. Catanach stated Platte River Power Authority (PRPA) is
reducing their demand charge next summer. The demand charge will be approximately $10, a
decrease from $12.42. In the winter, the demand charge will decrease to approximately $7.50.
Ms. Bigner encouraged the board members to look at the presentation online. The presentation also
gives a history of the programs and how they are implemented.
2011 L&P Budget Exceptions and Rate Recommendations
(Presentation available upon request)
Utilities Financial Operations Manager Ellen Switzer presented information on this item. She began
the presentation by thanking the board members for arranging their schedule to review the
information before it is presented to Council. The residential energy rate will not be presented to
Council at this time. It will be presented later this year.
Electric Rate Increase
Staff is recommending an overall 8.3 percent electric rate increase. There are several components to
the rate increase. The wholesale electric rates from Platte River Power Authority (PRPA) will
increase 6.4 percent, with a 4.8 percent increase at the retail level. There will be higher seasonal
rates in June, July, and August. More costs will shift from the demand component to the energy
component. There are several key factors relating to the PRPA rate increase, including reduced
surplus sales, increased Operation and Maintenance (O&M) costs, increased financing cost and
depreciation, and reduced interest income. Reduced interest income is affecting all the Utilities
funds.
Board discussion:
Did anyone question the increase to O&M costs? Mr. Catanach stated he will have to research the
answer to this question.
Electric Board Meeting Minutes
October 6, 2011
3
Ms. Switzer stated the remaining 3.5 percent rate increase is related to internal needs for Light and
Power. Utilities is trying to slow the use of reserves for capital projects. Since 2007, expenses have
been greater than revenues.
Is there a target for reserves? Mr. Catanach stated there is a mandated minimum that Utilities
should reserve. He also stated Light &Power operational expenses for 2010-2011 have been
reduced. The budget structure was revamped and there was a 2.4 percent reduction for the 2011-
2012 Budget.
Is the reserve based on a percent of the revenue? Ms. Switzer stated it is based on two things. There
is an operating reserve equal to 8 percent of the operating budget less purchase power. There is also
a capital reserve. There was also a fairly large reduction in other revenues not related to rates,
including increased development fees. Also, because of lower interest rates, interest income has
been reduced.
Proposed Electric Rates
All electric rates will be seasonal. Rates will be higher during the months of June, July, and August.
The residential energy rate is not included in the ordinance. The residential demand rate will be
restricted to those customers who do not have natural gas service.
Board discussion:
A customer will have to be 100 percent electric to participate in the residential demand rate?
Currently, it is an option.
The General Service (GS) Rate will be split into two classes (General Service <25 kW Energy Only
and General Service >25kW Energy and Demand). General Service 50 and 750 (larger commercial
and industrial customers) will retain coincident peak pricing with seasonal differential.
Ms. Switzer stated the rate schedules are posted on the City Clerk’s webpage at www.fcgov.com.
Ms. Switzer explained the graph for the 8.3 percent electric rate increase by customer class for
Summer, Non Summer, and Average. The average increase is 6 percent.
Board discussion:
This chart shows the percentage in rate change? Where does that leave the overall rate? Ms.
Switzer stated the actual rate schedules are on the City Clerk’s webpage with the old and new rates
listed. The rate changes are based on load factor and load characteristics.
What is a typical customer profile for GS<25? Ms. Switzer stated this is typically a small office,
such as an attorney or accountant.
What customer class do most of the restaurants belong to? Most of the restaurants are as high as
GS50.
What are the criteria for generating the differential for cost of service versus seasonal rates? Ms.
Switzer stated this is purely based on purchase power cost from PRPA.
Recommended Electric Rate Clarifications
Staff is recommending a new definition for wholesale transactions be included in the City Code.
This is subject to requirements for interconnection and is not governed by the electric rate schedules
or electric development fees. The code clarification sets the value of the energy.
