October 27, 2022
A regular meeting of the Building Review Commission was held on Thursday, October 27, 2022, at
9:00 a.m. in the Council Chambers of the Fort Collins Municipal Building at 300 Laporte Avenue, Fort
Collins, Colorado.
• CALL TO ORDER
Vice Chair Johnson called the meeting to order at 9:01 a.m.
• ROLL CALL
PRESENT: Dunbar, Johnson, Moscrip, Richards, Teplitsky, Zimmerman
ABSENT: Cram
STAFF: Coldiron, Manno, Guin, Matsunaka, Brennan
• PUBLIC COMMENT ON ITEMS NOT ON THE AGENDA
None.
• DISCUSSION AGENDA
[Timestamp: 9:03 a.m.]
1. CONSIDERATION AND APPROVAL OF THE MINUTES OF THE OCTOBER 27, 2022 MEETING.
Richards moved to approve the minutes of the September 29, 2022 meeting. Moscrip seconded.
The motion passed 6-0.
2. USA EAGLE CARPORTS NEW LICENSE REQUEST WITHOUT EXAM
DESCRIPTION: Mr. Holland of USA Eagle Carports, Inc. is requesting a new license and
supervisor’s certificate to be issued without a passing ICC testing certificate.
Building Review
Commission
City of Fort Collins Page 2 October 27, 2022
Disclosure of Conflicts
None.
Staff Presentation
Admin Services Manager Manno presented the staff report. The appeal was a new license request for
a waiver of the testing requirement for a Class C1(DR) license and supervisor’s certificate to build
carports for a development. Mike Hall would be presenting for USA Eagle Carports. An application
was received in September of 2021 for David Murphy, which was incomplete and returned. In April
2022, she received an email from Jordan Mike asking which license classification would be needed.
Hall also called and emailed to ask what was required for a license to be issued. Manno answered
those questions several times. In April 2022, a new incomplete application was received for a person
named Clark. Manno again communicated with employees of USA Eagle explaining what was missing
from the application and why testing was necessary. In June 2022, Hall informed her the individual did
not work for USA Eagle anymore and a new application would be sent. No new application was
received, and USA Eagle had instead chosen to appeal to the Commission.
The City was following the 2021 ICC Codes, but since new testing had not been made available the
CBO allowed for the highest year testing available, as well as the year below it. The City would accept
2018 testing, with some exceptions where 2015 was the most recent available. The C1(DR) license
was required because the carports would be assembled at a multi-family dwelling.
Staff recommended denial of the request based on current testing requirements and lack of a complete
licensing application packet; to issue a license, the Commission could require a current testing
certificate. However, the Commission could grant the request and allow issuance of a new license
without testing.
Appellant Presentation
Hall and Mike spoke to the Commission on behalf of USA Eagle. Hall stated USA Eagle was solely a
carport company, and it had been hired by the main contractor to fabricate and build the carports onsite
in Fort Collins. It had been in business for 30 years, operated nationwide, and had never needed to
apply for a license to do work as a subcontractor working under the General Contractor license. He
had been in contact with Manno because he was unsure about what kind of license would be needed.
They had worked in Denver and Colorado Springs previously. An employee had taken the required
testing twice and fallen short. USA Eagle was appealing to the Commission because it was pressed
for time on the project and needed work to begin as soon as possible.
Mike worked for the general contractor of the multi-family dwelling project. He stated his company had
multiple building projects underway in Fort Collins. It was important to have licensed supervisors onsite
and to continue a good working relationship with the City. He was supporting USA Eagle’s request.
They built carports for a variety of project classifications across the country. His company would ask
them to solely focus on carports, nothing more.