Electric Board Meeting Minutes
October 6, 2011
4
Mr. Catanach stated there will be a net metering credit for net excess generation that will be based
on the summer season retail energy charge. The value is carried month to month. With the tiered
rate structure, the value is impossible to track over a 12 month period. Utilities will purchase the
power back at the lowest tiered rate for the season.
Board discussion:
Is there more incentive in the summer? The majority of the production is in the summer.
Mr. Catanach stated the parallel generation credit for energy delivered to the utility will be based on
PRPA’s avoided cost rate. The Special Services Agreement states the customer can earn the credit
for offsetting the demand. If a customer consistently generates a benefit to the system (for example
10 kW), Utilities will recognize the demand benefit. Since Utilities has to invest in system capacity,
it is important to ensure the rate reflects the true value that a generating customer brings to Utilities.
Was there a change in the City Code to implement this? No; however, the change in the Special
Services Agreement was presented to Council.
Electric Development Fees
The Electric Development Fees are required to be adjusted by Council every other year. Typically,
they are presented to Council every year. The 2011 Electric Development Fees were approved in
2010. The proposed changes for 2012 include a 3.0 percent increase for a typical single family lot
and a 0.3 percent decrease for a model commercial development. The changes are based on the
current construction estimates.
Ms. Switzer explained the graph for the 2011-2012 Electric Development Fee Comparison based on
a typical single family lot and a model commercial development.
Board discussion:
How do these rates compare with other cities? Mr. Catanach stated these rates are comparable with
other nearby cities.
Miscellaneous Fees
These changes will be presented to Council on November 15, 2011. The after-hours service charge
will increase to $85.35. It is currently at $55.45. A monthly charge for manual meter reading for
those customers who opt out of the Automated Metering Infrastructure (AMI) program needs to be
determined. Currently, it is estimated at $10-15 per month. Mr. Catanach stated the rate should not
be a punishing rate for individuals who choose to opt out of the AMI program.
Board discussion:
How long do you expect this rate structure to continue? When is the next phase of the rate change
for the other classes? The rate form will remain the same until at least 2014.
A board member expressed concern that the timing of the rate changes along with the AMI program
implementation should be considered.
2012 Budget Revisions/Exceptions
The following changes are recommended to the original 2012 budget:
• Purchase Power: $1,724,505
• Payment in Lieu of Taxes (PILOTs): $121,969
Electric Board Meeting Minutes
October 6, 2011
5
• Energy Efficiency Financing Program: $300,000
Ms. Switzer stated the $300,000 for the Energy Efficiency Financing Program will cover loans and
fees to set-up and administer the program. Council has been asking for this program.
Board discussion:
Is this in lieu of on-bill financing? Energy Services Manager John Phelan stated there is a range of
options with the program. The requested amount would be sufficient to get the program started as a
pilot program. Utilities would like the program up and running in the first quarter of 2012.
What is the increase from last year’s budget? Last year’s budget was $50,000.
Is this an exception or a revision? Ms. Switzer stated that typically these are called exceptions;
however, a Councilmember requested they be referred to as revisions in the future.
Ms. Switzer stated there may also be a city wide exception for increasing salaries for employees
currently paid less than market value. This is a city wide recommendation. Mr. Catanach stated the
City has budgeted 2 percent for increases. $800,000 would be dedicated to market increases. The
City will also supplement this with a budget exception.
How far are some of the Utility employee’s salaries below market value? Mr. Catanach stated some
salaries are 15-20 percent below market value; however, some of these positions are entry level or
new hire positions. Approximately half of the Light and Power employee’s salaries are 6-7 percent
below market value.
Vote on the motion: It passed unanimously.
* Chairperson Wolley abstained from the vote due to a conflict of interest as a representative of a
business.
Vote on the motion: It passed unanimously.
Discussion on the motion:
A board member recommended the line item for the Energy Efficiency Financing Program be
removed from the list of exceptions. He would like more explanation on the program.