Board Questions of Staff and Parties-in-Interest
Vice Chair Johnson asked if USA Eagle had anything to add and Hall pointed out carports were treated
as relatively minor on the ICC Exam. He directed the Commission to the Commercial Buildings Tab
under General Contractor on the City’s Contractor Licensing website and asked why they could not fall
under a Class MM license. Manno clarified it was for single family or residential areas. Class C2 was
held by the General Contractor and was for multi-family residential buildings, but everything else
constructed in the development is considered commercial in nature by the Code. Hall pointed out that
sometimes carports fall under the same section as awnings and he would not need a license to attach
an awning to the buildings here; could the carports be considered as something attached to the
building?
Moscrip asked for an explanation of the design of the carports. Hall provided drawings to the
Commission with engineer stamps. There were two 36-foot long structures. Due to snow in Colorado,
the materials are strengthened compared to carports they build elsewhere. Their engineers were very
good at tailoring the carports to the project. The two carport designs were identical structures, with one
43 feet and one 36. They would be married together to make a big carport.
City of Fort Collins Page 3 October 27, 2022
Richards asked Staff if the General Contractor holds the appropriate license, what the requirement for
Subcontractors would be. Manno answered they had the same standards, each one must turn in a
complete application license packet for the applicable license and hold a license with the City. In this
particular instance, the C1(DR) was needed for a structural addition on a commercial property.
Richards asked if there was any other classification the City could use for this specific type of work.
Manno said no, MM licenses were for residential carports but the Commission could possibly find some
common ground there since the structure in the development is residential in nature. Coldiron stated
it would not work because MM holders build smaller carports for individual homeowners.
Guin advised variances from the strict application of the Code could be granted if the Commission
found there was an exceptional difficulty or undue hardship or if the Commission found the applicant
had other qualifications not specifically listed in Code which would qualify the applicant to perform the
construction in a competent manner but there would not be substantial detriment to the public good.
Richards asked what inspections and oversight would be required from the City for a structure like the
carports. Coldiron said these kind of structures would typically need to be inspected by a credentialed
third party inspector but if the Commission preferred a City inspector could do it as part of the
Commission’s requirements if granting the applicant’s request.
Teplitsky asked if the General Contractor had a supervisor onsite would it waive the requirements so
USA Eagle could build the carports under its umbrella. Manno answered it did not because all trades
were required to have a license or registration. No one could use another’s license to cover their work.
Johnson asked if the General Contractor had to have the supervisor’s certificate and license and each
subcontractor had to have their own, as well. Manno said that was correct.
Teplitsky asked Hall if they had scored 66 and 62 on attempts at passing testing, with the passing grade
being 70. Hall said they failed the structural part of the test, which was 22 percent. Hall asked if the
requirement was for a General Contractor to build the carports. Manno clarified a licensed party had
to build them, but the way the City’s licensing worked the C1(DR) was a General Contractor’s license.
Hall emphasized that time was of the essence in beginning work on the carports. The next test would
be offered in December, but it took seven or eight hours away from someone that could be working on
other projects in Colorado. Hall provided a document showing what topics were on the test, how they
were weighted, and how employees had scored in each area on the test.
Richards asked Hall how many projects with which they were involved and how many licenses USA
Eagle currently held. They did not hold licenses because they had never need them. USA Eagle was
a nationwide company that had been around for 30 years and had built over a million carports. It
averaged from $14 to 20 million in revenue each year.
Dunbar asked about the differences between residential and commercial carports. Manno did not know
and would have to look it up.
Teplitsky asked which project Hall had under contract within the City. Hall did not have any because
he could not sign a contract in good conscience knowing he was not yet allowed to work within the City.
He wanted to work with Mike’s company on the project discussed and there were others wanting to hire
him. Hall wanted to work in the City. Mike wanted to have USA Eagle build carports for them for current
projects in Colorado Springs and other locations in Colorado. He had a development in Fort Collins
next year for which he wanted to hire USA Eagle. His company had supervisors with certificates in the
City and they would be onsite supervising USA Eagle staff for that project. Teplitsky asked if USA
Eagle’s request was granted that day, when would the project begin. Mike said roughly two weeks in
November. The duration would be less than two to three weeks. Teplitsky asked if there was another
project in Fort Collins for which he would hire USA Eagle in the future. No project as described was
set in stone.