Board Member Yurash moved that the Electric Board recommend that City Council adopt
the proposed electric rate increases for all rate classes with the exception of the Residential
Energy Rate. Board Member Graham seconded the motion.
Board Member Harris moved that the Electric Board recommend that City Council adopt
the proposed changes to the 2012 Electric Development Fees and Charges. Vice Chairperson
DeCourcey seconded the motion.
Vice Chairperson DeCourcey moved that the Electric Board recommend that City Council
approve the proposed exceptions to the Light and Power Fund’s 2011-2012 Budget. Board
Member Graham seconded the motion.
Electric Board Meeting Minutes
October 6, 2011
6
A board member asked for clarification on the item. Is it a form of a loan program? Yes.
How did Utilities arrive at $300,000 for the program? Mr. Phelan stated this amount is enough to
establish a pilot program.
When City Council requested an increase to the budget, did they ask for a specific increase for this
item? No, Council only asked that the program be implemented.
What is the duration of the loan program? Typically, it is 5-10 years. Utilities can design the terms
of the loan.
Does Utilities have a document that describes the scope of the program? No, not currently.
A board member suggested dividing the recommended motion into two segments. Vice Chairperson
DeCourcey withdrew the original motion. Board Member Yurash requested a friendly amendment
to staff’s recommended motion.
Vote on the motion: It passed unanimously.
Board discussion:
Is this the last chance for Utilities to add this amount to the exception process? Yes, it will be voted
on by Council on October 18, 2011.
The board members agreed to not modify the recommendation concerning the Energy Efficiency
Financing Programs. A board member felt the original recommended motion concerning this was
too vague.
Routine Updates
Platte River Power Authority: No report.
Capitol News (Vice Chairperson DeCourcey): No report.
Staff Reports
Monthly Financial Report
Utilities Financial Operations Manager Ellen Switzer provided a monthly Financial Report included
in the packet.
Board discussion:
What is the total cost of the BRT/Mason Corridor Project? Ms. Switzer stated the total cost of the
project is $500,000. Utilities will spend approximately $1 million, and they will receive $500,000
back on the project. This is over the life of the project.
Other Business
Pineridge Natural Area Transmission Line Construction Alternatives Study
Mr. Catanach gave an update on the proposed transmission lines in the Pineridge Natural Area. The
alternative study was originally planned to be presented to Council on October 18, 2011. It will be
presented on October 11, 2011. Staff is seeking Council direction on the issue. The study looks at
Amended Motion: Board Member Yurash moved that the Electric Board recommend that
City Council approve the recommended budget additions for Purchase Power costs,
Payments in Lieu of Taxes (PILOTs), and the creation of an exception for increasing Utility
employees’ salaries for market rate adjustments. Vice Chairperson DeCourcey seconded the
motion.
alternatives including moving the lines, increasing the span length over the open area, and changing
the appearance of the proposed lines. Western Authority Power Administration (WAPA) stated they
would be cooperative in moving the lines, but would not consider undergrounding the lines. Council
will meet with the City Attorney regarding the legal issues at the Executive Session on October 11.
2011. After the Executive Session. Utilities staff will present the draft alternatives study.
Review ofPRPA Organic Contract
Mr. Catanach stated the Electric Board will review the PRPA Organic Contract for any significant
changes. This item will be presented to the board at the November meeting. Proposed changes will
need to be communicated to Council. The Organic Contract is an agreement between PRPA and the
four cities. It is essentially an operating document.
2011 Annual Report
The board members discussed how the annual report will be produced. Vice Chairperson
DeCourcey stated he will take the lead for drafting the report.
Future Agenda Items
N one
Open Items Tracking
None
Adjournment
The meeting was adjourned at 7:36 p.m.
Submitted by Harriet Davis. Administrative Assistant. Fort Collins Utilities
Approved by the Board on SO . 2011
Signed
Board Secretary Date
Electric Board Meeting Minutes 7
October 6, 2011