Manno stated the G11 testing covers the International Building Code (IBC), G12 covers both the IBC
and the International Residential Code (IRC), and G13 covers the IRC only. As to licensing, G13 was
the class C, G12 was the Class B, and G11 is the Class A.
Teplitsky asked Manno if the project was permit ready, aside from the USA Eagle license issue. Manno
looked it up, and the permit was just waiting on a contractor license to be approved.
Teplitsky asked Guin what the protocol was for the Commission to talk amongst themselves. Guin said
once questions were satisfied, the Chair could open up discussion. Alternatively, a motion could be
made, then discussion about the motion would follow. Vice Chair Johnson clarified that he could open
discussion but if there were more questions, the Commission could ask them. Guin affirmed.
City of Fort Collins Page 4 October 27, 2022
Teplitsky thanked Manno for looking up the permit information and verified the project in South Fort
Collins was the one for which USA Eagle was requesting a license. Manno replied it was a project with
five pending permits on Horizon Drive waiting for USA Eagle’s particular license.
Motion and Board Discussion
Vice Chair Johnson closed the hearing and asked for discussion.
Richards felt that USA Eagle had demonstrated vast knowledge and experience with carports. He
thought it would be unreasonable to ask them to demonstrate a much wider knowledge on a test than
what they perform. Third party inspections and a licensed supervisor onsite were sufficient to guarantee
safety. The licensing requirements were overly burdensome and restrictive in this specific instance,
but he wondered what would happen if USA Eagle wanted to join another project in Fort Collins in the
future.
Johnson said when Guin reviewed the Code, the thing that struck him was the public good. He felt that
was why Code was in place and established specific processes. He did not think it was the
Commission’s place to say parts of the Code were unnecessary. It existed to protect the public. Guin
reminded the Commission they could approve the request with conditions.
Zimmerman asked which was better: if the General Contractor built the carports because it had the
license to do so or if USA Eagle built them with its vast specialized experience. He posited the public
would be safer if USA Eagle built the carports.
Teplitsky was encouraged that USA Eagle had taken the test twice and come close to passing. If the
test taker had gotten two more questions correct, he would have passed and been qualified to build
structural items. He was not engineering the carports, but instead they would be engineered and
inspected by a third party. The safequards were already in place to ensure safety and Code
compliance. However, his strong preference was to follow the Code and require normal licensing
procedures, which was what the Commission usually required in the spirit of fairness and precedent.
He pointed out the Commission had granted temporary licenses in the past to allow time to take the
test, as well as variances which Guin had suggested.
Moscrip said it did not undermine the public good to allow this one project to go forward. The
Commission could consider requiring USA Eagle to take the test for subsequent projects. He asked
the contractors on the Commission what their experience was like with construction of pre-engineered
shelters. Dunbar said they always hire a third party, Teplitsky said they had done it both ways, and
Johnson said they used a third party and the permitting and licensing of that part was all through the
subcontractor.
Teplitsky wanted to move toward crafting a motion. He would be in favor of granting an exemption to
allow USA Eagle to build the current project with the requirement that any further projects require a
passing test grade to be licensed; if there was no passing grade, a similar appeal would be required.
Vice Chair Johnson asked if Teplitsky would allow USA Eagle to build one carport or all five involved in
the project, and Teplitsky said all after verifying that the entire apartment complex, including carports,
would be built in 30 days or less. He thought if necessary, they could apply for extensions on this
project, but USA Eagle should provide required testing for the next project.
Richards read through a proposed motion drafted by City staff and asked if there was a way to require
the General Contractor to have a supervisor onsite and were there safeguards from the City to ensure
it happened. Coldiron replied Code required a supervisor to be onsite during inspections. If a license
was granted to USA Eagle, its supervision would be sufficient to build carports and the General
Contractor’s supervision would not be necessary. Richards asked which company was the permit
holder. USA Eagle would be the permit holder for the carports. Vice Chair Johnson clarified from a
practical standpoint, the named supervisor was not always onsite but would be for inspections.
Guin asked if the Commission would like to tweak any conditions for the proposed motion on their
screens.
Dunbar asked City staff if a third party inspection report would be required before issuing Certificates
of Occupancy for this project. Coldiron said that was correct.
Richards moved based on Staff’s report and analysis, and the evidence and testimony
presented today I move to APPROVE the applicant’s request for a variance from the licensing
standards in this Appeal in accordance with Section 15-156 of the City Code, WITH
CONDITIONS.
City of Fort Collins Page 5 October 27, 2022
I find that:
The applicant has demonstrated to my satisfaction that they possess other qualifications such
as specialized knowledge and significant experience in building these types of structures that
is not specifically listed in our Contractor Licensing section of the City Code that would qualify
the applicant to perform construction authorized under the license or certificate sought in a
competent manner.
AND
The applicant has demonstrated that, if the relief requested were granted, there would not be
substantial detriment to the public good and would not substantially impair the intent and
purpose of this section of the City Code, particularly as there is a general contractor and
supervisor with the requisite license on site and Building Services will still perform inspections.
The CONDITIONS upon the approval I want to require are:
This variance is applicable to this project only and only as to carports; no other work in the City
of Fort Collins is to be performed by Applicant until such time as the Applicant meets all
requirements of the City’s building code, including passing the required ICC exam.
Moscrip seconded. The motion passed 5-1.
Manno stated Staff would need an application packet from USA Eagle, minus the testing, so she had
their information to put into the City’s system. Vice Chair Johnson asked if the motion would need to
be amended. Guin suggested getting an affirmation from the applicant on the record; they asked for a
variance from the examination but would have to meet all the other requirements so an amended motion
was not necessary. Vice Chair Johnson asked the applicant on the record if he understood the
additional requirements. Hall understood and would follow them.
[Timestamp: 10:10 a.m.]
3. CONSIDERATION AND APPROVAL OF THE BUILDING REVIEW COMMISSION’S 2023 ANNUAL
WORK PLAN
DESCRIPTION: The purpose of this item is to approve the 2023 Annual Work Plan of the Building
Review Commission.
Staff Report
Coldiron presented the staff report. The Work Plan covered the normal scope of BRC activities and
the Commission was welcome to ask questions.
Moscrip requested Coldiron to do a readthrough and Coldiron obliged. He stated the Contractor
Mentorship Program would allow an additional path of compliance for contractor licensing with project
verifications. Vice Chair Johnson stated the Commission had seen many instances where such a
program was necessary.
The Contractor Licensing item would make the process more streamlined and simple. It would be more
in line with licensing throughout Northern Colorado.
Board Deliberation
Moscrip moved the Commission approve the Work Plan as presented in the October 27, 2022
Agenda.
Vice Chair Johnson seconded. The motion passed 6-0.
[Timestamp: 10:16 a.m.]
• OTHER BUSINESS
Coldiron reminded the Commission with the retraction of the Covid Emergency Order, they would now
be meeting in person. Many had voiced concerns that in person format did not allow for meeting
quorum or public comment. The City was looking at presenting an ordinance to Council in December
City of Fort Collins Page 6 October 27, 2022
that would allow for virtual and hybrid meetings. He asked the Commission to think about and discuss
if it would support the change in the November meeting.
Guin stated the City Code did not allow for virtual and hybrid meetings. The Emergency Order allowed
for remote meetings, but now the City had gone back to in person Boards and Commissions meetings.
There was a proposal going before City Council in December to change Code to allow remote and
hybrid meetings. Coldiron was asking them to consider if they would support it.
• ADJOURNMENT
Vice Chair Johnson adjourned the meeting at 10:19 a.m.
Minutes prepared by Aubrie Brennan and respectfully submitted by Melissa Matsunaka.
Minutes approved by a vote of the Commission on
_________________________________ ______________________________
Russ Hovland, Acting Chief Building Official Alan Cram, Chair
November 17, 2022